Briefing Paper for
Committee of
Public Accounts
12th October 2017 Transport Infrastructure Ireland
Briefing Paper for Committee of Public Accounts
Table of Contents
1. Introduction ............................................................................. 3
2. Background to TII .................................................................... 3
3. TII Grant Allocations 2016 ....................................................... 4
4. National Road Construction & Improvement ........................... 5
5. National Road Maintenance .................................................... 6
6. Regional & Local Roads ......................................................... 7
7. Public Private Partnerships (PPPs) ......................................... 7
8. Public Transport Construction and Improvement .................... 8
Appendix A: Roads Capital Programme Update
Capital Investment Plan Projects Other Major Projects Not in the Capital Investment Plan
Minor Schemes Programme Pavement Schemes Programme
Appendix B: Public Transport Capital Programme Update
Briefing Paper for Committee of Public Accounts
3
1. Introduction
Transport Infrastructure Ireland (TII) has been invited to attend a session of the Committee of Public Accounts. In order to assist the members of the Committee, TII is pleased to present this briefing paper. In this paper we set out some background information on:
TII’s Grant Allocations 2016;
Progress on Roads and Public Transport Capital Programme projects
2. Background to TII
Transport Infrastructure Ireland
Transport Infrastructure Ireland (TII) is a non-
commercial semi-State body which operates
under the aegis of the Department of Transport,
Tourism & Sport. Our mission is to provide high
quality transport infrastructure and services,
delivering a better quality of life and supporting
economic growth. TII was formed on 31st July
2015 from a merger of the Railway Procurement
Authority and the National Roads Authority.
TII's primary function is to provide an integrated approach to the development, maintenance and operation of the national road network and light rail infrastructure.
In relation to national roads, our key role is to secure the provision of a safe and efficient network of national roads. This includes responsibility for the planning and supervision of construction and maintenance of national roads. TII works with different partners to fulfil this role:
A number of major new motorways have been procured on a Public Private Partnership basis;
The remainder of the motorways and dual carriageways are maintained by contractors under long term contracts; and
Local authorities continue to work as road authorities for their respective areas.
In relation to light rail, the core functions of TII is to secure the provision of such light railway and metro railway infrastructure as may be determined from time to time by the National Transport Authority (NTA). Funding for light rail and metro railway infrastructure is provided by the NTA. This submission is limited to discussing the delivery aspects of light rail, as NTA is responsible for planning and funding of the light rail networks.
OUR MISSION STATEMENT “To provide high quality transport infrastructure and services, delivering a better quality of life and supporting economic growth”
Briefing Paper for Committee of Public Accounts
4
3. TII Grant Allocations 2016
The grant allocations to TII for national roads, forming part of the Department of Transport Tourism & Sport vote, were as follows:
€m (rounded)
2015 2016 2017
B.3.1 National Road Construction & Improvement 332 290 267
B.3.2 National Road Maintenance 38 39 37
B.3.4 Public Private Partnership Operations 59 82 132
Sub-total National Roads 429 411 462
The grant allocations relating to regional and local roads, administered by TII on behalf of the Department, were as follows:
€m (rounded)
2015 2016 2017
B.1.5(a) Regional & Local Road Maintenance Construction & Improvement
274 328 280
B.1.5(b) Regional & Local Road Maintenance & Management
43 43 45
Sub-total Regional & Local Roads 429 371 325
Total (National, Regional & Local Roads) 746 782 787
The total grant allocation to TII in 2016 for the Road Network was €782m.
Public Transport Grant allocations provided to TII by the National Transport Authority and forming part of Department of Transport Tourism & Sport vote, were as follows:
€m (rounded)
2015 2016 2017
Public Transport Grant 17 111 78
(5 months post-merger)
Administration
The grant allocation for the TII’s internal costs, and was €23m for 2015. This included the RPA costs for 5 months post-merger.
