bridge

105

Upload: vamshi-krish

Post on 27-Jan-2015

1.698 views

Category:

Documents


1 download

DESCRIPTION

 

TRANSCRIPT

Page 1: Bridge
Page 2: Bridge

PROJECT WORK ON PRAKASH NAGAR

BRIDGEBY

G.KIRANT.VAMSHI KRISHNAR.SANDEEPK.SRAVAN KUMARV.MADHU

Page 3: Bridge

A bridge is a structure providing passage over an

obstacle without closing the way beneath.

IN OTHER WORDSbridge is a structure for

carrying the road traffic or other moving loads over a depression or obstruction such as channel, road or

railway.

Page 4: Bridge

BRIDGE SPECIFICATIONS:The total bridge length from back to back

of backing walls is 332.74 m.Vent way: 20V of 16.00 M Foundations and substructure: Open

foundation in VRCC M20 grade concrete is proposed.

Abutments: Wall type abutments in VCC M15 with skin reinforcement 8mm dia

Piers: VRCC M20 & M25 circular piers of 2m dia.

Wing walls: Walls type wing walls are proposed in VCC M15 grade concrete with skin reinforcement of 8mm dia.

Hammer Head Bed Blocks over piers: VRCC M20 grade

Page 5: Bridge

Function of A BridgeA bridge has to carry a service

(which may be highway or railway traffic, a footpath, public utilities, etc.) over an obstacle (which may be another road or railway, a river, a valley, etc.) and to transfer the loads from the service to the foundations at ground level.

Page 6: Bridge

Components of bridge

SUPER STRUCTURE or DECKINGBEARINGSSUBSTRUCTUREPIERS AND ABUTMENTSWING WALLS AND RETURNSFOUNDATIONS

Page 7: Bridge
Page 8: Bridge
Page 9: Bridge
Page 10: Bridge

SUPERSTRUCTURE OR DECKING

This includes slab, girder, truss,

etc. This bears the load passing over it and transmits the forces

caused by the same to the substructures

Page 11: Bridge

BEARINGSThe BEARINGS transmit the load received from the decking on to the substructure and are provided for distribution of the load evenly over the substructure material which may not have sufficient bearing strength to bear the superstructure load directly

Page 12: Bridge

SUBSTRUCTURE

This comprises of Piers Abutments , Wing walls or return & their foundations.

Page 13: Bridge
Page 14: Bridge

Piers and Abutments:-These are vertical structures supporting deck/bearing provided for transmitting the load down to the bed/earth through foundation.

Page 15: Bridge
Page 16: Bridge

Wing walls and Returns: These are provided as

extension of the abutments to retain

the earth of approach bank

whichotherwise has a natural

angle of repose.

Page 17: Bridge

FOUNDATION

This is provided to transmit the load from the piers or abutments and wings or returns to and evenly distribute the load on to the strata

Page 18: Bridge

Open foundation (Raft or individual footings)Well foundations or pile foundations.

Here in this project the foundation is Open Foundation .

Page 19: Bridge

Materials for Construction

Page 20: Bridge

Classification of Bridges According to functions : aqueduct, viaduct, highway,

pedestrian etc. According to materials of construction : reinforced

concrete, prestressed concrete, steel, composite, timber etc.

According to form of superstructure : slab, beam, truss, arch, suspension, cable-stayed etc.

According to interspan relation : simple, continuous, cantilever.

According to the position of the bridge floor relative to the superstructure : deck, through, half-through etc.

According to method of construction : pin-connected, riveted, welded etc.

Page 21: Bridge

Classification of Bridges According to road level relative to highest

flood level : high-level, submersible etc. According to method of clearance for

navigation : movable-bascule, movable-swing, transporter

According to span : short, medium, long, right, skew, curved.

According to degree of redundancy : determinate, indeterminate

According to type of service and duration of use : permanent, temporary bridge, military

Page 22: Bridge

According to the flexibility of superstructure:FIXED SPAN BRIDGES .

MOVABLE SPAN BRIDGES.

Page 23: Bridge

A swing bridge is a movable bridge that has as its primary structural support a vertical locating pin and support ring, usually at or near to its centre of gravity, about which the turning span can then pivot horizontally

Swing bridge

Page 24: Bridge
Page 25: Bridge

A bascule bridge (sometimes referred to as a drawbridge) is a moveable bridge with a counterweight that continuously balances the span, or "leaf," throughout the entire upward swing in providing clearance for boat traffic.

