bruce power radiological event november-december, 2009 · 09.04.2014 · 1 bruce power radiological...
TRANSCRIPT
1
Bruce PowerRadiological Event
November-December, 2009
Overview of the 2009 Radiological Eventand
Lessons Learnedfor the
Bruce Power Units 1 & 2 Restart Leadership TeamPresented to:
The Connecticut Local Section of the American Nuclear SocietyEast Windsor, CT
byMichael D. Quinn
April 9, 2014
1
2
Discussion Overview
• Site and Project Overview
• What Happened
• Event Causes, Consequences, and Significance
• Effective Lessons to be Learned Review
• Takeaways
2
Bruce A Units 1-4
• Had been shut down in the 1990s
• Decision to restart/ refurb in 2002
• Units 3&4 patched and running by 2004
• Units 1&2 need complete refurb starting~2007
• Schedule: four years
3
The Setup in Late 2009
• Reactor rebuilds at Bruce U1 and U2 in Year 3
• Feeder tube preparation for tie-in to pressuretubes
• Flapper wheeling/ grinding of the 480 inletand 480 outlet tubes
6
Figure 1.1.1
Top: section of feederpipe with J shaped bevel;
Bottom left:grinding of inner surfaceof feeder tube;
Bottom right: grinding ofouter surface of feeder tube.
The Job at the Local Level
10
Consequences• 557 workers more or less internally exposed to transuranics
between 11/24 and 12/21, 2009; Extent of Condition: >900
• Very unsettled workforce
• Vault closed both Units 1&2 for 42 days (early February 2010)
• Regulatory scrutiny by Canadian Nuclear Safety Commission
• About 10 exposed to alpha radiation received radiation dosesgreater than 500 mrem; all were less than 1,000 mrem;
• Extensive urine and fecal sampling regime
• Dose data handling regime
• Recovery team of 24 established for 11 months (6 Countries)
• $$
• Many more
13
14
Significance
– Over-dose potential if we do not effectively address
– Protection model improvements
– Nuclear workers taking more ownership in theirRP practices and their dose
– An agreed-upon approach with OPG
– Turn-key projects at risk unless Licensee ownershipimproves
– Increased regulatory interest and impact
– Increased costs of doing business
14
Dosimetry Options
1. Measure in Urine
2. Measure in Feces
3. Lung counting
• Selected #1 – measure urine
• # 3 under evaluation
• Urine preferred to feces – samples easier toprovide and easier to handle
15
Present and Future Extent
Three phases:• Potential exposure before building tents
for feeder work (from 24 November to 28 November)
• Potential exposures after 28 Novemberuntil the end of feeder work(21 December 2009)
• Extent of condition assessment goingback several years through all units
16
The Isotopes . . . .
17
Nuclide
Half Life
years
Alpha Activity % Dose % Alpha energy (yield)
Pu238 87 38 16 5.5(72) 5.4(28)
Pu239
Pu240
24,000
6560
14 7 5.2(88) 5.1(11)
5.2(76) 5.1(24)
Pu241 14 Beta only small None
Am241 432 30 33 5.5(85) 5.4(13)
Cm242 0.5 0 0
Cm243
Cm244
28
18
18 12 5.8(73) 5.7(11)
5.8(100)
- Courtesy of Canberra
The Actions• Recovery Team plan developed with over 200 programmatic
and tactical actions
• Third Party Oversight (RSIC) brought in
• Dose modeling
• Designed and built two state of the art counting rooms: fieldlab and a spectroscopy lab
• Alpha Training by RSIC to over 1000 crafts
• Developed and delivered Rad Tech training to109 Green Men
• Action Plan became focal to the Restart Project
• Lessons to be Learned presentation to >500
18
Figure 2.6.4RADOS Whole Body Monitor
Post-Event
Figure 2.6.3Left: ICAM with Trolley Mount;
Right: Portable Air Sampler ("Gooseneck")
Figure 2.6.2 - Ludlum Model 12 Ratemeterwith Model 43-5 Alpha Detector
19
Sample Excerpt from Over 900 . . . .
