burundi - gitega-nyangungu-ngozi road … 1. client information country : burundi project name :...
TRANSCRIPT
Language : English Original : French
PROJECT : GITEGA-NYANGUNGU-NGOZI ROAD DEVELOPMENT
AND ASPHALTING PHASE I: NYANGUNGU-NGOZI SECTION
COUNTRY : BURUNDI
PROJECT APPRAISAL REPORT
Date: July 2010
Appraisal Team
Team Leader:
Team Members:
P. MORE NDONG, Transport Engineer OICT.2 Ext. 2284
A.I. MOHAMED, Principal Transport Economist OITC.2 Ext. 2774 M.LEKE, Socio-economist, (Consultant) OITC.2 O.S.A BAH, Environmentalist, (Consultant) OITC.2 B. NTUNDA, Public Health Specialist, (Consultant) OITC.2
Regional Director: Mrs. D. GAYE OREA Ext. 2064
Sector Director: Mr. G. MBESHERUBUSA OICT Ext. 2034
Sector Manager: Mr. J. RWAMABUGA OICT.2 Ext. 2181
Peer Reviewers
A. KARANGA, Transport Economist OICT.1 Ext. 2607 M. MBODJ, Transport Economist OICT.1 Ext.2348 N. NDOUNDO, Energy ONEC.1 Ext.2725 P. RUGUMIRE, Transport Engineer OICT.1 Ext.3803
AFRICAN DEVELOPMENT FUND
TABLE OF CONTENTS
I. STRATEGIC THRUST AND RATIONALE ........................................................................................ 1
1.1 Project Linkages with Country Strategy and Objectives ............................................................... 1 1.2 Rationale for Bank Involvement ................................................................................................... 2 1.3 Donor Coordination ....................................................................................................................... 2
II. PROJECT DESCRIPTION ............................................................................................................... 3 2.1 Project Components ...................................................................................................................... 3 2.2 Technical Solutions Retained and Other Alternatives Explored ................................................... 4 2.3 Project Type .................................................................................................................................. 4 2.4 Project Cost and Financing ............................................................................................................ 4 2.5 Project Area and Beneficiaries ...................................................................................................... 6 2.6 Participatory Process for Project Identification, Design and Implementation .............................. 7 2.7 Bank Group Experience and Lessons in Project Design ............................................................... 7 2.8 Key Performance Indicators .......................................................................................................... 7
III. PROJECT FEASIBILITY ................................................................................................................. 8 3.1 Economic and Financial Performance ........................................................................................... 8 3.2 Environmental and Social Impact ................................................................................................. 8
IV. PROJECT IMPLEMENTATION AND MONITORING/EVALUATION .................................... 12 4.1 Implementation Arrangements .................................................................................................... 12 4.2 Monitoring/Evaluation ................................................................................................................ 14 4.3 Governance .................................................................................................................................. 14 4.4 Sustainability ............................................................................................................................... 15 4.5 Project Management .................................................................................................................... 16 4.6 Knowledge Building .................................................................................................................... 16
V. LEGAL FRAMEWORK ................................................................................................................. 16 5.1 Financing Instrument ................................................................................................................... 16 5.2 Conditions Associated with ADF Intervention ........................................................................... 16 5.3 Compliance with Bank Policies................................................................................................... 17
VI. CONCLUSIONS AND RECOMMENDATIONS .......................................................................... 17 6.1 Conclusions ................................................................................................................................. 17 6.2 Recommendations ....................................................................................................................... 17
Major Related Projects Financed by the Bank Group and Other Development Partners in Burundi 1
i
CURRENCY EQUIVALENTS
[July 2010]
UA 1 = BIF 1813.57
UA 1 = EUR 1.20520
EUROS UA 1 = USD 1.47890
FISCAL YEAR
1 July - 30 June
WEIGHTS AND MEASURES
1 kilogramme (kg) = 2.200 pounds (lbs)
1 metre (m) = 3.28 feet (ft)
1 kilometre (km) = 0.621 mile
1 square kilometre (km2) = 0.3861 sq mile
1 hectare (ha) = 2.471 acres
ACRONYMS AND ABBREVIATIONS
AADT Average Annual Daily Traffic
ABEDA Arab Bank for Economic Development in Africa
ADF African Development Fund
BIF Burundian Franc
EAC East Africa Community
EDF European Development Fund
EIRR Economic Internal Rate of Return
HDM Highway Design and Maintenance Model
IDA International Development Association
MF Ministry of Finance
MTPE Ministry of Public Works and Equipment
NEPAD New Partnership for Africa’s Development
NPV Net Present Value
NRF National Road Fund
ODR Roads Authority (Burundi)
PIA Project Impact Area
PAP Priority Action Programme
PDSR Road Sector Development Project (Burundi)
PIMU Project Implementation Monitoring Unit
PRGSF Poverty Reduction and Growth Strategy Framework
STAP Short Term Acton Plan on Infrastructures (NEPAD)
Veh/d Vehicles Per Day
ii
LIST OF ANNEXES
No. of
No. TITLE Pages
Appendices
I. Comparative Socio-economic Indicators of Burundi 1
II. Table of Bank Portfolio in Burundi 1
III. Major Related Projects Financed by the Bank Group and Other
Development Partners in Burundi 1
IV. Road Network Map of Project Area 1
LIST OF TABLES
No. TITLE Page
Table 2.1: Summary of Project Components………………… 3
Table 2.2: Technical Solutions Retained and Alternatives Explored 4
Table 2.3: Summary of Project Cost Estimates by Component …………………….……... 5
Table 2.4: Summary of Project Cost Estimates by Expenditure Category ……………… 5
Table 2.5: Project Source of Financing………… 6
Table 2.6: Schedule of Expenditure by Source of Financing……………………………… 6
Table 3.1: Summary of Economic Analysis…… 8
Table 4.1: Monitoring/Evaluation Schedule… 15
iii
1. Client Information
COUNTRY : Burundi
PROJECT NAME : Gitega-Nyangungu-Ngozi Road Development and
Asphalting Phase 1: Nyangungu-Ngozi Section
LOCATION Gitega, Ngozi, Kanyaza and Karuzi Provinces
DONEE : Republic of Burundi
EXECUTING AGENCIES : Ministry of Infrastructure and Public Works (METP) /
Roads Authority / Road Projects Implementation
Monitoring Unit (PIMU); B.P. 1860 BUJUMBURA,
(Burundi), Fax: (257) 25 36 95; Telephone: (257) 22 29 40
/ 22 09 59; E-mail: [email protected] .
2. Financing Plan
Source
Amount net-of-taxes (in
UA Million) Instrument
ADF Grant (from “Fragile States Facility” FSF
Pillar I) 24.1
Grant (project)
GOVERNMENT 0.155
Capital Budget (Counterpart
Fund)
TOTAL 24.255
3. ADF Grant Key Financing Information
Grant Currency Unit of Account (UA)
Interest Type N/A
Interest Rate Spread N/A
Service Fee N/A
Commitment Fee N/A
Other Fees N/A
Loan Tenor N/A
Grace Period N/A
FIRR, NPV (baseline scenario) N/A (project road is managed by the Administration, its use will not
generate direct operating income)
EIRR, NPV (baseline scenario) 14.9% and USD 3.5 Million
4. Timeframe – Main Milestones (Expected)
Activities (Month, Year)
Concept Note Approval July 2010
Project Approval September 2010
Signing of Grant Protocol of Agreement / Effectiveness (latest) December 2010
Project Completion October 2012
Last Disbursement of ADF Grant July 2013
iv
BURUNDI: GITEGA-NYANGUNGU-NGOZI ROAD PROJECT PHASE 1
RESULT-BASED LOGICAL FRAMEWORK
HIERARCHY OF OBJECTIVES EXPECTED
RESULTS
REACH PERFORMANCE
INDICATORS
INDICATIVE TARGETS
AND TIMEFRAMES ASSUMPTIONS /RISKS
Goal (Overall objective to which project must contribute)
Contribute to opening up rural areas and increasing sub-regional trade
Impacts (Long-term result(s) or logical
consequence of
project impacts)
(i) Opening up of rural
areas; (ii) sub-regional trade facilitated and
enhanced
Beneficiaries (Population
reaping benefit
directly and indirectly from
project)
Burundi
Impact Indicators (Evidence of achievement of results –Source
and method)
(i)Length of priority roads
developed;
(ii)growth rate of sub-regional
trade by road
Source: Ministry of Public
Works and Infrastructure
(MTPE), Ministry of Trade; Methods: national economic
and transport statistics
Progress Anticipated in the Long Term
(i).Between 2010 and 2020, the length of the paved
national roads increases
from 1 230km to 1 950 km; (ii) increase in sub-
regional trade by about
10% starting from 2013
Source: MTPE and Ministry
of Trade; Methods: national economic and transport
statistics
Assumption Statement (Risk factors and critical conditions of success Mitigation strategy(s)
Risks: (i) Delay in country’s stabilization process; (ii) lack of mobilization of financing and necessary reforms for financing sector
investments
Mitigative measures: (i) country reconciliation and the security policy
initiated in recent years as well as the ongoing democratization process
are likely to strengthen peace and stability in the country; and (ii) the return of donors since 2004 would likely speed up and attract the
necessary funding, given the expected political stability.
v
Project Purpose (Changes pursued or expected through project implementation)
Facilitate the movement of people and goods along the Gitega-Nyangungu-Ngozi
Road and improve the population’s access
to basic services.
