Project Exercises
1
Project Scenario
During the course of this manual we will be creating and managing a project for the construction of a
Bungee Jump at West Coast Waterland.
We will be using the Checklist found at rear to guide us through this project. This checklist is intendedas a guide only and you will need to customise it for your particular company and projects.
You are the Project Manager for this project and the company that you work for is called Belly Flop
Constructions Pty Ltd.
The project is due to start on the first working day of next month and you have four months in which to
complete the project. The budget that you have been allocated is $175,000.
You standard working week is from Monday to Friday, 8.00am to 12.00noon and from 1.00pm to
5.00pm.
The completed jump will be 50m tall with a four-person elevator on it.
-
8/22/2019 Bungee Jump for C Grade
2/33
Project Exercises
2
EXERCISE 1
Starting a New Project
1. Close any open projects.
2. Create a new project file.
EXERCISE 2
Setting Project Options
1. Set the date format to display both the date and time.
2. Check the options in the Calendartab to ensure that they display:
Week Starts On : Monday
Fiscal Year Starts In : January
Default Start Time : 8:00
Default End Time : 17:00
Hours Per Day : 8
Hours Per Week : 40
Days Per Month : 20
3. Click on the Ok button to close the Options dialog box.
-
8/22/2019 Bungee Jump for C Grade
3/33
Project Exercises
3
EXERCISE 3
Editing the Standard Calendar
1. Ensure that the Standard Calendar shows Mondays to Fridays to start at 8:00 go to 12:00, lunchuntil 1:00 and finish at 5:00.
2. Set the standard calendar to have non working days for:
New Year's Day
Australia Day
Labour Day
Good Friday
Easter Monday
Anzac Day
Foundation Day
Queen's Birthday
Christmas Day
Boxing Day
Your facilitator will provide you with a list of the actual dates for the above.
3. Close the dialog box.
-
8/22/2019 Bungee Jump for C Grade
4/33
Project Exercises
2
EXERCISE 4
Entering Project Details
1. Using the above method enter the following details in the Summary tab.
Title : Construction of Bungee Jump at West Coast Waterland
Author : Your name
Manager : Your name
Company : Belly Flop Constructions Pty Ltd
Comments : Project starts first working day of next month, needs to becompleted within four months and at a budget of $175,000.
EXERCISE 5
Entering the Project Start Date
1. Set your project's Start Date to the first working day of next month or what your facilitator givesyou.
2. Ensure that Standard is displayed in the Calendardrop down box.
-
8/22/2019 Bungee Jump for C Grade
5/33
Project Exercises
3
EXERCISE 6
Saving Your Project
1. Using the above method save your project under the My Documents directory and call itBungee Jump.
EXERCISE 7
Entering Tasks
1. Using the above method enter the following tasks:
1. Site survey 15. Install winching equipment
2. Prepare plans 16. Install pond plumbing
3. Estimate project costs 17. Fill pond
4. Prepare / submit loan documents 18. Fit rubber bungee
5. Order supplies and equipment 19. Final inspection
6. Prepare construction site 20. Test elevator system
7. Deliver materials to site 21. Test pond pump
8. Pour concrete bases for pylons 22. Test winch
9. Dig footings for pylons 23. Invite guests to the opening
10. Pour concrete in pond 24. Invite Premier to jump
11. Erect pylons 25. Arrange catering
12. Erect launch platform 26. Arrange marquee hire
13. Install electrical wiring 27. Gala Opening
14 Install elevator system
2. Save your project.
-
8/22/2019 Bungee Jump for C Grade
6/33
Project Exercises
4
EXERCISE 8
Inserting Tasks
1. Insert the following tasks:
Dig well for pond insert before Pour Concrete in Pond
Test electrical system insert before Test Elevator System
Test Bungee insert before Invite Guests to the Opening
Arrange Band insert before Gala Opening
2. Save the project.
EXERCISE 9
Moving. Copying & Editing Tasks
1.Move the following tasks:
Pour concrete bases for pylons should be afterDig Footings for Pylons
Final inspection should be afterTest Bungee
2. Copy the following task:
Prepare / submit loan documents
Paste it above Order Supplies and Equipment
Edit the duplicated task so that the second Prepare / submit loan documents now readsPrepare / submit permit applications.