Briefing Paper for Committee of Public Accounts
5
€m (rounded)
2015 2016 2017
B.3.3 Administration 23 25 26
(5 months Post-merger)
4. National Road Construction & Improvement
Works during 2016 included the following:
121 pavement overlay projects
Planning and design work on 54 minor improvement schemes with 23 new minor schemes being introduced to the programme during 2016
Rehabilitation works on 119 bridges
69 safety improvements schemes
17 Signing & lining projects
The major schemes at construction were:
M11 Gorey Enniscorthy PPP
M17/M18 Gort to Tuam PPP
N25 New Ross Bypass PPP
During 2016 eleven minor projects opened to traffic namely:
N15 Blackburn Bridge Realignment Scheme Phase 1
N17 Carrownurlar to Ballindine (part of Gort to Tuam)
N20 Buttevant Streets
N53 Barronstown to Hackballs Cross
N56 Boyoughter to Kilkenny
N59 Rossow Bends
N59 Moycullen on line improvements
N61 Rathallen / Treanagry realignment scheme
N71 Releagh – Bonane Bends
N83 Forty Acres
Briefing Paper for Committee of Public Accounts
6
N84 Luimnagh realignment scheme
In accordance with the Government’s Capital Investment plan - Building on Recovery 2016 – 2021, work continued on the progression to construction on the following major schemes, all of which have planning approval:
N4 Collooney to Castlebaldwin
N5 Westport to Turlough
N7 Naas Newbridge upgrade (Contract awarded in September 2017)
N8/N40 Dunkettle
N22 Ballyvourney to Macroom
N56 Mountcharles to Inver (being delivered as a series of minor projects)
N56 Dungloe to the Glenties (being delivered as a series of minor projects)
N59 Moycullen Bypass
Also in accordance with Building on Recovery, work continued to bring the following major schemes through the planning process:
N2 Slane Bypass
N6 Galway City Transport Project
N21/N69 Foynes to Limerick
N28 Ringaskiddy to Cork
N72 Mallow Relief Road
One Major PPP contract commenced construction in 2016 which was the N25 New Ross bypass. This project along with the other two PPP projects, the M11 Gorey Enniscorthy and the M17/M18 Gort to Tuam, were the only Major projects at construction in 2016.
The N17/N18 Gort to Tuam opened to traffic on 27th September 2017.
5. National Road Maintenance
The national road maintenance allocation in 2015, 2016 and 2017 has remained largely unchanged and is €39m for 2016.
As recently as 2008 the maintenance budget was €58m, but this figure was cut sharply during the financial crisis and has not been increased subsequently.
The maintenance budget is used for drainage, signs, litter picking, grass cutting, verge trimming, pot hole filling, boundary and safety fence repairs, lighting, and the like, and for winter operations such as road weather information services, salt supply and distribution, and clearance of snow and ice. The maintenance budget also funds
Briefing Paper for Committee of Public Accounts
7
incident response activities on the M50 and other motorways and this is an increasing demand on maintenance funding.
6. Regional & Local Roads
The grant allocations for Regional & Local Roads, administered by TII on behalf of the Department of Transport, Tourism & Sport, totalled €371m in 2016.
7. Public Private Partnerships (PPPs)
TII has entered into thirteen road PPP Contracts and also a PPP contract for the provision of motorway service areas. Following the recent (27th Sept 2017) opening of the N17 Gort to Tuam scheme, PPP operated roads now comprise some 33 per cent of the c.1270km of motorway/dual carriageway network. Two PPP schemes are currently under construction i.e., the M11 Gorey-Enniscorthy scheme and the N25 New Ross Bypass Scheme.
PPP payments in 2016 amounted to circa €109m. PPP payments will increase in the coming years with the opening of the N25 New Ross Bypass and M11 Gorey-Enniscorthy schemes. There are no further road PPPs in procurement at this time.
The thirteen road PPPs comprise:
Eight toll road concession PPP Contracts –
in the case of six of these PPP Contracts, traffic risk rests entirely with the PPP Co. In the case of two of the PPP Contracts, i.e. the M3 Clonee-Kells Scheme and the N18 Limerick Tunnel, the PPP Contract provides for a sharing of downside traffic risk (referred to as Variable Operation Payments) between the PPP Company and TII, and
Five Design Build Finance Operate Maintain (DBFOM) PPP Contracts
- three of which are operational (M50, N7/M11 & M17/M18) and two of which are in the construction phase (M11 Gorey-Enniscorthy & N25 New Ross both of which are to open in 2019). The PPP Companies on these schemes are reimbursed through Availability Payments paid by TII.
Risk Sharing Payments
Variable Operation Payments payable for 2016 amounted to €5.2m of which €0.8m was for the M3 Clonee-Kells scheme and €4.4m was in respect of the N18 Limerick Tunnel scheme
The Variable Operation Payments apply where traffic volumes are below traffic volumes specified in the respective contracts. The Variable Operation Payments contribute to the senior debt service requirements.
Variable Operation Payments, under a low traffic growth scenario, are expected to continue to 2025 (the concession term runs to 2052) on the M3 Clonee-Kells scheme.
Briefing Paper for Committee of Public Accounts
8
Variable Operation Payments are expected to continue throughout the concession term, which runs to 2041, on the N18 Limerick Tunnel scheme.
Risk Sharing Receipts
Amounts receivable by TII under risk share receipts were €6.9m in 2016. These payments arose from traffic related revenue sharing on the M4 Kilcock-Kinnegad and M1 Drogheda Bypass schemes (totalling €3.5m) and on insurance cost savings across a number of schemes of €3.4m.