Outcomes (medium-term results, i.e.
logical consequence
of project outputs) (i) Movement of
people and goods on
the Gitega- Nyangungu-Ngozi
road improved; (ii)
improved access to communities within
the project area
Beneficiaries (target group(s)-
benefiting from
project outcomes) Burundi
Outcome Indicators (Target group(s) benefiting from
project outputs)
1.(i) average traffic speed
between Gitega and
Ngozi; and (ii) general reduction of transportation
costs on the Gitega-Ngozi
road
2.Number of persons located at
less than 2 km of walking distance from an all-season
motorable road
Source: MTPE
Methods: national statistics,
socio-economic surveys
Progress anticipated in the medium term
By 2014: (i) average traffic speed between Gitega and
Ngozi increases from
20km/h in 2010 to 60 km/h; (ii) vehicle operating costs
decreases by an average of
25% over the life span of the road, and average travel time
on the road reduces from 4
hours in 2010 to 1 hour 30 minutes by 2014
2. The population of the
project area located at less than 2 km of walking
distance from an all-season
motorable increases from 15% in 2010 to 60% in 2014
Sources :(MTPE); Method: national statistics
Assumption Statement ( Risk factors and critical conditions of success
Mitigation strategy(s))
Risks (i) Lack of road maintenance due to insufficient resources; and (ii)
weak capacity of local SMEs to undertake maintenance works
Mitigative measures: (i) Mobilization of supplementary sources such as
tolls to replenish the already established Road Fund; and (ii) financing
of a diagnostic study on Burundi’s road construction industry leading to a support project on the training of SMEs and a reform of the road
maintenance works contracting method.
vi
Inputs and Activities (financial and human
resources for carrying out activities for the
production of an output)
1. (i) Nyangungu-Ngozi road section development
and asphalting; (ii) control and supervision of road works of the said section; (iii) raising the
awareness of the population on environmental
protection, STIs, including HIV//AIDS and road safety on the entire Gitega -Nyangungu -
Ngozi road (cost, net of taxes and customs duty
= UA 21.347M)
2. Construction of related facilities and amenities, including control and supervision of such
facilities (cost, net of taxes and customs duty =
UA 2.651 M)
3. Annual auditing of project and
monitoring/evaluation of project impacts; support to project management (cost, net of
taxes and customs duty = UA 0.257 M)
PROJECT COST, net of taxes and customs duty, including physical contingencies and price
escalation = UA 24.255 M
Outputs (Short-
term results)
1. Nyangungu-
Ngozi road
paved
2- Connecting
feeder roads developed;
health education
centres along the road
provided with sanitation
facilities/protect
ed
3. Population in
within the PIA sensitized on
road safety,
environmental protection and
STIs, including
HIV-AIDS
4- Temporary
employment created through
works execution
Beneficiaries
(target
group(s)-benefiting from
project outputs)
PIA : Gitega,
Ngozi, Karuzi
and Kayanza Provinces)
about 775,000
inhabitants
Output Indicators (evidence
showing that outputs have been
achieved -Source and method)
1. (i) Length of paved road;
and (ii) number of persons sensitized about road
safety, environmental
protection and STI-AIDS
2. Length of feeder roads and
number of socio-economic infrastructure
developed/protected
3.Number of jobs created
through execution of works
4. (i) Number of audit reports
produced and validated; and (ii)project impact
monitoring/evaluation
reports produced and validated
Source: MTPE Methods: reports from central
and decentralized departments
Progress anticipated in the
short term
1 – (i) 30 km of paved road
between Nyangungu and
Ngozi; and (ii) about 100,000 persons sensitized
2. (i) 80 km of connecting feeder roads developed; (ii)
Rehabilitation of 2 markets
(Nyangungu and Gitaramuka); and (iii) 2
health centres - in Busarira and Mubuga – and 5
schools (Busarira, Gitamo,
Ruhororo, Mugomera and Mubuga) fenced,, provided
with washrooms and
latrines as well as drinking water standpipes; (iv) 10
rice hullers operational and
farm implements supplied to women’s associations;
3. 500 temporary jobs created, including 300
local workers employed
4. (i) 3 project accounts audit
reports produced; and (ii) 3
project impact monitoring evaluation reports
produced.
Source : MTPE; Methods: Quarterly progress
reports and project final
activity report
Assumption Statement ( Risk factors and critical conditions of
success
Mitigation strategy(s)
Risks: (i) Financing gap due to weak competition; (ii) lack of
security in the area during the works implementation phase; and (iii) capacity of the executing agency
Mitigative measures: (i) inclusion of this factor in the project cost (provision for price escalation), drawing from the experience
of ongoing projects, and use of Advanced Action on Procurement
which will likely win the participation of contractors currently undertaking works in Burundi and Rwanda in the competitive
bidding process; and (ii) as with other projects currently financed by the Bank, the Authorities will dispatch security forces to the
area in order to bolster security; and (iii) capacity building with
technical assistance, training and computer hardware provided under ongoing projects financed by the Bank.
viii
EXECUTIVE SUMMARY
Project Overview
1. To implement its economic development and poverty reduction strategy, Burundi has
defined a programme for improving the road network that supports the productive sectors. The
Gitega-Nyangungu-Ngozi earth road, the subject of this project, falls under the said programme.
This classified road, which forms part of Burundi’s primary network, connects the country’s
second and third largest cities and constitutes a key link in the development of trade between the
north and south. The location of Ngozi near the border is also an asset for trade with Rwanda.
The service level of various road sections varies significantly (from average to seriously
degraded). In view of the financial resources available, the Bank and the Government have
agreed to implement the works in phases. The first phase concerns the Nyangungu-Ngozi Section
which is the most degraded portion and whose year-round accessibility is not assured. The
project comprises: (A) the development and asphalting of the Ngozi-Nyangungu Section (30 km);
(B) associated structures, including the rehabilitation of 80 km of feeder roads, the development
of socio-economic and market amenities; and (C) support to project management and monitoring.
The implementation of project activities will run from September 2010 to July 2013. The total
project cost, excluding taxes and customs duty, is estimated at UA 24.255 million.
2. The Project Impact Area (PIA) has an estimated population of 775,000 inhabitants,
representing 10% of the country’s total population. The PIA also has a population density of
nearly 450 inhabitants/km² - which outstrips by almost half the already high average national
density (310 inhab./km²). This project is expected to contribute to the development of trade
between the north and south of the country, as well as with neighbouring Rwanda. Specifically,
the project aims to facilitate the movement of people and goods along the Gitega-Nyangungu-
Ngozi Road and improve the living conditions of the communities within the PIA.
Needs Assessment
3. Investment needs under this project result from the current difficult traffic situation on
the road which serves a large population. Given the state of the road, it is necessary to adapt it to
meet demand needs in order to guarantee quality service. The project design is based on the
update of the detailed studies conducted in 2009, which also recommended the need to undertake
the proposed investments. In addition to its contribution to opening up the regions along the road
and sub-regional trade, project implementation will have a significant reducer effect on poverty
(very high in Burundi at 70%). Indeed, it will improve the service level of the road while
ensuring access by the population to the farm production areas within the PIA and marketing of
such production on provincial and district supply markets.
Bank Value Added
4. Infrastructure development is one of the objectives under the Government’s Poverty
Reduction Strategy. With this project, the Bank will contribute to implementing the country’s
Priority Investment Programme and attaining the infrastructure development objective. The
project will contribute to implementing the Infrastructure Action Plan funded by the Bank and
strengthen the execution of the two previous operations that the Institution is financing in the
same sector.
ix
Knowledge Management
5. The project design drew on the achievements of similar road projects. Technical skills
obtained by the Implementation Unit (notably in procurement and management procedures) in
previous and ongoing road projects financed by the Bank and other donors will be put to good
use when implementing this project. The project monitoring/evaluation mechanism will also help
to build knowledge that will be used to design future projects.
