blackspring ridge project update liaison committee presentation july 14th, 2014

10
BLACKSPRING RIDGE PROJECT UPDATE Liaison Committee Presentation July 14th, 2014

Upload: dinah-webster

Post on 18-Jan-2016

216 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: BLACKSPRING RIDGE PROJECT UPDATE Liaison Committee Presentation July 14th, 2014

BLACKSPRING RIDGEPROJECT UPDATELiaison Committee Presentation

July 14th, 2014

Page 2: BLACKSPRING RIDGE PROJECT UPDATE Liaison Committee Presentation July 14th, 2014

GOAL OF THE LIAISON COMMITTEE

As part of this project, a Liaison Committee is being established to facilitate the participation of the community in the development of the wind farm.

The Liaison Committee will ensure that the interests of landowners are considered and participation of local businesses and services is encouraged.

The objectives of the committee are to:

Ensure effective communication between all stakeholders and EDF EN Canada Development Inc.;

Understand issues related to the development and construction of the wind farm;

Recommend satisfactory solutions to stakeholders;

Identify potential opportunities for local business and services

Page 3: BLACKSPRING RIDGE PROJECT UPDATE Liaison Committee Presentation July 14th, 2014

LIAISON OFFICE

Liaison Office As Manager of the Blackspring Ridge Wind Project, EDF EN Canada

Development Inc. is committed to working with all stakeholders during the development, construction and operation phases of the Project.

If you have any questions or comments, please do not hesitate to contact the Blackspring Ridge Liaison Office at: Kimberli Kenna, Site and Liaison Administrator

If meetings are needed or requested, Paul Lawson is available by appointment.

Tel.: 403-671-4000 E-mail: [email protected]

More information on the Project can also be found at www.blackspringridge.ca.

Page 4: BLACKSPRING RIDGE PROJECT UPDATE Liaison Committee Presentation July 14th, 2014

BLACKSPRING RIDGE TEAMS (ON-SITE)

As the project approaches Commercial Operation, various teams are preparing for the Operations phase of the project which will last for the next 20 years.

Following is a brief description of each of the teams responsibilities: EDF EN Canada Development Inc.: ECDI will continue to be the

Manager of the Project and will continue to be the main point of contact for all stakeholders and manage tasks such as landowner payments.

Enbridge: Enbridge will be the Balance of Plant Operations & Maintenance (BOP O&M) Manager and will be responsible for the maintenance of the site and the substation.

Vestas: With approximately 20 technicians on site, Vestas will be the Operations & Maintenance Manager and will be responsible for the day to day Operations & Maintenance (O&M) of all the turbines.

Operations Team Contact Information Contact information for the Operations team will be communicated to all project landowners

and other stakeholders through upcoming letters and next months newsletter update.

Page 5: BLACKSPRING RIDGE PROJECT UPDATE Liaison Committee Presentation July 14th, 2014

BLACKSPRING RIDGE DEDICATION CEREMONY

Date/TimeTuesday, July 15

Time11am – 1pm

LocationOperations & Maintenance facility parking lot

Guest list will include: Blackspring Ridge landowners Local, municipal, provincial and federal leaderships First Nations dignitaries Other special guests Media

Page 6: BLACKSPRING RIDGE PROJECT UPDATE Liaison Committee Presentation July 14th, 2014

ACTIVITIES ON SITE (POST-OPERATION)

Activities on site

Now that the project is in Commercial Operation, activities on site will include: Restoration/Reclamation:

Restoration of the lands has been the main focus over the last two months. We want to capture any open issues landowners and tenant farmers may have

regarding construction damage or areas that may have been overlooked during restoration.

Seeding of cover crop in is progress, our intent is to seed a cover crop around the turbine sites that were still under restoration and were not able to be planted with 2014 planned crop.

Continued reduction of traffic on site as main activities revolve around restoration Down from peak of 330+ on site

Reduction of laydown area footprint Occupation of O&M building

Vestas and Enbridge

Page 7: BLACKSPRING RIDGE PROJECT UPDATE Liaison Committee Presentation July 14th, 2014

SAFETY ON SITELANDOWNER PAYMENTS

Blackspring Wind Project is fully Energized (Safety is always a priority) The site is considered energized:

Underground cables Junction boxes Overhead line Substation

Call “Alberta One Call” prior any excavating

or digging

Landowner Payment Schedule

Landowner payments related to the: 2014 crop compensation will be issued in the fall once Restoration/Reclamation

activities have been substantially completed. Royalty payments related to the production of the Blackspring Ridge Wind Project will

be issued in July/August along with updated contact information for the Manager.

Page 8: BLACKSPRING RIDGE PROJECT UPDATE Liaison Committee Presentation July 14th, 2014

ENVIRONMENTAL MONITORING OPERATIONS PHASE

EDF EN Canada and Enbridge consider environmental protection to be an important and integral part of the Project.

As per ESRD requirements, ECDI and Enbridge plan to run Post Construction Monitoring of birds and bats for 2 years post June 2014.

Noise assessment will also be conducted on site and all documents and findings will be publically available online.

Page 9: BLACKSPRING RIDGE PROJECT UPDATE Liaison Committee Presentation July 14th, 2014

2014 COMMUNITY PROJECT FUNDING UPDATE

Upon the official announcement and launch of the Blackspring Ridge Community Project Fund, the selection committee comprised of representatives from ECDI, Enbridge, Vestas and a member of the liaison committee received and reviewed:

16 applications representing $151,635 in donation request.

$19,600 was allocated to the Fund for 2014 by the Co-Owners and Vestas.

7 of the 16 submissions will receive part of their funding requests.

Page 10: BLACKSPRING RIDGE PROJECT UPDATE Liaison Committee Presentation July 14th, 2014

THANK YOU FOR YOUR TIME

For questions, comments or inquiries, please contact the Blackspring Ridge Liaison Office:

Tel.: 403-671-4000 E-mail: [email protected]

A wealth of renewable experience in Canada.

1010/04/2014Liaison Committee Presentation