brief summary -...

51
BRIEF SUMMARY SCCL has obtained Environmental Clearance from MoEF&CC, New Delhi for establishing 2x600 MW coal based TPP of the Singareni Collieries Company Limited (SCCL) at Pegadapali Village, Jaipur Mandal, Mancherial District, Telangana State vide MoEF&CC lr. No. J- 13012/88/2008-IA.II (T), dated 27.12.2010 and amendment to EC was obtained vide MoEF&CC lr. No. J-13012/88/2008-IA.II(T), dated.10.08.2016. Due to acute power shortage in newly formed Telangana State, Government of Telangana directed SCCL to take up further expansion of SCCL Power Plant from 2X600MW (Stage-I) to add additional unit of 1x800 MW (Stage-II) in order to meet shortfall power generation of Telangana State. Accordingly, SCCL Board accorded approval for expansion of the existing 2x600 MW (Stage-I) Power Plant by setting up additional 1x800 MW (Stage-II) unit at the same location. SCCL has attended EAC meeting for ToR on 30.08.2017 and a presentation was made before EAC. EAC advised the SCCL to submit the revised Form-I and PFR for amendment in ToR issued earlier for 1x600 MW sub-critical to 1x800 MW super-critical technology. Present proposal is amendment to ToR issued vide MoEF&CC lr. No. J-13012/08/2015-IA.I(T), dated.27.05.2015 for expansion of Singareni Thermal Power Plant (From 2x600 MW to 2000 MW by adding 1x800 MW) at Pegadapalli village, Jaipur Mandal, Mancherial District of Telangana State by M/s Singareni Collieries Company Limited. 1 Name of the Project Expansion of Singareni Thermal Power Plant (from 1200 MW to 2000 MW by adding 1X800 MW). 2 Name of the Company M/s Singareni Collieries Company Limited 3 Location Pegadapalli Village, Jaipur Mandal, Mancherial Dist, Telangana State. Bounded between Latitude:18 0 48’ 30”N and 18 0 50’ 35”N and Longitude: 79 0 3400”E and 79 0 35’ 30”E. Covered in SOI Topo sheet No. 56 N/9 Second Edition 4 Environmental Clearance Lr.No EC amendment J-13012/88/2008-IA-II (T), dt.27.12.2010. J-13012/88/2008-IA-II (T), dt.10.06.2016. 5 Total Land requirement for the project Presently 2X600 MW TPP is under operation in area of 300.972 Ha. Land required for additional unit of 1X800 MW will be 127.31 Ha. Thus total Land required is 428.28 Ha. Total land is under possession of SCCL. 6 Coal Linkage The required coal will be supplied from SCCL mines. 7 Source and total water requirement The required water will be met from River Godavari & Pranahitha. 1.05 TMC of water from Godavari River and 2.00 TMC of water from Pranhitha River were allocated by State Government Vide Ltr.no GO Rt No. 474, Dt: 19.07.2010, I&CAD Water requirement: For 2x600 MW plant under construction: 88,800 KLD (3700 m3/hr) For additional 1X800 MW : 48,000KLD (2000 m3/hr) Total Water required for 2x600 MW & 1x800 MW : 1,36,800 KLD (5700 m3/hr).

Upload: duongdieu

Post on 13-Apr-2018

226 views

Category:

Documents


2 download

TRANSCRIPT

BRIEF SUMMARY

SCCL has obtained Environmental Clearance from MoEF&CC, New Delhi for establishing 2x600 MW coal based TPP of the Singareni Collieries Company Limited (SCCL) at Pegadapali Village, Jaipur Mandal, Mancherial District, Telangana State vide MoEF&CC lr. No. J-13012/88/2008-IA.II (T), dated 27.12.2010 and amendment to EC was obtained vide MoEF&CC lr. No. J-13012/88/2008-IA.II(T), dated.10.08.2016.

Due to acute power shortage in newly formed Telangana State, Government of Telangana directed SCCL to take up further expansion of SCCL Power Plant from 2X600MW (Stage-I) to add additional unit of 1x800 MW (Stage-II) in order to meet shortfall power generation of Telangana State. Accordingly, SCCL Board accorded approval for expansion of the existing 2x600 MW (Stage-I) Power Plant by setting up additional 1x800 MW (Stage-II) unit at the same location.

SCCL has attended EAC meeting for ToR on 30.08.2017 and a presentation was made before EAC. EAC advised the SCCL to submit the revised Form-I and PFR for amendment in ToR issued earlier for 1x600 MW sub-critical to 1x800 MW super-critical technology.

Present proposal is amendment to ToR issued vide MoEF&CC lr. No. J-13012/08/2015-IA.I(T), dated.27.05.2015 for expansion of Singareni Thermal Power Plant (From 2x600 MW to 2000 MW by adding 1x800 MW) at Pegadapalli village, Jaipur Mandal, Mancherial District of Telangana State by M/s Singareni Collieries Company Limited.

1 Name of the Project Expansion of Singareni Thermal Power Plant (from 1200 MW to 2000 MW by adding 1X800 MW).

2 Name of the Company M/s Singareni Collieries Company Limited

3 Location Pegadapalli Village, Jaipur Mandal, Mancherial Dist, Telangana State. Bounded between Latitude:180 48’ 30”N and 180 50’ 35”N and Longitude: 790 34’ 00”E and 790 35’ 30”E. Covered in SOI Topo sheet No. 56 N/9 Second Edition

4 Environmental Clearance Lr.No EC amendment

J-13012/88/2008-IA-II (T), dt.27.12.2010.

J-13012/88/2008-IA-II (T), dt.10.06.2016. 5 Total Land requirement

for the project Presently 2X600 MW TPP is under operation in area of 300.972 Ha. Land required for additional unit of 1X800 MW will be 127.31 Ha. Thus total Land required is 428.28 Ha. Total land is under possession of SCCL.

6 Coal Linkage The required coal will be supplied from SCCL mines. 7 Source and total water

requirement The required water will be met from River Godavari & Pranahitha. 1.05 TMC of water from Godavari River and 2.00 TMC of water from Pranhitha River were allocated by State Government Vide Ltr.no GO Rt No. 474, Dt: 19.07.2010, I&CAD Water requirement: For 2x600 MW plant under construction: 88,800 KLD (3700 m3/hr) For additional 1X800 MW : 48,000KLD (2000 m3/hr)

Total Water required for 2x600 MW & 1x800 MW :

1,36,800 KLD (5700 m3/hr).

8 Power evacuation Through 400KV system 9 Rehabilitation and

Resettlement No R&R is involved and total land is under possession of SCCL

10 Manpower (Operation ) 700(2x600MW) and 450 (additional 1x800MW) 11 Estimated Capital Cost

of the project 2X600MW: Rs.7573.51 crore and 1x800MW: Rs. 5879.62

Crores. Total 2x600MW & 1X800 MW:Rs 13,453.13 Crores

12. Present Status of 2x600MW 12.1 Major Milestones

S.No Major Mile Stone Unit‐1 Unit‐2

01 Commencement of Boiler Erection 14‐02‐2013 29‐05‐2013

02 Boiler Drum Lifting 12‐09‐2013 14‐12‐2013

03 Boiler Hydraulic Test 27‐08‐2014 03‐11‐2014

04 Boiler Light up 04-07-2015 06-08‐2015

05 Synch. With Coal Firing 13-03-2016 01-06‐2016

06 Commercial Operation 25-09-2016 02-12‐2016

12.2 MAJOR ACHIEVEMENTS OF STPP

Unit #1 & 2 boiler light-up achieved in span of 32 days.

Synchronization of Unit #1 & 2 achieved in span of 80 days.

Commercial operation of both Units achieved in span of 68 days.

Unit # 2 COD declared within 7 days achieving full load.

During very 1st year of commercial operation STPP achieved 17th position in TOP 25

best performing stations in India as issued CEA.

Highest ever Monthly Station PLF 95.06% in Feb’2017.

Unit # 2 achieved PLF 100.11% in Feb’2017.

Declared Capacity of the Station for very first year of Commercial operation is 87.92%.

100% Fly ash utilisation during 2016-17.

Unit # 1 achieved PLF 100% in Apr’2017.

Unit # 2 achieved PLF 100% in May’2017.

*****

0

THE SINGARENI COLLIERIES COMPANY LIMITED

(A Govt. Company)

P.O. Kothagudem Collieries – 507101 Bhadradri Kothagudem District, Telangana

Project Consultant: M/s Ramky Enviro Services Private Ltd., Gachhibowli, Hyderabad, Telangana

Project Proponent:

Submitted to

Ministry of Environment, Forest & Climate Change (MoEF&CC), Government of India,

Indira Paryavaran Bhawan, Jorbagh, Jorbagh Road, New Delhi

FORM – I

of

Expansion of Singareni Thermal Power Plant

(From 1200 MW to 2000 MW by adding 1X800 MW) at

Pegadapalli Village, Jaipur Mandal, Mancherial District, Telangana State

August 2017

1

“A” CATEGORY PROJECTS (I) Basic Information

S. No Item Details

Whether it is a violation case and

application is being submitted under

notification no. S.O.804(E) dated

14.03.2017?

No

1 Name of the Project /s

Brief Summary of the project

Proposal No.

Project Cost (in Lacs)

Expansion of Singareni Thermal Power

Plant (from 1200 MW to 2000 MW by

adding 1x800 MW)

Annexure – Brief Summary of the Project

IA/TG/THE/67046/2017, dt.29.07.2017

Rs.587962

2 S.No. in the schedule

Project Sector

1(d), Thermal Power Plants

Thermal Projects

3 Proposed capacity /Area 1x800MW/ 127.31Ha

4 New / Expansion / Modernization

Proposal No.

MoEF&CC File number

Uploaded EC letter

Expansion

IA/TG/THE/27854/2009,

J-13012/88/2008-IA.II(T), dt. 27.12.2010 Annexure - EC letter uploaded

5 Existing Capacity/area etc 2x600 MW /300.972 Ha

6 Location of the project Pegadapalli Village, Jaipur Mandal,

Mancherial Dist, Telangana State.

Bounded between Latitude: 180 48’ 30”N

and 180 50’ 35”N and Longitude:

79034’00”E and 79035’30”E.

4 Shape of the project land

Uploaded GPS File

Uploaded copy of survey of India

Toposheet

Block (Polygon)

Annexure-I-GPS File

Annexure-II-Survey of India Toposheet

5 Brief Summary of the project Annexure-III Brief Summary of Project

6 Category of Project i.e. ‘A’ or ‘B’ A

7 Does it attract the general conditions? If

yes, please specify

No

8 Does it attract the Specific conditions? If

yes, please specify

No

2

S. No Item Details

9 Location of the project

Shape of the project land

Upload GPS file

Uploaded copy of Survey of India

Topo sheet

Plot/survey/khasra No.

Town/Village

State of the Project

Pegadapalli Village, Jaipur Mandal,

Mancherial District, Telangana

Block (Polygon)

Annexure – GPS File

56N/9 Second Edition

Pegadapalli

Telangana

Details of State of the Project

S. No. State Name District Name Tehsil Name

1 Telangana Mancherial Jaipur - 504216

10

Nearest railway station along with

distance in Kms

Nearest airport along with distance in

kms

Mancherial Railway station at a distance

of 14.6 Km (Nagpur-Kazipet main rail line

of South-Central Railway)

Rajiv Gandhi International Airport,

Shamshabad, Hyderabad at a distance of

250 Km.

11 Nearest town/city/district headquarters

along with distance in kms

Town: Mancherial (14.6 Kms)

City: Hyderabad (250 Kms)

District Head Quarters : Mancherial

(14.6 Kms)

12 Village Panchayats, Zilla Parishads,

Municipal Corporation, Local Body

(Complete Postal Address with telephone

nos. to be given)

Pegadapalli Village, Jaipur Mandal,

Telangana State – 504216

Ph: 08737-243243

13 Name of the applicant Salakula Shankar,

Director (E&M), SCCL

14 Registered address M/s Singareni Collieries Company Ltd.

P.O.Kothagudem – 507101,

Bhadradri Kothagudem District,

Telangana State

15 Address for correspondence

Name of the company

Name of the applicant

Designation (Owner/Partner/CEO)

Pin code

M/s Singareni Collieries Company Ltd. Salakula Shankar,

Director (E&M), SCCL

507101

3

S. No Item Details

E-mail

Telephone No.