REPORT AND RECOMMENDATION OF ADB GROUP MANAGEMENT TO THE BOARD
OF DIRECTORS CONCERNING A GRANT TO THE REPUBLIC OF BURUNDI
FOR THE GITEGA-NYANGUNGU-NGOZI ROAD PROJECT PHASE 1
Management submits the following report and recommendation for the award of a
UA 24.10 million grant to the Republic of Burundi to contribute to financing the Gitega-
Nyangungu-Ngozi Road Project Phase I: Nyangungu-Ngozi Section.
I. STRATEGIC THRUST AND RATIONALE
1.1 Project Linkages with Country Strategy and Objectives
1.1.1 The Poverty Reduction Strategy Framework (PRSF) (2007-2010) constitutes the
reference document of cooperation with development partners. It entails four (4) strategic
thrusts: (i) improving governance and security; (ii) promoting sustainable and equitable
economic growth, notably through infrastructure development in support of production; (iii)
human capital development; and (iv) the fight against HIV-AIDS. In 2006, the Government
adopted a Priority Action Programme (PAP) for the same period to make the PRSF more
operational and better measure the impact of poverty reduction actions. The Bank’s assistance
strategy for the 2008-2011 period is mainly geared towards strengthening good governance
and infrastructure development.
1.1.2 As part of implementing this strategy, Burundi has defined a programme to improve
its road network, which provides support to the productive sectors. The development and
asphalting of the Gitega-Nyangungu-Ngozi National Road that forms part of the classified
network, is included in the programme. It connects the country’s second and third cities and
constitutes a key link for the development of trade between the north and the south. The
location of Ngozi close to the border is also an asset for the development of trade with
Rwanda.
1.1.3 Covering 80 km, the service level on the project road varies significantly. The project
has been divided into the following three lots based on the road sections: (i) Lot 1: Kitega-
Bugendana section (25 km) currently in fair condition; (ii) Lot 2: Bugendana-Yangungu
section (25 km) currently in average condition; and (iii) Lot 3: Yangungu-Ngozi section (30
km) currently in an advanced state of degradation. In view of the available financial
resources, the Bank and the Government have agreed to implement the works in phases. The
first phase of the project relates to the Nyangungu-Ngozi section which is the most degraded
and whose year-round access cannot be guaranteed. The project is consistent with the
objectives pursued by Burundi’s Poverty Reduction Strategy, the Bank’s Intervention Strategy
and the Country Strategy Paper (CSP) for the 2008-2011 period (Pillar 2), as well as the
Infrastructure Action Plan for Burundi financed by the Bank. This plan proposes an integrated
framework for assessing the country’s infrastructure and investments needs and their
attendant maintenance costs, in addition to the human and institutional capacity required to
design such a programme and ensure its successful implementation. It puts forward, for the
benefit of the Government, the donor community and the private sector, a detailed assessment
of infrastructure investment opportunities available in the country and the region. It defines an
action plan for harnessing these opportunities and, consequently, makes up for the lack of
master plans for managing the expansion of the electricity, transport and communications
sectors. In the road sector, the plan aims to rehabilitate and pave the national road network (1
950 km) by 2020.
2
1.2 Rationale for Bank Involvement
1.2.1 A landlocked country located far from sea ports, Burundi underwent a period of
political instability that resulted in the deterioration of its infrastructure and maintenance
backlog. This situation constitutes a major drawback for opening up the country whose
population density (305 inhabitants/km) is among the highest in the world. The road project is
in line with the priorities set out in the country’s Poverty Reduction Strategy Paper (PRSP).
The PRSP underscores road infrastructure development as a contribution to opening up the
rural areas and improving access to basic social services and regional integration. The Bank’s
involvement in the project is part of financial assistance towards implementing the Priority
Road Network Improvement Programme to support the productive sectors by ensuring
continuous traffic flow. Specifically, the Bank’s involvement is also in pursuit of its support
for the rehabilitation of this road network.
1.2.2 Road transport in Burundi constitutes the main means of transporting people and
goods, and spans the breadth of the agricultural and industrial production spectrum (i.e.
upstream and downstream). An estimated 90% of domestic passenger and goods transport is
by road. This makes it the dominant mode of transport.
1.2.3 In Burundi, the promotion of economic growth for poverty reduction will be
achieved mainly through rural and agricultural development. Indeed, the share of the primary
sector ranges between 50 and 55 % of GDP, depending on the year. Sector programmes
cannot be successfully implemented without the existence of road infrastructure to move
people and goods. This is particularly so with regard to the supply of agricultural inputs to the
rural world and the haulage of agricultural production to consumption centres.
1.3 Donor Coordination
Sector Importance
in % of GDP in % of Exports in % of Labour
Years 2001-2006 2005-2009 2005-2009
Burundi Transport and
Communications Sector 4.1 N/A N/A
Stakeholders – Annual Public Expenditures of the Transport Sector in BURUNDI
(Averages in BIF Million)
Donors (ADF, IDA, EDF, China,
Arab Fund etc.)
Year Total Gov.
2000 to 2003
In BIF M 2490 1360 1130
In % 100% 55% 45%
2004
In BIF M 4040 670 3370
In % 100% 17% 83%
2005 In BIF M 4650 750 3900
In % 100% 16% 84%
2006
In BIF M 5330 560 4770
In % 100% 11% 89%
Level of aid coordination in Burundi
Existence of Thematic Working Groups
Existence of a General Sector Programme
ADB’s role in aid coordination
Yes
Yes
Member
3
Aid coordination in Burundi is the responsibility of a National Aid Coordination Unit, chaired
by the second Vice-President. The various development partners and the Government
maintain constant dialogue. The Bank is a stakeholder in this endeavour and shares
information within that framework. Within the context of road projects, this dialogue has
allowed for the establishment of synergy in co-financing and complementarity. With specific
regard to the project under consideration, consultations were held between the Bank and the
major road sub-sector donors (the World Bank and the European Union). These donors all
emphasized the strong complementarity of actions proposed by the Bank and expressed their
support to the project. Lastly, during the project implementation phase, meetings coordinated
by the METP will be held with these development partners.
II. PROJECT DESCRIPTION
2.1 Project Components
The project components are summarized in Table 2.1 below:
Table 2.1
Summary of Project Components
NO. Component
Estimated Cost (net of taxes
and customs duty) (UA
Million) Description of Components
A Road Works 21.347
A.1 Development and asphalting of the Nyangungu –
Ngozi Section: ADF Financing
A.2 (i) Works control and supervision. (ii) sensitization
of the project impact area population on: road
safety, environmental protection and control of
sexually transmitted infections (STIs) including
HIV/AIDS: ADF Financing
B Associated Developments 2.651
B.1 (i) Rehabilitation of 80 km of connecting feeder
roads; (ii) protection/provision of sanitation
facilities to 8 social amenities (surrounding
education and health centres); (iii) development of
two rural markets; (iv) construction of footbridges;
and (iv) support to women’s groups through the
supply of rice hulling machines and farm
implements: ADF Financing
B.2 Control and supervision of associated works: ADF
Financing
C
Support to Project
Management and
Monitoring
0.257
C.1 Auditing of project accounts: ADF financing
C.2 Project monitoring/evaluation: ADF financing
C.3 Operation of the Project Implementation Monitoring
Unit (PIMU): Financing: Government
4
2.2 Technical Solutions Retained and Other Alternatives Explored
2.2.1 The engineering/economic feasibility studies and the preliminary designs were
examined to ensure the viability of the works to be carried out. The technical design is in line
with recognized international standards. Overall, the geometric trace of the current road has
been preserved, albeit improved at specific points to bring it in line with safety standards in
light of the mountainous nature of the project area. The solution retained will consist of a
roadbed for the development of a 6 metre-wide running strip and two shoulders of 1.25 metres
each.
2.2.2 Based on the class of traffic and type of supporting soil of the road indicated in the
engineering studies, the structure of the road will consist of: (i) an average 30 centimetre-thick
lateritic gravel sub-grade; (ii) a 15 centimetre-thick road base also in lateritic gravel; and (iii)
surfacing of the entire road with a 5 centimetre-thick bituminous concrete (BC) layer. This
road structure takes into account the nature of the various structures of the supporting soil.
The shoulders will entail a single layer surface dressing.
2.2.3 The alternative technical solutions explored and the reasons for their rejection are
summarized in Table 2.2 below.
Table 2.2
Technical Solutions Explored and Rejected
Alternatives Brief Description Reason for Rejection
Solution 1:
The road base is
composed of crushed
gravel.
This is not very different from the one
retained, except that the road base will
consist of crushed gravel instead of
lateritic gravel.
High cost essentially due to the
preparation and transportation of
the materials over a long
distance.
Solution 2:
The road base is
composed of coarse
aggregate bitumen.
This solution differs from the one
retained. The road base will consist of
aggregate bitumen instead of lateritic
gravel.
Very high cost due to the
preparation and transportation of
the materials over a long
distance, and the cost of bitumen.