Traffic related revenue share payments are expected to exceed Variable Operation Payment amounts in future years.
Service Area PPP
TII awarded a Motorway Service Area Contact in 2009.
The Contract includes service stations located on the M1 and on the M4. The service areas have been operational since 2010 and the contract runs to 2034. All revenue risk rests with the PPP Co.
Amounts receivable by TII for revenue share on this contract amounted to €2.0m in 2016 and revenue share payments will continue throughout the concession period.
Motorway Service Areas – Tranche 2
A tender competition was held by TII to procure the fit out, operate the Gorey Service Area and to design, build, fit out and operate two other service areas; on the M6 at Athlone and on the M9 at Kilcullen. In August 2015, prior to the award of the contract, one of the unsuccessful tenderers issued legal proceedings seeking a judicial review of the tender evaluation process leading to the selection of the preferred tenderer. In December 2016 the Applicant requested the Court to put a stay on its judgement and the legal challenge was subsequently withdrawn by the Applicant at the end of April 2017.
TII has now resumed contract discussions with the preferred bidder in order to bring this tender to financial close.
8. Public Transport Construction and Improvement
Works at construction during 2016 included the following:
Luas Cross City.
Luas Green Line Infrastructure Upgrade.
Luas Green Line Capacity Enhancement.
In accordance with the Government’s Capital Investment Plan - Building on Recovery 2016 – 2021, TII assisted the NTA on the planning and design of New Metro North
Briefing Paper for Committee of Public Accounts
Appendix A Roads Capital Programme Update
MAJOR SCHEMES PROGRAMME
Committee of Public Accounts 12th October 2017
CAPITAL INVESTMENT PLAN PROJECTS AT CONSTRUCTION
PROJECT STATUS October 2017
M11 Gorey to Enniscorthy PPP
The permanent fencing works and the site clearance are now substantially complete. Earthworks operations and culvert construction are now well advanced. Works are ongoing on the bridge structures, including both railway bridges and the River Slaney crossing. The Ballywater wind farm diversion works are complete. Approx. 48% of the works are complete. Permit to Use date is 31 July 2019.
M17/M18 Gort to Tuam PPP
The mainline opened to the public on 27th September 2017 which was two months early.
N25 New Ross Bypass (PPP)
Earthworks are 70% complete. The works include a very large bridge over the river Barrow. Foundation works to all 8 piers and 2 abutments on the River Barrow bridge are completed and pier stem construction has commenced. Work on construction of the bridge deck has commenced. Testing of the cable and saddle system for the bridge has commenced. Approximately 57% of the works are complete. Permit to Use date is 31 January 2019.
Briefing Paper for Committee of Public Accounts
CAPITAL INVESTMENT PLAN PROJECTS WITH PLANNING APPROVAL
PROJECT STATUS October 2017
N4 Collooney to Castlebaldwin
Archaeological works and Ground Investigations are ongoing. Designers have been appointed for the preparation of the tender documents, managing the tender process and construction monitoring. Projected construction start date is Q2/2019.
N5 Westport to Turlough Advanced works including Fencing & Hedge Clearance and Archaeology are completed. Designers have been appointed for the preparation of the tender documents, managing the tender process and construction monitoring. Projected construction start is Q1/2021.
N7 Naas Newbridge Upgrade
The contract for site monitoring has been awarded. Kildare County Council has issued the Letter of Acceptance to the successful tenderer. It is expected that activity will commence on site in the coming weeks. The scope of the Design & Build contract includes the Sallins Bypass and the Osberstown Interchange on the M7. These works are being funded separately by DTTAS
M8/N40/N25 Dunkettle Nine expressions of interest were received. Five candidates have been shortlisted. It is intended that Invitations to Tender will issue in October.
N22 Ballyvourney to Macroom
Archaeological works are 50% complete. EIRGRID and Cork County Council have sought procedural advice from An Bord Pleanála in relation to pylon relocation. Projected construction start is Q1/2020.
N56 Dungloe to Glenties (Rolling Programme)
This scheme is being delivered in 6 sections. Two sections are now complete, from Cloughbolie to Boyoughter and from Boyoughter to Kilkenny. The Letter of Intent to award the construction contract for the third section, from Kilkenny to Letterilly, was issued by Donegal County Council to the successful tenderer on 18th September.
N56 Mountcharles to Inver (Rolling Programme)
Donegal County Council will construct the project in sections commencing with the section from Mountcharles to Drumbeigh. The tender process is underway with tenders due to be returned in October 2017.
N59 Moycullen Bypass Improvements on the line of the existing road are complete. The design and build tender documents for the bypass were completed some time ago. Procurement of technical advisors for the preparation of the tender documents, managing the tender process and construction monitoring is due to commence in Q4/2017. Projected construction start is Q1/2021.
