The Hop is a success! BY THE NUMBERS JOBS Construction of the M-Line was on-time and on-budget • Over 60,000 Resident Preference hours and over $14 million invested in local Disadvantaged Business En- terprises (DBE) during construction • The Hop directly employs 36 employees Over 200,000 rides in first three months (Nov 2018 – Jan 2019) 2,109 Average Daily Rides (Nov 2018 – Jan 2019) (1,850 projected) 16,409 Total rides during opening weekend (Nov. 2-4, 2018) 4,882 Highest single-day total (Saturday, Dec. 15, 2018) Building on our Momentum Momentum

Upload: others

Post on 10-Jan-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Building on our MomentumMomentum · adjusts the $20M already approved by the Common Council in 2016 and identifies an additional $26.8M. TID Funding Uses ... Envisioned as a green

The Hop is a success!BY THE NUMBERS

JOBS• Construction of the M-Line was on-time

and on-budget

• Over 60,000 Resident Preference hours and over $14 million invested in local Disadvantaged Business En-terprises (DBE) during construction

• The Hop directly employs 36 employees

Over 200,000 rides in first three months (Nov 2018 – Jan 2019)

2,109 Average Daily Rides (Nov 2018 – Jan 2019) (1,850 projected)

16,409 Total rides during opening weekend (Nov. 2-4, 2018)

4,882 Highest single-day total (Saturday, Dec. 15, 2018)

Building on our

MomentumMomentum

Page 2: Building on our MomentumMomentum · adjusts the $20M already approved by the Common Council in 2016 and identifies an additional $26.8M. TID Funding Uses ... Envisioned as a green

MICHIGAN STMICHIGAN ST

WISCONSIN AVE WISCONSIN AVE

CLYBOURN STCLYBOURN ST

STATE STSTATE ST

HIGHLAND AVEHIGHLAND AVE

JUNEAU AVEJUNEAU AVE

KILBOURN AVEKILBOURN AVE

6TH

ST

6TH

ST

OLD

WO

RLD

3RD

ST

OLD

WO

RLD

3RD

ST

NORTH AVENORTH AVE

KNAPP STKNAPP ST

MASON STMASON ST

VLIET STVLIET ST WATER ST

WATER ST

ST. PAUL AVEST. PAUL AVE

OGDEN AVEOGDEN AVE

BRO

AD

WAY

B

ROA

DW

AY

WELLS STWELLS ST

MILW

AU

KEE ST

MILW

AU

KEE ST

FRESHWATER WAYFRESHWATER WAY

2ND

ST

2ND

ST

WA

TER ST

WA

TER ST

LIN

CO

LN M

EMO

RIAL D

R

LIN

CO

LN M

EMO

RIAL D

R

JAC

KSO

N S

TJA

CK

SON

ST

MCKINLEY AVEMCKINLEY AVE

1ST

ST

1ST

ST

6TH

ST

6TH

ST

NATIONAL AVENATIONAL AVE

4TH

ST

4TH

ST

ERIE STERIE ST

CHICAGO STCHICAGO ST

WASHINGTON STWASHINGTON ST

GREENFIELD AVE GREENFIELD AVE

E A S TT O W N

H I S T O R I CT H I R DW A R D

FLORIDA STFLORIDA ST

FARW

ELL A

VE

FARW

ELL A

VEPRO

SPECT A

VE

PROSPEC

T AVE

VEL

R P

HIL

LIPS

VEL

R P

HIL

LIPS

MILWAUKEEINTERMODAL

STATION

MAR

TIN

LUT

HER

KIN

G D

RM

ART

IN L

UT

HER

KIN

G D

R

HENRY MAIERFESTIVAL PARKHENRY MAIER

FESTIVAL PARK

UWM SCHOOL OF FRESHWATER

SCIENCES

UWM SCHOOL OF FRESHWATER

SCIENCES

BRADY STREETBRADY STREET

NORTH AVENUENORTH AVENUEBRONZEVILLEBRONZEVILLE

WALKER’SPOINT

WALKER’SPOINT

ROCKWELLAUTOMATIONROCKWELL

AUTOMATION

SCHLITZPARK

SCHLITZPARK

MSOEMSOE

CBDEASTCBDEAST

Dee

rD

IST

RIC

TD

eer

DIS

TR

ICT

To UWM

LakeMichigan

M-Line(2018)

Walker’s Point

Future extension

L-Line(2020)

