boc agenda 6.19.19 - gresham-barlow bondagenda bond oversight committee district facilities office...
TRANSCRIPT
AGENDA
Bond Oversight Committee District Facilities Office
2020 SE Fleming Avenue Gresham, 97080
June 19, 2019 6:00 pm
COMMITTEE MEMBERS:
George Seaman, Chair
Jason Dugan, Vice-Chair
Brianna Bigham
Sharon Estes
Michael Harris
Karen Johnston
Norm Hancock
Rick Searls
John Vandermosten
Bess Wills
MEETING DATES:
September 18, 2019
December 18, 2019
March 18, 2020
June 10, 2020
1. Welcome and Introductions
2. Proposed Meeting Dates
3. Project Updates
4. Budget Update
5. Review Draft Annual Report
6. Questions and Comments
______________________________________________________
Gresham-BarlowSchoolDistrictBondProjectStatusReport
NORTHGRESHAMELEMENTARYSCHOOL
ProjectTitle:NorthGreshamElementarySchoolReplacement ProjectManager:EmilHameedReportingStatusDate:June2019 ProjectManagerPhone:503-539-2245ProjectDescription:NewElementarySchoolandsiteworkPackagetoreplacetheexistingNorthGreshamElementarySchoolonthesamesite.
StatusataGlanceStatusItem As
Planned Caution RequiresResolution
LEGEND:
Budget X Movingalongwell,nosignificantconcernsatthistime.
Schedule X Resolutionmayimpactcostorschedule.
Construction X Requiresattentionandresolution.
DesignandConstructionSchedule
DesignPhase ConstructionPhase ORIGINALESTIMATE
CURRENTBUDGET
COMMITTEDTODATE
CURRENTBUDGETVARIANCESTART FINISH START FINISH
12/2016 1/2018 5/2018 8/2019 $30,369,354 $28,869,354 $28,616,169 $253,185CriticalIssues
1. Demolitionofcurrentbuildingandassociatedsitework.Somelandscape/fieldworktooccurintheFall.
ScheduleUpdates1. Constructionbegan5/21/182. BuildingConstructionstartedon6/18/183. Interiorfinishesnearlycomplete4. Classroomfinishesnearlycomplete5. Teachercontentmovedintonewbuilding6. Classroomcleaninghasbegun7. Abatementanddemolitionofoldbuildinghasbegun8. Siteimprovementscontinue9. Buildingconstructionaheadofschedule,siteworkonschedule
BudgetUpdates
1. Trackingconstructionandprojectcostsclosely2. Nomajorunforeseenissuesatthistime
GeneralProjectUpdates
1. LivewebcamvideoaccessibleonBondwebsite
Gresham-BarlowSchoolDistrictBondProjectStatusReport
EASTGRESHAMELEMENTARYSCHOOL
ProjectTitle:EastGreshamElementarySchoolReplacement ProjectManager:EmilHameedReportingStatusDate:June2019 ProjectManagerPhone:503-539-2245ProjectDescription:NewElementarySchoolandSiteworkPackagetoreplacetheexistingEastGreshamElementarySchoolonthesamesite.
StatusataGlanceStatusItem As
Planned Caution RequiresResolution
LEGEND:
Budget X Movingalongwell,nosignificantconcernsatthistime.
Schedule X Resolutionmayimpactcostorschedule.
Construction X Requiresattentionandresolution.
DesignandConstructionSchedule
DesignPhase ConstructionPhase ORIGINALESTIMATE
CURRENTBUDGET
COMMITTEDTODATE
CURRENTBUDGETVARIANCESTART FINISH START FINISH
12/2016 1/2018 5/2018 8/2019 $30,441,915 $32,141,915 $31,883,222 $258,692CriticalIssues
1. Costbenefitanalysisperformedtocompareprojectdelayvs.scheduleacceleration.-Toocostlytoallowfordelay
2. Scheduleaccelerationcostestimateincludedincommittedtodate3. Exteriorchangeremovingconcreteveneerpanelsandaddingsteelframedwalls.Positiveimpacton
schedule4. Demolitionofcurrentbuildingandassociatedsitework.Somelandscape/field/playareaworktooccurin
theFall.
