bond construction update · 01-05-2015 rooftop above areas b & c . elementary #8 01-05-2015...

22
BOND CONSTRUCTION UPDATE January 15, 2015 PROJECTS: 1. ELEMENTARY SCHOOL #8 BOND 2013 2. STEELE HIGH SCHOOL ADDITIONS & RENOVATIONS BOND 2013 3. DOBIE MIDDLE SCHOOL ADDITIONS & RENOVATIONS BOND 2013

Upload: others

Post on 23-Aug-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: BOND CONSTRUCTION UPDATE · 01-05-2015 Rooftop above Areas B & C . ELEMENTARY #8 01-05-2015 Kitchen Area with Ceiling Installation Ongoing . ELEMENTARY #8 ... Frame up interior walls,

BOND CONSTRUCTION UPDATE January 15, 2015

PROJECTS:

1. ELEMENTARY SCHOOL #8 – BOND 2013

2. STEELE HIGH SCHOOL ADDITIONS & RENOVATIONS – BOND 2013

3. DOBIE MIDDLE SCHOOL ADDITIONS & RENOVATIONS – BOND 2013

Page 2: BOND CONSTRUCTION UPDATE · 01-05-2015 Rooftop above Areas B & C . ELEMENTARY #8 01-05-2015 Kitchen Area with Ceiling Installation Ongoing . ELEMENTARY #8 ... Frame up interior walls,

ELEMENTARY #8 UPDATE SCUCISD BOND 2013 •$ 34,000,000 Bond Allocation

•900-1,200 Student Capacity

•153,000 Square Feet

•Architects - O’Neil Conrad Oppelt Architects Inc. & Pfluger & Associates

•General Contractor – Bartlett Cocke

•Construction Management – AG|CM, Inc.

January 15, 2015

Page 3: BOND CONSTRUCTION UPDATE · 01-05-2015 Rooftop above Areas B & C . ELEMENTARY #8 01-05-2015 Kitchen Area with Ceiling Installation Ongoing . ELEMENTARY #8 ... Frame up interior walls,

ELEMENTARY #8 (GREEN VALLEY ROAD NEAR FM 1103 SITE)

• ES #8 CURRENT STATUS ▫ Brick installation ongoing throughout all exterior areas. ▫ Roofing continues in areas A through G ▫ Exterior & interior CMU continues to be installed at Area F & G ▫ MEP rough-ins continue on the interior ▫ HVAC Ductwork being installed ▫ Window installation ongoing at Areas A through F ▫ Concrete polishing ongoing throughout ▫ Interior Drywall continues throughout the building ▫ Interior painting has begun in Areas A through C

• FEBRUARY

▫ Brick Veneer to Continue ▫ Window and Storefront Installation to Continue ▫ Ceiling Grid Installation ▫ Irrigation and Landscape to begin

Page 4: BOND CONSTRUCTION UPDATE · 01-05-2015 Rooftop above Areas B & C . ELEMENTARY #8 01-05-2015 Kitchen Area with Ceiling Installation Ongoing . ELEMENTARY #8 ... Frame up interior walls,

Perspective Views

ELEMENTARY #8

Page 5: BOND CONSTRUCTION UPDATE · 01-05-2015 Rooftop above Areas B & C . ELEMENTARY #8 01-05-2015 Kitchen Area with Ceiling Installation Ongoing . ELEMENTARY #8 ... Frame up interior walls,

ELEMENTARY #8

01-16-15 View of Bus Pick-Up / Drop-Off

Location

Page 6: BOND CONSTRUCTION UPDATE · 01-05-2015 Rooftop above Areas B & C . ELEMENTARY #8 01-05-2015 Kitchen Area with Ceiling Installation Ongoing . ELEMENTARY #8 ... Frame up interior walls,

ELEMENTARY #8

01-05-2015

Rooftop above Areas B & C

Page 7: BOND CONSTRUCTION UPDATE · 01-05-2015 Rooftop above Areas B & C . ELEMENTARY #8 01-05-2015 Kitchen Area with Ceiling Installation Ongoing . ELEMENTARY #8 ... Frame up interior walls,