Fax No.

Copy of documents in support of the

competence/ authority of the person

making this application to make

application on behalf of the user agency.

[email protected]

08744-243059

08744-244115

Annexure – Uploaded copy of the

documents in support of the

competency/authority

16 Details of Alternate Sites examined

shown on a topo sheet.

No, present proposal is expansion of

existing project.

17 Whether part of interlinked projects? No

18 Whether separate application of

interlinked project has been submitted?

Not applicable

19 If yes, MoEF file number

Date of submission

Not applicable

20 If no, reason Not applicable

21 Whether the proposal involves Approval / Clearance under: if yes, details of the same

and their status to be given

i) Whether the proposal involves approval / clearance under the Forest (Conservation) Act, 1980?

ii) Whether the proposal involves approval / clearance under the Wildlife (Conservation) Act, 1972?

iii) Whether the proposal involves approval / clearance under the C.R.Z. Notification, 2011?

No No No

22 Whether there is any Government Order

/ Policy relevant / relating to the site?

No

23 Whether any Forest land involved?

Area of forest land involved (Ha.)

No

Not applicable

24 Whether there is any litigation pending against the project and / or land in which the project is proposed to set up?

(a) Name of the Court (b) Name of the sub-court (c) Case No (d) Orders / directions of the court, if

any and its relevance with the proposed project.

No

Not applicable

4

(II) Activity

1) Construction, operation or decommissioning of the project involving actions, which will

cause physical changes in the locality (topography, land use, changes in water bodies,

etc.)

S.No Information/Checklist

confirmation Yes/No

Details thereof (with approximate

quantities/rates wherever possible) with

source of information data

1.1 Permanent or temporary

change in land use, land cover

or topography including

increase in intensity of land

use (with respect to local

land use plan)

Yes Presently 2X600 MW STPP is existing in area of 300.972 Ha. Land required for additional unit of 1X800 MW will be 127.31 Ha. Thus total Land required is 428.28Ha. Total land is under possession of SCCL. The land use will change from open barren land to mixed use development as the proposed land will be occupied by the proposed thermal power plant.

1.2 Clearance of existing land,

vegetation and buildings?

Yes Clearance of existing land cover would be

done as per the requirement for

grading/leveling for the project site to

construct power plant and associated utility

and infrastructure facilities. There are no

buildings and structures exist in the

proposed project site, hence there is no

requirement for the clearance.

1.3 Creation of new land uses? Yes After completion of the project the land use will permanently change from open barren land to mixed use development as the proposed land will be occupied by the proposed thermal power plant.

1.4 Pre-construction investing-

ations e.g. bore holes, soil

testing?

Yes Detailed soil investigation work involving

borehole and trial pit tests and electrical

resistivity tests will be carried.

1.5 Construction works?

Yes Office buildings and Civil structures will be constructed to accommodate Boiler, Turbine, Generator, Condenser, Cooling water system, Coal handling system, Ash handling system, Coal handling plant, ESPs, ETP, Reservoir, Switchyard and other mechanical and electrical plant and equipment. Complete details are given in prefeasibility report.

1.6 Demolition works? No Not envisaged

5

S.No Information/Checklist

confirmation Yes/No

Details thereof (with approximate

quantities/rates wherever possible) with

source of information data

1.7 Temporary sites used for

construction works or

housing of construction

workers?

No Temporary sheds constructed for the construction of 2x600 MW STPP will be used for present proposal of additional 1X800 MW unit . Majority of labour will be sourced from nearby villages & existing township of the SCCL.

1.8 Above ground buildings,

structures or earthworks

including linear structures, cut

and fill or excavations

Yes Boiler, Turbine, Generator, Condensor,

Cooling Tower, Chimney, Water system,

Coal Handling Plant, ESP, ETP, Switchyard,

and other civil, mechanical and electrical

facilities required for the project.

1.9 Underground works including

mining or tunneling?

No Not required

1.10 Reclamation works? No Not required

1.11 Dredging? No Not Applicable

1.12 Offshore structures? No Not Applicable

1.13 Production and

manufacturing processes?

Yes Coal received from the mines at (-) 200 mm size is crushed in the crusher house to (-) 20mm size, which is subsequently pulverized in the coal mill. The powdered coal is burnt in the furnace to generate steam in the boiler. The steam generated in the boiler is expanded in the HP, IP & LP turbines and power is generated in the generator. The steam after expansion in the turbine is condensed in the condenser and the condensed steam is replaced back to the boiler. The hot gasses from the furnace after losing heat in different areas goes through the Electrostatic Precipitators (ESP) where ash is trapped. The clean gas goes through the chimney. Stack height of 275 m is proposed.

1.14 Facilities for storage of goods

or materials?

Yes The following facilities will be provided for storage of goods or materials.

Stores

Coal Yard

Fuel tanks

6

S.No Information/Checklist

confirmation Yes/No

Details thereof (with approximate

quantities/rates wherever possible) with

source of information data

Temporary storage sheds are proposed during construction.

1.15 Facilities for treatment or

disposal of solid waste or

liquid effluents?

Yes Solid Waste: Dry ash handling systems are proposed for collection of fly ash in dry form and storage facilities (Silo) and will be supplied to cement or brick industries or end users and balance will be sent to ash pond area. Hydrobins will be provided be provided to utilize bottom ash and will be sent to nearby coal mines of SCCL for stowing/void filling or for embankments of roads and others.

Liquid effluents: ETP and STP are proposed for treatment of plant effluents and sewage from plant and colony.

1.16 Facilities for long term

housing of operational

workers?

Yes Staff quarters will be constructed for the operational manpower for both the plants under operation and proposed unit in the space available outside the main plant area.

1.17 New road, rail or sea traffic

during construction or

operation?

No No sea traffic facilities required. The project area is having well developed road and rail network. Additional internal roads required will be formed. Railway line will be extended from the existing Srirampur CHP of the SCCL up to the plant site.

1.18 New road, rail, air,

waterborne or other

transport infrastructure

including new or altered

routes and stations, ports,

airports etc?

Yes No sea traffic facilities required. The project

area is having well developed road and rail

network. Additional internal roads required

will be formed. Railway line will be

extended from the existing Srirampur CHP

of the SCCL.

1.19 Closure or diversion of

existing transport routes or

infrastructure leading to

changes in traffic

movements?

No No change in existing road network is

envisaged.

1.20 New or diverted transmission

lines or pipelines?

No No diversion of transmission or pipelines

required. New EHV power transmission

7

S.No Information/Checklist

confirmation Yes/No

Details thereof (with approximate

quantities/rates wherever possible) with

source of information data

lines and water pipelines are envisaged for

the 2x600 MW plant will cater the needs of

expansion unit.

1.21 Impoundment, damming,

culverting, realignment or

other changes to the

hydrology of watercourses

or aquifers?

No Not envisaged.

1.22 Stream crossings? No There are no streams crossing in the

proposed site.

1.23 Abstraction or transfers of

water from ground or surface

waters?

Yes Required water for the proposed power plant will be met from the Pranahita river through pipeline.

1.24 Changes in water bodies or

the land surface affecting

drainage or run-off?

No Existing Nalla diversion is proposed within

the plant boundary, permission was

obtained from competent authority for

diversion of Nalla within the plant

boundary.

1.25 Transport of personnel or

materials for construction,

operation or

decommissioning?

Yes Transportation of construction material,

construction machinery, power plant

machinery will be transported through rail

and road networks. Manpower will be met

from the nearby villages and existing

township.

During the operational stage required

material will be transported through rail

and road networks and operational

manpower will be accommodated in the

township proposed outside main plant

area.

1.26 Long-term dismantling or

decommissioning or

restoration works?

No No long term dismantling works involved

1.27 Ongoing activity during

decommissioning which could

have an impact on the

No Not envisaged

8

S.No Information/Checklist

confirmation Yes/No

Details thereof (with approximate

quantities/rates wherever possible) with

source of information data

environment?

1.28 Influx of people to an area in

either temporarily or

permanently?

Yes About 3000 labourers during construction

will be employed temporarily. About 450

permanent staff will work in the power

plant during operational phase.

1.29 Introduction of alien species? No No Introduction of alien species

1.30 Loss of native species or

genetic diversity?

No No loss of native species or genetic

diversity

1.31 Any other actions? No None

2) Use of Natural resources for construction or operation of the Project (such as

land, water, materials or energy, especially any resources which are non-

renewable or in short supply)

S.No Information/Checklist

confirmation

Yes/

No

Details thereof (with approximate

quantities/rates wherever possible) with

source of information data

2.1 Land especially undeveloped

or agricultural land (ha)

Yes Land already developed for Existing

2x600MW power plant is 300.972 Ha (Main

plant 280.40 Ha, Land for Rail

system:15.245 Ha, Land for water pipe line

:5.327 Ha)

Undeveloped land available for expansion

of additional unit 1X800MW : 127.31Ha

(314.65 acres)

2.2 Water (expected source &

competing users) unit: KLD

Yes Water requirement:

1) For 2x600 MW plant under

operation: 88,800 KLD (3700 m3/hr)

2) For additional 1X800 MW :

48000KLD (2000 m3/hr)

3) Total Water required for 2x600

MW& 1x800 MW : 1,36,800 KLD

(5700 m3/hr)

The required water will be met from River

Godavari and Pranahitha. 2.00 TMC of

water from Pranahitha River was allocated

by State Government.

9

S.No Information/Checklist

confirmation

Yes/

No

Details thereof (with approximate

quantities/rates wherever possible) with

source of information data

2.3 Minerals (MT) Yes Coal requirement:

1) For 2x600 MW plant under

construction: 4.784 MTPA

2) For additional 1X800 MW : 4.05

MTPA

3) Total coal required for 2x600 MW &

1x800 MW: 8.834 MTPA

The required coal will be supplied from

SCCL mines. MoC will be approached to

grant bridge linkage for the proposed

1x800 MW.

2.4 Construction material –

Cement, steel, stone,

aggregates, sand/soil (expected

source – MT)

Yes Cement: 1,32,000 MT

Structural Steel: 21,750 MT

Reinforcement Steel: 26,000 MT

Sand: 1.50 L.Cu.m

Stone/aggregate: 2.25 L.Cu.m

2.5 Forests and timber

(Source – MT)

No Nil

2.6 Energy including electricity &

fuels (source, competing

users) Unit: Fuel (MT)

Energy (MW)

Yes Electricity required during construction will

be met from existing source / nearest 33 KV

sub-station.

HFO/LDO requirement for startup and

flame stabilization:

1) For 2x600 MW plant under

operation: 8935 KL/annum

2) For additional 1X800 MW : 3153

KL/annum

3) Total fuel required for 2x600 MW &

1X800 MW : 12,088 KL/annum

2.7 Any other natural resources

(use appropriate standard

units)

No The required HFO/LDO will be met from the

nearest oil depots.

10

3) Use, storage, transport, handling or production of substances or materials which could

be harmful to human health or the environment or raise concerns about actual or

perceived risks to human health

S.No Information/

Checklist confirmation

Yes/

No

Details thereof (with approximate

Quantities/rates wherever possible)

with source of information data

3.1 Use of substances or materials,

which are hazardous (as per

MSIHC rules) to human health or

the environment (flora, fauna, and

water supplies)

Yes Precautions and safe operating

practices will be followed in storage,

handling and use of Hazardous material

like Furnace Oil, HSD, Chlorine, Alum,

Caustic soda, HCL, etc will be used

immediately.

3.2 Changes in occurrence of disease

or affect disease vectors (e.g.

insect or water borne diseases)

No No changes in occurrence of disease

3.3 Affect the welfare of people e.g.

by changing living conditions?

