bof 2011: procurement of goods and works - jeff taylor
TRANSCRIPT
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
1/44
B O S 1
Procurement ofGoods and Works
Asian Development Bank Business Opportunities Fair 2011
Presented byJeff Taylor, Senior Procurement SpecialistAsian Development Bank
2 March 2011, Manila
http://www.adb.org/documents/events/2011/business-opportunities-fair/default.asp -
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
2/44
B O S 2
Business OpportunitiesFinding the Contract www.adb.og
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
3/44
B O S 3
Read UN Development Business (UNDB on
Check Opportunities www.adb.org
Get to know the ADB.
Study the Country
Business OpportunitiesFinding the Contract
PLEASE
http://c/Documents%20and%20Settings/EEA/Documents%20and%20Settings/brz/My%20Documents/ADB/BOS/BOS%20EUR%202005/Web%20Demo/ADB%20Home.htmhttp://c/Documents%20and%20Settings/EEA/Documents%20and%20Settings/brz/My%20Documents/ADB/BOS/BOS%20EUR%202005/Web%20Demo/ADB%20Home.htm -
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
4/44
B O S 4
Executing AgencyEnglish Language Newspaper of general distribu
in Borrowers country or well-known websiteTrade Journals (optional)
ADBADB Business Opportunities at (www.adb.org)UN Development Business
Business OpportunitiesAdvertising and Notices
http://www.adb.org/http://www.adb.org/ -
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
5/44
B O S 5
Business Opportunities
ADBs Procurement System
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
6/44
B O S 6
ADBBoard Policy
CommercialPractices
OtherMDBs
ADB
Experience
ADBCharter
Procurement SystemSources
ProcurementGuidelines
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
7/44
B O S 7
Responsibility for Procurement Actions
The Borrower (Executing Agency) is responsibfor all procurement activities
ADB will review the procurement activities toensure that the ADBs Procurement Guidelinesare followed
Procurement SystemResponsibilities
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
8/44
B O S 8
Procurement SystemEligibility
Eligibility by NationalityGoods must be produced in a member country
Supplier must be a national of a member coun
Other Eligibility FactorsNo conflicts of interestNot sanctionedState-owned enterprises
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
9/44
B O S 9
Economy and Efficiency
Fairness
Transparency
Procurement SystemBasics
Development of Domestic Industry.
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
10/44
B O S 1 0
Procurement SystemSource of Funds
Contracts not financed by ADBBorrowers procurement procedures apply
Must be suitable for the projectContracts financed by ADB entirely or par
ADB System must be followed
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
11/44
B O S 1 1
Business Opportunities
Anti-corruption
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
12/44
B O S 1 2
Procurement BasicsAnticorruption Policy - Definitions
Corrupt Practice
Fraudulent PracticeCollusive Practice
Coercive Practices
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
13/44
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
14/44
B O S 1 4
Business Opportunities
Procurement Methods
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
15/44
B O S 1 5
Procurement MethodsInternational Competitive BiddingLimited International BiddingNational Competitive BiddingShoppingDirect Contracting (Single Source)Force Account
Performance-based procurementProcurement under Loans to Financial IntermediariesProcurement under Private Sector LoansProcurement under Disaster and Emergency Assistance
Community Participation in Procurement.
Procurement MethodsOverview
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
16/44
B O S 1 6
Must be used for contracts valued at US$0.5 millor more for Goods, above US$1.0 million for wo
Provides for borrowers a wide range of choices inselection from among competing suppliers /contractors
Gives prospective bidders from eligible sourcecountries adequate, fair and equal opportunities
Procurement MethodsInternational Competitive Bidding (IC
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
17/44
B O S 1 7
AdvertisementPrequalificationReference to ADBLanguage
Bid SecuritySource of Procurement
Currency of Bid
Currency of Bid ComparisoCurrency of Payment
Domestic Preference SchemPublic Bid Opening
Clarification and AlterationAward of Contract
Rejection and Retendering
Performance Security
Essentials of ICB
Bid Preparation Period
Procurement MethodsInternational Competitive Bidding
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
18/44
B O S 1 8
Two StageTwo-Stage: Two-Envelope
Single-Stage: Two-Envelope
Single-Stage: One-Envelope
Bidding ProceduresOverview
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
19/44
B O S 1 9
Procurement Plan
List of goods to be procured Proposed grouping of goods into contracts Proposed number and scope of civil works contra
Prequalification
Invitation to Prequalify Prequalification Document Evaluation of Applications
Preparation ofBidding Documents
Invitation to Bid Bidding Documents
Bid Evaluation Evaluation Report Proposal of Award
Award of Contract
Contract as executed
ADB Review Review of Procurement Actions
EA
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
20/44
B O S 2 0
Award of contracts for values of $10.0mill. and abomust be approved by the ADB
Procurement CommitteeChairman :Principal Director, COSOMembers : Assistant General Counsel
Director, Sector DivisionSecretary : Principal Procurement Specialist
(Non-Voting)
ADB Review Procurement Committee
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
21/44
B O S 2 1
Matters for ConsiderationFor contracts estimated at $10.0 million or more
Prequalification EvaluationTechnical Evaluation (2-stage/2-envelope bidding)Bid Evaluation AwardProposal for Rebidding
Proposal for CancellationActions in conflict with the ADB requirementsProposal to vary previous PC decisionsAny matters designated by Management.