ScheduleUpdates1. Constructionbegan6/4/182. BuildingConstructionstartedon7/9/183. Interiorsheetrockandpaintingnearlycomplete4. Classroomcaseworkinstallationcontinues5. Ceilingandlightinstallationcontinues6. Abatementanddemolitionofoldbuildinghasbegun7. Buildingconstructiontobecompleteby8/21/19foradministrationand8/27/19forstaff8. SiteworkforbusandparentdropoffwillbereadyforschoolintheFall.Remainderofsiteworkwill
continueintotheFall.
BudgetUpdates1. Siteconstraints
a. Limitedspacebetweenexistingbuildingscreatedchallengesforconcretetiltpanels2. Plancheckprocessimpactedprojectschedule3. Schedule
a. Projectaccelerationtocompletebuildingandsiteforstaff,studentsandcommunitywillhavecostimplications
4.Continuetomonitorbudgetanduseofovertimecarefully
GeneralProjectUpdates1. LivewebcamvideoaccessibleonBondwebsite
Gresham-BarlowSchoolDistrictBondProjectStatusReport
SAMBARLOWHIGHSCHOOL
ProjectTitle:SamBarlowHighSchoolReconstruction/Modernization ProjectManager:JohnAbelReportingStatusDate:June2019 ProjectManagerPhone:503-705-4640ProjectDescription:SelectiveDemolition,NewStandardClassrooms,ScienceClassroomsandCTEClassrooms,RenovationstoExistingClassrooms,MediaCenter,Auditorium,BandandChoirClassrooms,NewBleachersandFieldsandRequiredSiteImprovements.StatusataGlanceStatusItem As
Planned Caution RequiresResolution
LEGEND:
Budget X Movingalongwell,nosignificantconcernsatthistime.
Schedule X Resolutionmayimpactcostorschedule.
Construction X Requiresattentionandresolution.
DesignandConstructionSchedule
DesignPhase ConstructionPhase ORIGINAL*ESTIMATE
CURRENT*BUDGET
COMMITTED*TODATE
CURRENTBUDGETVARIANCESTART FINISH START FINISH
12/2016 4/2018 4/2018 7/2020 $70,100,000 $76,505,069 72,987,114 $3,517,955 *IncludesDeferredMaintenanceCriticalIssues
1. Budgetrequiresresolution.$4,700,000tobeaddedfromprogramcontingencytocovercompleteclassroomrenovations,exteriorsoffitreplacementandexteriorpainting,HVACreplacementinauditorium,additionalasbestosremoval,track&fieldimprovements
2. SummerconstructionpushforAugustcompletionofthefollowing:a. NewAddition–20classrooms,newadministration,newbusloopandnewcommonsb. RemodelWork–21existingclassroomscompleterenovation,oldadministrationtospecial
educationandartroomsc. Auditorium–completefullremodelofauditoriumd. PerformingArts–beginabatement,demolitionandrenovationofband,choirandblackbox
ScheduleUpdates
1. NewAddition:a. Buildingexteriornearlycompleteb. Buildinginterior2ndfloorclassroomsfinishinstallation,1stfloorpaintandfinishesinstallationc. Buildingpowerfullyoperational,elevatorcompleteawaitingfinalinspection
2. ExistingBuilding:a. Replacementdomesticwaterlineinstallation,classroomconversionsandrenovations
3. StadiumArea:a. StadiumStructure,trackandfieldimprovements,newturffield,lights,goalpostsandvisitor
bleachercompleteb. Newrestrooms,concessionstandandscoreboardinstallationunderway
BudgetUpdates
1. SomeUnforeseenConditionsencountered–(thinkhomeremodel)asreferencedaboveundercriticalissues.$4,700,000programcontingency
GeneralProjectUpdates-LivewebcamvideoaccessibleonBondWebsite
Gresham-BarlowSchoolDistrictBondProjectStatusReport
GRESHAMHIGHSCHOOL
ProjectTitle:GreshamHighSchoolReconstruction/Modernization ProjectManager:JohnAbelReportingStatusDate:June2019 ProjectManagerPhone:503-705-4640ProjectDescription:SelectiveDemolition,NewStandardClassrooms,ScienceClassroomsandCTEClassrooms,NewAuditorium,NewBusDropOff,NewParkingandRequiredSiteImprovements.
StatusataGlanceStatusItem As
Planned Caution RequiresResolution
LEGEND:
Budget X Movingalongwell,nosignificantconcernsatthistime.