Yes Proposed expansion of the 1x800 MW

power project will lead to upliftment of

socio-economic conditions of the local

people

3.4 Vulnerable groups of people who

could be affected by the project

e.g. hospital patients, children,

the elderly etc.,

No All pollution control norms will be

strictly followed with respect to

Particulate Matter (PM), SO2 and NOx

emissions by installation of pollution

control equipments. There is no effect

envisaged for the vulnerable groups of

people who could be affected by the

project.

3.5 Any other causes No No other causes envisaged

4) Production of solid wastes during construction or operation or decommissioning

(MT/month)

S.No Information/

Checklist confirmation

Yes/

No

Details thereof (with approximate

quantities/rates wherever possible)

with source of information data

4.1 Spoil, overburden or mine wastes Yes The spoil generated during the

construction will be reused for leveling

within the plant site and green belt

development

11

S.No Information/

Checklist confirmation

Yes/

No

Details thereof (with approximate

quantities/rates wherever possible)

with source of information data

4.2 Municipal waste (domestic and

or commercial wastes)

Yes During the construction and operational

phase of the proposed plant collection

and handling of domestic solid waste will

be disposed as per the provisions of

Solid Waste Management Rules, 2016.

4.3 Hazardous wastes (as per

Hazardous Waste Management

Rules )

Yes The Hazardous wastes generated during

construction and operational phases will

be disposed as per the provisions of

Hazardous and other wastes

(Management & Transboundary)

Movement Rules, 2016.

4.4 Other industrial process wastes Yes During the operation 3950 TPD of fly ash

and 987 TPD of bottom ash will be

generated in the present proposal of

1X800 MW TPP. The fly ash will be

collected and disposed in dry form for

utilization for cement & other end users

and bottom ash will be collected through

hydrobins and utilized for stowing/void

filling in SCCL mines.

4.5 Surplus product No There is no surplus product generation.

4.6 Sewage sludge or other sludge

from effluent treatment

Yes Sewage Sludge generated from the STP

will be used as manure in greenbelt

development.

4.7 Construction or demolition waste Yes During construction some amount of

construction debris may be generated

which will be segregated and whatever is

re-saleable will be sold to buyers and

rest of the waste will be used for filling

up of low lying areas and development

of internal roads and boundary walls.

4.8 Redundant machinery or

equipment

No Not envisaged

4.9 Contaminated soils or other

materials

No No contamination is anticipated.

4.10 Agricultural wastes No Not Envisaged

4.11 Other solid wastes No No other solid wastes

12

5) Release of pollutants or any hazardous, toxic or noxious substances to air (Kg / hr)

S.No Information/Checklist Confirmation Yes/

No

Details thereof (with approximate

quantities/rates wherever possible)

with source of information data

5.1 Emissions from combustion of

fossil fuels from stationary or

mobile sources

Yes Vehicles transporting man and

material for construction, operations

are sources of emission from fossil

fuel. The pollutions likely to be

released are PM10, PM2.5, SO2, NOx,

CO and HC etc. control measures will

be taken to keep these pollutants with

in the prescribed norms of CPCB and

TSPCB.

5.2 Emissions from production

processes

Yes PM10, PM2.5, SO2, NOx will be the

major emissions from the power plant

operations. The boiler will be attached

to Electrostatic Prespitator (ESP) of

99.98% efficiency with 275 m stack

height to restrict the emissions below

<30 mg/Nm3. There will be marginal

increase in emissions and will be

adequately covered in impact

assessment and EMP.

5.3 Emissions from materials handling

including storage or transport

Yes Fugitive emissions are envisaged from

material handling and transportation

areas during construction stage. These

will be controlled by good

housekeeping, sprinkling water in dust

prone areas, providing paved roads,

proper fencing and green belt

development.

Fly ash collected in ESP will be stored

in ash silos for transportation to

cement & brick industries. Unutilized

ash if any during exigency will be

disposed in the ash pond.

5.4 Emissions from construction

activities including plant and

equipment

Yes The gasses emissions like oxides of

Nitrogen and CO will be emitted from

the equipment during construction

phase only. However, these are

fugitive emissions of temporary

13

S.No Information/Checklist Confirmation Yes/

No

Details thereof (with approximate

quantities/rates wherever possible)

with source of information data

nature and will be controlled by

sprinkling water.

5.5 Dust or odors from handling of

materials including construction

materials, sewage and waste

Yes Dust generated due to handling

construction material will be

controlled by sprinkling of water. The

sewage will be treated in septic tanks

followed by soak pits.

5.6 Emissions from incineration of waste No No incineration is proposed

5.7 Emissions from burning of waste

in open air (e.g. slash materials,

construction debris)

No No material will be openly burnt in air.

5.8 Emissions from any other sources No Nil

6) Generation of noise and vibration and emissions of Light and Heat:

S.No Information/Checklist

confirmation

Yes/

No

Details thereof (with approximate

quantities/rates wherever possible)

with source of information data

6.1 From operation of equipment e.g.

engines, ventilation plant, crushers

Yes i) Noise will be generated during

operation of generator, Turbines,

compressors, pumps, fans, coal

handling plant etc. The expected noise

level during those operations is 75 dB

(A), necessary PPEs will be provided.

Noise level will be limited as per Norms.

Suitable acoustic enclosures will be

provided.

ii) Most of the equipment structures are

static. The vibration effect of these will

be only local and the design of supports

and foundations will nullify the

intensity.

iii) Light emissions are not envisaged

iv) Heat emissions will be felt nearby

boiler, generator areas.

v) Noise generation during construction

will not be continuous and meager.

14

S.No Information/Checklist

confirmation

Yes/

No

Details thereof (with approximate

quantities/rates wherever possible)

with source of information data

6.2 From industrial or similar processes Yes Heat is released in the furnace that

heats up the surrounding air due to

convection. Therefore insulation will be

applied to furnace walls to minimize the

heat transfer to air.

6.3 From construction or demolition Yes Noise generated from Excavation,

drilling and welding will be temporary.

6.4 From blasting or piling No Not applicable

6.5 From construction or operational

traffic

Yes There will be marginal additional traffic

which may lead to the slight increase in

the noise levels.

6.6 From lighting or cooling systems Yes The noise level due to operation of

cooling towers will be of the order of 75

dB(A)

6.7 From any other sources No Nil

7) Risks of contamination of land or water from release of pollutants into the ground or

into sewers, surface waters, ground water, coastal waters or the sea

S.No Information/Checklist

confirmation

Yes/

No

Details thereof (with approximate

quantities/rates wherever possible)

with source of information data

7.1 From handling, storage, use or

spillage of hazardous materials

Yes Precautions and safe operating

practices will be followed to minimize

hazard due to accidental spill of

hazardous materials which are stored

in small quantities.

7.2 From discharge of sewage or

other effluents to water or the

land (expected mode and place of

discharge)

Yes No discharge of sewage or other

effluents to water or the land is

envisaged outside the plant boundary.

Power plant waste water and sewage

water will be treated in Treatment

Plants and 100% reused for green belt

development, dust control, etc. A zero

discharge concept will be followed.

7.3 By deposition of pollutants

emitted to air into the land or into

water

No The major emission from the proposed

project are Particulate Matter (PM),

SO2 and NOx. Adequate control

15

S.No Information/Checklist

confirmation

Yes/

No

Details thereof (with approximate

quantities/rates wherever possible)

with source of information data

systems like ESP and stack height

meeting the MoEF guidelines will be

provided to control the emissions. FGD

is proposed to remove the sulphur

form flue gases. Hence there will not

be any chance of contamination of

land and water by deposition of

pollutants emitted to air.

7.4 From any other sources No No other sources

7.5 Is there a risk of long term build up

of pollutants in the environment

from these sources?

No Not envisaged

8) Risk of accidents during construction or operation of the project, which could affect

human health or the environment

S.No Information/Checklist

confirmation

Yes/

No

Details thereof (with approximate

quantities/rates wherever possible)

with source of information data

8.1 From explosions, spillages, fires etc

from storage, handling, use or

production of hazardous

substances

Yes Adequate safety measures will be

followed to control fire and other

disasters by preparing and

implementation of Disaster

Management Plan during construction

and operational phase. LDO/HFO will

be stored and handled as per all

applicable safety regulations.

8.2 From any other sources No Not envisaged

8.3 Could the project be affected by

natural disasters causing

environmental damage (e.g. floods,

earthquakes, landslides, cloudburst

etc.)?

No The proposed project site falls in Zone

III as per the IS 1893 (Part-1): 2002. It

is lesser seismic prone zone. There are

no landslides, erosion and other

natural calamities.

16

9) Factors which should be considered (such as consequential development) which

could lead to environmental effects or the potential for cumulative impacts with

other existing or planned activities in the locality

S.No Information/

Checklist confirmation

Yes/

No

Details thereof (with

approximate quantities/rates

wherever possible) with source

of information data

9.1 Lead to development of supporting

facilities, ancillary development or

development stimulated by the project

which could have impact on the

environment e.g. Supporting

infrastructure (roads, power supply,

waste or waste water treatment, etc.)

Housing development Extractive

industries Supply industries Others

Yes

Proposed plant will result in

considerable growth of service

sector, which will lead to

supporting and ancillary

development in the region. New

housing facilities and social

infrastructure may come up due

to influx of the people.

9.2 Lead to after-use of the site, which

could have an impact on the

environment

No

No major impacts are envisaged

9.3 Set a precedent for later developments Yes Ancillary industries would

develop.

9.4 Have cumulative effects due to

proximity to other existing or planned

projects with similar effects.

No Cumulative impact of proposed and existing units will be in the statutory limits.

(III) Environmental Sensitivity

S.No Areas Name/

Identity

Aerial distance (within 15 km.)

Proposed project location

boundary

1 Areas protected under international

conventions, national or local

legislation for their ecological,

landscape, cultural or other related

value

No No areas protected under

international conventions,

national or local legislation for

their ecological, landscape,

cultural or other related value

are present.

2 Areas which are important or

sensitive for ecological reasons -

Wetlands, watercourses or other

water bodies, coastal zone,

biospheres, mountains, forests.

No No wildlife sanctuary and

National park exists. River

Godavari, Tekumatla Vagu,

Elkanti Cheruvu, Indaram Tank,

etc and Indaram R.F., Kundaram

R.F present in buffer zone.

17

S.No Areas Name/

Identity

Aerial distance (within 15 km.)

Proposed project location

boundary

3 Areas used by protected, important

or sensitive species of flora or fauna

for breeding, nesting, foraging, resting,

over wintering, migration

No Nil

4 Inland, coastal, marine or underground

waters

Yes Godavari River at a distance of

8.6 Km.

5 State, National boundaries No Nil

6 Routes or facilities used by the public for

access to recreation or other tourist,

pilgrim areas

No Nil

7 Defence installations No Nil

8 Densely populated or built-up area Yes Mancherial at a distance of 14.6

Km.

9 Areas occupied by sensitive man-

made land uses (hospitals, schools,

places of worship, community facilities)

Yes There are no. of schools,

hospitals, temples, churches,

majids, etc within 15 Kms.

