1BUSINESS SYSTEMS IMPLEMENTATION (BSI) AMWAY ASIA PACIFICBUSINESS SYSTEMS IMPLEMENTATION (BSI) AMWAY ASIA PACIFIC

BSI Status ReportMay 2016

Prepared by:

Program Management OfficeBSI - APAC

2BUSINESS SYSTEMS IMPLEMENTATION (BSI) AMWAY ASIA PACIFIC 2

BSI Status Report – May 2016Executive Summary (1/2)

Project Status Highlights

BSI Overall • ATLAS Solution Confirmation documentation preparation & approvals in progress

• RedPrairie Philippines Project Schedule ended

• RedPrairie Indonesia testing and training on track

• JDA System Integration testing (SIT) for Malaysia completed.

ATLAS • Approvals for BR030 & BPDs delayed, catch up in good progress. No major impact to overall

timeline as of now

• Philippines market will lead the initiative to get Bureau Of Inland Revenue (BIR) certification,

supported by BSI.

• Supplier & Customer data cleansing in progress and on track

• Drafted ATLAS APAC OCM Road Map for PH, KR, Busan and Indonesia (2016-17)

RedPrairie

(including JDE)

• Philippines: Hypercare support phase has ended on 19th May 2016

• Indonesia: Configuration and Validation Phase & SME training completed

• Indonesia System Integration Testing (SIT) is in progress

• Korea: Business Requirement finalization is in progress

JDA • SIT sign off (Malaysia & Brunei) have been completed & approved.

• Project work plan Malaysia & Brunei has been finalized and communicated to Malaysia & Brunei

markets. Project work plan for remaining markets (Thailand, Korea & Japan) are still in progress

• User training has been conducted for Malaysia & Brunei

hybrisOrder Management (OM)

• Malaysia, Singapore and Brunei (MSB) design documents have been reviewed and approved by

business

• Vietnam BRD review (Process & UI/UX) has conducted and will be completed by the end of this

month

• Business User Testing for MSB planning and preparation has been initiated

• Draft timeline shared for Web Modernization in Vietnam, Indonesia and Philippines

DFC • Korea - QA environment completed and Prod in progress

• Japan – QA environment completed and Prod in Progress

Resource

Management

• Current total BSI headcount is 42

• Recruitment activity is on-going

3BUSINESS SYSTEMS IMPLEMENTATION (BSI) AMWAY ASIA PACIFIC 3

BSI Status Report – May 2016Executive Summary (2/2)

Key Risks (R) / Issues (I)

• ATLAS: Philippines Statutory Reports requires BIR (Biro of Inland Revenue). Certification effort in progress (R)

• RedPrairie: Dummy SKU solution for Thailand, Vietnam, Malaysia and Singapore are still in discussion phase. Each market has their action items and there are no any concrete solution defined at the moment. CER has not been raised should any customization is needed. (I)

• RedPrairie: Hardware purchase and setup for Indonesia are not ready before the beginning of User Acceptance Testing (UAT) (I)

• JDA: Inaccurate parameter input and data records may lead to the delay of the user acceptance test activities. Proactive discussion between JDA project team and Malaysia & Brunei supply chain planner is required to obtain accurate input (R)

• Hybris: Other key initiatives are impacting Japan hybris implementation. This is being discussed with Japan management team (R)

• Hybris: Alignment of Web Modernization & hybris Order Management scope/deliverables & timeline needs to be further discussed and agreed with

SEA IT team (R)

• Hybris: Facing challenges in freezing the requirements for MSB which can potentially impact the timeline for subsequent phases (R)

4BUSINESS SYSTEMS IMPLEMENTATION (BSI) AMWAY ASIA PACIFIC 4

BSI Status Report – May 2016

Enterprise Resource Planning (ERP)Regional

AssessmentPrepare & Engage

Solution Confirmation

Functional Specification

Build ` Deploy Hypercare

Deliverables Status Highlights

Scope/Requirement • Approvals for BR030 & BPDs delayed, catch up in good progress. No major impact to overall

timeline as of now

• Philippines market will lead the initiative to get Bureau Of Inland Revenue (BIR) certification,

supported by BSI.

Data Management • Supplier & Customer data cleansing in progress and on track

• Updated on the progress status by Regional HR at ASSC for Employee data – name and

department change for Oracle – EBS interface..

• Identified and mapped existing global CV40 document for each Philippines data conversion

element for further review by Deployment and BSI team.

Change Management • Constant updating of Change Impact Register based on deep dive discussions & BPD Review

session

• Drafted ATLAS APAC OCM Road Map for PH, KR, Busan and Indonesia (2016-17)

IT • BR030 review completed. Now preparing the Functional Design Documents (FDDs) for OMS

related changes and DFC integration. (50% task completed).

Tasks Planned – Next Month (June 2016)

• Completion and approval for P2 BR30 document

• Completion of MD50 preparation for P1 and RICE list & BR100 for P2 & P3

• Initiated and scheduled discussion with ATLAS & JDE team in June to confirm item data cleansing and conversion requirement for Philippines.

• Begin Training Needs Assessment

• Begin review process for Philippines test scenarios

• APAC Tech Workshop to be held in Kuala Lumpur late June

• Preparation of design document on OMS related changes & DFC Integrations to be closed by June, 2016.

Key Risks (R) / Issues (I)

• Philippines Statutory Reports requires BIR (Biro of Inland Revenue). Certification effort in progress(R)

5BUSINESS SYSTEMS IMPLEMENTATION (BSI) AMWAY ASIA PACIFIC 5

BSI Status Report – May 2016

Warehouse Management

Phase & Timeline

Deliverables Status Highlights

Scope/Requirement • Philippines:

• Hypercare support phase has ended on 19th May 2016

• Indonesia:

• Configuration and Validation phase has been completed

• System Integration Testing (SIT) is in progress

• Korea:

• Business Requirement finalization is in progress

Data Management • Indonesia:

• Local Item dimension validation activity has completed except for 9 assembly items which may require Indonesia team to manually enter into JDE directly.