Briefing Paper for Committee of Public Accounts
CAPITAL INVESTMENT PLAN PROJECTS REQUIRING PLANNING APPROVAL
PROJECT STATUS October 2017
N2 Slane Bypass (incl. land)
Designers have been appointed by Meath County Council. Public Consultation in relation to Constraints has been undertaken. Meath County Council and TII have engaged in pre-appraisal discussions with the evaluation unit of DTTAS in compliance with the DTTAS Common Appraisal Framework. The competition for the Ground Investigation contract has commenced.
N6 Galway City Ring Road
The National Park and Wildlife Service (NPWS) have carried out a preliminary review of the Natura Impact Statement and the Biodiversity chapter of the Environmental Impact Appraisal Report. A further pre-application consultation meeting took place with An Bord Pleanála (ABP) on 31st August and this consultation process is ongoing. As advised by ABP, Galway County Council will request more comprehensive feedback from NPWS so that all issues of concern are addressed in advance of the submission of the scheme to ABP. The review of the business case has been completed by DTTAS and DPER and no issues of concern were identified. The scheme will be submitted to An Board Pleanála when NPWS have completed the review of the documents and any issues raised are addressed.
N21/N69 Foynes to Limerick
Preparation of the documentation for planning approval is ongoing. Two Ground Investigation contracts are nearing completion. Limerick County Council will seek a pre-application consultation with An Bord Pleanála in October 2017.
N28 Cork to Ringaskiddy This scheme was submitted to An Pleanála on 15th May 2017 which was in advance of the date for the Introduction of the new Environmental Directive. The date for receipt of submissions to ABP was the 18th August. Over 130 submissions were received. No date has been given for the oral hearing.
N72 Mallow Relief Road (incl. land)
Cork County Council are advancing the feasibility study.
Briefing Note for Committee of Public Accounts
Briefing Paper for Committee of Public Accounts
OTHER MAJOR PROJECTS NOT IN THE CAPITAL INVESTMENT PLAN
PROJECT STATUS October 2017
N5 Ballaghaderreen Bypass to Scramogue
Review comments were received from DTTAS. The Business Case has been revised and resubmitted to DTTAS. Revision of the EIAR, NIS and CPO in compliance with the new EIA directive is underway.
N59 Westport to Mulranny
This project has planning approval. Land acquisition is underway, construction of the first two sections of the scheme is complete. Tender documentation has been prepared for a third section.
N11 M50 to Glen of the Downs
The feasibility study was published in April 2017. The project will commence as a Major Scheme in Q4/2017.
N13/14/15 North Donegal TEN-T
Donegal County Council have appointed the designers and work is ongoing on feasibility and design.
N14/N15/A5 Link This scheme is a cross-border project. The section south of the border was approved by An Bord Pleanála in 2014. Progression of the scheme is contingent upon completion of the statutory processes in relation to the A5. Report of Planning Appeals Commission complete.
Limerick, Cork A Project Appraisal Plan has been prepared and will be submitted to DTTAS for review and comment.
N52 Ardee Bypass This project has planning approval. Land acquisition is complete. A competition for the task of preparing the tender documents, managing the tender process and monitoring construction is underway. It is anticipated that the tender documents will be completed in Q4 2017.
N59 Maam Cross to Oughterard and Maam Cross to Clifden
The section of this project from Maam cross to Oughterard has been approved by An Bord Pleanála with a condition that requires the agreement of NPWS and IFI to method statements. Agreement has been reached for ground investigations in the section between Maam Cross and Bunakill which is outside the catchment of the Owenriff river. Pavement works are underway on a 7km section east from Bunnakill. The scheme which covered the section between Maam Cross and Clifden was refused planning approval by An Bord Pleanála.
N69 Listowel Bypass The Business Case was approved by DTTAS and DEPR. Kerry County Council submitted the EIS to An Bord Pleanála on 12 May and published the CPO. The oral hearing was conducted over three days commencing 5th September 2017. The decision of An Board Pleanála is awaited.
N86 Dingle to Tralee This project has planning approval. The first 4km section of the scheme is being constructed as minor scheme, Lispole to Mountoven. The construction completion date is Q2/2018.
Briefing Paper for Committee of Public Accounts
Major Schemes Programme
August 2017
Number of Schemes
Change in Two Months
PPP Projects at Construction 3 0
With Planning Approval for Construction 8 0
Requiring Planning Approval 5 0
Other Major Projects at Planning 9 0
Total Number of Schemes 25 0
Briefing Paper for Committee of Public Accounts
MINOR SCHEMES PROGRAMME
Committee of Public Accounts October 2017
Minor Schemes at Construction Project Status October 2017
N52 Cloghan to Billistown phase 1 The scheme is now under construction and completion is expected Q4 2017.
