bond construction update facilities advisory committee

16
Bond Construction Bond Construction Update Update Facilities Advisory Facilities Advisory Committee Committee Long Beach Community College District April 6, 2011 EDUCATE ENGAGE EMPOWER 1

Upload: ting

Post on 11-Jan-2016

27 views

Category:

Documents


2 download

DESCRIPTION

Bond Construction Update Facilities Advisory Committee. Long Beach Community College District April 6, 2011. EDUCATE  ENGAGE  EMPOWER. Agenda. Completed Construction Projects LAC Parking Structure LAC Building O Complex PCC Walnut Ave. Arrival Court Current Construction Projects - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Bond Construction Update  Facilities Advisory Committee

Bond Construction Bond Construction UpdateUpdate

Facilities Advisory Facilities Advisory CommitteeCommittee

Bond Construction Bond Construction UpdateUpdate

Facilities Advisory Facilities Advisory CommitteeCommittee

Long Beach Community College District April 6, 2011

EDUCATE ENGAGE EMPOWER 1

Page 2: Bond Construction Update  Facilities Advisory Committee

Agenda

Completed Construction Projects LAC Parking Structure LAC Building O Complex PCC Walnut Ave. Arrival Court

Current Construction Projects LAC Building A – Student Services Retrofit LAC Infrastructure Improvements Project and District Wide –

Energy Efficiency Project LAC Building I (Bookstore) LAC South Walkway Extension LAC W Trailers Demo PCC MDAB (Multi-Disciplinary Academic Building) District Wide – Monument Signs

Upcoming Construction Projects PCC Building CC Retrofit

Q & A

2

Page 3: Bond Construction Update  Facilities Advisory Committee

Completed Construction ProjectsLAC Parking Structure – Measure E 2008LAC Parking Structure – Measure E 2008

3

Spaces for 893 Vehicles Solar generation system is commissioned and

operational Project is complete and being used for student parking

Page 4: Bond Construction Update  Facilities Advisory Committee

Completed Construction ProjectsLAC Building O Complex – Measure E 2008LAC Building O Complex – Measure E 2008

4

Two structures totaling 87,000 square feet Occupants for Building O2 are Foundation, ERD, LBNP and

ALCI IITS and BMT are moved in, Warehouse Facility moving Project is complete with some punch walk items left

Page 5: Bond Construction Update  Facilities Advisory Committee

Completed Construction Projects

5

UU/VV demo completed. Site converted to a parking lot April 4th, 2011.

PCC Walnut Ave. Arrival Court - Measure E 2008PCC Walnut Ave. Arrival Court - Measure E 2008

Page 6: Bond Construction Update  Facilities Advisory Committee

Current Construction ProjectsLAC Building A – Student Services RetrofitLAC Building A – Student Services Retrofit

Measure E 2008Measure E 2008

6

New home for A&R, Counseling, Health Services, Cashier, Transfer Center

Project currently in demolition and structure upgrade

Construction fence and temporary walkways complete

End of construction anticipated Summer 2012.

Page 7: Bond Construction Update  Facilities Advisory Committee

7

LAC Infrastructure Improvement Project and District LAC Infrastructure Improvement Project and District Wide Energy Efficiency Project Measure E Wide Energy Efficiency Project Measure E

20082008

Current Construction Projects

Total annual estimated savings of 1.5 mil. Kwh Project started Fall 2009; currently hydro seeding all

affected areas(All phases) Majority of existing building HVAC systems to be

upgraded and connected to the Central Plant Buildings C,D, G,H, & J are connected Buildings B and E will be scheduled by end of April

Exterior lighting and controls upgrades All parking lots north of Lew Davis are on new system

New Reclaimed Water tie-ins to irrigation connected New gas lines installed for Buildings B, C, D, E, G, H, J, M,

N, and P New domestic lines installed for Buildings B, C, D, E, F, G,

H, I Trailers, J, K,L, M, N, P Anticipated end of construction Winter 2011

Page 8: Bond Construction Update  Facilities Advisory Committee

Current Construction Projects

8

Adds additional 4,000 square feet to existing building Architecture to match LAC Mediterranean Theme G2K Construction working on demolition and utlitites End of Construction anticipated Fall 2011

LAC Building I - Measure E 2008LAC Building I - Measure E 2008

Page 9: Bond Construction Update  Facilities Advisory Committee

Current Construction ProjectsLAC South Walkway ExtensionLAC South Walkway Extension

Measure E 2008Measure E 2008

9

99% complete Palm trees to be replaced May 2011 Continues Master Plan pedestrian corridor

Page 10: Bond Construction Update  Facilities Advisory Committee

Current Construction Projects

10

Green Giant Construction has remove old W trailers Grading of lot to commence in this month Project will address storm run off issues with bio swales Site to be converted to a parking lot Estimated project completion Summer 2011.

LAC W Trailers Demo - Measure E 2008LAC W Trailers Demo - Measure E 2008

Page 11: Bond Construction Update  Facilities Advisory Committee

Current Construction ProjectsPCC MDAB PCC MDAB

(Multi-Disciplinary Academic Building)(Multi-Disciplinary Academic Building)Measure E 2002 and 2008Measure E 2002 and 2008

11

MDAB building remodel project Phase 1 of 2 currently under construction Project currently in demolition and structural reinforcement Phase 1 Project to be completed Summer 2012

Page 12: Bond Construction Update  Facilities Advisory Committee

Current Construction ProjectsDistrict Wide – Monument SignsDistrict Wide – Monument Signs

Measure E 2008Measure E 2008

12

District Wide Monument Signs. Locations:

LAC-Clark/Conant – completed January 8, 2011 PCC-20th/Walnut Ave. – Completed March 30, 2011

Installation of building designators for LAC Bldg. O1 and O2 completed

Estimated construction completion Spring 2011.

LAC Bldg. Designator LAC Monument SignPCC Monument Sign

Page 13: Bond Construction Update  Facilities Advisory Committee

Upcoming Construction ProjectsPCC Building CC Retrofit - Measure E 2008PCC Building CC Retrofit - Measure E 2008

13

Houses the Fitness Center, Gymnasium, Weight Room, and Faculty and Staff Offices

Swing space located on PCC Campus (Bldg. GG) Approved by DSA on 1/27/11. Currently in bid process To be completed concurrently with MDAB project phase 1 Anticipated end of construction 2012

Page 14: Bond Construction Update  Facilities Advisory Committee

l i b

e r

a l

a r

t s

Liberal Arts CampusSite Plan

Page 15: Bond Construction Update  Facilities Advisory Committee

p a

c i f

i c

c

o a

s t

Pacific Coast CampusSite Plan

Page 16: Bond Construction Update  Facilities Advisory Committee

QUESTIONS&

ANSWERS

EDUCATE ENGAGE EMPOWER 16