3. Edit the Invite Premier to jump task to read Invite Premier and Opposition Leader to jump.
4. Save your project.
-
8/22/2019 Bungee Jump for C Grade
7/33
Project Exercises
5
EXERCISE 10
Check Project
1. Check that your project is the same as the one shown below:
2. Save your project.
-
8/22/2019 Bungee Jump for C Grade
8/33
Project Exercises
6
EXERCISE 11
Entering Task Durations
1. Enter the following durations.
2. Save your project.
-
8/22/2019 Bungee Jump for C Grade
9/33
Project Exercises
7
EXERCISE 12
Creating Summary Tasks
1. Insert the following tasks:
o Prepare paperwork before Site survey
o Prepare supplies and site before Order supplies and equipment
o Prepare foundations before Dig footings for pylons
o Construction before Erect pylons
o Testing and Inspection before Test electrical systems
o Opening before Invite guests to the opening
These will become the summary tasks so don't enter anything for the durations.
2. Select Task ID 2 (Site Survey) through to Task ID 6 (Prepare / Submit permit applications)
3. Click on the Indent Task button.
4. Repeat steps 2 and 3 above for the following groups:
o Task ID 8 through Task ID 10o Task ID 12 through Task ID 15
o Task ID 17 through Task ID 24
o Task ID 26 through Task ID 31
o Task ID 33 through Task ID 38
5. Save your project.
EXERCISE 13
Hiding & Displaying Subordinate tasks
1. Hide and display subordinate tasks.
-
8/22/2019 Bungee Jump for C Grade
10/33
Project Exercises
8
EXERCISE 14
Creating A Project Summary Task And Display Outline Numbering
1. Create a project summary task for your project.
2. Display outline numbering in your project.
3. Save your project.
EXERCISE 15
Entering Milestones
1. Add the following milestones into your project:
Paperwork completed before Prepare supplies and site
Preparations finalised before Prepare foundations
Foundations completed before Construction
Construction completed before Testing and Inspections
Testing and inspections completed before opening
Project completed as the last task
2. Save your project.
-
8/22/2019 Bungee Jump for C Grade
11/33
Project Exercises
9
EXERCISE 16
Creating Task Relationships Using Menu Buttons
1. Create the following relationships
Predecessor Successor
Site survey Prepare plans
Prepare plans Estimate project costs
Prepare plans Prepare/submit loan documents
Site survey Prepare/submit permit applications
-
8/22/2019 Bungee Jump for C Grade
12/33
Project Exercises
10
EXERCISE 17
Creating Task Relationships Using Drag and Drop
1. Create the following relationships
Predecessor Successor
Prepare/submit loan documents Order supplies and equipment
Prepare/submit loan documents Prepare construction site
EXERCISE 18
Creating Task Relationships Using the Task Information Dialog Box
1. Create the following relationships
Predecessor Successor
Order supplies and equipment Deliver materials to site
Dig footings for pylons Pour concrete bases for pylons
EXERCISE 19
Creating Task Relationships Using the Task Entry View
1. Create the following relationship
Predecessor Successor
Prepare construction site Dig footings for pylons
-
8/22/2019 Bungee Jump for C Grade
13/33
Project Exercises
11
EXERCISE 20
Creating Task Relationships Using the Gantt Chart Predecessor column
1. Check and create the following relationships
-
8/22/2019 Bungee Jump for C Grade
14/33
Project Exercises
12
EXERCISE 21
Changing Task Dependency Types using the Gantt Bar Chart
1. Change the relationship between Task ID 2 (Site Survey) and Task ID 3 (Prepare Plans) to aStart-to-Start relationship.
2. Use the Undo button to set this relationship back to the Finish-to-Start relationship.
EXERCISE 22
Changing Task Relationship Types
1. Using the above method change the relationship between Task ID 2 (Site Survey) and Task ID3 (Prepare Plans) to a Start-to-Start relationship.
2. Use the Undo button to set this relationship back to the Finish-to-Start relationship.
-
8/22/2019 Bungee Jump for C Grade
15/33
Project Exercises
13
EXERCISE 23
Unlinking Tasks
1. Unlink Task ID 2 (Site Survey) and Task ID 3 (Prepare Plans).
2. Use the Undo button to set this back to a Finish to Start relationship.
EXERCISE 24
Adding Lead to a Relationship
1. Create an overlap of20% between Task ID 22 (Install electrical wiring) and Task ID 23(Install elevator system).
EXERCISE 25
Adding Lag to a Relationship
1. Add the following lags:
Predecessor Successor Lag
Prepare / submit loan
documentsOrder supplies and equipment 2 weeks
Prepare / submit loan
documents
Prepare construction site 2 weeks
Pour concrete bases for pylons Erect pylons 1 week
Pour concrete in Pond Install pond plumbing 3 days
-
8/22/2019 Bungee Jump for C Grade
16/33
Project Exercises
14
EXERCISE 26
Check Project
1. Create new relationships if necessary. Check that your project is the same as the one shownbelow:
-
8/22/2019 Bungee Jump for C Grade
17/33
Project Exercises
15
EXERCISE 27
Adding a Constraint
1. Using the above method, add a constraint so that the Gala Opening must start at 7pm on thelast Friday of the fourth month from the beginning of the project (i.e. if you started your project inJanuary, the Opening will be on the last Friday of April, etc).
