Burbank Bob Hope Airport. Replacement Terminal and Opportunity Site Development October 28, 2013. The Goals. Replace an 83 year old building with a safe, modern 14-gate terminal that meets current earthquake design standards and FAA standards for distance from the runways - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Burbank Bob Hope Airport

Burbank Bob Hope Airport

Replacement Terminal and Opportunity Site Development

October 28, 2013

Page 2: Burbank Bob Hope Airport

The Goals

• Replace an 83 year old building with a safe, modern 14-gate terminal that meets current earthquake design standards and FAA standards for distance from the runways

• Provide the same conveniences and easy access that Burbank residents and air travelers now enjoy

• Provide additional amenities which the public has identified and are typically available in a modern airport terminal

2

Page 3: Burbank Bob Hope Airport

The Goals

• Maximize the use of the former Lockheed Plant B6 site to develop a replacement terminal and create an economic engine for the region that takes advantage of vacant real estate and proximity of air and ground transportation.

3

Page 4: Burbank Bob Hope Airport
Page 5: Burbank Bob Hope Airport
Page 6: Burbank Bob Hope Airport

Preliminary Terminal Concept

Preliminary Terminal Concept Site Plan

6

Page 7: Burbank Bob Hope Airport

What passengers and residents want

• Don’t “screw it up!”

• Don’t use local taxes to pay for it!

7

Page 8: Burbank Bob Hope Airport

What passengers and residents want

• A variety of restaurants and concessions

• Larger spaces for TSA passenger and baggage security screenings

• Roomier baggage claim areas

• A larger ticket lobby and airline ticket counters

8

Page 9: Burbank Bob Hope Airport

What passengers and residents want

• Adequate space for airline administrative, ramp, bag service, and ticket offices

• More room for airline baggage processing

• Additional restroom facilities and increased family restrooms

• Fully integrated designs for ADA accessibility

9

Page 10: Burbank Bob Hope Airport

Terminal

10

• Existing Terminal – 14 Gates– 6,631 Parking Spaces– 210,599 SF

• Excludes Apron Space Uses

• Replacement Terminal Size– 14 Gates– 6,631 Parking Spaces– 355,102 SF

• Net Increase = 144,503 SF (68.6% increase)

Page 11: Burbank Bob Hope Airport

Space Summary

11

SPACE CATEGORY EXISTING TERMINAL

Total Space

REPLACEMENT TERMINALTotal Space

DIFFERENCE

AUTHORITY 48,873 35,615 (13,258)

PUBLIC 49,283 90,107 40,824

CONCESSION 17,102 38,683 21,581

AIRLINE COMMON (ENCLOSED)

42,146 72,792 30,646

AIRLINE COMMON (UNENCLOSED)

7,284 28,609 21,325

AIRLINE EXCLUSIVE 18,916 32,823 13,907

SECURITY 25,023 45,393 20,370

MECHANICAL / MISC 1,972 11,080 9,108

TOTAL 210,599 355,102 144,503

Page 12: Burbank Bob Hope Airport

How Will the Burbank Bob Hope

Airport Replacement Terminal Benefit the Region?

12

Page 13: Burbank Bob Hope Airport

Tremendous Opportunity

• Invests $300-400M in local economy – funded by the FAA, airlines, and airport

users– NOT Burbank taxpayers

• Creates a substantial number of terminal related jobs in construction, transportation, and services

• Attracts more companies and jobs to nearby Media District North

13

Page 14: Burbank Bob Hope Airport

Tremendous Opportunity

• Preserves what is good about the Airport and makes it great – still convenient and friendly with: • loading from front and rear of aircraft• parking choices (close-in and remote

parking) • shorter walks• single screening area• improved baggage claim• more amenities

14

Page 15: Burbank Bob Hope Airport

Tremendous Opportunity

• Acts as a unique catalyst to attract a mix of highest and best uses and jobs to the adjacent 58-acre Opportunity Site

• Strengthens Burbank’s appeal as a growing media and hi-tech hub served by convenient air transportation in a modern terminal

15

Page 16: Burbank Bob Hope Airport

Tremendous Opportunity

• Introduces Burbank, Glendale, Pasadena and the Valley to millions of airport passengers and visitors through a showcase new front door

• Mitigates traffic congestion with more rail and bus links to the Airport and adjacent commercial areas

16

Page 17: Burbank Bob Hope Airport

Tremendous Opportunity

• Locks in place protections for Burbank residents by changing the Airport Authority’s governance rules to require not a simple majority vote but a “supermajority” vote (2 commissioners from each city) – for such actions as • adding more gates or expanding the

terminal• ending the voluntary curfew or changing

noise rules• acquiring land

17

Page 18: Burbank Bob Hope Airport

Process and Schedule

• October 29, 2013– Burbank City Council Meeting to review

the Proposed Configuration of a 14-gate Replacement Terminal and Opportunity Site Development scenario

18

Page 19: Burbank Bob Hope Airport

Process and Schedule

• November 14, 2013– Joint City and Airport Authority Meeting

to consider approval of a general project description for a proposed 14-gate replacement terminal and associated airport improvements, as well as development scenarios for the 58 acre Opportunity Site.

– This general description will then be used as the project description for study in the Environmental Impact Report.

19

Page 20: Burbank Bob Hope Airport

Process and Preliminary Schedule

• End of 2013 - CEQA Project Description and Public Scoping Meeting

• Early 2015 - Completion of CEQA analysis and Public Comment Period

• Spring 2015 - Completion of Required Approvals

• Mid 2015 - Measure B Vote

20