21
NAME Union Contractor
CategoryA= <100,
B= 100-499,C= > 500
24Nov-21Dec-TotalAlpha
DAChrs(based on
0.26Bq/m3 for
a DAC)
Totalexposure(DAChrs)
Trade
1 A #233 A 22 Carpenter
2 B #244 A 81 Labourer
3 C #255 B 141 Labourer
4 A #266 B 98 Millwright
5 B #277 B 135 Electrician
6 C #288 C 522 Carpenter
7 A #299 C 650 Labourer
8 B #310 B 181 Labourer
9 C #321 B 442 Millwright
10 A #332 A 70 Boilermaker
11 B #343 A 15 Carpenter
12 C #354 A 18 Millwright
13 A #365 B 178 Boilermaker
14 B #376 B 231 Boilermaker
15 C #387 A 88 Boilermaker
16 A #398 A 4 Less than 10 Boilermaker
17 B #409 A 3 Less than 10 Electrician
18 C #420 A 35 Pipefitter
19 A #431 B 113 Millwright
22
Bruce PowerRadiological Event
November-December, 2009
Overview of the 2009 Radiological Eventand
Lessons Learnedfor the
Units 1 & 2 Restart Leadership Team
Michael D. QuinnJune 10, 2009 This LL
Workshopwas 2-3hours inlength
23
Objectives
• ‘Lessons Learned’ to be communicated withemphasis on their role in this event toenhance future conduct of RestartManagement and identified workgroups.
• The Challenger video will be used to facilitatediscussion and communicate the need toutilize lessons learned.
23
24
Effective Lessons to be Learned Review
is Critical to Two Specific Objectives:
• Not repeating the same or similar behaviors/mistakes in the Radiation Protection Program
• Not repeating the same or similar behaviors/mistakes in all Restart Programs
24
25
We Avoid Repeats By:
Improving the methods and processes thatidentify problems earlier
in a safer, better, higher quality,
schedule congruent, and
more cost-effective manner
25
26
The Occurrence Pyramid
Infractions/ Deviations ~1000
- adapted W.R. Corcoran 2001
Compromises ~100
Near-misses ~10
High Consequence Event
Less serious issues indicateprocess and
implementation challenges
High consequence events result fromcommand accountability issuesthat lead to program failures in:
• Human Performance• PI&R
• Safety Culture
Levels of Precursors
26
27
The Lessons are Learned by:
– Comprehensively enacting the event’s Corrective Actions– Leadership providing clear expectations and accountability– Decreasing the problem identification threshold to below the
‘near miss’ level (preferably lower), which encourages staff toreport problems
– And . . . . . . by fully engaging:
• The Restart Human Performance Program
• Problem Identification & Resolution (PI&R)(Corrective Action Program)
• Nuclear Safety Culture Concepts
27
28
Barriers to Effective Lessons Learned
There’s no leadershipinvolvement or commitment
We don’t have timefor this stuff - I havea milestone to meet
This is a lot of workfor something that doesn’t
apply to my work group
These lessons learnedare too general
to make a difference
Management just payslip service to
this stuff - nothing will change
Yeah . . . butmy project is different
I don’t know how to do this,and if I ask,
it’ll make me look stupid.
What’s the point -we’re almost done !
28
31
Radiological Event November-December 2009:Event Causes/ Contributors
(nearly all have important underlying factors)
1. Turn-Key Approach
2. ‘Unknown’ MaterialCondition
3. LTA Radiation workplanning procedure
4. Deficient source termdetermination
5. LTA Performance testingof tool
6. LTA RP knowledge
7. Tent installation . . . . . . .
8. NE Radiation workplacemonitoring
9. EPRI Guidelines (OPEXMissed)
10. LTA REPs
11. Unmonitored loosecontamination
12. LTA Bruce Poweroversight
Reference: RCA Alpha Event Report March 2010 31
33
Principles for aStrong Safety Culture
WANO/ INPOThe 8 Principles:
Everyone is personally responsiblefor nuclear safety.
Leaders demonstrate commitment tonuclear safety.
Trust permeates the organization.
Decision-making reflects safety first.
Nuclear technology is recognized asspecial and unique.
A questioning attitude is cultivated.