• Local item data will be loaded into JDE-QA by 03 June 2016 and Prod the following week.

• Re-labelling activity of new SKU number for all affected Local items has commenced.

Site Assessment Harmonize Solutioning BuildTesting & Training

Deploy HypercarePhilippines

Site Assessment Harmonize Solutioning BuildTesting & Training

Deploy Hypercare

Site Assessment Harmonize Solutioning BuildTesting & Training

Deploy Hypercare

Indonesia

Vietnam

18 Apr 16

18 Jul 16

18 Sep 16

6BUSINESS SYSTEMS IMPLEMENTATION (BSI) AMWAY ASIA PACIFIC 6

BSI Status Report – May 2016

Warehouse Management

Deliverables Status Highlights

Change Management • Philippines:

• All OCM activities has been completed, PH will be used as an example of a RP warehouse in sharing and learning sessions with other markets

• Indonesia:

• Training - Completed SME Training

• Communications - Completed warehouse and affiliate announcement, WIIFM, posters, pre-launch survey

• Change Initiatives - Completed Change Agent Training and Resistor Management Training; mini team building exercise done with all staff

IT • Indonesia:

• IT support during SIT is in progress

• Korea:

• IT requirements finalization is in progress

Tasks Planned – Next Month (June 2016)

• Completion of System Integration Testing activities for Indonesia

• Stock movement from old to new SKU will take place during mid-year Stock Count day on 05 June 2016

• JDE roll out for Indonesia

• Indonesia User Acceptance Testing (UAT) and End User Training (EUT) to commence

• Change Pulse 1, End User Training and Best Practice sharing session with Philippines warehouse manager Helen

Key Risks (R) /Issues (I)

• Dummy SKU solution for Thailand, Vietnam, Malaysia and Singapore are still in discussion phase. Each market has their action items and there are no any concrete solution defined at the moment. CER has not been raised should any customization is needed. (I)

• Hardware purchase and setup for Indonesia are not ready before the beginning of User Acceptance Testing (UAT) (I)

7BUSINESS SYSTEMS IMPLEMENTATION (BSI) AMWAY ASIA PACIFIC 7

Site Assessment Harmonize Solutioning BuildTesting & Training

Deploy Hypercare

BSI Status Report – May 2016

Deliverables Status Highlights

Scope/Requirement • SIT sign off (Malaysia & Brunei) has been completed & approved.

• Project work plan Malaysia & Brunei has been finalized and communicated to Malaysia & Brunei markets.

Project work plan for remaining markets (Thailand, Korea & Japan) are still in progress

• User training has been conducted to Malaysia & Brunei Supply Chain Planners.

• Parameter input & data records has been finalized with the Malaysia & Brunei supply chain planner.

Enhancement to obtain most accurate forecast will be ongoing until the JDA go live phase for Malaysia &

Brunei

Data Management • NA

Change Management • Refresher training (1 week) for Malaysia completed

• Self learning (2 weeks) for Malaysia completed

• Sharing of Global JDA Newsletter

IT • Completion of configuration & setup on QA environment for Malaysia user acceptance test.

• Completion of DFC refresh for Malaysia user acceptance test

Shop Replenishment Planning

Tasks Planned – Next Month (June 2016)

• Completion of the Malaysia & Brunei User Acceptance Test (UAT)

• End User Training to start, with QA Environment as the platform

• Finalization on Thailand, Korea & Japan project timeline

• Thailand: Completion of translation of Work Instructions

Key Risks (R) /Issues (I)

• Inaccurate parameter input and data records may lead to the delay of the user acceptance test activities. Proactive discussion between JDA

project team and Malaysia & Brunei supply chain planner is required to obtain accurate input (R)

8BUSINESS SYSTEMS IMPLEMENTATION (BSI) AMWAY ASIA PACIFIC 8

Regional Assessment

Market Assessment

Design BuildTesting & Training

Release Hypercare

BSI Status Report – May 2016

Deliverables Status Highlights

Scope/Requirement • Malaysia, Singapore and Brunei (MSB) design documents are reviewed and approved by

business

• Vietnam BRD review (Process & UI/UX) has conducted and will be completed by the end of this

month

• Business User Testing for MSB planning and preparation has been initiated

• Planning for Regional Core Capability build has started

Data Management • Not started

Change Management • OCM strategy & activities are being reviewed with market SMEs.

• Detail OCM activity Work Breakdown Structure (WBS) is being defined and will be included in

overall project WBS

IT • Build effort for MSB is in progress by the IT vendor Nagarro; Sprint 2 has been completed and

Sprint 3 is in progress

• Draft timeline shared for Web Modernization in Vietnam, Indonesia and Philippines

Tasks Planned – Next Month (June 2016)

• Conduct Business User Testing for MSB (Order Management & ABO Management)

• Completion of project timeline & organization chart for Vietnam, Philippines and Indonesia

• Hybris ad MAGIC Workshop in Japan (June 13 - 17)

• Continue discussion with IT team on ATLAS impact on hybris and agree on strategies & approaches

Key Risks (R) /Issues (I)

• Other key initiatives are impacting Japan hybris implementation. This is being discussed with Japan management team (R)

• Alignment of Web Modernization & hybris Order Management scope/deliverables & timeline needs to be further discussed and agreed with SEA

IT team (R)

• Facing challenges in freezing the requirements for MSB which can potentially impact the timeline for subsequent phases (R)

Order Management

9BUSINESS SYSTEMS IMPLEMENTATION (BSI) AMWAY ASIA PACIFIC 9