10 Areas containing important, high

quality or scarce resources (ground

water resources, surface resources,

forestry, agriculture, fisheries, tourism,

minerals)

No Nil

11 Areas already subjected to pollution or

environmental damage. (those where

existing legal environmental standards

are exceeded)

No Nil

12 Areas susceptible to natural hazard

which could cause the project to

present environmental problems

(earthquakes, subsidence, landslides,

erosion, flooding or extreme or adverse

climatic conditions)

No Nil

__

PRE-FEASIBILITY REPORT For

THE PROPOSED

EXPANSION OF SINGARENI THERMAL POWER PLANT

(From 1200 MW to 2000 MW by adding 1x800 MW)

at Pegadapalli Village, Jaipur Mandal, Mancherial Dist, Telangana State

Submitted to Ministry of Environment, Forests & Climate Change (MoEF&CC),

Government of India, Indira Paryavaran Bhavan, Jorbagh,

Jorbagh Road, New Delhi

Project Proponent

THE SINGARENI COLLIERIES COMPANY LIMITED (A Government Company)

P.O. Kothagudem Collieries - 507 101 Bhadradri Kothagudem District: Telangana State

August 2017

Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

THE SINGARENI COLLIERIES COMPANY LIMITED

i

INDEX

S. No. Description Page No.

1 Executive Summary 1-4

2 Introduction of the Project / Background information

2.1 Identification of Project and Project Proponent 5

2.2 Brief description of nature of the project 6

2.3 Need for the Project and its Importance to the Country and or Region 6

2.4 Demand – Supply Gap 7

2.5 Imports Vs Indigenous Production 8

2.6 Employment Generation (Direct & Indirect) 8

3 Project Description

3.1 Type of Project including interlinked and interdependent projects if any

8

3.2 Details of alternate sites considered and the basis of selecting the proposed site, particularly the environmental considerations gone into should be highlighted

13

3.3 Size or Magnitude of operation 13

3.4 Project Description with process details 13

3.5 Raw material required along with estimated quantity likely source, marketing area of final products, mode of transport of raw material and finished product

14

3.6 Resource Optimization Recycling & Reuse envisaged in the project, if any, should be briefly outlined)

15

3.7 Availability of water its source, energy/power requirement and source should be given

15

3.8 Energy / Power requirement and source 16

4 SITE ANALYSIS

4.1 Infrastructure 16

4.2 Connectivity 16

4.3 Land Details 17

4.4 Existing land use pattern, shortest distance from the periphery of the project to periphery of the forests, water bodies

17

4.5 Soil Classification 18

4.6 Climatic Data from Secondary Sources 18

4.7 Social Infrastructure available 18

5 Planning Brief

5.1 Planning Concept 19

5.2 Population Projection 19

5.3 Land use planning 20

5.4 Assessment of Infrastructure Demand (Physical & Social) 20

5.5 Amenities / Facilities 20

6 Proposed Infrastructure

6.1 Industrial Area 20

Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

THE SINGARENI COLLIERIES COMPANY LIMITED

ii

6.2 Residential Area 21

6.3 Green Belt 21

6.4 Social Infrastructure 21

6.5 Connectivity 21

6.6 Drinking Water Management 21

6.7 Sewage System 21

6.8 Industrial Waste Management 21

6.9 Solid Waste Management 22

6.10 Power Requirement & Supply 22

7 Rehabilitation & Resettlement Plan 22

8 Project Schedule & Cost Estimates 22

8.1 Likely date of start of construction and likely date of completion 22

8.2 Estimated Project cost along with analysis in terms of economic viability of the project

22

9 Analysis of proposal

9.1 Project cost estimates and financial analysis 24

9.2 Financial and social benefits (With special emphasis on the benefit to the local people including tribal population, if any, in the area)

24

Plates

Location plan 25

Topo Sheet 26

Plant layout 27

Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

THE SINGARENI COLLIERIES COMPANY LIMITED

1

1. Executive Summary:

Singareni Collieries Company Limited (SCCL) is proposing to set up a 1x800 MW (additional unit) besides the 2x600 MW units already in operation. The third unit of 1x800 MW will be constructed as an expansion project and will be located adjacent to already constructed and in operation of Stage-I (2x600 MW) units.

The project site is located near Pegadapalli Village, Jaipur Mandal, and District Mancherial of Telangana. The proposed site is situated between 18°48’30” to 18°50’35” Northern latitude and between 79°34’00” to 79°35’30” Eastern longitude. The site is 14.6 km from nearest town Mancherial and 4.6 km from the Rajiv Rahadari and 500 meters from NH-63.

The proposed project falls under the category ‘A’ of Project Activity 1(D) under the schedule as per EIA notification issued on 14th September, 2006 and hence the proposed expansion of the project requires Environmental Clearance from MoEF&CC, Govt. of India.

The salient features of the proposal are as follows:

S.No Description Existing

(a)

ToR issued

(b)

Proposed (c)

Total (after expansion)

(a+c)

1. Plant Configuration

2x600 MW 1x600 MW 1x800 MW 2000 MW (2x600+1x800)

2. Land requirement, Ha

300.972 105.21 127.31 428.28

3. Forestland involved

Nil Nil Nil Nil

4. R&R Involved Nil Nil Nil Nil

5. Water allocation 1.05 TMC per annum during

lean period from River

Godavari and 2.0 TMC from

River Pranahitha as main source

sanctioned by State

Government

From Godavari and

Pranahitha River

From Pranahitha River

From Godavari and Pranahitha

River

6. Coal Supply Naini coal block was

allocated for STPP.

Expected coal production is

2020. Meanwhile MoC has

granted bridge linkage for use

of coal from SCCL mines

Naini coal block was

allocated for STPP.

Expected coal production is 2020. MoC

was requested for grant of

bridge linkage for use of coal

from SCCL mines

Naini coal block was allocated for STPP. Expected coal production is 2020. MoC was requested for grant of bridge linkage for use of coal from SCCL mines. MoC during its meeting advised SCCL that the issue will be discussed in

Naini coal block was allocated for STPP. Expected coal production

is 2020. Meanwhile MoC

has granted bridge linkage for its 2x600 MW. SCCL

made a request to MoC to

consider the required coal for

Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

THE SINGARENI COLLIERIES COMPANY LIMITED

2

S.No Description Existing

(a)

ToR issued

(b)

Proposed (c)

Total (after expansion)

(a+c)

the next SLC meeting.

1x800 MW under bridge linkage from SCCL mines.

7. Coal Transport Through Rail/Trucks

Through Rail Through Rail Through Rail

8. Man Power requirement

700 100 450 1150

9. Capital Cost in Rs. Crores

7573.51 3570.20 5879.62 13453.13

10. Power Evacuation Through 440 KV system

Through 440 KV system

Through 440 KV system

Through 440 KV system

11. Boiler

Boiler type Sub-critical pulverized fuel, coal

fired unit to produce sub-critical steam parameters

Sub-critical pulverized fuel, coal fired unit

to produce sub-critical

steam parameters

The boiler shall be Super-Critical,

once through, water tube, direct pulverized coal

fired, suitable for outdoor

installation.

-

Capacity (TPH) 2050 2050 2690 2690

Main Steam Pressure (bar)

175 175 275 -

Main Steam Temperature, ˚C

540 540 603 -

Efficiency, % 87 86 During detailed engineering

-

12. Turbine

Heat Rate, K.Cal/KWH

1935 1935 During detailed engineering

-

Exhaust Pressure, ata

0.1047 0.1047 77 mm Hg (a) -

Exhaust Temperature, 0C

40 40 During detailed engineering

-

Station Heat Rate, KCal/KWh

2425 2351 2250

-

13. Generator

MW Capacity, MW 2x600 1x600 1x800 2000 (2x600+1x800)

Generator Transformer

3 Nos. single phase Transformers -

Type 3 x 1 Phase 3 x 1 Phase Power Transformer (OFAF)

-

MVA 260 260 315 -

Voltage Ratio, KV 21.5/400 21.5/400 22/400 -

Unit Transformer (UT)

2 nos. for each unit

2 nos. 2 nos. -

MVA 31.5 31.5 63 -

Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

THE SINGARENI COLLIERIES COMPANY LIMITED

3

S.No Description Existing

(a)

ToR issued

(b)

Proposed (c)

Total (after expansion)

(a+c)

Voltage Ratio, KV 400/21.5 400/21.5 22/11.5 -

Station Transformer

2 Nos. 1 No. 2 nos. -

MVA 100 each 50 130 -

Voltage Ratio, KV 400 / 11 400 / 11 400 / 11 -

14. Coal Handling Plant

Track hopper, MT 6000 No additional requirement

No additional requirement

6000

Crusher 4 Nos. (770 TPH)

No additional requirement

Separate Crusher House

(4 nos )

8

Paddle feeders 4 Nos. (1050 TPH)

No additional requirement

No additional requirement

4

Vibrating screen feeders

4 nos. (770 TPH)

No additional requirement

4 nos. Separate 8

Wagon tippler - 1 No. proposed 2 nos. proposed 2

All conveyors 1400 mm wide

(1400 TPH)

To be extended

Provision for interconnection

between Stage-1 and Stage-2

-

Stacker Reclaimer 2 Nos. (1400 TPH)

1 No. of suitable capacity

1 No. (1750 TPH)

-

Coal requirement, TPH

625 (Heat Rate –

1935 KCal/KWh,

GCV of Coal – 4529

( KCal/Kg)

310 (Heat Rate –

1935 KCal/KWh,

GCV of Coal – 4529

( KCal/Kg)

514 (Heat Rate –

2250 KCal/KWh, GCV of Coal -

3500( KCal/Kg)

-

15. Fuel Oil Storage Capacity

LDO, Cu.m. 2x500 No additional requirement

No additional requirement

1000

HFO, Cu.m. 2x2000 No additional requirement

1x2000 6000

16. Ash Handling System

BA HP water pumps (W-working, S-Standby)

2 nos. (1W+1S)

2 nos. (1W+1S)

2 nos. (1W+1S)

4 nos. (2W+2S)

Capacity, m3/hr 465 250 760 1225 BA LP water pumps

3 Nos. (2W+1S)

2 Nos. (1W+1S)

2 Nos.

(1W+1S)

5 Nos.

(3W+2S)

Capacity, m3/hr 600 300 940 1540 Fly Ash main SILO 4 Nos. 2 Nos. During detailed

engineering -

Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

THE SINGARENI COLLIERIES COMPANY LIMITED

4

S.No Description Existing

(a)

ToR issued

(b)

Proposed (c)

Total (after expansion)

(a+c)

Capacity, MT 4 x 900 900 During detailed engineering

-

HCSD silo 3 Nos. No additional requirement

During detailed engineering

-

Capacity, MT 500 Not applicable During detailed engineering

-

Ash dyke area, Ha 30 52.61 59.44 89.44

17. Water Pumps Details

Raw water source from Rivers Godavari near Shetpalli village & Pranahitha near Devulawada Village, Mancherial

Water allocation 1.05 TMC per annum during

lean period from River

Godavari and 2.0 TMC from

River Pranahitha as main source

sanctioned by State

Government

No additional requirement

2.00 TMC per annum

sanctioned by State

Government

2 TMC per annum from

River Pranahitha

No. of VT pumps, W- working, S-standby

2+1 (W+S)

No additional requirement

3+1 (W+S)

3+1 (W+S)

Rating, KW 685 Nil 1050 1050

Flow, m3/hr 2916 - 2592 2592

Quantity of water to be pumped, TMC

1.01 - 2.00 2.00

Plant Reservoir Capacity, L.Cu.m.

25 (0.089 TMC)

No additional requirement

25 (0.089 TMC)

25 (0.089 TMC)

18. Date of Commissioning

Unit:1 – 39 Months (COD) done on 25.09.2016 Unit:2 – 43 Months (COD) done on 02.12.2016

50 months from zero date

50 months from zero date

50 months from zero date

Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

THE SINGARENI COLLIERIES COMPANY LIMITED

5

2. INTRODUCTION OF THE PROJECT/BACKGROUND INFORMATION

2.1 Identification of Project and Project Proponent

The Singareni Collieries Company Limited (SCCL) is a Government Company jointly owned by the Government of Telangana and Government of India on a 51:49 equity basis. The Singareni coal reserves stretch across 350 km of the Pranahita – Godavari valley of Telangana with a proven geological reserves aggregating to 8791 MT The studies of Geological Survey of India attribute as much as 22207 million tonnes of coal reserves in the Godavari valley coalfield. The inventory covers up to a depth of 1200 meters and it includes reserves proved, indicated as well as inferred. The SCCL has been exploiting coal for more than 127 years the Company had expanded its mining activities in Mancherial, Komaram Bheem Asifabad, Peddapalli, Jayashankar Bhoopalpalli, Bhadradri Kothagudem and Khammam districts of Telangana. The coal produced by SCCL in the Godavari valley coalfield in the year 2016-17 was 61.34 Million tonnes. The targeted production for the year 2017-18 is 66.06 Million tonnes.

SCCL also operating small captive power plants since 1960 and recently SCCL is foraying into large scale power generation. SCCL constructed Non pithead power station of 2x600 MW units located at Pegadapalli village, Jaipur Mandal in Mancherial district of Telangana which is commisioned in the year 2016.

