General Contractors Association General Membership MeetingOctober 17, 2017
Ernest Y. W. Lau, P.E., Manager and Chief Engineer
Board of Water SupplyCity and County of Honolulu
94 active potable water sources
90 booster pump stations
171 reservoirs Nearly 2,100 miles of
pipeline Average Daily Demand
= 145 million gallons
Oahu’s Water System
FY18 CIP• Supports the BWS mission of Water For Life:
Safe, dependable and affordable water now and into the future
• Aligned with the BWS Strategic Plan 2018-2022, Divisions’ Goals & Objectives and the Six-Year Capital Improvement Program
Project Category HighlightsResearch and Development ($5.5 million)
• Beretania Site Master Plan• Construction Management for Various BWS Construction Projects• Project Management for Various BWS Projects• Nuuanu Hydro-Electric and Managed Aquifer Recovery Study and
Environmental Assessment
Project Category HighlightsRenewal and Replacement ($85.4 million)
• Punanani Wells System Improvements• Pearl City Wells II System Improvements• Moanalua Wells: Replacement of Pump No. 1• Pump Renewal and Replacement
Renewal and Replacement (continued)• Water Meter Transponder Replacement – Phase I• Facility Repair and Renovation• Beretania Engineering Building Window Replacement• Security Enhancements for BWS Corporation Yards• Waimalu Wells I Site Drainage Improvements
Project Category Highlights
Project Category HighlightsRenewal and Replacement
(continued)• Water Main Replacement
• Pipeline tunnel rehabilitation –Moanalua and Quarry Tunnels
• Main replacement construction in Moiliili, Manoa, and Kaneohe
• Main replacement design in Waikiki, Sand Island, Nuuanu, Moanalua, Foster Village, Pearl City, Kaneohe, Kapolei, and Waianae
Project Category HighlightsCapacity Expansion ($21.8 million)
• Ewa Shaft Tunnel Improvements• Kahuku Wells Unit No. 3• Pacific Heights Booster No. 1
Project Category HighlightsCapacity Expansion (continued)
• Water main upsizing• Wahiawa Water System
Improvements, Part IA• Wahiawa Water System
Improvements, Part III
Improvements to BWS Management of Construction Activities
GCA-BWS Committee Continued collaboration Improvements to
specifications Improvements in
procurement methods Quality management