Builders’ Liens and OH&S: NOT TO BE FORGOTTEN Presented by: Collin K. Hirschfeld to Saskatchewan P3 Summit 2014 Date: September 9, 2014

Upload: arianna-apple

Post on 14-Dec-2015

217 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Builders’ Liens and OH&S: NOT TO BE FORGOTTEN Presented by: Collin K. Hirschfeld to Saskatchewan P3 Summit 2014 Date: September 9, 2014

Builders’ Liens and OH&S:NOT TO BE FORGOTTEN

Presented by: Collin K. Hirschfeld to Saskatchewan P3 Summit 2014

Date: September 9, 2014

Page 2: Builders’ Liens and OH&S: NOT TO BE FORGOTTEN Presented by: Collin K. Hirschfeld to Saskatchewan P3 Summit 2014 Date: September 9, 2014

AGENDA

Overview of Builders’ Liens

Trust ProvisionsLien ProvisionsHoldback ProvisionsPractical Considerations

OH&S

Prime ContractorRequired WorksitePrime Contractor Obligations

Page 3: Builders’ Liens and OH&S: NOT TO BE FORGOTTEN Presented by: Collin K. Hirschfeld to Saskatchewan P3 Summit 2014 Date: September 9, 2014

BUILDERS’ LIENS

Page 4: Builders’ Liens and OH&S: NOT TO BE FORGOTTEN Presented by: Collin K. Hirschfeld to Saskatchewan P3 Summit 2014 Date: September 9, 2014

PRELIMINARY THOUGHTS

Pay attention to the definitions and concepts under the Act, like:

• Contract• Subcontract• Substantial performance (section 3)• Completion (section 4) (NEW)• ALL APPLY TO A P3 SITUATION

Page 5: Builders’ Liens and OH&S: NOT TO BE FORGOTTEN Presented by: Collin K. Hirschfeld to Saskatchewan P3 Summit 2014 Date: September 9, 2014

TRUST PROVISIONS

Three types

Owner, Contractor, Subcontractor

If have non-monetary consideration, the value can be part of the trust

Page 6: Builders’ Liens and OH&S: NOT TO BE FORGOTTEN Presented by: Collin K. Hirschfeld to Saskatchewan P3 Summit 2014 Date: September 9, 2014

TRUST PROVISIONS (CONT’D)

Directors and others in control can be liable for breach of trust

Have to assent or acquiesce in conduct knew or ought to have known was breach

Two years from completion to sue

Page 7: Builders’ Liens and OH&S: NOT TO BE FORGOTTEN Presented by: Collin K. Hirschfeld to Saskatchewan P3 Summit 2014 Date: September 9, 2014

LIEN PROVISIONS

Arises as soon as work or materials are provided to a project

Provided doesn’t necessarily mean actually on site

Is a lien on the real property and the materials for as much as remains unpaid

Page 8: Builders’ Liens and OH&S: NOT TO BE FORGOTTEN Presented by: Collin K. Hirschfeld to Saskatchewan P3 Summit 2014 Date: September 9, 2014

LIEN PROVISIONS (CONT’D)

Can have a general lien on more than one parcel

If you can’t identify which piece of land was improved

Cannot register against Crown landbut serve Crown

Page 9: Builders’ Liens and OH&S: NOT TO BE FORGOTTEN Presented by: Collin K. Hirschfeld to Saskatchewan P3 Summit 2014 Date: September 9, 2014

LIEN PROVISIONS (CONT’D)

Lien is a charge againstHoldbackAny additional amounts owing

Needs to be registered within 40 days of:

Substantial completionAbandonmentCompletion

Page 10: Builders’ Liens and OH&S: NOT TO BE FORGOTTEN Presented by: Collin K. Hirschfeld to Saskatchewan P3 Summit 2014 Date: September 9, 2014

LIEN PROVISIONS (CONT’D)

Two ways to claim lien

Claim of LienAttaches to land and holdback

Can discharge in whole or in part

BUT cannot be revived

Page 11: Builders’ Liens and OH&S: NOT TO BE FORGOTTEN Presented by: Collin K. Hirschfeld to Saskatchewan P3 Summit 2014 Date: September 9, 2014

LIEN PROVISIONS (CONT’D)

Written Notice of Lien

Binds other 90% Effective in stopping project

Cuts both ways though Can still pay other funds if holdback lien amount Can withdraw and reserve

Page 12: Builders’ Liens and OH&S: NOT TO BE FORGOTTEN Presented by: Collin K. Hirschfeld to Saskatchewan P3 Summit 2014 Date: September 9, 2014

HOLDBACK PROVISIONS

Each payer in the pyramid has to maintain

Applies regardless of payment terms under the contract

Mortgagee may maintain

Page 13: Builders’ Liens and OH&S: NOT TO BE FORGOTTEN Presented by: Collin K. Hirschfeld to Saskatchewan P3 Summit 2014 Date: September 9, 2014

HOLDBACK PROVISIONS (CONT’D)