Schedule X Resolutionmayimpactcostorschedule.
Construction X Requiresattentionandresolution.
DesignandConstructionSchedule
DesignPhase ConstructionPhase ORIGINALESTIMATE
CURRENTBUDGET
COMMITTEDTODATE
CURRENTBUDGETVARIANCESTART FINISH START FINISH
12/2016 4/2018 4/2018 12/2020 $85,968,545 $98,168,545 $97,491,309 $677,236CriticalIssues
1. Budgetandscheduleprogressingasplanned2. Beginningphase2requiringnewsitesafety&logisticsplan
ScheduleUpdates
1. 3rdfloorclassroomcasework,ceiling,lights,finishes&triminstalled2. 2ndfloorclassroompainting,ceiling,lightsandfloorbaseinstallationcontinues3. 1stfloorclassroomceilinggridandwallfinishinstallation4. Auditoriumpainting,HVACroughin,catwalkinstallationandexteriorwaterproofing5. Autoshop,SceneShopandotherPerformingArtsareasHVACinstalled,wallframingandpaintcontinues6. KitchensupportareaMEProughin,ceilinggridinstallationandrestroomfloorinstallation7. Newpoolentryunderconstruction8. Phase2moveout,abatementanddemolitionbeginningsoon
BudgetUpdates1. PoolandMen’sLockerRoomSeismicupgradecostestimatesunderreview2. Concessionsbuildingdesignbeingfinalizedandpricingtofollow3. Nomajorunforeseenissuesatthistime.
GeneralProjectUpdates-LivewebcamvideoaccessibleonBondWebsite
Gresham-BarlowSchoolDistrictBondProjectStatusReport
DEEPCREEK/DAMASCUSK-8SCHOOL
ProjectTitle:DeepCreekMiddleSchoolAdditionandRenovation ProjectManager:MathieuJacobsReportingStatusDate:June2019 ProjectManagerPhone:503-575-5141ProjectDescription:AdditiontoexistingDeepCreekSchoolandRenovationstosystemsandfinishes.
StatusataGlanceStatusItem As
Planned Caution RequiresResolution
LEGEND:
Budget X Movingalongwell,nosignificantconcernsatthistime.
Schedule X Resolutionmayimpactcostorschedule.
Construction X Requiresattentionandresolution.
DesignandConstructionSchedule
DesignPhase ConstructionPhase ORIGINALESTIMATE
CURRENTBUDGET
COMMITTEDTODATE
ESTIMATEDBUDGETVARIANCESTART FINISH START FINISH
7/2017 3/2018 1/2019 8/2019 $4,045,923 $5,305,559 $3,714,436 $1,591,123CriticalIssues
1. MaintenanceprojectfundsaddedtocurrentbudgetScheduleUpdates
1. Phase1,newclassroomadditiondriedinand90%drywallcomplete2. Asbestosabatementandinteriorremodelunderway3. Overallprojectaheadofscheduleatthistime
BudgetUpdates1. Nomajorunforeseenbudgetissuesatthistime
GeneralUpdates
1. Noneatthistime
Gresham-BarlowSchoolDistrictBondProjectStatusReport
HALLELEMENTARYSCHOOL
ProjectTitle:HallElementarySchoolAdditionandRenovation ProjectManager:MathieuJacobsReportingStatusDate:June2019 ProjectManagerPhone:503-575-5141ProjectDescription:AdditiontoexistingHallElementarySchoolandRenovationstosystemsandfinishes.Newbuslooptoseparateparentandbustrafficatpickup/dropofftimes.
StatusataGlanceStatusItem As
Planned Caution RequiresResolution
LEGEND:
Budget X Movingalongwell,nosignificantconcernsatthistime.
Schedule X Resolutionmayimpactcostorschedule.
Construction X Requiresattentionandresolution.
DesignandConstructionSchedule
DesignPhase ConstructionPhase ORIGINALESTIMATE
CURRENTBUDGET
COMMITTEDTODATE
ESTIMATEDBUDGETVARIANCESTART FINISH START FINISH
7/2017 12/2018 3/2019 12/2019 $6,592,543 $9,186,983 $1,180,828 8,006,155CriticalIssues
1. Buildingpermithasnotbeenissued2. Firewallattieintoexistingbuildingdoesnotmeetcode.Solutionhasbeenidentifiedandwilladdcost.
