blog cost and schedule risk analysis

4

Click here to load reader

Upload: asaman-patnaik

Post on 22-Jan-2018

72 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Blog Cost and Schedule Risk Analysis

Schedule Risk Analysis

Asaman Patnaik

Project schedules are plans for future activities based on estimates of time and cost. There is

always a factor of uncertainty in predicting these estimates. Estimates about activity time and

cost are predictions for the future and depend on human beings who often tend to be overly

optimistic (most of the projects worldwide experience time overrun of more than 50%) or, on the

contrary, may add some reserve safety to protect themselves against unexpected events.

Thus, knowledge about the potential impact of these estimation errors on the project objective is

a key add-on to the construction of a project’s baseline schedule. Schedule Risk Analysis is a

simple but effective technique that connects the time and cost risk uncertainty of individual

activities to the base line schedule by replacing the deterministic duration for each task by a

distribution representing the range of likely durations.

Steps for Schedule Risk Analysis:

1. Baseline schedule: Construct an activity timetable

2. Define uncertainty: Define activity time and cost probability distributions

3. Run Monte-Carlo simulations: Run multiple project progress simulations

4. Interpret the simulation results: Interpret the sensitivity measures

1. Baseline schedule

The construction of a project baseline schedule involves the definition of start and finish times

for each project activity, using earliest and latest start calculations.

The project baseline schedule serves as a point of reference. In case everything goes according

to plan, then the project can be completed as per this base line schedule which is very unlikely.

2. Define risk/uncertainty

Time and cost estimates are often subject to a margin for error. It is more accurate to estimate a

range of duration and cost estimates for project activities.

3. Monte-Carlo simulations

Monte-Carlo simulation is a simple technique to quickly generate multiple runs simulating real

project progress. Each simulation run generates duration for each project activity.

4. Sensitivity results

Page 2: Blog Cost and Schedule Risk Analysis

The output of a schedule risk analysis is a set of measures that define the degree of activity

criticality and sensitivity. Each measure gives the project manager an indication of how sensitive

the activity is towards the final project duration or total cost

A case study of cost and schedule risk analysis carried out for an Industrial Waste Water

Treatment Plant Project at Saudi Arabia is outlined in the subsequent paragraphs.

ABOUT THE PROJECT

Make up water for the client’s existing plant at Saudi Arabia is met by purchasing from a utility

company. The effluent generated in the plant is also sent for treatment at a common effluent

plant for which the client pays the treatment cost.

The client proposes to set up an Industrial Waste Water Treatment Plant to treat about 6000

cum/ day of waste water, to generate around 3600 cum/day of treated water that can replace

part of makeup water being used in the plant. The IWWTP shall generate about 2200 cum/day

of reject that still needs to be sent to CETP.

Thus, by setting up the project, client will reduce the cost towards purchase of makeup water of

3600 cum/day and also reduce the cost of treatment of effluent from 6000 cum/day to 2200

cum/day.

TCE was asked by the client to carry out the cost risk analysis and schedule risk analysis for the

project.

A. Cost Risk Analysis

Cost Risk Analysis carried out consisted of the following:

A1 Impact: Impact of variation in cost and sales revenue on the financial indices such as

Profit before Tax (PBT) and Contribution was calculated. This was estimated by carrying out the

financial evaluation of the project, followed by a sensitivity analysis for variation of 5 to 20% in

(a) variable costs (b) sales revenue and combination of both (a) and (b).

For each of three scenarios the variation of PBT for base case, 5%, 10%, 15% and 20% were

plotted.

Further, considering stable operation in 3rd year, the trend of PBT and contribution was analyzed

for the above 5 cases to indentify the sensitivity.

For decrease in sales revenue, two options were analyzed. (1) Decrease in makeup water price

(2) Decrease in productivity.

A2 Likelihood: The likelihood of variation in cost, sales volume was identified.

Page 3: Blog Cost and Schedule Risk Analysis

Key items of variable cost are treatment cost (45%), chemicals (22%) and electricity (13%). The

price trends for these were analyzed, and also the future trend as per Dow’s Chemical Index

was analyzed, to predict likelihood of increase in variable cost.

The trends of makeup water cost over the last 10 years were analyzed, to predict the likelihood

of decrease in sales price.

A3 Conclusion

Based on the above, the risk on financial parameters of the project was analyzed and mitigation

plan suggested.

B. Schedule Risk Analysis

The schedule risk analysis was carried out to find the impact and likelihood of project

delay.

B1 Impact

The impact on project cost, revenue and profit for 10 years period were estimated for base case

(on schedule), delay of 3 month, 6 months, 9 months and one year.

B2 Likelihood

The likelihood of project delay was estimated using Monte Carlo Simulation as follows:

1. The probabilistic duration of each activity the project was analyzed and mutually agreed

with client on three scenarios:

(a) Likely (Probable)

(b) Best Case (Minimum)

(c) Worst Case (Maximum)

2. The overall project duration was found out for the above three scenarios.

3. Based on the minimum and maximum duration, a Monte Carlo Simulation was carried

out by generating 1000 random numbers. The simulation was done 500 times. Based on

the same, the probability of project completion with 80% and 90% confidence level were

found out.

Page 4: Blog Cost and Schedule Risk Analysis

B3 Causes of Project Delay and Mitigation Plan

The probable causes of project delay and mitigation plan were identified and tabulated.

0.00%

2.00%

4.00%

6.00%

8.00%

10.00%

12.00%

14.00%

16.00%

35 36 37 38 39 40 41 42 43 44 45 46 47 48 49

Lik

elih

oo

d %

Project Completion in Months

0.00% 10.00% 20.00% 30.00% 40.00% 50.00% 60.00% 70.00% 80.00% 90.00%

100.00%

35 36 37 38 39 40 41 42 43 44 45 46 47 48 49

Lik

elih

oo

d%

Project Completion on or before, months