N55 Corduff to South of Killydoon Phase A
The scheme is now under construction and projected construction completion is Q4 2018.
N56 Mountcharles to Drumbeigh Tenders are due to be returned in October 2017. Projected construction completion date is set for Q4 2019.
N56 Kilkenny to Letterilly The Letter of Acceptance has issued. It is expected that the contract will be awarded in Q4 2017. Projected construction completion date is set for Q2 2019.
N56 Kiltoy Roundabout Construction was completed Q2 2017.
N59 Rossow Bends Construction was completed in Q3 2017.
N63 Abbeyknockmoy to Annagh Hill (Part of Gort to Tuam Residual Networks)
Construction is underway. Projected construction completion date is Q3 2018.
N76 Callan Road Realignment Construction is underway. Projected construction completion date is Q1 2018.
N86 Lispole to Mountoven Construction is underway. Projected construction completion date is Q2 2018.
Minor Schemes being progressed to construction
Project Status October 2017
N2 Monaghan to Emyvale Phase 3 At tender, return date currently Q4 2017
N56 Coolboy to Kilmacrennan At tender, return date currently Q4 2017
N61 Coolteige Tenders have been returned.
N70 Kilderry Bends At tender, return date currently Q4 2017
Briefing Paper for Committee of Public Accounts
Minor Works under Construction
August 2017
Number of Schemes
Change in One Months
To be Tendered 2017 0 -5 Recently Tendered 6 +5
Construction Commenced 6 0
Construction Complete 3 0
Total Minor Works 15 0
Briefing Paper for Committee of Public Accounts
COUNTY
MINOR PROJECTS AT PLANNING & DESIGN
PROJECT NAME PROJECT STATUS October 2017
Cavan N3 Dublin Road Roundabout Preliminary Design completion is expected during December 2017.
Cavan N3 Virginia to Maghera Preliminary Design completion is expected during December 2017.
Sligo N4 Sligo Urban Improvement Scheme Option 1
Preliminary Design and CPO documents have been published. CPO/NIS approval is expected during Q4 2017.
Galway N6 Bothar na dTreabh Kirwan Roundabout
Part 8 Planning approval expected in Q1 2018
Limerick M7 Junction 28 Feasibility Study CPO documents are currently being prepared.
Donegal N15 Blackburn Bridge Realignment Scheme Phase 2
Part 8 approved. This project is impacted by the TEN T assessment that is underway. In the short term safety works are underway.
Leitrim N16 Drummahan Part 8 complete. CPO documents being prepared.
Leitrim N16 Munakill Realignment At preliminary design stage.
Sligo N16 Lugatober Realignment At preliminary design stage
Galway N17 Milltown to Gortnagunnad Realignment
At preliminary design stage
Limerick N20 O'Rourke's Cross Part 8 under preparation
Tipperary N24 Ballydrehid Bends At preliminary design stage.
Limerick N24 Beary's Cross Part 8 under preparation
Kilkenny N24 Carrick Road Improvement At preliminary design stage.
Wexford N25 Rosslare Harbour: New Access Rd & Link to N25
Part 8 underway
Mayo N26 Cloongullane Bridge Realignment
The oral hearing for this scheme took place on the 8th March. Significant additional information was sought by and provided to An Bord Pleanála
Meath N51 Dunmoe Phase 2 CPO documents are under preparation
Meath N52 Grange to Clontail Scheme (previously Stephenstown to Fringestown Realignment Scheme
At preliminary design stage.
Westmeath N52 Cloghan to Billistown - Phase 2
Part 8 in progress
Louth N53 Hackballscross to Rassan At preliminary design stage.
Cavan N55 Corduff to South of Killydoon Phase B
At preliminary design stage.
Westmeath N55 Tang to the Pigeons (Ballymahon)
At preliminary design stage.
Briefing Paper for Committee of Public Accounts
COUNTY
MINOR PROJECTS AT PLANNING & DESIGN
PROJECT NAME PROJECT STATUS October 2017
Galway N59 West of Letterfrack Widening At preliminary design stage
Westmeath N55 Glasson to Cornamaddy At preliminary design stage
Mayo N59 Westport to Mulranny Kilmeena LVNS
Tender documents are complete.
Mayo N59 Newport to Derrada Realignment LVNS
CPO/NIS is now complete and Detailed design completion is expected Q3 2018.
Sligo N59 Corhawnagh to Lugnadeffa At preliminary design stage
Mayo N60 Manulla Cross Preparation of CPO documents underway
Mayo N60 Lagnamuck Detailed design complete.