Noadditionalfundsfortheprojectproposedatthistime3. Maintenanceprojectfundsaddedtocurrentbudget
ScheduleUpdates
1. Finalpermitresolutionmeeting6/18/20192. Newbusloopunderway3. Existingportablesdemolished4. Roofingunderway5. Asbestosabatementandinteriorremodelunderway6. Potentialaddedtimeduetopermitdelay
BudgetUpdate
1. Pricingexteriorfirewall–noadditionalfundsrequestedatthistime2. Nomajorunforeseenbudgetissuesatthistime
GeneralProjectUpdates
1. Noneatthistime
Gresham-BarlowSchoolDistrictBondProjectStatusReport
HOLLYDALEELEMENTARYSCHOOL
ProjectTitle:HollydaleElementarySchoolAdditionandRenovation ProjectManager:MathieuJacobsReportingStatusDate:June2019 ProjectManagerPhone:503-575-5141ProjectDescription:AdditiontoexistingHollydaleElementarySchoolandRenovationstosystemsandfinishes.
StatusataGlanceStatusItem As
Planned Caution RequiresResolution
LEGEND:
Budget X Movingalongwell,nosignificantconcernsatthistime.
Schedule X Resolutionmayimpactcostorschedule.
Construction X Requiresattentionandresolution.
DesignandConstructionSchedule
DesignPhase ConstructionPhase ORIGINALESTIMATE
CURRENTBUDGET
COMMITTEDTODATE
ESTIMATEDBUDGETVARIANCESTART FINISH START FINISH
7/2017 12/2018 3/2019 12/2019 $4,530,967 $7,451,296 $1,073,841 $6,377,455CriticalIssues
1. Firewallattieintoexistingbuildingdoesnotmeetcode.Solutionhasbeenidentifiedandwilladdcost.Noadditionalfundsfortheprojectproposedatthistime
2. Maintenanceprojectfundsaddedtocurrentbudget
ScheduleUpdates1. Permitissued2. Abatementbeginsinexistingbuildingthismonth3. Interiorremodelandrenovationunderway4. Roofingunderway5. Buildingadditionunderway
BudgetUpdates
1. Pricingexteriorfirewall–noadditionalfundsrequestedatthistime2. Nomajorunforeseenbudgetissuesatthistime
GeneralProjectUpdates1. Noneatthistime
Gresham-BarlowSchoolDistrictBondProjectStatusReport
PLAYGROUNDS/TRACKS/FIELDS/ASPHALTPROJECT
ProjectTitle:Playgrounds/Tracks/Fields/AsphaltProject ProjectManager:ToddJohnsonReportingStatusDate:June2019 ProjectManagerPhone:503-880-1616ProjectDescription:Renovationstoexistingplaygrounds,tracksandasphaltsurfacesinthedistricttoimproveequipmentandsurfaces.
StatusataGlanceStatusItem As
Planned Caution RequiresResolution
LEGEND:
Budget X Movingalongwell,nosignificantconcernsatthistime.
Schedule X Resolutionmayimpactcostorschedule.
Construction X Requiresattentionandresolution.
DesignandConstructionSchedule
DesignPhase ConstructionPhase ORIGINALESTIMATE
CURRENTBUDGET
COMMITTEDTODATE
ESTIMATEDBUDGETVARIANCESTART FINISH START FINISH
10/2017 4/2018 5/2018 8/2019 $3,957,791 $4,457,791 $4,052,099 $405,692CriticalIssues
1. Noneatthistime.SummaryStatusMilestones/deliverables/informationitemsforthisreportingperiod:
1. TracksatDexterMcCartyMiddleSchoolandGordonRussellMiddleSchoolwerecompleteduringSummer2017.However,duetodefects,bothtrackswillberesurfacedinSummer2019andreadyforstudentsinSeptemberatnocosttothedistrict.