Bascule bridge

Page 26: Bridge
Page 27: Bridge

A transporter bridge (also ferry bridge or aerial transfer bridge) is a type of movable bridge that carries a segment of roadway across a river.

Page 28: Bridge
Page 29: Bridge

Basic Types of BridgesGirder/Beam BridgeTruss BridgeRigid Frame BridgeArch BridgeCable Stayed BridgeSuspension Bridge

Page 30: Bridge

Girder/Beam Bridge• The most common and basic type

• Typical spans : 10m to 200m

Page 31: Bridge

Truss Bridge

• Truss is a simple skeletal structure.

• Typical span lengths are 40m to 500m.

Page 32: Bridge

Forces in a Truss Bridge

In design theory, the individual members of a simple truss are only subject to tension and compression and not bending forces. For most part, all the beams in a truss bridge are straight.

Page 33: Bridge

Arch BridgesArches used a curved

structure which provides a high resistance to bending forces.

Both ends are fixed in the horizontal direction (no horizontal movement allowed in the bearings).

Arches can only be used where ground is solid and stable.

Hingeless arch is very stiff and suffers less deflection.

Two-hinged arch uses hinged bearings which allow rotation and most commonly used for steel arches and very economical design.

Hinge-less Arch

Two hinged Arch

Page 34: Bridge

Arch BridgesThe three-hinged arch

adds an additional hinge at the top and suffers very little movement in either foundation, but experiences more deflection. Rarely used.

The tied arch allows construction even if the ground is not solid enough to deal with horizontal forces.

Three-hinged Arch

Tied Arch

Page 35: Bridge

Forces in an ArchArches are well

suited to the use of stone because they are subject to compression.

Many ancient and well-known examples of stone arches still stand to this today.

Page 36: Bridge

Cable Stayed

A typical cable-stayed bridge is a continuous deck with one or more towers erected above piers in the middle of the span.

Cables stretch down diagonally from the towers and support the deck. Typical spans 110m to 480m.

Page 37: Bridge

Cable Stay Towers

Cable stayed bridges may be classified by the number of spans, number and type of towers, deck type, number and arrangement of cables.

Page 38: Bridge

Cable Stay Arrangements

Page 39: Bridge

Cable Stayed Bridges

Page 40: Bridge

Suspension Bridge

A typical suspension bridge is a continuous deck with one or more towers erected above piers in the middle of span. The deck maybe of truss or box girder.

Cables pass over the saddle which allows free sliding.At both ends large anchors are placed to hold the

ends of the cables.

Page 41: Bridge

Forces in Suspension Bridge

Page 42: Bridge

BASIC TYPES OF BRIDGE DECKS

1. In-situ reinforced concrete deck(most common type)

2. Pre-cast concrete deck(minimize the use of local labor)

3. Steel grid deck

4. Orthotropic steel deck

5. Timber deck

Page 43: Bridge

In-situ reinforced concrete deck(most common type)

A cast-in-place concrete deck is a thin concrete slab, either using normal reinforcement or pre stressing steel

The thickness of these slabs is between 7 to 12 inches

Page 44: Bridge

A large cost of bridge maintenance is in

maintaining the riding surface.

Lack of deck crack control can lead to rebar

corrosion and increased life cycle cost, not to

mention a poor riding surface for the public.

Advantages

the major advantages is its relatively low

cost

ease of construction and extensive

industry useDis Advantages

Page 45: Bridge

Pre-cast concrete deck

Precast concrete is a construction product

produced by casting concrete in a reusable mold

 or "form" which is then cured in a controlled

environment, transported to the construction site

and lifted into place

Page 46: Bridge

Advantages

The production process for Precast Concrete is performed on ground level, which helps with safety throughout a project. . There is a greater control of the quality of materials and workmanship in a precast plant rather than on a construction site. Financially, the forms used in a precast plant may be reused hundreds to thousands of times before they have to be replaced, which allows cost of formwork per unit to be lower than for site-cast productionAnd also speed ups the construction

Page 47: Bridge

steel grid deck

1.Half filled grid decks

2.Fully filled grid

decks

3. Exodermic Decks

4.Open grid decks

Page 48: Bridge

When selecting a bridge deck, both initial costs and life-cycle costs should be consideredSteel grid bridge decks are time-tested, economical solutions for new or rehabilitated structuresMany grid reinforced concrete decks on structures with 50+ years of service:

South 10th St. Bridge (PADOT) 1932Jerome St. Bridge (PADOT) 1937-1980 sM. Harvey Taylor (PADOT) 1952-2001Walt Whitman (Del River Port Auth) 1956Mackinac (Mackinac Bridge Authority) 1957

WHY USE GRID DECKS?