Organizational learning is embraced.
Nuclear safety undergoes constantexamination.
33
34
10. Ignorance -- “I didn’t know this was a hazard."
9. Lack of skill -- "I didn’t know what to do about it."
8. Mistrust of authority -- "They lied to us before about safety, so how do I
know they're telling the truth now?"
7. Personal experiences -- “Risk taking; Nothing bad ever happened to me
before by doing it this way, so why worry now?"
6. Lack of incentives -- "What's in it for me? Why should I follow this much
harder procedure?” (I’ll use my skills)
5. Mixed incentives -- "My boss tells me to report unsafe conditions but still expects me toget the job done on time and with less help.”
4. Inconsistent Accountability - "Nothing bad will happen to me if I ignore the hazard
or do things my own way."
3. Group norms -- "If I point out the hazard, my buddies will think I'm ratting on them;or if I insist on following some procedure, they'll think I'm a wimp"
2. Macho self-image -- "I can do this job in spite of the hazards, thrill of risk taking, I can be ahero, and others will respect me for it."
1. Personality factors -- "I know better - who needs to work that hard?”
“Who cares - it's not my problem.”
One More: Lack of clear expectations
Top 10 ReasonsNuclear Managers and Workers
Don't Comply withSafety Culture Expectations
- Adapted from Dr. Edgar Schein and INPO 34
35
Technical and StructuralCorrective Actions
Programs, Procedures, ProcessesAugmented Staff/ Recovery Team
Equipment Hardware/ Infrastructure
Lessons to be Learned:Engage existing organizational processes and tools, e.g.,
Human PerformanceProblem Identification and Resolution (PI&R)
(Blue Card reporting system/ Corrective Action Program)Nuclear and Radiological Safety Culture
Effective Self-Assessment/ OPEXKey Performance Indicators
Configuration Control/ Conduct of Operations
Behavioral and Cultural Actions
Provide clear expectations and accountabilityEstablish consistent roles, responsibilities, and authority
Role model and establish an open climate and cultureEffectively plan, organize, lead, and control processes
Provide timely information to LeadershipMake informed decisions
Effectively manage organizational interfaces- Picture by Ralph Clevenger
RP Event Corrective Actions and Lessons to be Learned
© 2010 Michael Quinn
35
36
Recapping
• People will make Skill, Rule and Knowledge-Based Errors
• Systems that make such errors less consequential (e.g., HumanPerformance, PI&R, Safety Culture) find and address the precursors
• High Reliability Organizations encourage the reporting of errors andconstantly seek ways to reduce errors and improve safety andreliability
• Serious consequences are preceded by missed patterns, manyprecursor opportunities, smaller incidents, and ‘near-miss’ events
• Interactions between organizations do contribute to events
• Most events have multiple causes (technical, structural, cultural,behavioural) that need to be carefully identified and addressed
• Enacted lessons Learned from event analysis can improveSafety Culture
36
37
Take-Away Lessons LearnedProgrammatic Areas
• Human Performance Program
• Incident reporting threshold levelas low as practical
• Corrective Action Program
• Nuclear Safety Culture
• Radiological Safety Culture
• Industrial Safety Culture
• Quality Programs
• Effective Self-Assessment/ OPEX
• Conduct of Operations
• Configuration Management
• Configuration Control
• Others ?
Leadership Practices
• Establish consistent roles,responsibilities, and authority
• Provide clear expectations andaccountability
• Enact and role model the tenetsof Safety Culture
• Effectively plan, organize, lead,and control processes
• Provide timely information to theRestart Leadership Team
• Make informed decisions
• Effectively manage organizationalinterfaces
37
41
References
• WANO GL 2006-02:“Principles for a Strong Nuclear Safety Culture”
• Root Cause Report: Alpha Contamination Event (November - December, 2009)
• Ishikawa Fishbone - 2009 Radiological Event by the Root Cause Team
• RP Recovery Plan dated April 28, 2010
• Event Contributors May 17, 2010 (Romanowich, Widmeyer, Quinn)
• Irving Janis, Victims of Groupthink, 1972
• Michael D. Quinn (various references)
41