Is inviolable

Can’t be used to complete project

But not forever – 40 day period

Can be sued if fail to release

Page 14: Builders’ Liens and OH&S: NOT TO BE FORGOTTEN Presented by: Collin K. Hirschfeld to Saskatchewan P3 Summit 2014 Date: September 9, 2014

HOLDBACK PROVISIONS (CONT’D)

Owner has to maintain a holdback trust account

Crown does not have to maintain a holdback trust account

Page 15: Builders’ Liens and OH&S: NOT TO BE FORGOTTEN Presented by: Collin K. Hirschfeld to Saskatchewan P3 Summit 2014 Date: September 9, 2014

PRACTICAL CONSIDERATIONS

Liens can be lapsed under Land Titles Act

Section 47 direct payment

Section 56 application (no notice)

Section 57 application (holdback)

Page 16: Builders’ Liens and OH&S: NOT TO BE FORGOTTEN Presented by: Collin K. Hirschfeld to Saskatchewan P3 Summit 2014 Date: September 9, 2014

PRACTICAL CONSIDERATIONS

Can request information from owner or mortgagee

Can be questioned on lien claim

Cannot contract out of Act

Can argue substantially complied with form

Page 17: Builders’ Liens and OH&S: NOT TO BE FORGOTTEN Presented by: Collin K. Hirschfeld to Saskatchewan P3 Summit 2014 Date: September 9, 2014

PRACTICAL CONSIDERATIONS

Pay attention to if there is a certificate of substantial completion

Can request certification of completion of subcontract or contract

Important because it can affect when holdback is released

Page 18: Builders’ Liens and OH&S: NOT TO BE FORGOTTEN Presented by: Collin K. Hirschfeld to Saskatchewan P3 Summit 2014 Date: September 9, 2014

PRACTICAL CONSIDERATIONS

Is allowance for liens filed outside 40 days

But affects what you attach

Owner could payout funds and you are left with nothing

Page 19: Builders’ Liens and OH&S: NOT TO BE FORGOTTEN Presented by: Collin K. Hirschfeld to Saskatchewan P3 Summit 2014 Date: September 9, 2014

PRACTICAL CONSIDERATIONS

Are two holdback funds

Pre-substantial completionPost-substantial completion

Page 20: Builders’ Liens and OH&S: NOT TO BE FORGOTTEN Presented by: Collin K. Hirschfeld to Saskatchewan P3 Summit 2014 Date: September 9, 2014

PRACTICAL CONSIDERATIONS

Holdback on large contracts

Has to be over 1 year to complete

Value has to be over $25M

Allows for yearly release of holdback

Page 21: Builders’ Liens and OH&S: NOT TO BE FORGOTTEN Presented by: Collin K. Hirschfeld to Saskatchewan P3 Summit 2014 Date: September 9, 2014

OH &S

Page 22: Builders’ Liens and OH&S: NOT TO BE FORGOTTEN Presented by: Collin K. Hirschfeld to Saskatchewan P3 Summit 2014 Date: September 9, 2014

PRIME CONTRACTOR

Effective January 1, 2015

Applies to construction, forestry, and oil and gas industries

Applies to a required worksite

Page 23: Builders’ Liens and OH&S: NOT TO BE FORGOTTEN Presented by: Collin K. Hirschfeld to Saskatchewan P3 Summit 2014 Date: September 9, 2014

REQUIRED WORKSITE

Has 10 or more self-employed persons or workers under the direction of two or more employers

Page 24: Builders’ Liens and OH&S: NOT TO BE FORGOTTEN Presented by: Collin K. Hirschfeld to Saskatchewan P3 Summit 2014 Date: September 9, 2014

WHO IS THE PRIME CONTRACTOR

Party who enters agreement with owner to be the prime contractor

OR

If no agreement, owner of the worksite is the prime contractor

Page 25: Builders’ Liens and OH&S: NOT TO BE FORGOTTEN Presented by: Collin K. Hirschfeld to Saskatchewan P3 Summit 2014 Date: September 9, 2014

OBLIGATIONS OF PRIME CONTRACTOR

Gather all policies, procedures and safe work practices of all employers and self-employed parties on site

Coordinate activities at the work site affect health and safety

Page 26: Builders’ Liens and OH&S: NOT TO BE FORGOTTEN Presented by: Collin K. Hirschfeld to Saskatchewan P3 Summit 2014 Date: September 9, 2014

OBLIGATIONS OF PRIME CONTRACTOR (CONT’D)

Ensure all parties on site have adequate and appropriate policies etc. re safety and ensure compliance with them

Prepare written plan prior to work that outlines above and lists supervisors of parties on site

Page 27: Builders’ Liens and OH&S: NOT TO BE FORGOTTEN Presented by: Collin K. Hirschfeld to Saskatchewan P3 Summit 2014 Date: September 9, 2014

OBLIGATIONS OF PRIME CONTRACTOR (CONT’D)

Identify hazards and inform

Ensure parties on site eliminate hazards identified before work starts OR identified after work starts.

Page 28: Builders’ Liens and OH&S: NOT TO BE FORGOTTEN Presented by: Collin K. Hirschfeld to Saskatchewan P3 Summit 2014 Date: September 9, 2014

Thank You!