Page 49: Bridge

Commonly used for lightweight deck on moveable bridges such as 17th St. Causeway Bridge in Ft. Lauderdale, FL(spanning floorbeams spaced @ 14.4 ft with no stringers)

Page 50: Bridge

OPEN GRID SYSTEMSFirst used in the 1920 s & is the oldest lightweightdeck systemIt is the lightest grid deck available, however spanlengths are limited

Page 51: Bridge

RECTANGULAR GRIDDIAGONAL GRID

Page 52: Bridge

ADVANTAGESLightweight

DISADANTAGESNoisyUnpleasant ride qualityPossible safety issuesAllows debris and salt laden water through

TYPICALLY ONLY USED FORREPLACEMENT IN KIND.

Page 53: Bridge

Full-depth grid was introduced by engineers in the 1930 s to speed up construction on large bridge projectsCan be precast or cast-in-place for very quick installation; high performance to cost ratio High durability and longevity are demonstrated by the great service history

FullyFILLED GRID SYSTEMS

Page 54: Bridge

FULL-DEPTH CONCRETE FILLED GRID

Page 55: Bridge

Partially filled grid – first used in the 1950 s to further reduce weight by eliminating concrete in bottom tension zoneCan be precast or cast-in-place offering rapid construction; verygood strength to weight ratioProven performance, this LW system offers similar span capabilities to Full-Depth

Half filled grid decks

Page 56: Bridge

PARTIAL-DEPTH CONCRETE FILLED GRID

Page 57: Bridge

DEVELOPED IN THE EARLY 1980 S EVOLVED FROM TRADITIONAL CONCRETE FILLED GRID DECKSAASHTO DEFINES AS UNFILLED STEEL GRID DECK COMPOSITE WITH A REINFORCED CONCRETE SLABTHROUGH OPTIMIZING THE MATERIAL PROPERTIES WHERE THEY BEST FIT, EXODERMIC DECKS HAVE THE BEST STRENGTH TO WEIGHT RATIO

EXODERMIC DECK

Page 58: Bridge

EXODERMIC DECK

Page 59: Bridge

Orthotropic steel deck

An orthotropic

bridge or orthotropic deck is one

whose deck typically comprises

a structural steel deck plate

stiffened either longitudinally or

transversely, or in both directions.

Page 60: Bridge

This allows the deck both to directly bear vehicular loads and to contribute to the bridge structure's overall load-bearing behavior. The same is also true of the concrete slab in a composite girder bridge, but the steel orthotropic deck is considerably lighter, and therefore allows longer span bridges to be more efficiently designed.The  Akashi-Kaikyō Bridge's orthotropic deck allowed the Japanese to build the longest span at about 6000 ft or 50% longer than the Golden Gate Bridge

Page 61: Bridge
Page 62: Bridge

Timber deck

Page 63: Bridge

EXPANSION JOINTS

Page 64: Bridge

INTRODUCTION• Cooling and heating of decks causes deck contraction and expansion, respectively• When contraction is restrained, cracking can occur when the tensile stress exceeds the tensile strength• When expansion is restrained, distortion or crushing can occur• Joints are often specified to accommodate deck movements without compromising the structural integrity of the bridge

Page 65: Bridge

• Bridge deck joints should protect the interior edges of concrete decks from vehicle loads, seal the joint openings, and accommodate movements resulting from temperature changes and creep and shrinkage of concrete• Joint failure is a internationwide problem in the • Failure is not necessarily caused by the joint material itself but also by careless design, improperinstallation, and inadequate maintenance

Page 66: Bridge

Problem: Incompressible Debris

Page 67: Bridge

Result: Failed Joint Seal

Page 68: Bridge

Consequences

• When joints fail, the integrity of the whole structure is affected!