2.3 Project Type
Burundi is eligible solely for ADF grants. The financing instrument used for this project is the
“Project Grant” type. Indeed, there is no budgetary support mechanism in Burundi for
transport infrastructure projects.
2.4 Project Cost and Financing
Cost Estimate
2.4.1 Phase 1 of the project is estimated to cost UA 24.255 million, net of taxes and
customs duty, of which UA 18.885 million in foreign exchange and UA 5.370 million in local
currency. The estimated cost of compensations for land expropriation not included in the cost
of the project to be borne by the Government amounts to UA 0.034 million. The unit costs of
works were based on: (i) the project design finalized in 2009; (ii) the unit costs stemming
5
from bids received in 2010 for similar road works conducted in the country and financed by
the ADF and other donors; (iii) programming of works procurement scheduled for 2010; and
(iv) execution of works scheduled for the 2011-2012 period. In estimating the costs, account
was taken of the recommendations of the study on increase of the unit cost of road networks
conducted by the Bank, details of which are specified as Annex B: (i) recourse to Advanced
Action on Procurement for the procurement of goods, works and services; (iii) inclusion of
the provision for fluctuations between the UA and the local currency, as well as the
probability of the prices of some inputs escalating. Provision for physical contingencies is
maintained at 10% of the base cost. Provision for price escalation represents 4.37% of the
base cost and the physical contingencies. Details on Phase 1 cost estimates are given in Annex
A1. The costs are summarized in Table 2.3 below:
Table 2.3
Summary of Project Cost Estimate by Component (Phase 1)
Component USD Million UA Million
F.E. L.C Total F.E. L.C. Total
A. Road Works 25.563 6.165 28.728 14.603 3.990 18.593
B. Associated
Developments 2.792 0.776 3.568 1.807 0.502 2.309
C. Project
Management 0.060 0.286 0.346 0.039 0.185 0.224
Base Cost 25.415 7.227 32.642 16.449 4.677 21.127
Physical Contingencies 2.542 0.723 3.264 1.645 0.468 2.113
Price Escalation 1.222 0.347 1.569 0.791 0.225 1.015
Total 29.179 8.297 37.475 18.885 5.370 24.255
2.4.2 The project cost by expenditure category is given as Annex A2 and summarized in
Table 2.4 below: Table 2.4
Summary of Project Cost by Expenditure Category
Expenditure Category
USD Million UA Million
F.E. L.C Total F.E. L.C. Total
A – Goods 0.014 0.089 0.102 0.009 0.057 0.066
B – Works 24.281 6.042 30.323 15.715 3.911 19.626
C – Consultancy Services 1.121 0.887 2.009 0.726 0.574 1.300
D – Miscellaneous - 0.208 0.208 - 0.135 0.135
Base Cost 25.415 7.227 32.642 16.449 4.677 21.127
Physical Contingencies 2.542 0.723 3.264 1.645 0.468 2.113
Price Escalation 1.222 0.347 1.569 0.791 0.225 1.015
Total 29.179 8.297 37.475 18.885 5.370 24.255
Financing Arrangement
2.4.2 The project will be financed by the ADF and the Government. The ADF grant
amounting to UA 24.10 million represents 99.37% of the project cost, excluding taxes and
customs duty. This grant will be used to finance: (i) the entire cost of works of the Yangusi-
Ngonzo section and associated developments; and (ii) the entire cost of services for works
control and supervision, sensitization of the population, monitoring/evaluation of project
impacts and auditing of project accounts. The sources of financing by expenditure category
and the expenditure schedule by component are given as Annexes A3 and A4.
6
2.4.3 Government’s contribution (0.63% of the project cost, net of taxes and customs
duty), will be used to finance the cost of operation of the Project Implementation Monitoring
Unit (PIMU). Burundi is eligible for 100% financing in accordance with the current Bank
policy on expenditure eligible for financing. However, the counterpart funding will essentially
cover the travel expenses and allowances for PIMU staff. These expenditures are not eligible
under this policy. The project sources of financing are presented in Table 2.5 below.
Table 2.5
Source of Financing of Project Components (in UA million) Source of Financing Amount %
ADF 24.100 99.36%
Government 0.155 0.63%
Total 24.255 100.00%
Expenditure Schedule
2.4.4 The expenditure schedule by source of financing is summarized in Table 2.6 below.
The expenditure schedule by project component is given as Annex A4.
Table 2.6
Expenditure Schedule by Source of Financing (UA million)
Source of Finance 2010 2011 2012 2013
ADF 0.019 17.900 6.159 0.022
Government 0.021 0.096 0.038 -
Total 0.040 17.996 6.197 0.022
% 0.2% 74.2% 25.5% 0.1%
2.5 Project Area and Beneficiaries
2.5.1 The direct Project Impact Area (PIA) comprises 10 communes in the Gitega, Ngozi,
Karuzi and Kayanza provinces. The impact area covers a total 1887 km² with an estimated
population of 775,000 representing 10% of Burundi’s total population. The PIA also has a
population density of nearly 450 inhabitants/km² - which outstrips by nearly half the country’s
already high average density (310 inhabitants/km²). In addition, the area hosts Burundi’s
second and third largest cities (Gitega and Ngozi) and constitutes a key national socio-
economic development pole. Indeed, many decentralized administrative structures and a large
number of schools and tertiary institutions are located in Gitega and Ngozi provinces.
2.5.2 The project beneficiaries will be the road users, rural communities (farmers and
stockbreeders) and traders. The results expected by the beneficiaries are an improved
movement of people and goods, reduction of the general transportation cost and improved
access to basic social services. The economy of the PIA essentially comprises agricultural
activities, coffee and beer industries, and trading. Agricultural activities occupy about 90% of
the working population, generating an estimated annual production of 810,000 tonnes
including 45% of marketable surpluses. Tourism constitutes an undeveloped potential that
could be harnessed, thanks to the project
7
2.6 Participatory Process for Project Identification, Design and Implementation
2.6.1 The participatory approach involving the beneficiaries was used at all stages of the
project. It is worth noting that during project preparation and appraisal, contacts, meetings for
information, gathering of the views and concerns of the beneficiaries took place in the project
area, together with regional and local officials, transport professionals, traders, civil society,
women’s organizations and environmental protection organizations. These meetings were
complemented with socio-economic surveys conducted among sector and village heads. The
overall opinion on the project was favourable. Furthermore, these communities requested: (i)
the rehabilitation of feeder roads connecting the main road and providing access to farming
areas and produce markets; (ii) protection/sanitation facilities for education and health centres
along the road (sanitation via the construction of latrines); (iii) development of two rural
markets; and (iv) support to three women’s cooperatives by providing them with rice hulling
machines and farm implements. The choice of associated priority activities was made in
consultation with these communities. Based on the discussions held, feeder roads linking the
main road were chosen in consultation with the stakeholders. The participatory approach will
also be pursued throughout the project implementation phase, notably during site coordination
and when establishing the baseline scenario for impact monitoring to ensure project
ownership by the beneficiaries.
2.7 Bank Group Experience and Lessons in Project Design
2.7.1 The Bank has financed similar operations in the road sub-sector. The implementation
of these projects has helped it to acquire relevant experiences and draw a few lessons. The
project design took into account lessons drawn from the Bank’s experience in Burundi
notably: (i) the importance to have various stakeholders buy into the project design through
the participatory approach; (ii) the need to have quality engineering design that improves the
technical design of works; (iii) recourse to Advanced Action on Procurement (AAP)
procedure to accelerate project implementation; (iv) enhanced supervision of projects by the
Bank (at least twice annually); (v) development of performance indicators in project
monitoring; and (iv) the need to build the technical and operational capacity of executing
agencies. The project design also tapped from lessons learnt based on challenges encountered
during the implementation of various similar road projects in the country, notably the impact
of works cost increases that delay work start-up. The cost estimate specifically factors in the
procurement, start- up and works execution period.
2.8 Key Performance Indicators
2.8.1 The key indicators identified are those provided in the logical framework together
with their deadlines. These are: (i) the rate of increase of traffic speed between Gitega and
Ngozi; (ii) the rate of reduction of the overall transportation cost (vehicle operating cost
reduced by 25% on average and travel time reduced by 60%) on the project road; (iii) increase
in the volume of sub-regional trade by about 10%; (iv) better access to basic social services,
production and marketing centres for an estimated 0.775 million inhabitants served by the
road and feeder roads, 52% of which women.
8
2.8.2 Apart from these output indicators, implementation performance indicators will be
established and monitored, mainly: (i) the time it takes to fulfil conditions precedent to first
disbursement of the grant; (ii) the procurement timeframe; (iii) the project implementation
timeframe; and (iv) disbursement rates in relation to the expenditure schedule.