Check the Start and Finish Date for this task once you have applied the constraint. Are there
any problems? What do you need to do to solve it?
____________________________________________________________________________
2. Make the necessary changes to your project.
EXERCISE 28
Setting a Deadline
1. Set a deadline for the Final inspection to occur on the day before the Gala Opening.
-
8/22/2019 Bungee Jump for C Grade
18/33
Project Exercises
16
EXERCISE 29
Entering Resources
1. Enter the following resources into your project.
-
8/22/2019 Bungee Jump for C Grade
19/33
Project Exercises
17
EXERCISE 30
Editing Resource Calendars
1. Edit the calendar for the Accountant giving the first week of the first month of the project off.
EXERCISE 31
Creating and Assigning a New Calendar
1. Create a Consultants Calendarwhere the hours on Friday are only from 7:30am to 12:00pm.
2. Assign this calendar to all the Consultants.
-
8/22/2019 Bungee Jump for C Grade
20/33
Project Exercises
18
EXERCISE 32
Assigning Resources to Tasks
1. Assign the following resources to the indicated tasks:
-
8/22/2019 Bungee Jump for C Grade
21/33
Project Exercises
19
EXERCISE 33
Removing Assigned Resources
1. Remove the Secretary from the Invite Premier and Opposition Leader to jump task.
2. Use the Undo button to set this back.
EXERCISE 34
Replacing Assigned Resources
1. Replace the Secretary with the Project Managerfor the Invite Premier and OppositionLeader to jump task.
EXERCISE 35
Contouring Resource Availability
1. Contour the availability of the Labourers to be 200% in the first month of the project and 300%for the rest.
-
8/22/2019 Bungee Jump for C Grade
22/33
Project Exercises
20
EXERCISE 36
Entering Variable Costs for Resources
1. Enter the following costs and check that the Accrue at column is correct.
-
8/22/2019 Bungee Jump for C Grade
23/33
Project Exercises
21
EXERCISE 37
Entering Fixed Costs for Resources
1. Enter a fixed cost of$1,500 forSteve's Crane Hire on the Install winching equipment task.
EXERCISE 38
Entering Fixed Costs for Tasks
1. Enter the following fixed costs for the tasks in your project:
-
8/22/2019 Bungee Jump for C Grade
24/33
Project Exercises
22
EXERCISE 39
Viewing Project Statistics
1. View the project statistics for your project.
EXERCISE 40
Using the Gantt Chart Wizard to Display the Critical Path.
1. Use the Gantt Chart Wizard to display the critical path of your project.
EXERCISE 41
Formatting Selected Tasks
1. Format the Gala Opening task so that it stands out.
-
8/22/2019 Bungee Jump for C Grade
25/33
Project Exercises
23
EXERCISE 42
Formatting Text Styles
1. Format the following items:
Critical path tasks
Milestone tasks
Summary tasks
2. Save your project.
EXERCISE 43
Formatting Selected Bars
1. Format the bar for the Gala Opening task to stand out.
2. Save your project.
EXERCISE 44
Formatting Bar Styles
1. Format the following items:
Milestone bars
Summary bars
Task bars show Resource Initials instead of Resource Names.
-
8/22/2019 Bungee Jump for C Grade
26/33
Project Exercises
24
EXERCISE 45
Formatting the Timescale
1. Experiment with the various timescale formatting options.
EXERCISE 46
Applying a Simple Exclusion Filter
1. Filter your project so that only Critical Tasks are displayed.
2. To remove the filter, choose All Tasks in the filter list.
EXERCISE 47
Applying an AutoFilter
1. Use the AutoFilter feature to filter for tasks with durations of1 week.
2. When you have finished turn the AutoFilter option off.
-
8/22/2019 Bungee Jump for C Grade
27/33
Project Exercises
25
EXERCISE 48
Applying A Highlight Filter
1. Use the Highlight filter feature to filter for tasks using a specific resource.
2. When you have finished turn the Highlight filter off.
EXERCISE 49
Applying a Grouping
1. Group your tasks by "Critical".
2. Try some of the other groups.
3. To remove the grouping, choose No Groups in the group list.
EXERCISE 50
Checking for Resource Overallocations
1. Use the Resource Sheet to determine if there are any overallocated resources in your project.
-
8/22/2019 Bungee Jump for C Grade
28/33
Project Exercises
26
EXERCISE 51
Determining Why Resources Are Overallocated
1. Determine which resources are overallocated and why.
Make a list of the overallocated resources and the reasons.