Page 69: Bridge

Open Joints• Butt Joints• Sliding Plate Joints• Finger Joints

Closed Joints• Poured Seals• Asphalt Plug Joints• Compression Seals• Strip Seals• Reinforced Elastomeric Joints• Modular Elastomeric Joints

Page 70: Bridge

Open joints

Page 71: Bridge

Butt Joints

Accommodate less than 1- in. movements or minor rotations

Are sometimes installed with armor angles to protect

concrete slabs Are effective only under the assumption that

the passage of water and debris through the opening will not have adverse effects on the supporting substructures

Page 72: Bridge
Page 73: Bridge

Sliding Plate Joints• ACCOMMODATE MOVEMENTS BETWEEN 1 AND 3 IN.• ARE SIMILAR TO A BUTT JOINT EXCEPT THAT A PLATE IS ATTACHED TO ONE SIDE, EXTENDING ACROSS THE JOINT OPENING• PARTIALLY STOP DEBRIS FROM PASSING THROUGH OPENINGS• MAY BEND UNDER REPEATED TRAFFIC LOADS AND ARE SUSCEPTIBLE TO DEBRIS ACCUMULATION

Page 74: Bridge
Page 75: Bridge

Finger Joints• Accommodate movements greater than 3 in.• Are comprised of cantilevered fingers loosely interlocking each other over the opening• Are sometimes installed with drainage troughs to catch and channel away water anddebris• Can jam, bend, or break during service due tohorizontal and/or vertical misalignment duringconstruction

Page 76: Bridge
Page 77: Bridge

Closed joints

Page 78: Bridge

Troughs• Troughs should be designed with adequate

slope

• May require frequent flushing to prevent

debris

accumulation

Page 79: Bridge
Page 80: Bridge

• Accommodate movements up to 0.25 in.• Generally consist of viscous, adhesive, and pourable waterproof silicone installed with backer rods to prevent the sealant from flowing down the joint• Work best if sealant is poured when the ambienttemperature is at the middle of the historical temperature range

Poured Seals

Page 81: Bridge
Page 82: Bridge

•Accommodate movements less than 2 in.

• Are constructed by placing a modified elasto-plastic bituminous binder with mineral aggregate in a block-out centered over the joint, with a backer rod in place

• Can sustain damage when subjected to very rapidchanges in temperature

Asphalt Plug Joints

Page 83: Bridge
Page 84: Bridge

Accommodate movements less than 2½ in.– Are typically classifi ed as neoprene or cellular, both of which are installed using a lubricant that also serves as an adhesive agent– Should be sized in a working range of 40 to 85% of the uncompressed width to ensure that positive contact pressure isalways exerted against the face ofthe joint

COMPRESSION SEALS

Page 85: Bridge
Page 86: Bridge
Page 87: Bridge

Accommodate movements up to 4 in.• Consist of a flexible neoprene membrane attached to two opposing side rails• Can be susceptible to tearing, puncturing, or detachment under trafficking when debris accumulation rates are high• Normally exhibit long service life, very good anchorage, and high degree of watertightness

Strip Seals

Page 88: Bridge
Page 89: Bridge

– Accommodate movements between 2 and 6.5 in.– Are classified as sheet seals or plank seals– Are typically constructed using an epoxy bedding compound and cast-in-place studs– Are susceptible to leakage at locations of field splices and at interfaces between the seal and the underlying concrete

Reinforced Elastomeric Seals

Page 90: Bridge
Page 91: Bridge
Page 92: Bridge

• Accommodate movements between 4 and 24

in. and

up to 48 in. with special designs

• Consist of sealers, separator beams, and

support bars

• Are susceptible to fatigue damage and

leakage between compression seals and steel

supports

Modular Elastomeric Joints

Page 93: Bridge
Page 94: Bridge

Leveling of slabs

Levels for slab.Levels for carriage way.Levels for footpath or KERB leveling.

Levels for camber

Page 95: Bridge
Page 96: Bridge

CUBE TESTTO CALCULATE THE STRENGTH OF CONCRETE

Page 97: Bridge

STUDY OF SLAB DRAWINGS

Page 98: Bridge
Page 99: Bridge
Page 100: Bridge
Page 101: Bridge
Page 102: Bridge
Page 103: Bridge
Page 104: Bridge
Page 105: Bridge