2.8.3 The lack of a functional monitoring/evaluation system right from the start of project
activities often accounts for the subsequent challenges encountered in assessing the level of
achievement of development objectives retained in the results matrix. Therefore, a
monitoring/evaluation mechanism will be put in place for this project: (i) to build and manage
information on the execution of various project components; (ii) establish the baseline
scenario for road impact monitoring; and (iii) at the end of the project, undertake an impact
assessment using the same methodology that was used to establish the baseline scenario. The
University of Ngozi will conduct the project monitoring/evaluation.
III. PROJECT FEASIBILITY
3.1 Economic and Financial Performance
The economic analysis was carried out using the HDM4 model, based on a cost-benefit
analysis between the “without” and “with” project situations over a 20-year period, starting
from road commissioning. A 12% discount rate and an average residual value of 47% were
assumed, depending on the road sections (resulting from the significant share of earthworks in
the project cost). The data considered are: (i) the investment costs, net of taxes, related to the
control and monitoring of works and physical contingencies; and (ii) the maintenance cost of
road sections and vehicle operating cost (VOC). The total reference AADT in 2009 on the
entire route was 84 vehicle days (arithmetic average of the AADTs by homogenous traffic
section). The quantifiable economic benefits relate to the general transport cost reduction
(VOC reduced by 25% on average and travel time reduced by about 40%). The cost of the
feeder roads as well as the agricultural value added were considered as exogenous costs and
benefits in the model. Table 3.1 below provides a summary of the economic analysis, details
of which are given as Annex A5.
Table 3.1
Summary of Economic Analysis
Financial Internal Rate of Return (FIRR) in % Not Applicable
Economic Internal Rate of Return (EIRR) of the Nyangungu-Ngozi Section Project in % 14.9%
Net Present Value (NPV) in USD million 3.5
Sensitivity of ERR (Combination of 10% increase in the costs and 10% decrease in benefits) 12.5%
Discount Rate 12%
3.2 Environmental and Social Impact
Environment
3.2.1 The project was subjected to in-depth environmental studies. Based on the findings
which were validated by the relevant authorities, the project was classified under
Environmental Category 2. This categorization was endorsed by the Bank on 21 May 2010.
Furthermore, an Environmental and Social Management Plan (ESMP) was prepared and the
summary published on 29 July 2010 on the Bank’s website in accordance with current
procedures.
9
Positive Impacts
3.2.2 The main project impact is the opening up of an estimated 10 districts (“communes”)
that currently lack adequate access to local markets and basic social services. The other
beneficial impacts will mainly be socio-economic, such as skilled and unskilled employment
opportunities (see paragraph 3.2.11), and some formal/informal trading activities (sale of
agricultural and artisanal products, opening of restaurants, etc.).
Negative Impacts
3.2.3 With regard to negative impacts, those identified are as follows: (i) dust emission,
noise pollution, (noise, vibration of site machinery); (ii) safety problems during works and
setting up of site equipment and materials; (iii) accidental spillage, fuel and lubricant leakage;
(iv) felling of roadside trees during the road right-of-way demarcation phase; and (v)
degradation of borrow areas, risk of the spread of STI/HIV/AIDS and change of moral
standards. Furthermore, during works, the disorderly disposal of solid and liquid waste from
the sites (rubble, various residues, etc.) could affect the quality of the natural environment,
especially near living areas. These disposal points could become unsightly dumpsites.
3.2.4 Mitigative measures will be taken for all the negative impacts identified, namely: (a)
the bidding documents will include environmental provisions relating to waste storage areas
identified by type: (i) area reserved for the storage of possibly contaminated/polluted earth,
protected area fitted with water-tight recipients for the recovery of waste oil; (ii) areas
intended for the storage or handling of hazardous, toxic, inflammable or polluting products
(laboratory reagents, dispensary waste, special products, etc.) and located as far away as
possible from human dwelling in order to protect human health, the soil and the subsoil; (iii)
establishment of a quality assurance scheme and a fire fighting plan, including provisions on
respect for the environment. Contractors will submit proposals on programmes for
implementing environmental and social measures as well as site restoration works backed by
a methodological presentation describing solutions for averting negative impacts and
minimizing inevitable ones; (b) the guarantee provided by the contractors will cover the
environmental and social components. Other measures will be prescribed to the contractors,
namely: (c) management of drainage and run-off; reduction of dust on construction sites;
employment of local workers; implementation of a hygiene, health and safety management
plan including tools with which to manage the project components relating to these three
areas; reuse of onsite digging equipment; recycling of waste. The contractors will observe the
country’s labour laws on the work sites; (d) sensitization of the local population on HIV-
AIDS and other pandemics, road safety and good environmental and social practices as well
as implementation of environmental and social surveillance and monitoring activities. A
detailed environmental and social assessment is given in Annex A6.
Climate Change
3.2.5 Lying across the Kimiriro natural region at an average altitude of 1600 m and the
Buyenzi natural region at an average altitude of 1800 m, the project area has a mean
temperature of 19° C with a minimum of 12.6° C and a maximum of 25° C. It is also
characterized by regular and abundant rains ranging between 1200 and 1500mm. Unusual
climatic conditions may result in severe flooding as well as an increase in temperature that
could exceed the maximum 25° C in normal times. The project design takes into account not
only the current climatologic data but also possible future adverse weather conditions. Thus,
10
emphasis is primarily given to the quality of road materials to be used (rocky and loose
materials, asphalt and adjuvant) and the project’s optimal implementation capacity. To this
end, the research already conducted led to the identification of sites and the determination of
the quality of materials already available there, based on the technical criteria. Using the same
approach, the project technical documents also include details on many appropriate structures
designed to drain abundant water and raise the road above water levels, notably in sensitive
areas. Furthermore, the Bank will select a contractor with solid technical references for the
execution of works as well as proper maintenance of the road and associated structures, in line
with the paved road network maintenance strategy supported by Burundi’s partners, including
the Bank.
3.2.6 Furthermore, with the increase in traffic following the road commissioning,
increased gas emissions with their attendant impact on the ozone layer should be expected. To
mitigate this risk, the project will preserve a significant portion of existing roadside trees. The
proposed felling of other trees is indispensable in order to free the 14 metres of right-of-way
needed for the road. However, this will essentially concern trees on one side of the road only.
Those affected will be replaced with the suitable species to be planted in close collaboration
with the National Water Sources and Forestry Department. Therefore, a long chain of
roadside trees will planted mainly to help reduce the effects of exhaust gas emissions induced
by the project during the operating phase.
Gender
3.2.7 Burundi has made significant progress in promoting women. Constitutional
arrangements guaranteeing that women take up at least 30% of seats in institutions have been
respected, particularly in the composition of the Government, the National Assembly and the
Senate. Furthermore, the percentage of women with access to political and economic
decision-making positions has increased from 11.2% in 2003 to over 20% in 2007. At the
local level, the electoral code, amended in September 2009, introduced for the first time in the
country a minimum 30% quota for women in municipal councils, thereby extending to local
governments a requirement that hitherto had been limited to the national level.
3.2.8 Out of the 775,000 inhabitants of the PIA, 52% (or 403,000) are women. It is
estimated that 95% of working women are in the agricultural sector, which constitutes their
main source of livelihood and the mainstay of the national economy. Thus, each commune
has at least one recognized working women’s association. To alleviate women’s work burden
and improve their production, an additional intervention will be provided under this project in
the form of support to women’s cooperatives concentrating on food and cash crop production
(rice hulling machines and more suitable farm implements).
3.2.9 The role of women in the other economic activity areas such as formal trade and
other informal services is still modest. In the project area, two of the six municipal
administrators are women and they have been discharging their duties to the satisfaction of
the citizens.
Social
3.2.10 The project (main road and associated works) will have direct and indirect impact on
the benchmark socio-economic indicators namely: endemic unemployment, rural income,
access to basic social services and provision of public utilities.
11
Unemployment
3.2.11 In 2008, unemployment affected 14% of the PIA workforce. There has been an
upsurge in demand for employment in the last three years, especially following the return to
the country of population groups displaced during the socio-political crisis (1993-2004). The
project will help to mitigate this soaring unemployment. Indeed according to appraisal
estimates, 500 persons including 350 local workers will have direct and indirect employment
opportunities during the works implementation phase.
Increase in Rural Income
3.2.12 The Burundian crisis also brought down the per capita income from USD 201 in
1990 to USD 110 in 2006. Based on this indicator, the project design also aims to raise the
level of income of the rural population through agricultural value added. This exogenous
benefit is inevitable since 90% of the PIA working population derives its income mainly from
agriculture and a significant portion of the road serves rural areas. The economic assessment
indicates that at least 15% of annual agricultural value added in the area will derive from this
project, equivalent to an annual average of BIF 2.25 billion.