ADB Review Procurement Committee
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
22/44
B O S 2 2
Preparation of Bids
Bid Opening
Bid Evaluation
Award of Contract
Prequalification
Procurement Sequence
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
23/44
B O S 2 3
JV RequirementsAll partners must be eligibleJ.V. agreement must contain provision for joint anseveral liabilityOne of the partners must be authorized to be incharge
Joint Ventures
P i f Bid
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
24/44
B O S 2 4
Preparation of BidsImportant Factors
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
25/44
B O S 2 5
Be compliant
No conditionalities
Get official clarification
Preparation of BidsImportant Factors
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
26/44
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
27/44
B O S 2 7
Ensure bid is complete
Make final check of bidAmount, validity and text of Bid SecuritySignatures and power of attorneyJoint venture agreement enclosedReferences enclosedDiscounts in covering letter or appropraiate place asspecified in the bidding documentMarking of envelopes
Preparation of BidsImportant Factors
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
28/44
B O S 2 8
Be on time
During opening ensureAll relevant prices are read outAll discounts are read outPresence and amount of bid security is read outNo envelope remains unopened
All the above is recorded correctlyThe record is signed by all bidders present and by the buyer
Be Aware of Possible Extension
Preparation of BidsImportant Factors
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
29/44
B O S 2 9
Business Opportunities Seminar
How Your Bid is Evaluated
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
30/44
B O S 3 0
Bid EvaluationPurpose
Determine the lowest evaluated and substantially responsive bid
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
31/44
B
O S 3 1
Complete Basic Data Sheet
Attach Record of Bid Opening
Prepare Table of Bid PricesExamine Bids for Responsiveness
Identify Bids for Detailed Evaluation
Evaluate Bids in DetailAdjust Bid Prices
Apply Other Adjustments
Bid EvaluationTypical Sequence
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
32/44
B
O S 3 2
Bid EvaluationBasics
ConfidentialityAfter opening of bids no information to be exchanged with non-authorized persons on
Substance of bidPreliminary examination results and statusEvaluation results and statusRecommendation of award
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
33/44
B
O S 3 3
Bid EvaluationBasics
Clarification and Alteration of BidsOnly clarifications not changing the substance or the price of thebid may be requested or accepted by the Borrower
Arithmetical ErrorsNot a cause for bid rejectionDiscrepancy between Unit Price and Total Price
Unit Price will prevail
Discrepancy between Total Bid Amount and Sum of Total PriTotal Prices will prevail
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
34/44
B
O S 3 4
Bid EvaluationBasics
Compliance with Bid DocumentsBids will be rejected if they
Do not substantially conform to Specifications
Contain inadmissible reservations to bid documentsDo not substantially respond to requirements
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
35/44
B
O S 3 5
Bid EvaluationBasics
Extension of Bid ValidityExceptional occurrenceAll bidders given the optionBidders willing to extend bid validity
cannot modify substance of bidmust extend validity of bid security
Negotiation with BidderNo negotiation to obtain more suitable offer, except if
Only one BidderOnly conforming Bid price is disproportionately high
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
36/44
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
37/44
B
O S 3 7
Bid EvaluationBasics
Exchange Rates
Bid comparison uses single currency as specified in bid documen(usually local currency or US$)
Bids may be quoted in currency of bidders choice, usually homecurrency, purchasers currency, and internationally traded currency,
or mix of all three (maximum of three currencies)
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
38/44
B
O S 3 8
Bid EvaluationBasics
Other Factors Considered in EvaluationEfficiency and Reliability of EquipmentMethod of ConstructionTime for CompletionDelivery TimeAvailability of After-Sales-ServiceAvailability of Spare PartsOperating Cost
id l i
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
39/44
B
O S 3 9
PurposeTo provide margin of preference to domesticallymanufactured goods or domestic contractors for
ADB-financed projectsTo allow domestic firms to compete with foreign firmon more equal footing
ConditionsGranting of preference subject to conditionsApplies only to ICBNeeds to be applied for by BorrowerTo be specified in Loan Agreement if scheme is appl
Bid EvaluationDomestic Preference
Bid E l i
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
40/44
B O S 4 0
Responsive bids are to be classified into three
categories:Category I: Goods manufactured locally with m
than 30% domestic value added
Category II: Goods manufactured locally with lethan 30% domestic value addedCategory III: Imported goods
Bid EvaluationDomestic Preference
Supply Contracts
Bid E l i
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
41/44
B O S 4 1
Responsive bids are to be classified into two
categoriesCategory IBids offered by Domestic Contractors and Joint Venture
eligible for the PreferenceCategory IIBids offered by other Contractors
Civil Works
Bid EvaluationDomestic Preference
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
42/44
Di b
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
43/44
B O S 4 3
Direct Payment Procedure
Reimbursement Procedure
Commitment Procedure
Imprest Fund Procedure
DisbursementProcedures
Di b
-
8/7/2019 BOF 2011: Procurement of Goods and Works - Jeff Taylor
44/44
B O
1 - Application for LC
1
SuppliersBank
ExecutingAgency
BorrowersBank
2
2 - LC Opened3
3 - Application for CL
44 - CL Approval
5
DisbursementCommitment Procedure