Bronzeville to Walker’s Point route

Amtrak Intercity Rail

to Wisconsin Avenue(2020)

Bronzeville to Walker’s Point(2024)

Getting to Wisconsin Avenue by July 2020The DNC is Coming

Extension to Bronzeville and Walker’s PointGetting to the Neighborhoods

THE PROJECT

0.4-mile M-Line extension

along Vel R. Phillips Avenue

and 5th Street

Stations at Intermodal Station and

new plaza

Brings riders to convention center

front door

Advances the Locally Preferred

Alternative already adopted by the

Common Council

Implements first section of

Bronzeville Extension

LET'S BE READY FOR THE DNC!For the first time in our City’s long history, Milwaukee will host a major political party convention. This is Milwaukee’s chance to showcase our City to the world.

COSTS AND FUNDING• $28 million to complete final design

and construction

• Funded through local tax increment financing

SCHEDULEThe City has already expedited planning and design work to ensure the extension can be up and running for the DNC.

• July 2019: Complete utility agreements and commence construction

• September 2019: Complete streetcar final design

• October 2019: Commence streetcar construction

• May 2020: Complete construction

• May-June 2020: Operations testing

• July 2020: Passenger service

THE PROJECT

3.0-mile route between Bronzeville and Walker’s Point (2.4 miles using new track)

Complete engineering and environmental studies

Complete financial planning

Request entrance into federal funding program (Capital Investment Grant Program/Small Starts)

Evaluating future route alternatives for Walkers Point

WHY?1. Getting to Bronzeville and Walker’s Point meets the goal of

extending to neighborhoods outside of downtown.

2. Positions the City for $75M to $80M in matching federal funds in a predictable federal program used by transit systems across the country.

3. Supports major development initiatives, such as Deer District, Journal Sentinel redevelopment, Convention Center expansion, The Avenue redevelopment, Bronzeville Cultural and Entertainment District, The Griot, Reed Street Yards, and Schuster’s Redevelopment.

COSTS AND FUNDING• $18.3M from local TIF districts to fund

project development activities

• Potential for 50/50 federal and local match as part of federal funding program

• Total project cost is approximately $150M-$160M (Planning Estimate)

• $0.5M from local TIF districts to study future route alternatives in Walker’s Point

SCHEDULE• Fall 2019: Commence engineering and

environmental services

• Summer 2020: Common Council meeting – commit remaining funds for local match

• September 2020: Submit Small Starts request for federal funding

• Spring/Summer 2022: Receive federal funding grant agreement and commence construction

• 2024: Open for passenger service

20+ million media impressions (Philadelphia Convention 2016)

National and international media exposure of Milwaukee

50,000+DNC-related visitors

Residual impact of people coming before and after or returning as a result of positive experience

At least 1,500 private events

Future convention holders, employees, employers, developers are all watching

Up to $200M in economic impact

BUILDING on our MOMENTUM

Page 3: Building on our MomentumMomentum · adjusts the $20M already approved by the Common Council in 2016 and identifies an additional $26.8M. TID Funding Uses ... Envisioned as a green

Funding Extensions to Bronzeville and Walker’s PointThe Path Forward

GETTING TO BRONZEVILLE AND WALKER’S POINT: FUNDING PLAN

The $46.8M will be funded through existing local tax increment finance districts and will not remove existing funding from any existing City services. The plan below adjusts the $20M already approved by the Common Council in 2016 and identifies an additional $26.8M.

TID Funding Uses

#39 Hilton $4.0M to Wisconsin Ave

#41 Time Warner Riverwalk $12.5M Bronzeville to Walker’s Point

#48 Park East $16.0M to Wisconsin Ave

#88 4th/Wisconsin $8.0M to Wisconsin Ave

#56 Erie/Jefferson $5.8M Bronzeville to Walker’s Point

#75 Reed Street Yards $0.5M Walker’s Point Alternatives Analysis

TOTAL $46.8M

Operations and maintenance (O&M) financial planning is ongoing for the first phase and future extensions. A variety of sources could be used and are being evaluated to help supplement the existing O&M funding sources of sponsorships and CMAQ.

Federal funding

5307 Urbanized Area Formula Grants – eligible 2021

5337 State of Good Repair Grants – eligible 2026

City Parking revenues

Additional CMAQ funding

Additional Private funding and sponsorships

Creation of Local Improvement District

Sustainable funding for local transit

GETTING TO BRONZEVILLE AND WALKER’S POINT: COSTS

To move forward with the plan outlined requires $46.8M in local funding.