2. FielddrainageimprovementsatClearCreekMiddleSchoolarecomplete3. PlaygroundinstallationatNorthGresham,EastGresham,HallandDeepCreekscheduledforSummer
20194. ParkinglotpavingatGordonRussellandDexterMcCartyscheduledforSummer2020.
Gresham-BarlowSchoolDistrictBondProjectStatusReport
DOORLOCKS/HARDWARE/SECURITYPROJECT
ProjectTitle:DoorLocks/Hardware/SecurityProject ProjectManager:MathieuJacobsReportingStatusDate:June2019 ProjectManagerPhone:503-575-5141ProjectDescription:Replaceinteriordoorhardwarewithhardwarethatallowsstafftolocktheirdoorsfrominsidetheirclassroomorofficespace.
StatusataGlanceStatusItem As
Planned Caution RequiresResolution
LEGEND:
Budget X Movingalongwell,nosignificantconcernsatthistime.
Schedule X Resolutionmayimpactcostorschedule.
Construction X Requiresattentionandresolution.
DesignandConstructionSchedule
DesignPhase ConstructionPhase ORIGINALESTIMATE
CURRENTBUDGET
COMMITTEDTODATE
ESTIMATEDBUDGETVARIANCESTART FINISH START FINISH
7/2017 3/2019 1/2018 12/2019 $1,273,620 $1,273,620 $1,065,413 $208,207CriticalIssues
1. Noneatthistime SummaryStatusMilestones/deliverables/informationitemsforthisreportingperiod:
1. InstallationcompleteatallschoolsexceptremainingclassroomsatGreshamHighSchoolandSamBarlowHighSchool.
Gresham-BarlowSchoolDistrictBondProjectStatusReport
DISTRICTWIDEFURNITUREPROJECT
ProjectTitle:DistrictwideFurnitureProject ProjectManager:CornerstoneReportingStatusDate:June2019 ProjectManagerPhone:ProjectDescription:Replacementofclassroomstaffandstudentfurniturethroughoutthedistrict.
StatusataGlanceStatusItem As
Planned Caution RequiresResolution
LEGEND:
Budget X Movingalongwell,nosignificantconcernsatthistime.
Schedule X Resolutionmayimpactcostorschedule.
Construction X Requiresattentionandresolution.
DesignandConstructionSchedule
DesignPhase ConstructionPhase ORIGINALESTIMATE
CURRENTBUDGET
COMMITTEDTODATE
CURRENTBUDGETVARIANCESTART FINISH START FINISH
10/2017 3/2019 5/2018 8/2020 $5,569,000 $5,569,000 $5,569,000 CriticalIssues
1. Remainingclassroomfurnitureordercompleteanddelivered2. “Other”spacesneedsandcostcurrentlyidentifiedfor“big4”projects3. Additional$400,000allocatedfromprogramcontingency
SummaryStatusMilestones/deliverables/informationitemsforthisreportingperiod:
1. Allclassroomfurnituredelivered2. Additionalareasforfurnitureidentifiedandordered
Gresham-BarlowSchoolDistrictBondProjectStatusReport
WestOrientMiddleSchool–HVACProject
ProjectTitle:WestOrientMiddleSchoolHVACProject ProjectManager:DistrictDirectReportingStatusDate:June2019 ProjectManagerPhone:503-261-4567ProjectDescription:Improveindoorairqualityin10classroomsatWestOrientMiddleSchool.
StatusataGlanceStatusItem OnTrack Caution OffTrack LEGEND:
Budget X Movingalongwell,nosignificantconcernsatthistime..
Schedule X Withoutresolution,mayimpactcostorschedule.
Construction X Requiresattentionandresolution.
DesignandConstructionSchedule
DesignPhase ConstructionPhase ORIGINALESTIMATE
APPROVEDBUDGET COSTTODATE
ESTIMATEDBUDGETVARIANCE
START FINISH START FINISH
02/2017 05/2017 06/2017 10/2017 $294,500 $294,500 $242,690 CriticalIssuesNone.Workinsidetheclassroomsiscomplete.Someelectrical/controlswork(outsidetheclassroom)isnecessaryforfinalcompletion.SummaryStatusProjectworkinsidetheclassroomswascompletepriortostaffreturningtowork.Closeoutwilloccuroncecontrolsworkiscomplete.
