Booster LV Electrical Distribution: Schedule and Quantities
Aims:Modernisation of Booster electrical infrastuctureTo install necessary infrastructure for transparent change-over of cablingMinimise impact on other work planned for the Booster (esp. cable removal campaign)Remove power cabling from false floor for easier installation + operation
Phasing:Phase 1 – New containment installation + Switchboards - YETS 2015 Phase 2 – Cable & Busbar installation - >YETS 2015 (During run)Phase 3 – Change over - EYETS 2016? TBA with usersPhase 4 – Cable removal – following change over, EYETS?
Quantities for removal:33 Cables to be removed (identified so far, however final number will be >> as no cablotheque exists for the majority)>1.6KM total cable length to be removed (identified so far)
Quantities for installation:BRF2 new rack zone – Additional ~100m containment to install, notional duration 2 weeksRefurbishment BCER zone – Additional ~400m containment to install, notional duration 3 weeksAdditional holes to be drilled for replacement of electrical supplies to distribution switchboards
Booster: LV Electrical Distribution Overview
Power Converters
RF
General Services
ESD
Machine Racks
General Services
CV
General Services
Bat. 245POPS-B
Final circuit distribution within Bldg. 361 to be consolidated
Booster LV Electrical Distribution: Before & After inside Bldg. 361
Racks Racks Racks
Structural Slab
Structural Slab
Existing service zone – Old cables + Power distribution
No Access
Before
Racks Racks Racks
Structural Slab
Structural Slab
Service zone dedicated for Control, DC cables and pipework
AfterElectrical containment zone
Racks supplies from above
Booster LV Electrical Distribution: Photos
Front
Typical configuration:• New Fluorescent Lighting• 2x300mm Cable trays• (EL+CF)• 1x100A Canalis
Structure supported on racks (allowing for individual rack removal) or ceiling, to be determined.
Similar systems used in Linac4 and CCC.
Zone for EL installation
False floor available for Control + DC cables