The Environmental Clearance was accorded by Ministry of Environment, Forest and Climate Change vide Lr. No. J-13012/88/2008-IA.II (T), dated 27.12.2010 and Consent for Establishment (CFE) under Air (Prevention & Control of Pollution) Act and Water (Prevention & Control of Pollution) Act by State Pollution Control Board vide Order No. 64/PCB/CFE/RO-NZB/HO/2010-818, dated 16.06.2011 and Consent For Operation (CFO) under Air (Prevention & Control of Pollution) Act and Water (Prevention & Control of Pollution) Act by State Pollution Control Board vide Order No. TSPCB/CFO/NZBG/HO/2017-42,Dt.04.04.2017 and valid up to 30.04.2022 under Auto Renewal for the 2x600 MW Thermal Power Plant which is under Operation. In view of the power crisis in the newly formed state of Telangana, State Government vide letter dated 16.03.2017 accorded approval for setting up 1x800 MW as expansion and directed the SCCL to establish one more unit of 1x800 MW in addition to 2x600 MW Thermal Power Plant.((From 1200 MW to 2000 MW by adding 1x800 MW)

As SCCL is already constructed 2x600 MW units and are in operation, some of the BOP facilities of these units have spare capacities which can be utilized for the proposed 1X800 MW unit. The review of existing system reveals their adequacy for the proposed additional unit. The spare capacities of the existing system have been worked out after meeting the requirements for the 2x600 MW units in operation.

Infrastructure facilities such as land, water transport arrangements, railway line, roads etc. are available. The advantages of proposing the additional unit at same location are:

No new infrastructure facilities are required for expansion unit. Total required land is available with SCCL. No Re-settlement is involved. Availability of adequate raw water from Pranahita River. Water will be pumped through the existing pipe line and pump house. There is no forest land involved for the project. Since existing facilities are being used, cost of the power would be less.

Address of the Project Proponent Director (E&M) The Singareni Collieries Company Limited Po:Kothagudem, PIN. Code: 507101 Dist: Bhadradri Kothagudem, Telangana State e-mail id: [email protected] Ph.No. 08744 – 245005; Fax No. 08744 – 241201

Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

THE SINGARENI COLLIERIES COMPANY LIMITED

6

Address of the Project In-charge/Occupier. Executive Director, Singareni Thermal Power Plant Pegadapalli Village, Jaipur Mandal, PIN Code: 504 216

Dist: Mancherial, Telangana State

e-mail ID: [email protected]

Ph. No. 08737-243243

2.2 Brief Description of the Nature of the Project

Singareni Collieries Company Limited (SCCL) is proposing to set up Singareni Thermal Power Plant by adding Stage-II 1x800 MW as expansion of 2x600 MW units already in operation, as per the directions of State Government in view of the acute power shortage in the state of Telangana. The third unit of Stage-II (1X800 MW) will be constructed as an extension project and will be located adjacent to the operating units.

SCCL has obtained Environmental Clearance from MoEF&CC, New Delhi for establishing 2x600 MW coal based TPP of the Singareni Collieries Company Limited (SCCL) at Pegadapali Village, Jaipur Mandal, Mancherial District, Telangana State vide MoEF&CC lr. No. J-13012/88/2008-IA.II (T), dated 27.12.2010 and amendment to EC was obtained vide MoEF&CC lr. No. J-13012/88/2008-IA.II(T), dated.10.08.2016.

Consent for Establishment (CFE) under Air (Prevention & Control of Pollution) Act and Water (Prevention & Control of Pollution) Act by State Pollution Control Board vide Order No. 64/PCB/CFE/RO-NZB/HO/2010-818, dated 16.06.2011 and Consent for Operation (CFO) under Air (Prevention & Control of Pollution) Act and Water (Prevention & Control of Pollution) Act by Telangana State Pollution Control Board vide Order No.TSPCB/CFO/NZBG/HO/2017-42,dt.04.04.2017 and valid upto 30.04.2022.

Presently, 2x600 MW TPP is in operation.

Present Proposal:

Present proposal is amendment to ToR issued vide MoEF&CC lr. No. J-13012/08/2015-IA.I(T), dated.27.05.2015 for expansion of Singareni Thermal Power Plant (From 2x600 MW to 2000 MW by adding 1x800 MW) at Pegadapalli village, Jaipur Mandal, Mancherial District of Telangana State by M/s Singareni Collieries Company Limited.

2.3 NEED FOR THE PROJECT AND ITS IMPORTANCE TO THE COUNTRY AND OR REGION

POWER SCENARIO OF TELANGANA STATE - POWER SUPPLY SCENARIO

As per the report “Power for All – Telangana State” A joint initiative of Govt. of India and Govt. of Telangana State, energy deficit in Telangana for last year’s was in the range of 4%-12%. Energy requirement in Telangana was 50,916 MU in FY 14-15, of which only 2,128 MU could not be met resulting in an energy deficit of nearly 4.2% with a maximum historic peak demand of 8,331 MW in 2014-15.

As can be seen from the table below, peak demand has increased by over 2,588 MW

during the period FY 2008-09 till FY 2014-15 as against which peak met has increased by 1,345 MW.

Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

THE SINGARENI COLLIERIES COMPANY LIMITED

7

2.4 Demand – Supply Gap Historical Power Supply Position in Telangana State

Period Peak Peak Peal Peak Energy Energy Energy Deficit

Energy Deficit

Demand

Met Deficit Deficit/ Requir Availability

(MU) (-/+) Surplus (-/+) (MW) (MW) / Surplus ement (MU)

Surplus

(%) (-/+)

(MU) (MW) ( -/+)

2008-09 5,743 5,303 -0.440 -8% 31,883 30,348 -1,535 -4.8% 2009-10 6,263 5,655 -0.608 -10% 34,808 32,752 -2,055 -5.9% 2010-11 6,600 6,239 -0.361 -5% 36,490 35,802 -0.688 -1.9% 2011-12 6,866 6,461 -0.405 -6% 47,987 45,312 -2,675 -5.6% 2012-13 6,741 6,317 -0.424 -6% 48,758 42,942 -5,816 -11.9% 2013-14 7,876 7,177 -0.699 -9% 47,428 44,946 -2,482 -5.2% 2014-15 8,331 6,648 -1.683 -20% 50,916 48,788 -2,128 -4.2%

There was a 11% increase in the peak deficit in FY 2014-15 over FY 2013-14 attributable to the increased agricultural loads whereas the energy deficit has decreased by 1% attributable to the extensive short term market purchases which contributed to 21% of the total power purchased in FY 2014-15.

Implementation of 24X7 supply across the State is likely to increase the electricity consumption substantially. Various factors that have been considered for future energy projections include:

Demand from Domestic segment

Agriculture supply from 7 hours to 9 hours in a day

Implementation of Lift Irrigation Schemes

Urban development in cities of Hyderabad, Warangal, Nizamabad and Karimnagar.

Upcoming major projects such as Hyderabad Metro Rail, Hyderabad ITIR region

Upcoming Bayyaram Steel Plant.

Existing Generation Capacity

Energy availability from existing sources as on FY 2014-15 was about 48,788 MU inclusive of market purchases and coal based power from long-term sources constituted nearly 66% of energy availability.

PPAs due to expire in the next 5 years

Some of the existing PPAs of TSDISCOMS with generators would expire during the next 10 years. Currently, Telangana is entitled to 53.89% of power from TSGENCO and APGENCO stations. Post expiry of PPA, no capacity would be available from APGENCO stations while 100% capacity of TSGENCO plants would be available to Telangana. This project (Singareni TPP Stage-II) has already been identified in the referred report while calculating the generation capacity and meeting the required supply of power against the demand to energize the power thirsty & development oriented newly formed Telangana State.

Considering above facts & data, it is prudent to go for a coal based supercritical unit of 1X800MW utilizing the space available and the facilities of Stage-I.

2.5 Imports Vs Indigenous Production

The entire saleable power from the project will be procured by TSTRANSCO independent consumers by utilizing the 400 kV power transmission grids being managed by TSTRANSCO. The saleable power from the additional unit will be of the order of 754 MW after accounting for

Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

THE SINGARENI COLLIERIES COMPANY LIMITED

8

auxiliary power consumption of 5.75%.The total salable power from the entire 2X600 MW &1X800 MW will be 1885 MW to the TSTRANSCO.

Indigenous production of the power will be much cheaper, reliable and comfort than the import of the power from other states, The proponent is operating number of coal mines in the area of power plant there will not be any problem of supply of coal to the power plant.

2.6 Employment Generation (Direct & Indirect) due to the Project

During the construction period the requirement of manpower will be about 2000 to 3000 persons on temporary basis. During Operational phase, direct employment for 1550 persons (1100 for 2x600 MW and 450 for additional 1X800 MW) will get and about 1000 persons will get indirect employment.

3 PROJECT DESCRIPTION:

3.1 Type of Project including interlinked and interdependent projects if any:

Expansion of 2x600 MW Coal Based Singareni Thermal Power Plant with 1x800 MW. Ultimate capacity of the station would be 2x600MW + 1x800MW i.e. 2000MW.

a. Location: The present proposal is for setting up of one unit of 1X800 MW Thermal Power Plant besides the 2x600 MW units already in operation at Pegadapalli Village, Jaipur Mandal of Mancherial District in Telangana State. The plan showing plant location ,mines from which coal is proposed to supply and water source is enclosed as Annexure-I The details of the Location are as follows:

Location Details of the Project

Village : Pegadapalli

Tehsil : Jaipur

District : Mancherial

State : Telangana

Latitudes : N 18° 48’ 30” and 18° 50’ 35”

Longitudes : E 79° 34’ 00” and 79° 35’ 30”

Survey of India Topo sheet No. : 56 N/9

Nearest Town : Mancherial (14.6 Km), NW

Nearest City : Hyderabad (250 Km), SW

District head quarters : Mancherial (14.6 Km), NW

State capital : Hyderabad (250 Km), SW

Nearest Railway Station : Mancherial Railway station at 14.6 Km (Nagpur-Kazipet main rail line of South-Central Railway)

Nearest Airport : Rajiv Gandhi International Airport, Shamshabad, Hyderabad at a distance of 250 Km.

Nearest Highway : Rajiv Rahadari State Highway (4.6 Km), W

Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

THE SINGARENI COLLIERIES COMPANY LIMITED

9

Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

THE SINGARENI COLLIERIES COMPANY LIMITED

10

Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

THE SINGARENI COLLIERIES COMPANY LIMITED

11

Co-ordinates of Main Plant and Ash Pond coordinates are as follows:

ID Latitude Longitude ID Latitude Longitude

Existing 2x600 MW Plant Coordinates:

A 180 48’57’’ 79034’10’’ J 180 50’22’’ 79035’14’’

B 180 49’12’’ 79034’09’’ K 180 50’10’’ 79035’10’’

C 180 49’15’’ 79034’21’’ L 180 50’00’’ 79034’58’’

D 180 49’45’’ 79034’21’’ M 180 49’20’’ 79034’56’’

E 180 49’45’’ 79034’53’’ N 180 49’09’’ 79034’56’’

F 180 49’57’’ 79034’53’’ O 180 49’06’’ 79035’14’’

G 180 49’57’’ 79034’40’’ P 180 48’42’’ 79035’14’’

H 180 50’21’’ 79034’39’’ Q 180 48’42’’ 79034’54’’

I 180 50’26’’ 79035’05’’ R 180 48’57’’ 79034’54’’

Existing 2x600 MW Ash Pond Coordinates:

a 180 49’03’’ 79034’56’’ c 180 48’43’’ 79035’13’’

b 180 49’03’’ 79035’13’’ d 180 48’43’’ 79034’56’’

Proposed 1x600 MW Plant Coordinates:

1 180 48’57’’ 79034’54’’ 6 180 48’42’’ 79034’55’’

2 180 48’52’’ 79034’54’’ 7 180 49’12’’ 79034’10’’

3 180 48’42’’ 79034’15’’ 8 180 49’40’’ 79034’10’’