ELEMENTARY #8

01-05-2015

Kitchen Area with Ceiling

Installation Ongoing

Page 8: BOND CONSTRUCTION UPDATE · 01-05-2015 Rooftop above Areas B & C . ELEMENTARY #8 01-05-2015 Kitchen Area with Ceiling Installation Ongoing . ELEMENTARY #8 ... Frame up interior walls,

ELEMENTARY #8

ES #8 SCHEDULE

• May 2015 ----------- Substantial Completion

• June 2015 --------- SCUC Begins Moving In To Building

• August 2015 ---------- Project Complete

Page 9: BOND CONSTRUCTION UPDATE · 01-05-2015 Rooftop above Areas B & C . ELEMENTARY #8 01-05-2015 Kitchen Area with Ceiling Installation Ongoing . ELEMENTARY #8 ... Frame up interior walls,

STEELE HIGH SCHOOL UPDATE SCUCISD BOND 2013 •$ 25,000,000 Bond Allocation

•Three Story Academic Wing Addition – 84,922 ft2

•Field House Addition – 17,299 ft2

•Cafeteria Addition & Athletic Locker Room Renovation

•Architects - O’Neil Conrad Oppelt Architects Inc. & Pfluger & Associates

•General Contractor – Bartlett Cocke

•Construction Management – AG|CM, Inc.

January 15, 2015

Page 10: BOND CONSTRUCTION UPDATE · 01-05-2015 Rooftop above Areas B & C . ELEMENTARY #8 01-05-2015 Kitchen Area with Ceiling Installation Ongoing . ELEMENTARY #8 ... Frame up interior walls,

Steele High School

• Steele CURRENT STATUS ▫ Forming up concrete pour #8 at Academic Wing ▫ Piers and partial slab poured at Cafeteria ▫ Structural Steel at the Field House 95% complete ▫ Hanging Duct and starting CMU at Field House ▫ Starting to hang sub floor piping at the Field House

• February

▫ Finish Slab Concrete pours at Academic Wing ▫ Start lower level interior wall framing and rough-ins at Academic Wing ▫ Frame up interior walls, CMU, and MEP rough-ins at the Field House ▫ Pour suspended sidewalk between boys locker room and Field House ▫ Mobilize Steel Erection at the Cafeteria

Page 11: BOND CONSTRUCTION UPDATE · 01-05-2015 Rooftop above Areas B & C . ELEMENTARY #8 01-05-2015 Kitchen Area with Ceiling Installation Ongoing . ELEMENTARY #8 ... Frame up interior walls,

Steele High School Academic Wing

Academic Wing Rendering

Page 12: BOND CONSTRUCTION UPDATE · 01-05-2015 Rooftop above Areas B & C . ELEMENTARY #8 01-05-2015 Kitchen Area with Ceiling Installation Ongoing . ELEMENTARY #8 ... Frame up interior walls,

01-16-2015

Academic Wing Second Floor being formed up for Pour

#8

Steele High School Academic Wing

Page 13: BOND CONSTRUCTION UPDATE · 01-05-2015 Rooftop above Areas B & C . ELEMENTARY #8 01-05-2015 Kitchen Area with Ceiling Installation Ongoing . ELEMENTARY #8 ... Frame up interior walls,

01-14-2015

Concrete pour #7 at the Second Floor of the Academic Wing

Steele High School Academic Wing

Page 14: BOND CONSTRUCTION UPDATE · 01-05-2015 Rooftop above Areas B & C . ELEMENTARY #8 01-05-2015 Kitchen Area with Ceiling Installation Ongoing . ELEMENTARY #8 ... Frame up interior walls,

Steele High School Field House

Field House Rendering

Page 15: BOND CONSTRUCTION UPDATE · 01-05-2015 Rooftop above Areas B & C . ELEMENTARY #8 01-05-2015 Kitchen Area with Ceiling Installation Ongoing . ELEMENTARY #8 ... Frame up interior walls,

Steele High School Field House

01-16-2015

Fieldhouse Duct being hung and starting to

place CMU walls.