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
-
8/22/2019 Bungee Jump for C Grade
29/33
Project Exercises
27
EXERCISE 52
Adding More Resources
1. Solve the problem with the Riggers, Labourers and Trades Assistants. (Remember, we appliedResource Contouring to the Labourers you may need to take this off to solve theoverallocation problems).
EXERCISE 53
Replacing Assigned Resources
1. Replace the Project Manageron the Prepare / submit loan documents with the Architect.
EXERCISE 54
Change the Level of Effort
1. Change the level of effort for the Secretary to 20% for each of the following tasks:
Invite guests to the opening
Arrange catering
Arrange marquee hire
Arrange band
-
8/22/2019 Bungee Jump for C Grade
30/33
Project Exercises
28
EXERCISE 55
Change Task Dependencies
1. Link the following tasks
Pour concrete bases for pylons (predecessor) to
Pour concrete in pond (successor)
In a Finish-to-Start relationship
EXERCISE 56
Saving a Baseline
1. Create a baseline for your project.
EXERCISE 57
Display the Gantt Chart Baseline Table
1. Display the Gantt Chart - Baseline Table.
2. When you have finished looking at this view, return the Gantt Chart to the Entry Table.
-
8/22/2019 Bungee Jump for C Grade
31/33
Project Exercises
29
EXERCISE 58
Display the Tracking Gantt Chart View
1. Display the Tracking Gantt Chart view.
2. When you have finished looking at this view, return to the Gantt Chart view with the Entry table.
EXERCISE 59
Displaying and Using the Tracking Toolbar
1. Display the Tracking Toolbarand update the following tasks to the percentage shown:
Site survey 100%
Prepare plans 75%
EXERCISE 60
Displaying and Using the Update Tasks Dialog Box
1. Update the following tasks as indicated:
Estimate project costs 100% complete
Prepare / submit loan documents started one day late but is 100% complete
Prepare / submit permit applications started one day early and is 100% complete
Paperwork complete 100% complete
Order supplies and equipment 50% complete, actual duration is 4d and remaining
duration is 4d.
2. Display the Project Information screen and check your results.
-
8/22/2019 Bungee Jump for C Grade
32/33
Project Exercises
30
EXERCISE 61
Displaying and Using the Tracking Gantt Chart Tracking Table
1. Update the following tasks as indicated:
Order supplies and equipment 100% complete.
Prepare supplies and site 100% complete
Prepare foundations 100% complete
EXERCISE 62
Printing the Gantt Chart View
1. Set up and print preview your Gantt Chart view.
EXERCISE 63
Printing a Pre-Defined Report
1. Print Preview the Project Summary report.
2. Print Preview the Budget report.
-
8/22/2019 Bungee Jump for C Grade
33/33
Project Exercises
CHECKLIST FOR USING M ICROSOFT PROJECT
Note: This checklist is provided as a guide only. You will need to customise it to suit your particular
working environment and projects.
1. Defining Phase
1.1 Establish project parameters (goal, start/finish date, budget)
1.2 Start a new project file (File, New)
1.3 Check definition of day, week and month (Tools, Options, Calendar)
1.4 Edit the standard calendar (Tools, Change Working Time)
1.5 Enter project details (File, Properties)
1.6 Enter project start or finish date (Project, Project Information)
1.7 Save and name the project (File / Save)
2. Planning Phase
2.1 Enter tasks (Gantt Chart)
2.2 Enter durations (Gantt Chart)
2.3 Enter summary tasks and milestones (Gantt Chart)
2.4 Link tasks (Gantt Chart)
2.5 Enter constraints (Gantt Chart Task Information; Advanced Tab)
2.6 Enter resources and associated costs (Resource Sheet)
2.7 Create and assign / edit resource calendars (Resource Sheet)
2.8 Assign resources to tasks (Task Entry View)
2.9 Enter fixed costs (Gantt Chart Table: Cost)
2.10 Review schedule deal with overallocations, budget constraints, deadlines
2.11 Create baseline (Tools / Tracking / Save Baseline)
3. Controlling
3.1 Enter actual progress (Gantt Chart Tracking Toolbar)
3.2 View progress against baseline (Tracking Gantt Chart)
4. Closing
4.1 Final Reports (Version 2003 or before View / Reports; Version 2007 Report / Reports)