4 180 48’57’’ 79034’15’’ 9 180 49’40’’ 79034’21’’

5 180 48’57’’ 79034’55’’ 10 180 49’15’’ 79034’18’’

Proposed 1X600 MW Ash Pond Coordinates:

1 180 48’57’’ 79034’54’’ 3 180 48’42’’ 79034’15’’

2 180 48’52’’ 79034’54’’ 4 180 48’57’’ 79034’15’’

Proposed 1x800 MW Plant coordinates:

1 180 48’57’’ 79034’54’’ 4 180 48’57’’ 79034’15’’

2 180 48’52’’ 79034’54’’ 5 180 48’57’’ 79034’55’’

3 180 48’42’’ 79034’15’’ 6 180 48’42’’ 79034’55’’

11 180 49’47’’ 79034’42’’ 13 180 49’48’’ 79034’70’’

12 180 50’18’’ 79034’42’’ 14 180 50’17’’ 79034’71’’

Proposed 1X800 MW Ash Pond Coordinates:

1 180 48’57’’ 79034’54’’ 3 180 48’42’’ 79034’15’’

2 180 48’52’’ 79034’54’’ 4 180 48’57’’ 79034’15’’

b. Land Requirement:

Presently 2x600 MW Thermal Power Plant is in operation in Pegadapalli Village, Jaipur Mandal of Mancherial district of Telangana in an area of 280.40 Ha in addition to the railway line for coal transportation & water supply pipelines in an area of 20.572 Ha. The present proposal is for setting up of one more unit of 1x800 MW Thermal Power Plant besides the 2x600 MW units. Some of the facilities like Coal Handling arrangements, Raw Water Intake System, Raw Water Reservoir, Fuel oil unloading etc envisaged for 2x600 MW units can also be used for the proposed unit of 1x800 MW TPP. As such, an additional area required for 1x800 MW is 127.31 Ha. All the land required for plant under operation and proposed unit of 1x800 MW is available and under possession of Singareni Collieries Company Limited. No further land acquisition is envisaged in the present proposal.

Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

THE SINGARENI COLLIERIES COMPANY LIMITED

12

c. Water Requirement:

The estimated water requirement for 2x600 MW plant under operation is 88,800 KLD (3700 m3/hr) and for additional unit of 1X800 MW is 48,000KLD (2000 m3/hr). Hence, Total Water required for 2000 MW (2x600 +1X800 MW) is 1, 36,800 KLD (5700 m3/hr).

S. No Description

Existing

2x600 MW

(a)

ToR issued

1x600 MW

(b)

Proposed 1x800 MW

(c)

Total (after expansion)

2000 MW (a+c)

1 Water Requirement, KLD

88,800 43,200 48,000 1,36,000

2 Water Requirement, m3/hr

3700

1800

2000

5700

State Government allocated vide G.O.Rt. No. 474, dated 19.07.2010 from River Pranahita 2.00 TMC near Devulawada Village, Mancherial District which will sufficient for total water requirement of 2000 MW.

d. Fuel requirement:

Coal requirement:

S.No Description

Existing

2x600 MW

(a)

ToR issued

1x600 MW

(b)

Proposed 1x800 MW

(c)

Total (after expansion)

2000 MW (a+c)

1 Coal,MTPA 4.784 2.32 4.05 8.834

Annual coal requirement for the plant shall be 4.05 MTPA considering PLF of 90% and the same is proposed to be met from Naini Mines allocated to SCCL.

LDO HFO/ requirement for startup and flame stabilization: The steam generator is

designed primarily for coal firing. A fuel oil system will be used for boiler start up as well as for

flame stabilization during low load. Light diesel oil will be used for furnace light up and boiler

start up while HFO will be used for flame stabilization. The required HFO/LDO will be met from

the nearest oil depots.

S.No Description

Existing

2x600 MW

(a)

ToR issued

1x600 MW

(b)

Proposed 1x800 MW

(c)

Total (after expansion)

2000 MW (a+c)

1 LDO/HFO,KL/annum 8935 4437 3153 12088

e. Power Evacuation:

The generation voltage is envisaged in the range of 22 to 27 kV. Evacuation of power from the proposed 800 MW extension unit will be done at 400 kV level. Two nos. 400 kV double circuit lines-3&4 to connect Nirmal substation are under construction.

f. Project Cost & Tariff:

The estimated Capital Cost, Capitalised Project Cost (including IDC) has been taken as Rs. 5879.62 Crs and Levelised cost of energy: 352 Paise/kWh.

Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

THE SINGARENI COLLIERIES COMPANY LIMITED

13

3.2 Details of alternate sites considered and the basis of selecting the proposed site, particularly the environmental considerations gone into should be highlighted

No alternate sites were considered as the present proposal is establishment of setting up of one additional unit of 1X800 MW Thermal Power Plant besides the 2x600 MW units already in operation at Pegadapalli Village, Jaipur Mandal of Mancherial District in Telangana State. Three alternate sites were examined before the establishment of 2x600 MW units. The location of the project meets guidelines issued by Ministry of Environment and Forests, Government of India.

3.3 Size or Magnitude of operation.

Size of the Total Plant is 2000MW and is expansion of Singareni Thermal Power Plant (From 2x600 MW to 2000 MW by adding one additional unit 1x800MW) by M/s Singareni Thermal Power Plant.

S.No Description Existing

(a)

ToR issued

(b)

Proposed (c)

Total (after expansion)

(a+c)

1 Size of the Plant,MW

2x600 1x600 1x800 2000

3.4 Project Description with process details

The proposed 1x800 MW Coal Based Thermal Power Plant of STPP, Stage-II is super-critical pulverised boiler technology. Coal received from the mines (expected bridge linkage from SCCL mines) at -200 mm size is crushed in the crusher house to -20mm size, which is subsequently pulverized in the coal mill. The powdered coal is burnt in the furnace to generate steam in the boiler. The steam generated in the boiler is expanded in the HP, IP & LP turbines and power is generated in the generator. The steam after expansion in the turbine is condensed in the condenser and the condensed steam is circulated back to the boiler. The hot gasses from the furnace after losing heat in different areas goes through the Electrostatic Precipitators, where ash is collected. The clean gas goes through the chimney. The bottom ash from boiler is collected in hydro-bins where water is separated and Ash in dry form is sent to underground mines of SCCL. The separated water will be reused / recirculated in the system.

Sitting Guidelines Conformity

The project shall be at least 500 m away from the HFL of the River

River Godavari is existing 4 KM away from the Project

The project shall be at least 500 m away from the High Way

NH-63 is at 500 m away from the project boundary.

The project shall be at least 500 m away from the Railway

The nearest railway line is Kazipet-Ballarsha section of South Central railway is at 14.6 Km from the project

Location of TPS should be avoided in the vicinity (10 Km) of places of archaeological, historical, cultural, religious or tourist importance and defence installations

No such areas are exists within 10 Km from the Project.

No forestland should be utilized for setting up of TPS or for ash disposal

No forest land is involved in the project.

Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

THE SINGARENI COLLIERIES COMPANY LIMITED

14

3.5 Raw material required along with estimated quantity likely source, marketing area of final products, mode of transport of raw material and finished product.

a. Coal requirement:

S.No Description

Existing

2x600 MW

(a)

ToR issued

1x600 MW

(b)

Proposed 1x800 MW

(c)

Total (after expansion)

2000 MW (a+c)

1 Coal,MTPA 4.784 2.32 4.05 8.834

The Annual coal requirement for the expansion unit at 4.05 million tonnes per annum at a plant load factor of 90%. Naini coal block was allotted for 3X600 MW STPP as end use plant. For 2X600 MW STPP Stage-I ,MoC has granted bridge linkage for the used coal from own mines of Singareni Collieries Company Limited namely SRP OC-I, SRP OC-II, RKP OC Phase-I, KK OCP and future mines like RKP Phase-II & SRP OC-III in Srirampur and Mandamarri areas at a distance of 6 to 15 Kms from the plant site.

MoC will be approached to grant bridge linkage for this 1X800 MW stage-2.The coal handling Plant is designed to handle the maximum coal required for the project.

b. HFO/LDO requirement for startup and flame stabilization:

The steam generator is designed primarily for coal firing. A fuel oil system will be used for boiler start up as well as for flame stabilization during low load. Light diesel oil will be used for

furnace light up and boiler start up while HFO will be used for flame stabilization. The

required HFO/LDO will be met from the nearest oil depots.

S.No Description

Existing

2x600 MW

(a)

ToR issued

1x600 MW

(b)

Proposed 1x800 MW

(c)

Total (after expansion)

2000 MW (a+c)

1 LDO/HFO,KL/annum 8935 4437 3153 12088

Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

THE SINGARENI COLLIERIES COMPANY LIMITED

15

c. Other Raw material:

Other Raw material like Cement (Estimated requirement: 90000 MT), Structural Steel

(Estimated requirement: 45000 MT), Reinforcement Steel (Estimated requirement: 26000 MT),

Sand (Estimated requirement: 1.10 L.Cu.m) and Stone/aggregate (Estimated requirement: 2.0

L.Cu.m) will be met from the local suppliers and transported through existing Rail/Road

networks.

d. Power evacuation:

Evacuation of power from the proposed plant will be done at 400 kV level, the generation voltage is envisaged as 22 KV. For evacuation of power, three nos. single phase 315 MVA, generator transformers for 1X800 MW unit will be connected to the 400 kV swithchyard of the 1x800 MW Power Plant which is to be constructed.

3.6 Resource Optimization Recycling & Reuse envisaged in the project, if any, should be briefly outlined)

Estimated total water requirement for the 2000 MW is 136800 KLD (5700 m3/hr). It will be met from Pranahita River. Continuous efforts would be made to reduce the water consumption and thereby to reduce the wastewater generation. Flow meters would be installed for all major water inlet and the flow rates would be continuously monitored. Periodic water audits would be conducted to explore the possibilities for minimization of water consumption.

Considering recirculation closed cooling water system with induced draught cooling tower, using river water for turbine condenser cooling, cycle make-up and other consumptive water requirements. The major quantity of this water will be essentially makeup water for the cooling towers, lost on account of evaporation, drift and blowdown.The filtered water shall be used for the cooling tower make-up, service water, potable water, DM plant, fire-fighting system etc.

3.7 Availability of water its source, energy/power requirement and source should be given

a. Water requirement, source and mode of transport:

Estimated water requirement for 2x600 MW plant under construction is 88800 KLD (3700 m3/hr) and for additional 1X800 MW is 48000KLD (2000 m3/hr). Hence, Total Water required for 2x600 &1x800 MW is 136800 KLD (5700 m3/hr).

S. No Description

Existing

2x600 MW

(a)

ToR issued

1x600 MW

(b)

Proposed 1x800 MW

(c)

Total (after expansion)

2000 MW (a+c)

1 Water Requirement, KLD

88,800 43,200 48,000 1,36,000

2 Water Requirement, m3/hr

3700

1800

2000

5700

The required water will be met from River Pranahita. 2.0 TMC of water per annum through infiltration galleries from Pranahitha River near Devulawada Village, Mancherial District was allocated by State Government vide G.O.Rt. No. 474, dated 19.07.2010. The quantity allocated water will be sufficient for entire 2x600 &1X800 MW. The water from the Pranahita River will be transported through pipeline.

Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

THE SINGARENI COLLIERIES COMPANY LIMITED

16

The details of water pumping are as follows:

B Raw water source from River Pranahitha near Devulawada Village, Mancherial District.

1 Water allocation 2.00 TMC per annum sanctioned by State Government

Same will be used

2 No. of VT pumps 3+1 (three working & one standby)

3 Rating 1050 kW

4 Flow 2592 m3/hr

5 Quantity of water to be pumped

2.00 TMC

C Plant Reservoir capacity 25 L.Cu.m. (0.089 TMC)- 47.92 Ha

Existing will be used

3.8 Energy / Power requirement and source: Construction power for the proposed expansion of 800 MW shall be availed from the existing source of TSTRANSCO / Nearest 33 KV substation.