Mayo N60 Heathlawn Completion of tender documents expected Q2 2018
Roscommon N60 Oran Completion of tender documents expected Q2 2018
Roscommon N61 Ballymurray to Knockcroghery At preliminary design stage
Roscommon N61 Clashaganny to Tulsk At preliminary design stage
Galway N63 Liss to Abbey Realignment At preliminary design stage
Tipperary N65 Carrigahorig Bends At preliminary design stage
Galway N67 Ballinderreen to Kinvara Phase 2
Detailed design complete.
Clare N67/N65 Blake's Corner At preliminary design stage
Kerry N70 Waterville to Ballybrack Preparation of CPO documents underway
Kerry N70 Coolroe to Glenbehy At preliminary design stage
Kerry N70 Blackwater Bridge to Sneem Preparation of CPO documents underway
Cork N73 Annakisha South Improvement Scheme
Detailed design stage
Cork N73 Clogher Cross Waterdyke Detailed design stage
Tipperary N74 Ballyhusty Realignment CPO/NIS approval is expected during Q2 2018.
Kilkenny N77 Ballyragget Village to Ballynaslee Road Improvement
At preliminary design stage.
Laois N80 Maidenhead Tender documents expected completion Q4 2017
Wicklow N81 Knockroe Bend Realignment Scheme
Tender documents expected completion Q4 2017
Wicklow N81 Hangmans Bends At preliminary design stage
Wicklow N81 Irishtown At preliminary design stage
Wicklow N81 Tuckmill At preliminary design stage
Wicklow N81 Whitestown Lower At preliminary design stage
Clare N85 Kilnamona Part 8 planning is underway.
Briefing Paper for Committee of Public Accounts
Minor Works at Planning and Design
August 2017
Number of Schemes
Change in Two Months
Schemes expected to Progress to P&D
24 -1
Preliminary Design Completed 3 +1
Part 8 Planning Approved 5 0
CPO Documents Prepared 3 +1
CPO / NIS Approved 1 -3
Detail Design Complete 5 +3
Tender DocumentsComplete 2 0
Total Schemes 2017 Planning & Design
43 +1
Briefing Paper for Committee of Public Accounts
PAVEMENT SCHEMES PROGRAMME
Committee for Public Accounts 12th Oct 2017
PAVEMENT SCHEMES PROGRAMME 2017.
COUNTY ROUTE SCHEME NAME
Louth 2 N2 Annaglog Pavement Resurfacing.
Louth 2 N2 Ardee Town Pavement Rehabilitation
Louth 2 N2 Collon Pavement Resurfacing
Louth 2 N2 Tattyboys to Harristown
Meath 2 N2 Cushinstown Pavement Resurfacing.
Meath 2 N2 Slane Southern Approaches Pavement Overlay
Monaghan 2 N2 Cornacreeve Pavement Strengthening.
Cavan 3 N3 Cornaslieve to North of Virginia
Cavan 3 N3 Raheelagh to Kilmore Roundabout (excl 2013 Lisnananagh section)
Longford 4 N4 Cooleeny
Longford 4 N4 Lacken Ph 2
Longford 4 N4 Newtownforbes
Longford 5 N5 Fallan Bridge
Mayo 5 N5 Bridge St Westport
Mayo 5 N5 Westport East
Wexford 11 N11 Kyle Upper Pavement Scheme
Wexford 11 N11 Crory to Ballylough Resurfacing
Wexford 11 N11 Scarawalsh Resurfacing
Wexford 11 N11 Tinnahask to Ballynaslaney Pavement Scheme
Donegal 13 N13 North of Newtowncunningham
Donegal 14 N14 Dromoghill
Donegal 14 N14 Lifford Bridge to R264
Donegal 15 N15 Killygordon to Corcam (Pavement)
Donegal 15 N15 Laghy (School)
Sligo 16 N16 Lugnagall Sligo Emergency Surface Repairs
Galway 17 N17 Tuam Town
Mayo 17 N17 Charlestown
Mayo 17 N17 Pavement Improvement at Kilkelly South, Bruff
Galway 18 N18 Claregalway to M6 Junction
Cork 20 N20 Ballygibbon to Ardamadane Pavement
Cork 20 N20 Ballymartin Pavement
Briefing Paper for Committee of Public Accounts
PAVEMENT SCHEMES PROGRAMME 2017.
COUNTY ROUTE SCHEME NAME
Cork 20 N20 Mallow Southern Approach Pavement Inlay / Overlay
Cork 20 N20 Charleville Pavement Strengthening.