Access to Basic Social Services
3.2.13 The road passes through ten districts (“communes”) with a total population of
775,000. This population, 52% of which women, is mostly located at less than 2 km from the
project road. However, as a result of the road’s advanced state of deterioration, vehicle travel
time from the largest localities to the main market and the main hospital in the project area
varies between 1 hour 30 minutes and 2 hours. In the absence of public transport, the
dominant means of transport are bicycles and motorcycles for moving both people and goods.
The disadvantages of these means of transport include reduced capacity and inability to meet
the needs of people in case of emergency (health evacuation, childbirth, etc.) or during rainy
periods. Thanks to the project, the population of the ten districts along the road will
henceforth be able to reach the socio-economic centres of the PIA in shorter time, estimated at
less than 30 minutes as against 1 hour 30 minutes/2 hours in the “without project” situation.
This social-related time gain is of particular significance in case of health evacuation for
delivery or other public health reasons such as immunization and environmental protection
awareness campaigns, HIV/AIDS and other pandemics (malaria, diarrhoeal diseases, acute
respiratory infections etc.).
Public Utilities Cover
3.2.14 There is an awful lack of public utilities in the PIA (drinking water and sanitation),
particularly in schools and some health centres. This deficit accounts for the numerous cases
of water-borne diseases or diseases related to lack of environmental hygiene, especially for
school goers and staff of unequipped health centres. To remedy this situation, the project will
entail as part of associated works, the construction of drinking water points and latrines for
two health centres and five schools identified to be highly needy. The Government and the
local authorities have also been sensitized about the pressing need to offset the lack of public
utilities in the PIA.
12
Resettlement of Displaced Persons
3.2.15 The Gitega-Nyangogo-Ngozi road exists already. The project will not entail any
change in design or axis plane. Consequently, the project implementation will not result in
any destruction of dwellings. It will entail a single forced displacement of one household (2
persons) within its current geographic space. The other proposed displacement will involve
makeshift structures mainly used as dwellings or for commercial purposes, to be moved a few
metres away from the road right-of-way. This resettlement will require a simple compensatory
procedure by the country to facilitate the reconstruction of such structures, compensation for
farmlands and burrow areas as well as trees to be felled to free the right-of-way. This
compensation should be paid before the start of works. The Government will provide the ADF
with evidence of paying compensation for the expropriation of houses and lands. This will be
a grant condition (Condition Bi).
IV. PROJECT IMPLEMENTATION AND MONITORING/EVALUATION
4.1 Implementation Arrangements
Executing Agency
4.1.1 The Project Executing Agency will be the Ministry of Public Works and
Infrastructure (MPTE) through the Roads Authority (ODR). However, for the day-to-day
monitoring of project activities, the Road Project Implementation Monitoring Unit (PIMU),
established since 2006, will be responsible for monitoring this project. Since its inception, the
PMIU has satisfactorily undertaken the monitoring and management of road operations
financed by the Bank in the country. Placed under the supervision of the MTE ODR, the
PIMU will oversee the project’s technical, administrative, financial, and organizational tasks.
The PIMU currently comprises: (i) two civil engineers in charge of the RN5-Nyamitanga-
Ruhwa Road Rehabilitation Project (a project manager and his assistant); (ii) an engineer in
charge of monitoring the RN14-Kirundo-Gasenyi Road Project; (iii) an accountant for
financial management; (iv) an environmentalist; (v) a specialist of STIs, including HIV/AIDS
and other pandemics; and (vi) administrative support staff. The PIMU staffing has been
consolidated under this project with two civil engineers appointed by the Donee, and an
assistant accountant. The Bank’s current focal point at ODR will maintain daily contact with
the Bank on all projects. The PIMU will benefit from the technical assistance put in place
under the RN5 - Nyamitanga-Ruhwa Rehabilitation financed by the Bank. This technical
assistance is a follow-up to the one financed by the Bank under the Kirundo-Gazeni Project,
which helped to improve the management of projects, the planning/programming of road
operations, the assessment of the socio-economic impacts of road projects and the training of
staff in various areas. An overview of the transport sector of Burundi is given as Annex (A7).
4.1.2 A consulting firm will be recruited for control and supervision of works for the main
road and related developments, and another for sensitization of PIA communities on road
safety, environmental protection and STI control, including HIV-AIDS. The consulting firms
will issue: (i) quarterly works progress reports and; (ii) reports on sensitization seminars. The
University of Ngozi will be hired to prepare the monitoring/evaluation report on project socio-
economic impacts. The specific project implementation arrangements are given as Annex A8.
13
Procurement
4.1.3 By letter dated 21 April 2010, the Bank approved the Government’s request to use
Advanced Action on Procurement for goods, works and services under this project. The
procurement of goods, works and services to be financed with the ADF grant will be based on
the Bank’s rules and procedures for the procurements of goods and works, or rules and
procedures for the use of consultants, as the case may be, based on Bank standard bidding
documents for works and consultancy services. Details on the modalities for the procurement
of works and services financed with the ADF grant and the Contract Award Plan are given as
Annex A9. Works for the construction of two pilot footbridges as part of a sector study
initiated by the OITC Department (Annex A10) will be entrusted to Helvetas Ethiopia, an
NGO.
Disbursement and Financial Management
4.1.4 The direct disbursement method will be used for the works and consultancy services
financed by the ADF. To facilitate the timely mobilization of counterpart funds, the
Government will open a special account bearing the project name in a bank in Burundi
acceptable to the ADF, into which the counterpart funds will be paid. This counterpart
account, which will also cover the operating cost of the PIMU, will be replenished yearly in
accordance with the annual expenditure schedule. Evidence of opening the account and its
regular replenishment by the Donee will be a grant condition (Condition C1). The financial
management will be based on Bank rules and guidelines and executed by the PIMU. In this
regard, the current accountant, who has the necessary qualifications and experience in projects
financed by the Bank, will be responsible for financial and cost accounting, in line with the
norms in force. A computerized accounting system will be put in place from project start up.
Details of the financial management and disbursement arrangements are given as Annex A11
Audit
4.1.5 The project executing agency will keep separate project accounts based on a private-
type computerized system. The accounting system should help to monitor project expenditure
in relation to the estimates, by component, expenditure category and source of financing as
well as prepare financial statements. An external auditing firm will undertake annual auditing
of the project accounts based on the International Federation of Accountants’ ISA standard
and the Bank’s Terms of Reference. The firm will be recruited in line with Bank procedures.
The audit report will be submitted to the Bank within six months following the end of each
accounting period. The detailed audit arrangements are specified as Annex A12.
Implementation and Supervision Schedule
4.1.6 The project implementation schedule by components, summarized at the beginning
of this report, is presented in detail as Annex A13. It takes into account the relevant
experience of the executing agency in managing works execution timeframes and that of the
Bank in dealing with issues in previous similar projects. According to the schedule drawn up,
project activities will begin following grant approval in the third quarter of 2010 and will be
completed by October 2012. The grant closing date is fixed at 31 July 2013. Project activities
will be closely monitored at the Bank in line with the schedule in Table 4.1 below.
14
4.2 Monitoring/Evaluation
4.2.1 Project monitoring/evaluation will consist of internal and external monitoring, launch
and supervision missions by the Bank and a final evaluation, including end-of-works and
project completion reports. Project implementation will entail the preparation of: (i) monthly,
quarterly, final works and sensitization reports by the works control consultant and the
consultant in charge of sensitization, respectively, no later than 15 days after the end of the
month or quarter concerned; (ii) quarterly project progress reports by the project
implementation monitoring unit; (iv) monitoring/evaluation reports on the socio-economic
impacts of the project by the University of Ngozi, which will be responsible for these
services. The University will define the socio-economic impact measures indicators and their
trend, in consultation with the project executing agency.
4.2.2 In conjunction with the University of Ngozi, which will be responsible for
monitoring/evaluation, the PIMU will undertake an assessment of the indicators defined in the
CSP and those in this project (see paragraph 2.8.1). At the end of the project and six months
following the completion of works, the executing agency will organize traffic count on the
road to test the traffic assumptions
Table 4.1
Monitoring/Evaluation Schedule
Period Milestone Monitoring Process /
Feedback Loop
Q3 2010 Works & Services Competitive Bidding AAP
Procedure Launch/ (Bank/ODR)
Q4 – 2010 Completion of Works and Services Procurement Evaluation and approval of works and
services contracts (Bank/ODR)
Q1 – 2011 Project Launch/Start Up Disbursement process and updating of
procurement plan
Q3 – 2011 30% of Works Completed Works monitoring /supervision
(Bank/ODR)
Q3 – 2012 100% of Works Completed Final works completion report (control
mission/ODR)
Q4 – 2012 Project Completion and Preparation of
Completion Report
Joint preparation of the project
completion report
4.3 Governance
4.3.1 The culture of good governance is emerging in Burundi. The rule of law is gradually
gaining ground, albeit with some difficulty. The administration is improving. On the political
front, since 2005 Burundi has made significant strides in the peace consolidation process. This
has been the fruit of the efforts by all national stakeholders, with the support of the
international community. It is in this context that long and difficult negotiations with the last
armed rebel movement, the National Liberation Forces (FNL), culminated in the cessation of
hostilities in the country, the return of security nationwide and the establishment of
progressively inclusive institutions. Other significant achievements have also been noted in
terms of economic and regional integration.