4 SITE ANALYSIS

4.1 Infrastructure The present proposal is expansion of 2x600 MW Thermal Power Plant in operation with addition of 1x800 MW in view of the availability of the land, coal, water, transportation facilities, etc. The infrastructure facilities envisaged for 2x600 MW TPP like Coal Handling Arrangements, Raw Water Reservoir, Coal transportation facilities (Railway line), Administrative building, etc can be used for proposed 1x800 MW additional unit also. The additional land required for the present proposal is 127.31 Ha is also available adjacent to the plant under construction and also under possession of SCCL. The additional coal required for the project can be met from the SCCL mines under operation and future mines of SCCL in the area. The township is also planned outside the main plant area for operational and maintenance staff and sufficient area is also available for additional accommodation of additional staff envisaged for the proposed 1x800 MW Plant.

4.2 Connectivity The proposed project site is situated at a distance of around 500 m from the National Highway, (NH – 63 which connects Nizamabad town in Telangana and Jagdalpur town in Chhattisgarh). The access roads connecting to the National Highway have already been built for existing units; however, internal roads within the proposed extension unit area would have to be built. The project area is also well connected with rail network. Mancherial Railway station situated at a distance of 14.6 Km (Nagpur-Kazipet main rail line of South-Central Railway). Railway siding is available up to Srirampur CHP belongs to SCCL which is at a distance of 10 Km. It is proposed to extend the Railway line from the Srirampur CHP to the proposed Power Pant via Srirampur Opencast project for coal transportation. The nearest air port is Rajiv Gandhi International Airport, Shamshabad, and Hyderabad at a distance of 250 Km.

4.3 Land Details

The land requirement for the 2x600 MW TPP in operation along with proposed additional unit of 1X800 MW is furnished in the following table. All the land required for the proposal is under the possession of Singareni Collieries Company Limited. No additional land is required to be acquired for the present proposal.

Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

THE SINGARENI COLLIERIES COMPANY LIMITED

17

Details of Survey No.s of existing 2x600 MW Coal Based Thermal Power Plant is as follows: Pegadapalli Village, Jaipur Mandal: Sy. Nos: 147(P) 471/2 (P), 472, 473/2, 474, 477 to 480, 481(P), 482(P), 483 to 485, 525 to 533, 534(P) to 539(P), 540(P) to 548, 592 to 605(P), 608(P), 609(P), 610(P), 613(P), 614, 615(P), 616(P), 759(P), 760(P), 761(P), 762(P), 766(P), 767(P), 768 to 953, 955 to 963(P), 964(P), 966(P), 967, 968, Vagu (P). Gangipalli Village, Jaipur Mandal: SY.Nos.: 36(P), 37 to 39, 40(P), 44(P), 45(P), 46 to 53, 54(P), 55(P), 56(P), 316, 317, 322, 324, 336, 365, 366, 367, 378, 379. Elakanti Village, Jaipur Mandal: Sy. Nos: 63(P),64(P), 67(P), 69(P), 70, 71, 72/1, 72/2, 73(P), 74, 75, 76/2, 76/3, 357(P), 358(P), 382(P), 383(P), 385(P), 386(P), 387(P), 388 to 394, 395/1, 395/2(P), 395/3(P), 396/1, 396/2, 397, 398, 399, 400(P), 401(P), 402(P) VAGU(P). Shetpalli Village, Jaipur Mandal: Sy.Nos:148(P), 150(P), 152(P), 153(P), 166(P), 167(P), 168(P), 181 (P), 188(P), 194(P), 195(P), 196(P), 200(P), 201(P), 202(P), 239(P), 245(P), 249(P), 253(P), 255(P), 256(P), 264(P), 265(P), 268(P), 269(P), 436(P), 477(P), 478(P), 479(P), 486(P), 488(P), 489(P), 491 (P), 537(P), 546(P), 549(P), 599(P). Tekumatla Village, Jaipur Mandal: Sy.Nos: 79(P), 80(P), 102(P), 103(P), 104(P), 110(P), 111(P), 113(P), 115(P), 359(P), 381(P), 720(P), 721(P), 722(P), 724(P), 737(P). Indaram Village, Jaipur Mandal: Sy.Nos: 26(P), 27(P), 37(P), 38(P), 39(P), 40(P), 46(P), 47(P), 116(P), 126(P), 128(P), 129(P), 134(P), 284/1(P), 284/3(P), 1184(P), 1196(P), Road(P). Ramaraopet Village, Jaipur Mandal: Sy.Nos: 282(P), 290(P), 295(P), 296(P), 384(P), 385(P), 386(P), 388(P), 395(P), 399(P), 402(P), 404(P). Note: P=Part

List of Survey No.s of the additional land required for setting 1x800 MW as follows: Pegadapalli Village, Jaipur Mandal: Sy. Nos: 534(P), 539(P), 615(P), 616(P), 617(P), 618(P), 619(P), 620(P). Elakanti Village, Jaipur Mandal: Sy.Nos: 59(P), 60(P), 61, 62, 63(P), 64(P), 65, 66, 67(P), 68(P), 338(P), 339, 340, 341(P), 342(P), 345(P), 349(P), 350 to 356, 364(P), 365 to 367, 368(P), 381(P), 382(P), 383(P), 384, 385(P), 386(P), 387(P), 400(P), 401(P), 402(P), 403 to 409, 410(P), 413(P), 414(P), 415 to 417, 418(P), 482(P).

4.4 Existing land use pattern, shortest distance from the periphery of the project to periphery of the forests, water bodies

Total land requirement for the 2000 MW will be 428.20 Ha. An extent of 127.31 Ha of the land mainly open barren land under possession of SCCL is required for additional 1X800 MW in addition to the 2x600 MW plant in operation in an area of 300.972 Ha. No structures or forestland exists in the proposed land area.

S. No Particulars

Area in Ha

2x600MW (a)

1x600MW (b)

1X800MW (c)

Total 2000MW

(a+c)

1 Main Plant & Equipment 110.00 26.60

47.632

177.932 2 Coal Handling Plant 20.30

3 Raw Water Reservoir 47.92 Nil Nil 47.92

4 Ash Dyke 30.00 52.61 59.44 89.44

5 Greenbelt 72.18 26.30 20.24 92.42

Land for Main Plant 280.40 105.21 127.31 407.71

6 Land required for transportation of coal by rail system

15.245 Nil Nil 15.245

7 Land required for water pipeline 5.327 Nil Nil 5.327

Total land requirement 300.972 105.21 127.31 428.28

Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

THE SINGARENI COLLIERIES COMPANY LIMITED

18

Description Name and Distance

Nearest major Villages Jaipur - 1Km (W), Pegadapalli – 1.0 Km (E), Gangipalli -1Km (S), Rasulapalli - 2.5 Km (NW).

Nearest Forest Indaram reserve forest– 1.85 Kms (NW) Kundaram reserve forest – 2.1 Kms (E)

Nearest Wildlife Sanctuary/National Park

No

Nearest River Godavari river (4 Km)

Nearest Historical Places No archeologically important places exist within 10 Km of the project

4.5 Soil Classification

Red loamy soils are the main soils, which are derived from country rocks. The other soils are black cotton soils mainly derived from basalt rock. In sedimentary formations the soils are deep up to 5 m and in other formations up to 1.5 m.

4.6 Climatic Data from Secondary Sources

Meteorological data for the site is shown below:

IMD Station: Ramagundam Lat.180 46’ Long. 790 26’ Mean Sea Level. 156 m

Month

Temperature º C Humidity % Rainfall Mean Wind speed KMPH

Pre-dominant wind

direction Mean Min

Mean Max

Highest

Lowest 8.30 Hrs

17.30 Hrs

Monthly mm

No of rainy days 1st 2nd

Jan 30.7 15.6 33.4 10.5 74 45 11.5 0.7 2.6 S NE

Feb 33.5 18.5 36.5 13.3 65 38 9.7 0.7 3.3 S SE

Mar 37.5 21.8 40.7 16.5 57 30 9.2 0.7 3.5 S SE

Apr 40.5 25.7 43.7 21.2 55 29 13.7 1.1 4.6 S SW

May 42.1 28.3 45.3 23.4 49 29 34.7 2.4 4.5 S SW

Jun 37.4 26.8 43.8 22.6 65 49 180.1 8.7 4.9 W NW

Jul 32.6 24.8 36.6 22.2 79 68 328.2 14.5 3.6 W NW

Aug 31.4 24.5 34.8 22.6 82 72 285.8 13.1 2.9 W NW

Sep 33.1 24.3 35.7 22.1 80 69 166.9 8.2 2.0 W NW

Oct 33.3 22.1 35.8 17.7 76 61 102.5 4.7 1.6 NE NW

Nov 31.5 18.0 34.1 13.4 71 54 24.0 1.7 1.5 NE E

Dec 30.0 14.4 32.4 10.4 72 49 6.5 0.6 1.7 NE E

Source: GOI, Ministry of Earth Sciences, IMD, Climatological Tables - 1971-2000

4.7 Social Infrastructure available

Employment is expected during construction period as well as operation phase, in trade, garbage lifting, sanitation, afforestation works and other ancillary services. Employment in these sectors will be primarily temporary or contractual and involvement of unskilled labour will be more. A major part of this labour force will be mainly from local villagers who are expected to engage themselves both in agriculture and project activities. This will enhance their income and lead to overall economic growth of the area.

Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

THE SINGARENI COLLIERIES COMPANY LIMITED

19

The following changes in socio-economic status are expected to take place with this project. The project is going to have positive impact on consumption behaviour by way of raising average consumption and income through multiplier effect.

a) The project is going to bring about changes in the pattern of demand from food to non-food items and sufficient income is generated.

b) The treated water supply from this proposed plant to nearby tanks can be used for agricultural purpose by the villagers which results in the economic growth of them.

c) Better indirect employment opportunities due to proposed project. d) Due to the corporate social responsibility activities of M/s SCCL, the socio economic

condition of the people will be improved. e) People perceive that the project will help in the development of social infrastructures/such

as.

Education facilities

Banking facilities

Post offices and Communication facilities

Medical facilities

Recreation facilities

Business establishments

Plantation and parks

Community facilities

Industrial development and consequent economic development should lead to improvement of environment through better living and greater social awareness. On the other hand, the proposed project is likely to have several benefits like improvement in indirect employment generation and economic growth of the area, by way of improved infrastructure facilities and better socio-economic conditions.

5 Planning Brief

5.1 Planning Concept

As SCCL is already constructed 2x600 MW units and in operation, existing infrastructure facilities such as land, water transport arrangements, railway line, roads etc. will be used.

No new infrastructure facilities are required for expansion unit.

Total required land is under possession of SCCL, No R&R is involved.

Availability of adequate raw water will be met from Pranahita River.

Water will be pumped through the existing pipe line and pump house.

There is no forest land involved for the project.

Since existing facilities are being used, cost of the power would be less.

5.2 Population Projection

Around 450 people would be required to operate and maintain the 1X800 MW in addition to 1100 People required for 2x600 MW power plant under construction. During the construction stage about 2000 to 3000 people required for various works of construction. It is expected that a fair percentage of skilled and unskilled personnel would be available from the nearby areas for operation and maintenance. In addition to the operational, maintenance and construction personnel, there will be indirect employment creation in the area through service sectors, material supply, establishment of ancillary units, transport, etc.

Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

THE SINGARENI COLLIERIES COMPANY LIMITED

20

5.3 Land use planning (Breakup along with green belt etc.) Land use planning of proposed expansion of 2x600 MW to 2000 MW by expansion of another 1X800 MW is as follows:

5.4 Assessment of Infrastructure Demand (Physical & Social) Power is an essential requirement for all facets of our life and has been recognized as a basic human need. It is the critical infrastructure on which the socio-economic development of the country depends. India faces formidable challenges in meeting its energy needs and providing adequate energy of desired quality forms to various users in a sustainable manner and at reasonable cost. The gap between availability of power and the demand is not likely to be met in the foreseeable future either in southern region or in state of Telangana. To meet the deficit power in newly formed Telangana state, the Singareni Collieries Company Limited (SCCL) (Which is a Government Coal Mining company jointly owned by the Government of Telangana and Government of India) has proposed to install one unit of 800MW at their existing 2x600 MW STPP at Jaipur Mandal, Mancherial District. Accordingly, the proposal of Singareni Collieries Company Limited, for expansion of unit of 800 MW will further help in meeting the shortfall in generating capacity in the Telangana State.