Cork 20 N20 Old Cork Rd Charleville Pavement Strengthening (N20_U_2015_017)
Cork 20 N20 Shean Upper to Killeens Pavement (MMaRC)
Cork 20 N20 Velvetstown to Shinanagh Pavement
Limerick 20 N20 Ballymacrory Pavement Overlay (N20_M_2015_026)
Limerick 20 N20 Ballyphilip to Howardstown North Pavement Overlay (N20_M_2015_020 023 & 025)
Limerick 21 N21 Adare Western Approach Pavement Strengthening
Cork 22 N22 Lisarda Village
Kerry 22 N22 Garries Bridge Pavement
Kerry 22 N22 Tulligmore (Kismit)
Kilkenny 24 N24 Granny Pavement Scheme
Tipperary 24 N24 Davitt Street Tipperary Pavement Strengthening
Cork 25 N25 Ballyvergan West Surface Course Replacement (N25_M_2015_006)
Cork 25 N25 Killeagh Village Pavement Strengthening
Cork 25 N25 Knockane Pavement
Cork 25 N25 Castlemartyr East Pavement Strengthening of 0.5km
Waterford 25 N25 Gortavickery Pavement Improvement
Waterford 25 N25 Ballynevoga to Shanbally Pavement Resurfacing
Wexford 25 N25 Ballygillane Little Pavement Scheme
Wexford 25 N25 Ballygoman to Knockeen Pavement Scheme
Wexford 25 N25 Ballynabola to Cushenstown Pavement Scheme
Wexford 25 N25 Carrigadaggan to Ballynabola Pavement Scheme
Tipperary 52 N52 Main Street, Borrisokane Pavement Strengthening
Louth 53 N53 Carrickastuck Pavement Resurfacing.
Monaghan 53 N53 Annadrumman & N53 Pavement Resurfacing Monaghan.
Monaghan 54 N54 Clones Road Pavement Resurfacing Phase 1
Monaghan 54 N54 Clones Road Pavement Resurfacing Phase 2
Donegal 56 N56 Ardara West
Donegal 56 N56 Creeslough (Log Cabin)
Donegal 56 N56 Crolly
Donegal 56 N56 Fallcarragh
Donegal 56 N56 Glenties
Donegal 56 N56 Gortnamucklagh
Briefing Paper for Committee of Public Accounts
PAVEMENT SCHEMES PROGRAMME 2017.
COUNTY ROUTE SCHEME NAME
Donegal 56 N56 Pavement Improvement at Dunfanaghy
Mayo 58 N58 Kilmore
Galway 59 N59 East of Oughterard to Maam Cross Phase 1
Galway 59 N59 East of Oughterard to Maam Cross Phase 2
Mayo 59 N59 Creggan Lough
Mayo 59 N59 Garraunard
Mayo 60 N60 Ballyhaunis Abbey St / N60 Railway Underpass
Mayo 60 N60 Drumkeen
Roscommon 60 N60 Castlerea West Phase 2
Roscommon 60 N60 Castlerea West pavement improvement Phase 1
Roscommon 61 N61 Athlone Road Roscommon (Hospital)
Roscommon 61 N61 Knockcroghery Pavement Overlay and Traffic Calming
Tipperary 62 N62 Camlin Surface Course Replacement (N62_M_2014_0047)
Tipperary 62 N62 Lismakin Surface Course Replacement (N62_M_2014_0048)
Tipperary 62 N62 Scart Roscrea
Tipperary 62 N62 Slievenamon Road Thurles Pavement Strengthening
Westmeath 62 N62 Creggan Lower Roundabout and Approach Pavement Strengthening.
Longford 63 N63 Farranyoogan
Roscommon 63 N63 Galway Road Roscommon
Roscommon 63 N63 Pavement Improvement Athleague
Galway 65 N65 Killimor Pavement Resurfacing.
Galway 65 N65 Portumna Pavement Resurfacing
Tipperary 65 N65 Carrigahorig to Balleiragh Bridge Strengthening (N65_M_2015_024)
Clare 67 N67 Bealaha Pavement Strengthening (N67_M_2015_038)
Clare 67 N67 Carrowdotia to Kilimer Pavement Strengthening
Clare 67 N67 Moneypoint Pavement Strengthening
Clare 67 N67 Mortyclough Pavement Overlay
Clare 68 N68 Darragh Pavement Overlay
Limerick 69 N69 Foynes to Sroolane North
Limerick 69 N69 Leahys Pavement Overlay
Kerry 70 N70 Caherleheen Pavement Strengthening
Kerry 70 N70 Carhan to Deelis Bridge Pavement Strengthening
Kerry 70 N70 Molls Gap
Briefing Paper for Committee of Public Accounts
PAVEMENT SCHEMES PROGRAMME 2017.