4.3.2 In May 2009, Burundi adopted a Public Finance Management Strategy backed by an
action plan for the 2009-2011 period. The overall objective of this strategy is to set up from
2009 to 2011 a more effective and transparent public finance system. To achieve this overall
objective, six specific objectives have been defined, namely: (i) adopt and implement a
coherent legislative and regulatory framework for public finance management; (ii) effectively
15
mobilize internal and external resources to finance public expenditure, while maintaining
budgetary balance; (iii) adopt an effective, stringent and transparent public resource
management system; (iv) render the auditing system consistent, effective and in line with
international standards; (v) make data on public finances exhaustive, accurate and regular and,
lastly; (vi) gradually strengthen the institutional capacity of the Ministry of Finance and
partner structures to effectively accomplish their mission. Each of these objectives is backed
by specific action plans for implementation.
4.4 Sustainability
4.4.1 Project sustainability depends on the quality of works and adequate operating and
maintenance conditions of the structures to be put in place. The engineering studies identified
quality materials in the project area that will be used. The technical design solution retained is
adequate and will ensure a normal project life span, given the estimated traffic as well as the
topographic and climatic conditions. Maintenance of the road (which forms part of the
classified network) will be included in the country’s annual maintenance programme.
Furthermore, the control of road works (road and associated feeder roads) will be carried out
by a qualified consultant who will ascertain the quality of the structures to be built.
4.4.2 With the capacity of the Roads Authority (ODR) strengthened during project
implementation, it is expected that its operational effectiveness will improve. The Authority’s
performance will be gradually enhanced thanks to the ongoing or expected institutional
support from sector donors. The establishment of a road database, currently in the completion
stage, will enable the ODR to monitor the state of the network, have an appropriate tool for
planning road maintenance and rehabilitation works and better control the costs of
maintenance operations.
4.4.3 The recurrent costs are those of the road and the associated feeder roads. The
relevant recurrent costs of feeder roads will be covered by the National Road Fund (NRF)
which has been operating since 2003. The resources of the NRF derive from road user fees
levied on fuel, road tolls on foreign vehicles, axle load fees, penalties for transport vehicle
overload, compensation for damage caused to the road network, and possible contributions by
the Government as well as grants and contributions from multilateral or bilateral aid
organizations. NRF revenue has multiplied by three and increased from USD 2.3 million in
2005 to USD 7 million in 2009. Major efforts have been made to improve NRF organization
and operation. The Fund has the capacity to finance the entire routine maintenance of the
national road network. In view of the road maintenance backlog due to the war, the
Government still depends on financial support from development partners. Hence, under the
Road Sector Development Project (PDSR), the World Bank is currently providing
institutional and financial support: (i) to the NRF to build its operational capacity and
contribute to financing road network maintenance; and (ii) to SMEs and local technical
consulting firms to strengthen their capacity, with a view to improving the quality of road
maintenance works. Furthermore, the beneficiary communities are involved in road
infrastructure maintenance and protection operations. The ODR has entrusted to Community
Development Associations (ACD)1 manual repair works and monitoring of rights-of-way or
road signs, while creating permanent employment in the rural and urban areas, notably for
female members of the ACDs. Additionally, the ODR will entrust mechanized maintenance to
SMEs in order to stimulate private sector development.
1 This falls within the framework of implementing the PRSF guidelines recommending high labour intensive works and
community involvement. An ACD will undertake spot maintenance and supervision of 10 km of the paved road, 1 km per
member. Each member receives a monthly wage of about BF50,000.
16
4.4.4 The annual routine maintenance cost of the Nyangungu-Ngozi road is estimated at
USD 103,000. The cost of scheduled maintenance of the road (every ten years) is estimated at
USD 2.7 million. For the feeder roads, the annual routine maintenance cost is estimated at
USD 50,700. The scheduled maintenance cost (every 3 years) of the feeder roads is estimated
at USD 3.25 million.
4.5 Project Management
4.5.1 The main risks identified that could impede project implementation are: (i) delay in
the country’s stabilization process; (ii) absence of mobilization of financing and reforms
needed for the funding of investments in the sector; (iii) lack of road maintenance as a result
of inadequate resources; (iv) financing gap due to inadequate competition; and (v) the
executing agency’s inability to adequately monitor project implementation.
4.5.2 The main risks identified will be mitigated by: (i) the reconciliation and territorial
protection policy initiated a few years ago, and the ongoing democratization process that are
likely to consolidate the country’s peace and stability; (ii) the return of donors since 2004
should be strengthened and provide the necessary financing in the wake of the expected
political stability; (iii) mobilization of supplementary sources such as tolls to replenish the
road fund already in place; (iv) use of Advanced Action on Procurement that will likely win
the participation of contractors currently undertaking works in Burundi and Rwanda in the
competitive bidding process; and (iii) capacity-building with the technical assistance, training
and computer hardware provided to ongoing projects financed by the Bank
4.6 Knowledge Building
4.6.1 Knowledge building forms part of the institutional strengthening of the department in
charge of roads. The training of sub-sector management staff and officers has suffered from
years of war, leading to a halt in training programs following the suspension of financing and
projects. Under ongoing projects, the Bank has provided financial support to the roads
department to train its technical staff (engineers and technicians), thus contributing to building
the department’s technical and operational capacity.
V. LEGAL FRAMEWORK
5.1 Financing Instrument
To finance this project, the Bank will use the ADF/FSF Pillar 1 grant allocated to the
Government of Burundi.
5.2 Conditions Associated with ADF Intervention
A. Conditions Precedent to Effectiveness
Effectiveness of the Protocol of Agreement is subject to its signature by the ADF and
the Donee.
17
B. Conditions Precedent to First Disbursement
The first disbursement of the Grant is subject to the fulfilment by the Donee of the
following condition:
(i) Provide the ADF with evidence of the effective payment of compensation for
land expropriation (paragraph 3.2.15);
C. Other Conditions
(ii) In addition to the above conditions, the Donee shall fulfil the following
condition:
Provide the ADF with evidence of opening a special account bearing the project
name in a commercial bank in Burundi acceptable to the ADF into which the counterpart
funds will be paid, and provide the ADF with evidence of replenishing the counterpart fund
account yearly, in accordance with the schedule of expenditure (paragraph 4.1.4).
5.3 Compliance with Bank Policies
Is this project in line with
the Bank’s applicable rules?
The project is line with the policy on expenditures
eligible for financing by the Bank
The project is in line with the Bank’s recommendations
on road works unit costs study
The project is also in line with the CSP of Burundi
VI. CONCLUSIONS AND RECOMMENDATIONS
6.1 Conclusions
6.1.1 The Gitega-Nyangungu-Ngozi Road, which forms part of Burundi’s priority network
linking the country’s second and third cities, constitutes a major link for the development of
trade between the north and the south. Its implementation will contribute to opening up the
rural areas. Specifically: (i) the project will help to reduce general transport costs; (ii) improve
access to basic social services, production centres and product marketing; and (iii) enhance
opportunities for commercial activities. The project forms part of Burundi’s national priorities
6.1.2 The negative environmental impacts have been identified and mitigative measures
incorporated into the project. The project underwent a comprehensive engineering study. It is
economically viable and shows an average economic rate of return of 14.9%, which is higher
than the opportunity cost of capital estimated at 12%. The sustainability of investments will
be assured through the strengthening of resources allocated to road maintenance and
compliance with axle load and heavy vehicle weight limits.
6.2 Recommendations
In view of the foregoing, it is recommended that an ADF grant not exceeding UA 24.1 million
be awarded to the Republic of Burundi. The grant will be used in implementing the project as
designed and described in this report. The grant will be subject to the conditions specified in
the Protocol of Agreement.
