Bureau of Materials and Research 2014 AASHTO RAC/TRB Annual Meeting High Value Research Sweet 16 Ann Scholz, P.E., Assistant Research Engineer [email protected]

Upload: delilah-sullivan

Post on 23-Dec-2015

218 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Bureau of Materials and Research 2014 AASHTO RAC/TRB Annual Meeting High Value Research Sweet 16 Ann Scholz, P.E., Assistant Research Engineer ascholz@dot.state.nh.us

Bureau of Materials and Research

2014 AASHTO RAC/TRB Annual MeetingHigh Value Research Sweet 16

Ann Scholz, P.E., Assistant Research Engineer

[email protected]

Page 2: Bureau of Materials and Research 2014 AASHTO RAC/TRB Annual Meeting High Value Research Sweet 16 Ann Scholz, P.E., Assistant Research Engineer ascholz@dot.state.nh.us

Roadway resurfacing reduced the height of the guardrail relative to the roadway

Reduced height did not meet AASHTO’s Roadside Design Guide

Resetting guardrail post added significant expense to pavement overlay projects

Performance of W-Beam Guardrail after Height Adjustment

Page 3: Bureau of Materials and Research 2014 AASHTO RAC/TRB Annual Meeting High Value Research Sweet 16 Ann Scholz, P.E., Assistant Research Engineer ascholz@dot.state.nh.us

Why Research?

Hey Boss. What’s the allowable range of height for a W-beam guardrail?

Hmmmm, let me check with the

FHWA Safety Office

New “unofficial” guidance is 27”

Top of Rail +3”/-1”

Page 4: Bureau of Materials and Research 2014 AASHTO RAC/TRB Annual Meeting High Value Research Sweet 16 Ann Scholz, P.E., Assistant Research Engineer ascholz@dot.state.nh.us

Research Findings

Topic investigation revealed possible solutions from:

Proposed use of WSDOT detail with FHWA-NH:

Page 5: Bureau of Materials and Research 2014 AASHTO RAC/TRB Annual Meeting High Value Research Sweet 16 Ann Scholz, P.E., Assistant Research Engineer ascholz@dot.state.nh.us

Proposed changes from traditional work

Standard detail for resetting offset block on existing wood post

Page 6: Bureau of Materials and Research 2014 AASHTO RAC/TRB Annual Meeting High Value Research Sweet 16 Ann Scholz, P.E., Assistant Research Engineer ascholz@dot.state.nh.us

Proof of Concept

FHWA-NH required:Two-year field study on installations

Evaluate in-service performanceCompare to traditional methods

Photograph and documentSummarize finding into a report

Provide donuts and coffeeNamesake your first born

Kind words to D.C.Kiss a frog

Etc.

Computer simulation by George Washington University

Page 7: Bureau of Materials and Research 2014 AASHTO RAC/TRB Annual Meeting High Value Research Sweet 16 Ann Scholz, P.E., Assistant Research Engineer ascholz@dot.state.nh.us

Research approved

November 2009 – National Crash Analysis Center study was released documenting the successful computer simulation providing additional confirmation of the anticipated performance.

Summer 2010 through Fall 2012 - Field in-service evaluations proved successful

June 2012 – Highway Design provides special detail for projects

Page 8: Bureau of Materials and Research 2014 AASHTO RAC/TRB Annual Meeting High Value Research Sweet 16 Ann Scholz, P.E., Assistant Research Engineer ascholz@dot.state.nh.us

Implementation Strategy

http://www.nh.gov/dot/org/projectdevelopment/highwaydesign/detailsheets/index.htm

Page 9: Bureau of Materials and Research 2014 AASHTO RAC/TRB Annual Meeting High Value Research Sweet 16 Ann Scholz, P.E., Assistant Research Engineer ascholz@dot.state.nh.us

Value of Implementing the Research

Highway safety was not compromised as evidenced by

several accidental hits and review of available crash reports

Page 10: Bureau of Materials and Research 2014 AASHTO RAC/TRB Annual Meeting High Value Research Sweet 16 Ann Scholz, P.E., Assistant Research Engineer ascholz@dot.state.nh.us

Value of Implementing the Research

$5,200,000 savings from Spring 2009 through Fall 2013.

Page 11: Bureau of Materials and Research 2014 AASHTO RAC/TRB Annual Meeting High Value Research Sweet 16 Ann Scholz, P.E., Assistant Research Engineer ascholz@dot.state.nh.us

Value of Implementing the Research

In addition to direct costs, projects required less time for completion which resulted in additional savings from other contract items:

Uniformed officersFlaggersMaintenance of trafficTemporary and portable signage

Page 12: Bureau of Materials and Research 2014 AASHTO RAC/TRB Annual Meeting High Value Research Sweet 16 Ann Scholz, P.E., Assistant Research Engineer ascholz@dot.state.nh.us

Return on Investment

$5.20

$0.01

Research Pays Off

Savings Costs

Mill

ion

s o

f d

olla

rs

Page 13: Bureau of Materials and Research 2014 AASHTO RAC/TRB Annual Meeting High Value Research Sweet 16 Ann Scholz, P.E., Assistant Research Engineer ascholz@dot.state.nh.us

Thank you Region 1 for your recognition

Acknowledgements: Mike Hazlett, NHDOT Highway Design – driving force Don Coleman,

NHDOT Construction – initial reviewJulie

Fowler, NHDOT Research – field monitor and reportMarty Calawa, FHWA – support and guidance