building a legacy rebuilding providence public schools

17
06/18/22 1 Building a Legacy Rebuilding Providence Public Schools 2009 Q1 Report

Upload: yasuo

Post on 12-Jan-2016

48 views

Category:

Documents


2 download

DESCRIPTION

Building a Legacy Rebuilding Providence Public Schools. 2009 Q1 Report. Overview. Required by School Board Resolution Timely Information to the School Board and Public Historical Reference for the Program Overall Focus will be on Phase I projects, estimated present value cost - $384MM - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Building a Legacy Rebuilding Providence Public Schools

04/21/23 1

Building a LegacyRebuilding Providence Public Schools

2009 Q1 Report

Page 2: Building a Legacy Rebuilding Providence Public Schools

04/21/23 2

Overview

• Required by School Board Resolution

• Timely Information to the School Board and Public

• Historical Reference for the Program

• Overall Focus will be on Phase I projects, estimated present

value cost - $384MM

• Targeted Focus on Active Projects

Page 3: Building a Legacy Rebuilding Providence Public Schools

Keys for Review

• Strikethrough means outstanding issue has been resolved

• Project comments may be updated and not show comments

from previous report

04/21/23 3

Page 4: Building a Legacy Rebuilding Providence Public Schools

04/21/23 4

Active Projects

• Alvarez (f/k/a Adelaide Avenue) High School

• Hanley Career and Technical High School (“Hanley”)

• Providence Career and Technical Academy (“PCTA”)

• Free Standing Athletic Complex

• Nathan Bishop Middle School

Page 5: Building a Legacy Rebuilding Providence Public Schools

04/21/23 5

Active ProjectsAlvarez (f/k/a Adelaide Avenue)

High School

Comments

• Opened on time September

2007

• 575 students in grades 9-11

Outstanding Issues

• Access route to the building

still pending

Page 6: Building a Legacy Rebuilding Providence Public Schools

04/21/23 6

Active ProjectsHanley Career and Technical School

Comments

• Estimated cost is $22 million

• Part of RIDE’s $90 million

approval (includes Hanley, PCTA

and Athletic Complex)

• Programming: Culinary,

Cosmetology, Graphic Arts,

Automotive

Outstanding issues

• Ready for occupancy August

2009

• No known outstanding issues at

this time

• Move Culinary and Cosmetology

from West Broadway building

October 2009

Page 7: Building a Legacy Rebuilding Providence Public Schools

04/21/23 7

Active ProjectsProvidence Career and

Technical Academy (“PCTA”)

Comments

• Estimated cost of $50 million

• Part of RIDE’s $90 million

approval (includes Hanley, PCTA

and Athletic Complex)

• Programming: Masonry, HVAC,

Electrical, Plumbing, Carpentry

Outstanding issues

• Obtain Certificate of Occupancy

• Completion and occupancy

October 2009

Page 8: Building a Legacy Rebuilding Providence Public Schools

Active ProjectsProvidence Career and

Technical Academy (“PCTA”)

Page 9: Building a Legacy Rebuilding Providence Public Schools

Active ProjectsProvidence Career and

Technical Academy (“PCTA”)

Page 10: Building a Legacy Rebuilding Providence Public Schools

Active ProjectsProvidence Career and

Technical Academy (“PCTA”)

Page 11: Building a Legacy Rebuilding Providence Public Schools

04/21/23 11

Active ProjectsAthletic Complex

Comments

• Estimated cost of $18 million

• Part of RIDE’s $90 million approval

(includes Hanley, PCTA and Athletic

Complex)

• Will house track and field and other

indoor sports events

• Significant community interest in

using the facility

Outstanding issues

• Receive Certificate of Occupancy

• Install bleachers/furniture

• Design process for receiving/granting

requests from the community to use

the facilities

• Expected occupancy date in

November 2009

Page 12: Building a Legacy Rebuilding Providence Public Schools

Active ProjectsAthletic Complex

Page 13: Building a Legacy Rebuilding Providence Public Schools

04/21/23 13

Active ProjectsNathan Bishop Middle School

Comments

• Estimated cost of $35 million

• Program designed with community

advisement

• First facility proposal approved under

State’s revised review process

Outstanding issues

• Temporary Certificate of Occupancy /

Certificate of Occupancy

• Partial completion September 2009,

students and faculty will be able to

occupy

• Completion of library, auditorium,

third floor, landscaping

Page 14: Building a Legacy Rebuilding Providence Public Schools

Warm, Safe and Dry Projects

• $11.5 million in FY 2007

• FY 2008/2009

– $2.0 million for 25 projects completed this past summer at 16 schools

– $750,000 for 5 projects scheduled for this fall at 5 schools

• FY 2009/2010

– General Assembly required approval for $23 million Warm, Safe and Dry

04/21/23 14

Page 15: Building a Legacy Rebuilding Providence Public Schools

Phase I Projects

04/21/23 15

Phase I Projects

School Facility

Ade

laid

e

Cen

tral

FSP

EF

Han

ley

Bis

hop

CT

E

W B

road

way

Mt.

Ple

asan

t

Wes

t

Fei

nste

in

Asa

Mes

ser

Mes

ser

Ann

ex

Lau

rel H

ill

L.H

.Ann

ex

1 Included in Rebuilding a Legacy Phase I2 Options Currently Under Review3 School Board Approval4 Building Committee Recommendation NA NA NA NA5 Final School Board and City Council Approval6 Facility Architects Identified7 RIDE Phase I Approval 8 RIDE Phase II Approval 9 Board of Regents Approval10 General Assembly Approval NA NA NA NA NA NA11 Bonds Sold12 Construction Underway13 Construction Complete14 Outstanding Final Issues Resolved

= Complete = Ongoing = Has not Begun

Act

ion

Step

s

Alv

arez

PC

TA

Phase I Projects

School Facility

Ade

laid

e

Cen

tral

FSP

EF

Han

ley

Bis

hop

CT

E

W B

road

way

Mt.

Ple

asan

t

Wes

t

Fei

nste

in

Asa

Mes

ser

Mes

ser

Ann

ex

Lau

rel H

ill

L.H

.Ann

ex

1 Included in Rebuilding a Legacy Phase I2 Options Currently Under Review3 School Board Approval4 Building Committee Recommendation NA NA NA NA5 Final School Board and City Council Approval6 Facility Architects Identified7 RIDE Phase I Approval 8 RIDE Phase II Approval 9 Board of Regents Approval10 General Assembly Approval NA NA NA NA NA NA11 Bonds Sold12 Construction Underway13 Construction Complete14 Outstanding Final Issues Resolved

= Complete = Ongoing = Has not Begun

Page 16: Building a Legacy Rebuilding Providence Public Schools

04/21/23 16

Action StepsJuly – December 2009

• School Board Approval– Capital Plan– Update of facilities Master Plan– Phase I Next Steps

• Bonds to be sold– $23 million for Warm, Safe and Dry

• Projects completed– Outstanding issues at Alvarez (Adelaide) resolved– Nathan Bishop– PCTA (including Hanley)– Athletic Complex

Page 17: Building a Legacy Rebuilding Providence Public Schools

Next Steps – July - December

School Board Approval

• Capital Plan

• Phase I Next Steps

04/21/23 17