North Link - Brooklyn Station 60% DesignOpen House

May 23, 2012

Page 2: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

• 6:00 pm – Open House• 6:30 pm – Presentation

• Introduction and Brooklyn Station Overview– Tracy Reed, U-Link Deputy Project Director

• Station and Landscape Design- Mark Reddington, Station Architect• STart Overview– Barbara Luecke, STart Program Manager• Station Art Concept- Annie Han + Daniel Mihalyo, Lead Pencil Studios• Next Steps• Questions and Answers-- Ron Endlich, North Link Deputy Project Director

• 7:45 pm – Return to Open House• 8:30 pm – Close

Tonight’s Agenda

Page 3: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

Link Light Rail System • 16 miles of light rail with 13

stations currently in service• University Link under

construction; opens 2016• ST2 Plan funded extensions

to Overlake, South King County, and Lynnwood

• 54 mile system

Page 4: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

• 4.3-mile light rail extension• Stations at U-District (Brooklyn),

Roosevelt and Northgate• Completion: 2021• 62,000 daily boardings added to

system by 2030

North Link(University District to Northgate)

Page 5: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

Facility Naming CriteriaSound Transit facility names will:

Reflect the nature of the environmentBe brief and easy to read and rememberComply with Americans with Disabilities Act and be limited to 30 charactersAvoid commercial referencesAvoid similar names or words in existing facility names

What do you think the station name should be? Please check a box.

U District StationBrooklyn StationNE 45th StreetOther (please specify):_____________________________

Page 6: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

Brooklyn Station

University of

Washington Station

Tunnel Alignment (From the University of

Washington Station to the Brooklyn Station)

Page 7: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

Brooklyn StationKey Features:• Station platform, 75-85 ft. underground

• Elevators, escalators and stairs• Bicycle parking• 12,000 daily boardings (2030)

• Constrained construction site

• Staging use of Brooklyn Avenue and NE 43rd followed by restoration to City Green Street principles

• Designed to accommodate future building above station

• LRRP reviewed 60% design on May 17

Page 8: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

Brooklyn Station ScheduleDRAFT

*As of 4/2012

Page 9: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link
Page 10: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

10

Page 11: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

11

Page 12: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

12

Page 13: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

13

Page 14: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

14

Page 15: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

15SITE PLAN

Page 16: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

16

Page 17: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

17

Page 18: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

18

Page 19: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

19

Page 20: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

20

Page 21: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

21

Page 22: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

22

Page 23: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

23

(65 feet zoning)

Page 24: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

24

Page 25: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

25

Page 26: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

26

Page 27: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

27

Page 28: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

28

Page 29: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

29

Page 30: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

30

Page 31: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

31

(65 feet zoning)

Page 32: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

32

Page 33: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

33

Page 34: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

34

Page 35: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

35

Page 36: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

36

Page 37: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

37

Page 38: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

38

Page 39: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

39

Page 40: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

40

Page 41: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

41

Page 42: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

42

Page 43: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

43

Page 44: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

44

Page 45: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

45

Page 46: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

46

Page 47: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

47

Page 48: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

48

Page 49: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

49

Page 50: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

David MarineInvoice No. 582012

Acct No. 62468.168100.61160Amount of $150.00

Installation at Cal Anderson Park, Seattle, University Link

Projec

STart (Sound Transit art program)

www.soundtransit.org/STart

Page 51: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link
Page 52: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link
Page 53: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link
Page 54: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link
Page 55: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

N

Page 56: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

W

Page 57: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link
Page 58: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link
Page 59: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

60 DEG CONE OF VISION

Page 60: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

50% NON-ARCHITECTURE

Page 61: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

40% NON-BUILDING

Page 62: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

AVG 33% REMAINS

Page 63: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

40% OF CITY

Page 64: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link
Page 65: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link
Page 66: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link
Page 67: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link
Page 68: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link
Page 69: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link
Page 70: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link
Page 71: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link
Page 72: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link
Page 73: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link
Page 74: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link
Page 75: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link
Page 76: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link
Page 77: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link
Page 78: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link
Page 79: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link
Page 80: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link
Page 81: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link
Page 82: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link
Page 83: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

Next Steps

• Review public comments

• Station name selection

• Demolition at Brooklyn Station – Early 2013

• 90% Design 2013

Page 84: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

Questions?

Page 85: Brooklyn Station 60% Design Open House presentation...• 6:00 pm – Open House • 6:30 pm – Presentation • Introduction and Brooklyn Station Overview – Tracy Reed, U-Link

Questions?

Request a briefing for your organization by contacting Wilbert Santos, Community Outreach Coordinator, at (206) 370-5516 or [email protected]

Visit Sound Transit’s Web site at www.soundtransit.org/northlink

Sign up for e-mail alerts at www.soundtransit.org

Click on “subscribe to E-mail alerts”