Page 16: BOND CONSTRUCTION UPDATE · 01-05-2015 Rooftop above Areas B & C . ELEMENTARY #8 01-05-2015 Kitchen Area with Ceiling Installation Ongoing . ELEMENTARY #8 ... Frame up interior walls,

Steele High School Field House

01-13-2015

Fieldhouse Duct being hung and starting to

place CMU walls.

Page 17: BOND CONSTRUCTION UPDATE · 01-05-2015 Rooftop above Areas B & C . ELEMENTARY #8 01-05-2015 Kitchen Area with Ceiling Installation Ongoing . ELEMENTARY #8 ... Frame up interior walls,

Steele High School Cafeteria Expansion

01-16-2015

Cafeteria Expansion Concrete Slab Pour

Page 18: BOND CONSTRUCTION UPDATE · 01-05-2015 Rooftop above Areas B & C . ELEMENTARY #8 01-05-2015 Kitchen Area with Ceiling Installation Ongoing . ELEMENTARY #8 ... Frame up interior walls,

Steele High School

Schedule for Project:

• August 2014 ------ General Contractor Selected • September 2014 ------ General Contractor begins

Construction • Substantial Completion Dates ▫ Academic Building Addition (Nov 2015) ▫ New Field House Building (July 2015) ▫ Renovation of Existing ROTC into Welding Shop (Feb 2016) ▫ Cafeteria Addition (June 2015) Changed from Nov 2015 ▫ Main Entry Renovations (Aug 2015) ▫ Renovation of PE Locker Rooms (Aug 2015)

• Feb. 2016 ----- Project Completion

Page 19: BOND CONSTRUCTION UPDATE · 01-05-2015 Rooftop above Areas B & C . ELEMENTARY #8 01-05-2015 Kitchen Area with Ceiling Installation Ongoing . ELEMENTARY #8 ... Frame up interior walls,

DOBIE JUNIOR HIGH SCHOOL UPDATE SCUCISD BOND 2013 •$ 10,000,000 Bond Allocation

•Proposed Site Improvements to Include New Drop-off Zone

•Proposed 8 New Classrooms / 1 New Science Lab

•Proposed New Kitchen Serving Lines

•Architect – Marmon Mok

•General Contractor – TBD

•Construction Management – AG|CM, Inc.

January 15, 2015

Page 20: BOND CONSTRUCTION UPDATE · 01-05-2015 Rooftop above Areas B & C . ELEMENTARY #8 01-05-2015 Kitchen Area with Ceiling Installation Ongoing . ELEMENTARY #8 ... Frame up interior walls,

Dobie JH School Renovations & Additions

Dobie New Front Entry Rendering (View from Dietz Rd.)

Page 21: BOND CONSTRUCTION UPDATE · 01-05-2015 Rooftop above Areas B & C . ELEMENTARY #8 01-05-2015 Kitchen Area with Ceiling Installation Ongoing . ELEMENTARY #8 ... Frame up interior walls,

Dobie JH School Renovations & Additions

Dobie New Front Entry Rendering (View From Borgfeld Rd.)

Page 22: BOND CONSTRUCTION UPDATE · 01-05-2015 Rooftop above Areas B & C . ELEMENTARY #8 01-05-2015 Kitchen Area with Ceiling Installation Ongoing . ELEMENTARY #8 ... Frame up interior walls,

Dobie JH School Renovations & Additions

Schedule for Renovations & Additions

• February 2015 -------- General Contractor Selected

• March 2015 ----------- Construction Begins

• Substantial Completion Dates

▫ April 2015 ----------- Phase 1

▫ May 2016 ------------ Phase 2

▫ August 2016 --------- Phase 3

• August 2016 ----------- Project Completion