COUNTY ROUTE SCHEME NAME
Kerry 70 N70 Tahilla Pavement Strengthening
Kerry 70 N70 Killorglan Approaches
Cork 71 N71 Newmills to Lissavard Pavement Strengthening
Cork 71 N71 Parkana to Knockroe Pavement Repairs
Cork 71 N71 Leap to Dromihilly **
Kerry 71 N71 Port Road Killarney Pavement
Cork 72 N72 Grange East & West Pavement Strengthening (N72_M_2015_024)
Cork 72 N72 Olivers Cross to Lacknamona Pavement Overlay
Kerry 72 N72 Killorglan Approaches
Kerry 72 N72 Kilbonane Pavement Overlay
Waterford 72 N72 Cappagh to Boherwillin Pavement Resurfacing.
Waterford 72 N72 Tallowbridge Lands to Castlerichard Pavement Scheme
Cork 73 N73 Shanagh Pavement Strengthening.
Tipperary 74 N74 Fr Matthew St Tipperary Pavement Inlay / Overlay (N74_U_2015_005)
Kildare 78 N78 Athy Pavement Resurfacing
Kilkenny 78 N78 Ballycomy to Castlecomer Resurfacing
Carlow 80 N80 Tullow Road, Carlow Pavement Improvement
Laois 80 N80 Dysart Pavement Scheme
Laois 80 N80 Graigue to Forest Upper Pavement Resurfacing 2017
Carlow 81 N81 Aghade to Castlegrace Pavement Scheme
Carlow 81 N81 Ballymogue Pavement Resurfacing
Carlow 81 N81 Pavement Improvement Tullow
Kildare 81 N81 Bishopslane to Blakestown Lower resurfacing
Wicklow 81 N81 Baltinglass Pavement Improvement
Mayo 83 N83 Tavron
Mayo 84 N84 Ballinrobe Streets
Mayo 84 N84 Castlebar to Ballinrobe at Gallagh
Mayo 84 N84 Castlebar to Ballinrobe at Ballintober (Gallagh split)
Mayo 84 N84 Kilmaine Shrule Road
Mayo 84 N84 Pavement Improvement at Cloondeash
Clare 85 N85 Rushaun Pavement Strengthening (N85_M_2015_007 008, 009 & 010)
Kerry 86 N86 Knockglass More to Camp Pavement
Cavan 87 N87 Lisnamaine to Rahaghan
Sligo 15/4 N15 – N4 to Shannon Eighter
Briefing Paper for Committee of Public Accounts
PAVEMENT SCHEMES PROGRAMME 2017.
COUNTY ROUTE SCHEME NAME
Sligo 16/4 N16 Clarion Road to N4 Phase 1
Sligo 16/4 N16 Clarion Road to N4 Phase 2
Mayo 84/60 N84 - N60 to Railway Station
Briefing Paper for Committee of Public Accounts
Pavement Programme
August 2017
Number of
Schemes
Change in
Two Months
Notified to Local Authority 52 -8 Pavement Asset Repair & Renewal Reports
10 -10
Approval for Tender 21 +5
Approval to Award Contract 23 -2
Construction Complete 28 +15
Total Schemes Pavement Programme 134 0
Briefing Paper for Committee of Public Accounts
Delineation Programme
August 2017
Length
km Change in
Two Months
Design & Implementation 0 0 Advance Design Works 533 -157
Design Completed 0 0
Local Authority & An Garda Síochána Liaison
0 0
Tender Commencement 0 -75
Contract Awarded 0 0
Works Commenced 753 +40
Works Completed 192 +192
Total Length Delineation Programme 1478 0
Briefing Paper for Committee of Public Accounts
Bridge Maintenance Programme
August 2017
Number
of
Schemes
Change
in Two
Months
Design Pending 4 0 Design Completed - No Construction 16 -15
Design Completed - Construction On-Going
18 +9
Design Completed - Construction Complete
29 +6
Total Schemes 67 0
Briefing Paper for Committee of Public Accounts
Appendix B Public Transport Capital Programme Update
Public Transport PROGRAMME
Committee of Public Accounts 12th October 2017
PROJECTS AT CONSTRUCTION
PROJECT STATUS October 2017
Luas Cross City Luas Cross City is on schedule to commence passenger operations / service in December 2017. Driver training and traffic signal optimisation commenced in October 2017.
Green Line Infrastructure Upgrade
Green Line Infrastructure Upgrade comprises extension of 11 platforms on the existing Luas Green Line between Sandyford and Harcourt stops with associated power and systems works to facilitate the operation of 55m long trams. The project is on schedule to be completed by end of November 2017
Green Line Capacity Enhancement (Sandyford Depot)
Extension of the existing Sandyford Luas Depot to accommodate 55m long trams is underway with track laying commencing in October 2017.
PROJECTS AT PLANNING & DESIGN
PROJECT STATUS October 2017
New Metro North The project is currently at Route Selection stage and will commence public consultation in Q1 2018.