Appendix I
Year Burundi Africa
Develo-
ping
Countrie
Develo-
ped
CountrieBasic Indicators Area ( '000 Km²) 28 80 976 80 976 54 658Total Population (millions) 2009 8,3 1 008 5 629 1 069Urban Population (% of Total) 2009 10,7 39,6 44,8 77,7Population Density (per Km²) 2009 298,3 3,3 66,6 23,1GNI per Capita (US $) 2008 140 1 428 2 780 39 688Labor Force Participation - Total (%) 2009 50,1 41,2 45,6 54,6Labor Force Participation - Female (%) 2009 51,5 41,2 39,8 43,3Gender -Related Dev elopment Index Value 2005 0,409 0,525 0.694 0,911Human Dev elop. Index (Rank among 182 countries) 2007 174 0,514 n.a n.a.Popul. Liv ing Below $ 1 a Day (% of Population) 2006 81,3 50,8 25,0 …
Demographic Indicators
Population Grow th Rate - Total (%) 2009 2,8 2,3 1,3 0,7Population Grow th Rate - Urban (%) 2009 5,7 3,4 2,4 1,0Population < 15 y ears (%) 2009 38,4 56,0 29,2 17,7Population >= 65 y ears (%) 2009 2,8 4,5 6,0 15,3Dependency Ratio (%) 2009 70,0 78,0 52,8 49,OSex Ratio (per 100 female) 2009 96,1 100,7 934,9 948,3Female Population 15-49 y ears (% of total population) 2009 26,2 48,5 53,3 47,2Life Ex pectancy at Birth - Total (y ears) 2009 50,9 55,7 66,9 79,8Life Ex pectancy at Birth - Female (y ears) 2009 52,4 56,8 68,9 82,7Crude Birth Rate (per 1,000) 2009 34,3 35,4 21,5 12,0Crude Death Rate (per 1,000) 2009 13,7 12,2 8,2 8,3Infant Mortality Rate (per 1,000) 2009 96,0 80,0 49,9 5,8Child Mortality Rate (per 1,000) 2009 161,7 83,9 51,4 6,3Total Fertility Rate (per w oman) 2009 4,5 4,5 2,7 1,8Maternal Mortality Rate (per 100,000) 2005 480,0 683,0 440,0 10,0Women Using Contraception (%) 2006 … 61,0 75,0
Health & Nutrition Indicators
Phy sicians (per 100,000 people) 2005 6,5 42,9 78,0 287,0Nurses (per 100,000 people)* 2005 75,9 120,4 98,0 782,0Births attended by Trained Health Personnel (%) 2005 33,6 50,5 63,4 99,3Access to Safe Water (% of Population) 2006 71,0 64,0 84,0 99,6Access to Health Serv ices (% of Population) 2006 … 61,7 80,0 100,0Access to Sanitation (% of Population) 2006 41,0 38,5 54,6 99,8Percent. of Adults (aged 15-49) Liv ing w ith HIV/AIDS 2007 2,0 4,5 1,3 0,3Incidence of Tuberculosis (per 100,000) 2007 367,0 313,7 161,9 14,1Child Immunization Against Tuberculosis (%) 2007 97,0 83,0 89,0 99,0Child Immunization Against Measles (%) 2007 99,0 74,0 81,7 92,6Underw eight Children (% of children under 5 y ears) 2005 … 25,6 27,0 0,1Daily Calorie Supply per Capita 2005 1 631 2 324 2 675 3 285Public Ex penditure on Health (as % of GDP) 2006 0,7 5,5 4,0 6,9
Education Indicators
Gross Enrolment Ratio (%)
Primary School - Total 2008 135,6 100,2 106,8 101,5 Primary School - Female 2008 132,1 91,7 104,6 101,2 Secondary School - Total 2008 17,7 35,1 62,3 100,3 Secondary School - Female 2008 14,4 30,5 60,7 100,0Primary School Female Teaching Staff (% of Total) 2008 53,0 47,5 … …Adult Illiteracy Rate - Total (%) 2006 … 59,4 19,0 …Adult Illiteracy Rate - Male (%) 2006 … 69,8 13,4 …Adult Illiteracy Rate - Female (%) 2006 … 57,4 24,4 …Percentage of GDP Spent on Education 2005 5,1 4,5 5,4
Environmental Indicators
Land Use (Arable Land as % of Total Land Area) 2007 38,7 6,0 9,9 11,6Annual Rate of Deforestation (%) 2006 … 0,7 0,4 -0,2Annual Rate of Reforestation (%) 2006 … 10,9 … …Per Capita CO2 Emissions (metric tons) 2008 0,0 1,1 1,9 12,3
Sources : ADB Statistics Department Databases; World Bank: World Development Indicators; last update :
UNAIDS; UNSD; WHO, UNICEF, WRI, UNDP; Country Reports.
COMPARATIVE SOCIO-ECONOMIC INDICATORS
Burundi
may 2010
0
20
40
60
80
100
120
20
03
20
04
20
05
20
06
20
07
20
08
20
09
Infant Mortality Rate( Per 1000 )
Burun di Africa
0
500
1000
1500
20
02
20
03
20
04
20
05
20
06
20
07
20
08
GNI per capita US $
Burun di Africa
0,0
0,5
1,0
1,5
2,0
2,5
3,0
3,5
200
3
200
4
200
5
200
6
200
7
200
8
200
9
Population Growth Rate (%)
Burundi Africa
111213141516171
20
03
20
04
20
05
20
06
20
07
20
08
20
09
Life Expectancy at Birth (years)
Burun di
Africa
Appendix II
Table of Bank Portfolio in Burundi
Sector No. Project Approval Date Signature Effective
ness Date
Amount (UA
M)
Amount
Disburse(
UA M)
Disburse
ment
Rate (%)
Deadline Project
Age
Agriculture 1
PPF Bugesera Integrated Rural
Development 27-Dec-08 27-Feb-09 27-Feb-09
0,32 0,00 0,00 31-Dec-10
1,2
2 Watershed Development Project 1-Mar-06 7-Apr-06 7-Apr-06
9,00 6,23 69,27 31-Dec-11
4,1
3 Lake Tanganyika Development Prog 17-Nov-04 12-Jan-05 13-Jan-06
4,96 0,16 3,27 31-Jan-12
5,4
Total Agric.
14,28 6,40 24,18
3,58
Multi-Sector 4 Economic Reform Support Prog. 8-Dec-04 12-Jan-05 28-Jun-05
6,72 6,72 100,00 30-Dec-10
5,3
8-Dec-04 12-Jan-05 28-Jun-05 1,50 0,60 40,01 30-Dec-10 5,3
Total Multi-
Sector
8,22 7,32 70,01
5,3
Energy 5
Electricity Infrastructures
Rehabilitation .and Extension 5-Jul-07 17-Aug-07
17-Aug-
07 7,32 1,71 23,41 31-Dec-11
2,7
Total Energy
7,32 1,71 23,41
2,7
Social 6 Multisector Re-integration Project 13-Dec-04 12-Jan-05 1-Oct-05
9,81 7,8 79,3 31-Dec-10
4,6
7 Employment Creation Project 24-Jun-09 14-Sep-09 14-Oct-09
10,00 1,31 13,08 31-Dec-13
0,5
Total Social 19,81 9,09 46,19 2,51
Transport 8
Kicukiro - Kirundo Road Project
(Multinational) 20-Sep-06 30-Oct-06 30-Oct-06
14,90 11,15 74,82
31-Nov -
11 3,5
9
Nyamitanga-Ruhwa-Ntendezi-
Mwityazo Road (Multinational) 16-Déct-08 16-Mar-09 16-Dec-08
49,38 0,00 0,00 31-Dec-13
1,3
10
Dsm-Isaka-Kiga/Keza-M Railway
Phase 2 (Multinational) 17-Nov-09 12-Feb-10 12-Feb-10
1,67 0,00 0,00 31-Dec-12
0,1
Total Transport
64,85 11,15 24,94
1,63
Water &
Sanitation 11 Rehabilitation and Extension Project 14-Dec-05 13-Jan-06 13-Jan-06
12,00 3,60 29,96 31-Dec-10
4,3
Total W&S. 12,00 3,60 29,96 4,3
Total 127,58 28,11 38,75 3,68
Appendix III
Major Related Projects Financed by the Bank Group and Other Development
Partners in Burundi
DONOR PROJECT AMOUNT
(millions)
1. EDF
(i) Gitega-Karuzi Road Development and Asphalting and
Gitega City Bypass;
(ii) Ruyigi- Cankuzo Road Development and Asphalting
40,00 Euros
22,00 Euros
2. OPEC Fund
(i) Supplement to Kicukiro – Kirundo: Gasenyi- Kirundo
Section Road Development and Asphalting
(ii) Supplement to Bubanza-Ntamba-Ndora Road Development
and Asphalting
USD 12,00
USD 18,00
3. ABEDA
Supplement to Bubanza-Ntamba Road Development and
Asphalting
USD 22,00
4. IDA Road Section Development Project SDR 34, 30
5ADF
(i) Kicukiro – Kirundo Road Project (Gasenyi-Kirundo Section)
(ii) Nyamitanga-Ruhwa-Ntendezi-Mwityazo Road Project
(Nyamitanga-Ruhwa Section)
UA 14,9
UA 49,38