Gresham Barlow School District 6/19/19 2016 Capital Improvements Projects Program Contingency Summary 1.1 Program Contingency $ 6,381,992 Additional bond premium 3,865,130
Interest earned 3/1/19 - 5/31/19 (contingency add) 1,159,139 1.2 Amounts Distributed from Program Contingency: 1.2a District Costs $ 500,000 (bond issuance, management)
1.2b Districtwide Furniture $ 400,000 (added cost due to standards) 1.2c Kelly Creek Elementary ($ 275,000) (project closeout)
1.2d Sam Barlow High School Project $ 4,700,000 (complete classroom renovations, paint entire
building exterior, replace exterior soffits, HVAC duct replacement-auditorium, track & field improvements, restroom renovations)
1.3 Current Program Contingency $ 6,081,261
Gresham Barlow School District2016 Capital Improvement ProjectsBond Budget Summary6/13/19
SCHOOL ORIGINAL ESTIMATE
PROGRAM CONTINGENCY/MISC
TRANSFERS UPDATED ESTIMATE
1.1 District Wide Costs -$ 5,000,000$ 5,000,000$ 1.2 District Wide FFE -$ 400,000$ 5,969,000$ 1.3 District Wide Radios 300,000$ -$ 300,000$ 1.4 District Wide Technology -$ -$ 5,610,292$ 1.5 Door Locks/Security -$ -$ 1,273,620$ 1.6 Tracks/Fields/Playgrounds/Asphalt -$ 500,000$ 4,457,791$ 1.7 East Gresham ES 28,970,000$ 3,300,000$ 32,141,915$ 1.8 East Orient ES 3,147,000$ -$ 1,197,036$ 1.9 East Orient ES Maintenance Projects -$ -$ 1,083,032$ 1.10 Hall ES 8,014,000$ 2,100,000$ 8,692,543$ 1.11 Hall ES Maintenance Projects -$ -$ 494,440$ 1.12 Highland ES 3,432,000$ -$ 1,645,401$ 1.13 Highland ES Roofing Project -$ -$ -$ 1.14 Highland ES Maintenance Projects -$ -$ 838,274$ 1.15 Hogan Cedars ES 1,672,000$ -$ 803,471$ 1.16 Hogan Cedars ES Maintenance Projects -$ -$ 128,558$ 1.17 Hollydale ES 6,514,000$ 2,000,000$ 6,530,967$ 1.18 Hollydale ES Maintenance Projects -$ -$ 920,329$ 1.19 Kelly Creek ES 4,334,000$ 113,152$ 3,322,643$ 1.20 Kelly Creek ES Maintenance Projects -$ (388,152)$ -$ 1.21 North Gresham ES 28,970,000$ 100,000$ 28,869,354$ 1.22 Powell Valley ES 3,747,000$ 944,414$ 3,556,657$ 1.23 Powell Valley ES Maintenance Projects -$ (419,414)$ 100,000$ 1.24 West Gresham ES 562,000$ -$ 137,108$ 1.25 Deep Creek K-8 6,340,199$ 115,000$ 4,160,923$ 1.26 Deep Creek K-8 2017 Roofing Project -$ -$ 123,500$ 1.27 Deep Creek K-8 2017 Maintenance Projects -$ -$ 1,021,136$ 1.28 Clear Creek MS 11,464,000$ -$ 8,177,154$ 1.29 Clear Creek Middle School Maint. Projects -$ -$ 1,592,500$ 1.30 Dexter McCarty MS 10,676,000$ -$ 9,354,466$ 1.31 Gordon Russell MS 13,334,000$ -$ 11,841,670$ 1.32 West Orient MS 3,232,000$ -$ 1,526,646$ 1.33 West Orient MS - 2017 HVAC Project -$ -$ 294,500$ 1.34 West Orient Middle School Maintenance -$ -$ 903,005$ 1.35 Gresham HS 93,244,000$ 7,500,000$ 98,168,545$ 1.36 Gresham HS Def. Maint. -$ -$ 1,461,000$ 1.37 Sam Barlow HS 70,100,000$ 12,600,000$ 75,793,875$ 1.38 Sam Barlow HS Def. Maint. -$ -$ 5,411,194$ 1.39 Springwater Trail HS 1,099,000$ -$ 913,655$
1.40 BOND SUBTOTAL * 299,151,199$ 33,865,000$ 333,816,199$
1.41 GRANTS & REIMBURSABLES 800,000$ -$ Included aboveINTEREST EARNINGS 6,270,777$ (6,270,777)$
