BOND CONSTRUCTION UPDATE January 15, 2015
PROJECTS:
1. ELEMENTARY SCHOOL #8 – BOND 2013
2. STEELE HIGH SCHOOL ADDITIONS & RENOVATIONS – BOND 2013
3. DOBIE MIDDLE SCHOOL ADDITIONS & RENOVATIONS – BOND 2013
ELEMENTARY #8 UPDATE SCUCISD BOND 2013 •$ 34,000,000 Bond Allocation
•900-1,200 Student Capacity
•153,000 Square Feet
•Architects - O’Neil Conrad Oppelt Architects Inc. & Pfluger & Associates
•General Contractor – Bartlett Cocke
•Construction Management – AG|CM, Inc.
January 15, 2015
ELEMENTARY #8 (GREEN VALLEY ROAD NEAR FM 1103 SITE)
• ES #8 CURRENT STATUS ▫ Brick installation ongoing throughout all exterior areas. ▫ Roofing continues in areas A through G ▫ Exterior & interior CMU continues to be installed at Area F & G ▫ MEP rough-ins continue on the interior ▫ HVAC Ductwork being installed ▫ Window installation ongoing at Areas A through F ▫ Concrete polishing ongoing throughout ▫ Interior Drywall continues throughout the building ▫ Interior painting has begun in Areas A through C
• FEBRUARY
▫ Brick Veneer to Continue ▫ Window and Storefront Installation to Continue ▫ Ceiling Grid Installation ▫ Irrigation and Landscape to begin
Perspective Views
ELEMENTARY #8
ELEMENTARY #8
01-16-15 View of Bus Pick-Up / Drop-Off
Location
ELEMENTARY #8
01-05-2015
Rooftop above Areas B & C
ELEMENTARY #8
01-05-2015
Kitchen Area with Ceiling
Installation Ongoing
ELEMENTARY #8
ES #8 SCHEDULE
• May 2015 ----------- Substantial Completion
• June 2015 --------- SCUC Begins Moving In To Building
• August 2015 ---------- Project Complete
STEELE HIGH SCHOOL UPDATE SCUCISD BOND 2013 •$ 25,000,000 Bond Allocation
•Three Story Academic Wing Addition – 84,922 ft2
•Field House Addition – 17,299 ft2
•Cafeteria Addition & Athletic Locker Room Renovation
•Architects - O’Neil Conrad Oppelt Architects Inc. & Pfluger & Associates
•General Contractor – Bartlett Cocke
•Construction Management – AG|CM, Inc.
January 15, 2015
Steele High School
• Steele CURRENT STATUS ▫ Forming up concrete pour #8 at Academic Wing ▫ Piers and partial slab poured at Cafeteria ▫ Structural Steel at the Field House 95% complete ▫ Hanging Duct and starting CMU at Field House ▫ Starting to hang sub floor piping at the Field House
• February
▫ Finish Slab Concrete pours at Academic Wing ▫ Start lower level interior wall framing and rough-ins at Academic Wing ▫ Frame up interior walls, CMU, and MEP rough-ins at the Field House ▫ Pour suspended sidewalk between boys locker room and Field House ▫ Mobilize Steel Erection at the Cafeteria
Steele High School Academic Wing
Academic Wing Rendering
01-16-2015
Academic Wing Second Floor being formed up for Pour
#8
Steele High School Academic Wing
01-14-2015
Concrete pour #7 at the Second Floor of the Academic Wing
Steele High School Academic Wing
Steele High School Field House
Field House Rendering
Steele High School Field House
01-16-2015
Fieldhouse Duct being hung and starting to
place CMU walls.
Steele High School Field House
01-13-2015
Fieldhouse Duct being hung and starting to
place CMU walls.
Steele High School Cafeteria Expansion
01-16-2015
Cafeteria Expansion Concrete Slab Pour
Steele High School
Schedule for Project:
• August 2014 ------ General Contractor Selected • September 2014 ------ General Contractor begins
Construction • Substantial Completion Dates ▫ Academic Building Addition (Nov 2015) ▫ New Field House Building (July 2015) ▫ Renovation of Existing ROTC into Welding Shop (Feb 2016) ▫ Cafeteria Addition (June 2015) Changed from Nov 2015 ▫ Main Entry Renovations (Aug 2015) ▫ Renovation of PE Locker Rooms (Aug 2015)
• Feb. 2016 ----- Project Completion
DOBIE JUNIOR HIGH SCHOOL UPDATE SCUCISD BOND 2013 •$ 10,000,000 Bond Allocation
•Proposed Site Improvements to Include New Drop-off Zone
•Proposed 8 New Classrooms / 1 New Science Lab
•Proposed New Kitchen Serving Lines
•Architect – Marmon Mok
•General Contractor – TBD
•Construction Management – AG|CM, Inc.
January 15, 2015
Dobie JH School Renovations & Additions
Dobie New Front Entry Rendering (View from Dietz Rd.)
Dobie JH School Renovations & Additions
Dobie New Front Entry Rendering (View From Borgfeld Rd.)
Dobie JH School Renovations & Additions
Schedule for Renovations & Additions
• February 2015 -------- General Contractor Selected
• March 2015 ----------- Construction Begins
• Substantial Completion Dates
▫ April 2015 ----------- Phase 1
▫ May 2016 ------------ Phase 2
▫ August 2016 --------- Phase 3
• August 2016 ----------- Project Completion