Segment Action Local Cost

to Wisconsin Ave Engineering & Capital (100% Local Funds)

$28M

Bronzeville to Walker’s Point Commit Project Development costs *

$18.3M

Walker’s Point Further study beyond 1st St/Pittsburgh Ave

$0.5M

TOTAL $46.8M

* Project Development consists of Final Planning, Environmental Review, Preliminary and Final Design, etc.

GARFIELD AVE

ST PAUL AVE

LLOYD ST

BROWN ST

RESERVOIR AVE

VINE ST

PLEASANT ST

CHERRY ST

VLIET ST

McKINLEY AVE

JUNEAU AVE

HIGHLAND AVE

STATE ST

KILBOURN AVE

WISCONSIN AVE

MICHIGAN ST

CLYBOURN ST

I-794

NORTH AVE

2ND ST

PLANKINTON AVE

MILWAUKEE RIVER

WATER ST

ERIE ST

WATER ST

CHICAGO ST

BUFFALO ST

BROADWAY

MILWAUKEE RIVER

PITTSBURGH AVE

OREGON ST

FLORIDA ST

WEST VIRGINIA ST

BRUCE ST

PIERCE ST

NATIONAL AVE

WALKER ST

MINERAL ST

WASHINGTON ST

MENOMONEE ST

SCOTT ST

GREENFIELD AVE

MA

RTI

N L

UTH

ER K

ING

DR

VEL

R P

HIL

LIP

S

Bronzeville

DeerDistrict

HistoricThirdWard

Milwaukee Intermodal

Station

ST P

AU

L A

VE

MIL

WA

UK

EE S

T1s

t STWalker’s

Point

BUILDING on our MOMENTUM

2019-0515

Page 4: Building on our MomentumMomentum · adjusts the $20M already approved by the Common Council in 2016 and identifies an additional $26.8M. TID Funding Uses ... Envisioned as a green

Vel R. Phillips PlazaThe Path Forward

THE PROJECTConstruct an approximately 0.9 acre urban plaza at Vel R. Phillips Ave. and Wisconsin Ave. at the site of an existing city-owned parking lot

Streetcar traverses through the plaza with level boarding

Envisioned as a green oasis with groves of trees and a future pavilion/café

COSTS AND FUNDING• Approximately $5M to complete

design and construction of the plaza

• Funded through nearby local tax incre-ment financing

SCHEDULE• September 2019:

Complete design of plaza

• October 2019: Commence plaza construction

• July 2020: Plaza open before DNC

WHY?• Creates an exciting urban gateway

to downtown Milwaukee, the convention center, and DNC

• Sets the stage for a unique transit-oriented development opportunity

• Helps to catalyze an underutilized parcel for a higher, better use than surface parking

• Creates a new front door and adds an active and vibrant public-space to Westown’s growing list of exciting developments

BUILDING on our MOMENTUM

2019-0515

Page 5: Building on our MomentumMomentum · adjusts the $20M already approved by the Common Council in 2016 and identifies an additional $26.8M. TID Funding Uses ... Envisioned as a green

JEFFREY S. POLENSKE, PECommissioner of Public Works City of Milwaukee Department of Public Works841 North Broadway, Room 501 Milwaukee, WI 53202 (414)286-3301 [email protected]

Further Questions?Contact information

All Aboard!The $46.8M requested will construct an extension to Wisconsin Avenue and prepare the remainder of the Bronzeville to Walker’s Point Route for federal funding opportunities.

Common Council meeting

MAY 29

Zoning, Neighborhoods, and Development Committee meeting

MAY 212019

Redevelopment Authority of the City of Milwaukee meeting

MAY 16

Local funding plan finalized/submitted

MAY 1

I M M E D I AT E NEXT STEPS

Proven Economic DevelopmentDevelopment facilitated by the streetcar generates new tax base that benefits the entire city.

THE VALUE• 435 apartment units under construction or planned directly on the M-Line or L-Line

• 660 new hotel rooms under construction or planned along the M-Line or L-Line

• 27.9% growth in new property value from 2015-2018 within 1/4-mile of the M-Line

• Downtown represents 3.5% of the City’s land area, but represents 22.6% of the City’s assessed value

THE PROJECTSSome of the City’s largest projects are right along the streetcar route:

• BMO Harris Tower (see photo, right): 25-story, $132M tower development

• Couture: $125 million, 44-story residential tower

• Countless other developments have referenced the streetcar in their decisions to develop property