1.42 PROGRAM CONTINGENCY 33,675,484$ (27,594,223)$ 6,081,261$
1.43 BOND TOTALS 339,897,460$ -$ 339,897,460$
NOTES:1.44 FFE costs have been removed from all project budgets to create stand alone budget1.45 Technology Costs of $5.569M have been deducted from all projects except GHS and SBHS Deferred Maintenance1.46 Original Program Contingency Amount is $29,810,3541.47 * Bond Subtotal includes Oregon School Capital Improvement Matching Grant of $8,000,000
Gresham-Barlow School District - 2016 Capital Improvement Project Bond Budget/Committed Summary
4/30/2019
Total BalanceToDate Encumbrance Remainig
2016BondDistrictWideCosts 4,500,000$ 4,202,707 604,638 -307,345DistrictWideFurniture/Fixtures/Equip 5,569,000$ 4,682,259 900,742 -14,001DistrictWideRadios 300,000$ 300,519 0 -519DistrictWideTechnology 5,610,292$ 2,444,351 1,168,034 1,997,907Security 1,273,620$ 857,127 208,286 208,207Playground/Track/Field 4,457,791$ 2,780,965 1,271,134 405,691EastGreshamE.S. 32,141,915$ 17,460,465 14,422,757 258,692EastOrientE.S. 1,197,036$ 3,585 140,882 1,052,569EastOrientE.S.-MaintenanceProjects 1,083,032$ 1,760 0 1,081,272HallE.S. 3,692,543$ 603,552 500,707 2,588,284HallE.S.-MaintenanceProjects 494,440$ 0 76,569 417,871HallE.S.-OSCIM 5,000,000$ 0 0 5,000,000HighlandE.S. 1,645,401$ 311,886 170,735 1,162,780HighlandE.S.-RoofingProject -$ 0 0 0HighlandE.S.-MaintenanceProjects 838,274$ 0 25,489 812,785HogansCedarsE.S. 803,471$ 3,450 91,859 708,162HogansCedarsE.S.-MaintenanceProjects 128,558$ 0 0 128,558HollydaleE.S. 3,530,967$ 487,035 504,222 2,539,710HollydaleE.S.-MaintenanceProjects 920,329$ 2,885 79,699 837,745HollydaleE.S.-OSCIM 3,000,000$ 0 0 3,000,000KellyCreekE.S. 3,597,643$ 3,122,477 4,257 470,909KellyCreekE.S.-MaintenanceProjects -$ 102,380 0 -102,380NorthGreshamE.S. 28,869,354$ 18,225,409 10,390,760 253,185PowellValleyE.S. 3,556,657$ 3,427,399 129,029 229PowellValleyE.S.-MaintenanceProjects 100,000$ 130,906 21,338 -52,245WestGreshamE.S. 137,108$ 21,727 10,655 104,726DeepCreekElementary 4,160,923$ 1,088,180 2,618,707 454,036DeepCreekElementary-RoofingProject 123,500$ 7,549 0 115,951DeepCreekElementary-MaintenanceProjects 1,021,136$ 0 0 1,021,136DeepCreekK-8 -$ 3,097 0 -3,097ClearCreekM.S. 8,177,154$ 16,458 40,390 8,120,306ClearCreekM.S.-MaintenanceProjects 1,592,500$ 293,790 0 1,298,710DexterMcCartyM.S. 9,354,466$ 98,965 36,920 9,218,581GordonRussellM.S. 11,841,670$ 12,443 472,891 11,356,337WestOrientM.S. 1,526,646$ 176,869 165,889 1,183,888WestOrientM.S.-HVACProject 294,500$ 227,367 0 67,133WestOrientM.S.-MaintenanceProjects 903,005$ 129,301 16,892 756,812GreshamH.S 98,168,545$ 41,302,590 56,188,719 677,236GreshamH.S-MaintenanceProjects 1,461,000$ 419,714 621,974 419,312SamBarlowH.S. 71,093,875$ 35,466,176 34,121,058 1,506,641SamBarlowH.S.-MaintenanceProjects 5,411,194$ 1,547,582 1,852,298 2,011,314SpringwaterTrailH.S. 913,654$ 3,752 26,347 883,555BondPremium 6,381,992$ 0 0 6,381,992
TOTAL 334,873,191$ 139,966,680 126,883,876 68,022,636
PROJECT Estimate