5.5 Amenities/ Facilities The main approach roads to the plant have already been constructed for the operating units. The approach roads for the proposed expansion unit have to be constructed and the drainage system for the proposed unit shall be constructed separately. The route of the existing Nallah has to be diverted which is currently passing though the BTG area of the proposed unit. Necessary approval from competent authority has already been obtained for diversion of existing Nallah. Additional quarters shall be constructed in existing township area to accommodate the plant personnel of proposed unit.

6 Proposed Infrastructure The proposed infrastructure are main plant building, boiler, transformer bay, switchyard, chimney, coal handling system, water system, Induced draught cooling towers, miscellaneous building like control room, diesel generator building, water treatment plant etc

6.1. Industrial Area (Processing Area) The plant layout of the proposed thermal power plant is enclosed.

6.2 Residential Area Additional quarters shall be constructed in existing township area to accommodate the plant personnel of proposed unit.

S. No Particulars

Area in Ha

2x600MW (a)

1x600MW (b)

1X800MW (c)

Total 2000MW

(a+c)

1 Main Plant & Equipment 110.00 26.60

47.632

177.932 2 Coal Handling Plant 20.30

3 Raw Water Reservoir 47.92 Nil Nil 47.92

4 Ash Dyke 30.00 52.61 59.44 89.44

5 Greenbelt 72.18 26.30 20.24 92.42

Land for Main Plant 280.40 105.21 127.31 407.71

6 Land required for transportation of coal by rail system

15.245 Nil Nil 15.245

7 Land required for water pipeline 5.327 Nil Nil 5.327

Total land requirement 300.972 105.21 127.31 428.28

Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

THE SINGARENI COLLIERIES COMPANY LIMITED

21

6.3 Green Belt

Landscaping shall be done for the entire plant and township area. A green belt of shall be provided as stipulated by the MoEF&CC. Green belt envisaged for 2x600 MW is 72.18 Ha and proposed additional unit area for 1X800 MW is 20.24 Ha.

6.4 Social Infrastructure

The access roads connecting to the National Highway have already been built for existing units; however, internal roads within the proposed expansion unit area would have to be built.

For existing 2x600MW During construction phase of the project, the project proponent earmarked approximately Rs.22.10 Cr as one time capital cost for CSR activities. Further during the operation phase of the project, Rs 4.40 Cr per annum will be earmarked as recurring expenditure for CSR activities.

Rs.11.71 Crores was spent for infrastructural facilities like roads, drains, community

Halls in the surrounding villages against allocated 15.5 Crs. Balance 3.79 is allocated

for the year 2017-18 infrastructural developments towards CSR activities.

Rs.6.6 Crs Funds were allocated for Training programmes for the local Youth,

medical camps, Environment works, support to agriculture/Social forestry

For proposed additional 1x800MW During construction phase of the project, the project proponent earmarked approximately Rs.15.0 Crores as one time capital cost for CSR activities. Further during the operation phase of the project, CSR cost will be as per the relevant directives in this regard.

6.5 Connectivity The proposed project site is situated at a distance of around 500 meters from the National Highway, NH–63, which connects Nizamabad town in Telangana and Jagdalpur town in Chhattisgarh. It passes through the states of Telangana, Maharashtra and Chhattisgarh.

6.6 Drinking Water Management Drinking water required during the construction will be met from the existing facility of 2x600 MW units.

6.7 Sewerage System The Effluent Treatment System and Sewage Treatment Plants are proposed to treat all liquid effluent generated so as to meet the standards as per the MOEF/TSPCB standards. The Effluent treatment plant comprises of CMB, Clarifier, oil separator and settling ponds, R.O plant, solar evaporation pond etc. Domestic effluents from plant will be treated in the STP. The treated water will be utilized for cooling water make up, bottom ash sluicing, green belt development, dust suppression, dust extraction, floor washing etc.

6.8 Industrial Waste Management The sludge from the raw water pre-treatment plant shall be treated in a sludge handling plant to convert the sludge into solid form and disposed off for land fill. There shall be a central monitoring basin (CMB) to which waste water from treatment plant and cooling tower blow down shall be led. Effluents from boiler blow down and plant area drains (after separation of oil) shall flow, also to CMB where they shall be treated to comply with pH levels to meet pollution control norms.

The treated effluents shall be used for green belt development and plantation works. As such, any appreciable impact on the quality of surface water and ground water is not anticipated during the operation phase of the plant.

Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

THE SINGARENI COLLIERIES COMPANY LIMITED

22

6.9 Solid Waste Management During the process of power generation, about 3316.02 TPD of Fly ash and 1421.15 TPD will be generated in 2x600 MW Plant. In addition to these, 3950 TPD of fly ash and 987 TPD of

bottom ash will be generated in the present proposal of 1X800 MW TPP. Fly ash and bottom

ash would be collected in dry form and stored in the silos and hydro bins respectively. Fly ash will be utilized for manufacturing cement and bricks. There is a demand for fly ash from cement and brick industries. The entire fly ash generated from the proposed power plant will be utilized for manufacturing cement, bricks and other end users. In case of exigency, the fly ash will be stored in ash pond area provided in the plant premises. Bottom ash will be used for stowing or void filling in the SCCL mines in the area.

S. No Description

Existing

2x600 MW

(a)

ToR issued

1x600 MW

(b)

Proposed 1x800 MW

(c)

Total (after expansion)

2000 MW (a+c)

1 Fly Ash, TPD 3316.02 1854 3950 7266.02

2 Bottom Ash, TPD

1451.15 463 987 2438.15

6.10 Power Requirement & Supply

The Electricity required during construction will be met from existing source / nearest 33 KV sub-station.

7 Rehabilitation and Resettlement Plan No R & R involved in the project.

8 Project Schedule & Cost Estimates.

8.1. Likely date of start of construction and likely date of completion

Likely date of start is from the date of Environmental Clearance obtained. The total time period is estimated to be 50 months for the proposed 1x800 MW unit (Stage-2) from “zero date” up to date of commercial operation. Zero date is the date of letter of award for the project. IDC will be provided up to the date of commercial operation.

8.2. Estimated Project cost along with analysis in terms of economic viability of the project The estimated Capital Cost of proposed additional unit of 1x800MW, Capitalized Project Cost (including IDC) has been taken as Rs. 5879.62 Crores.

The project cost and analysis of proposed additional unit of 1x800MW are given in Table below.

Cost of Generation

S.No

Particulars Existing ToR issued Proposed amendment

to ToR

Total (after

expansion)

1 Plant Capacity, MW 2x600 1x600 1x800 2000 (2x600+1x800)

2 Auxiliary Energy Consumption, %

6.50 5.50 5.75 12.25

3 Station Heat rate (kcal /kg)

2425 2351 2250

4 Depreciation 5.28% for 5.28% for 5.28% for first -

Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

THE SINGARENI COLLIERIES COMPANY LIMITED

23

first 12 years and 2.04% for balance period of 13

years

first 12 years and 1.78% for balance

period of 13 years

12 years and 1.78% for

balance period of 13 years

5 O&M 2.07% escalated

@5.72% per annum

3.08% escalated @6.29%

per annum

3.08% escalated

@6.29% per annum

-

6 Loan Repayment Period, years

12 12 12 -

7 Interest on Loan, % 12 12 9.5 -

8 Loan repayment 48 equal quarterly

installments with 6

months moratorium

48 equal quarterly

installments with 6

months moratorium

48 equal quarterly

installments with 6 months moratorium

-

9 GCV of coal (Design), kcal/kg

4529 4529 3500 -

10 Present day coal price Rs.2266/- tonne on delivered basis with

6.62% annual

escalation

Rs.2650/- tonne on delivered basis with

6.29% annual

escalation

Rs.2850/- tonne (Mar-

2017) on delivered basis

with 6.29% annual

escalation

-

11 GCV of support Fuel (LDO), kcal/kg

10000 10000 10000 -

12 Support fuel price Rs.45,000/- tonne

LDO/HFO

Rs.60,762/- tonne

LDO/HFO

Rs.44,607/- tonne for LDO

and Rs.32394/-

tonne for HFO (May-2017)

13 Plant Load Factor, % 85 85 90

14 Return on Equity (RoE), %

15.5 15.5 16

15 Completion Schedule Unit:1 – 39 Months (COD) done on 25.09.2016 Unit:2 –43 Months (COD) done on 02.12.2016

50 Months 50 Months

16 Economic life of plant 25 years 25 years 25 years

Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

THE SINGARENI COLLIERIES COMPANY LIMITED

24

9 Analysis of proposal (Final Recommendations)

9.1 Project cost estimates and financial analysis

For additional 1x800MW

The objective of this section is to estimate and analyze the project cost, cost of generation and Levelised tariff for the proposed project in order to assess overall financial viability of the project.

Basis of cost estimates

The project cost estimate for the proposed power plant has been worked out on the following basis;

i. Unit size considered is 800 MW for financial analysis. Commissioning of the project is considered as 50 months from zero date.

ii. Various items of packages covered in the cost estimates are based on most of the packages are based on the awarded rates for various ongoing projects of NTPC and suitably updated to current price level.

iii. The cost of Balance of Plant (BoP) and other equipment has been estimated based on preliminary design and on the benchmark cost of the similar projects.

iv. The project is financed through domestic funding. Taxes and duties on supply of equipment, civil works, contract and erection and commissioning have been worked out as per the prevalent rates. The economic plant life has been taken as 25 years for depreciation calculation as per CERC norms.

As per the above report, the overall peak demand shortage during 2014-15 in the newly formed state Telangana is 4.2%.

Conclusion As seen from the above, the gap between availability of power and the demand is not

likely to be met in the foreseeable future either in Southern region or in Telangana. All out efforts are called for to add capacity considering the fuel availability and evacuation system. Accordingly, the proposal of Singareni Collieries Company Limited, for extension of unit of 800 MW will further help in meeting the shortfall in generating capacity in the Telangana State.

9.2 Financial and social benefits (With special emphasis on the benefit to the local people

including tribal population, if any, in the area)

Financial

For proposed additional 1x800MW During construction phase of the project, the project proponent shall incur approximately Rs. 15.0 Crores on CSR activities. Further during the operation phase of the project, the CSR will be as per the relevant directives in this regard.

Social benefits The project will improve the socio-economic status of the society in the region by generating direct and indirect employment opportunities The project will contribute additional revenue to the State & Central exchequers in the form of taxes and cess etc.

The anticipated impacts of the project are explained below: Human settlement is expected to increase after this project gets operational. In the long term, the project will have impact on the population growth due to migration of people from outside area. Indirect employment opportunities will also add to this. The literacy level of the project area is

Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

THE SINGARENI COLLIERIES COMPANY LIMITED

25

likely to increase as there will be influx of many educated people taking up jobs in the project, which is likely to result in establishment of better educational facilities. The project related construction activities will benefit the local populace in a number of ways such as supply of construction laborers – skilled, semi-skilled and un-skilled, tertiary sector employment and provision of goods and services for daily needs including transport. The proposed project will provide employment to the skilled as well as un-skilled persons. The local population will be given preference depending upon their suitability to the job requirement. Besides direct employment, indirect employment opportunities will also open up. The project will have positive impact in the region. Quality of life of the people will improve, which in-turn will improve the socio-economic conditions of the area.

LOCATION PLAN

Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

THE SINGARENI COLLIERIES COMPANY LIMITED

26

P

re-F

easib

ility R

epo

rt for exp

an

sion

of Sin

ga

reni T

PP

(Fro

m 1

20

0 M

W to

20

00

MW

by a

dd

ing

1x8

00

MW

)

TH

E S

ING

AR

EN

I CO

LLIE

RIE

S C

OM

PA

NY

LIM

ITE

D

1

Ge

ne

ral L

ayo

ut P

lan