Building for Learning ProjectPhoto Progress Report 3

October 2009 – November 2009

Project commencement 21st September 2009

Internal Demolition Begins 6th Oct 2009

Classrooms 6-9 Demolition continues Oct 2009

Rooms emptied, carpets, ceilings, all electrics wiring removed ready for 1st storey construction and concrete slab floor

Racking construction for refurbishment storage 14th Oct 2009

Demolition continues Oct 2009

Corporate Services area refurbishment 19th Oct 2009

Windows removed Ceiling Fans replaced

Floor demolition 19th Oct 2009

Graeme Connelly supervising wall demolition 21st Oct 2009

Internal framing and windows being cut in 27th Oct 2009

Framing and floors added 28th Oct 2009

Staff inspections of works

Outside area demolition ready for major works to begin 29th Oct 2009

1st Storey works commences November 09

Scaffolding up early November

Room demolition – mid November

Some of the removed materials 24th November

Roof on – Roof Off (29th November 2009)

Over a period of about 2 weeks the roof and all timber roof trusses, wiring, air-conditioners, chimneys and a satellite dish were removed and prepared for a new 1st storey floor slab to be created.

This change meant that the possums who had taken residence in the ceiling over the last 100+ years have now moved on!!!