Agenda for the 67th Meeting of PCSC scheduled to be held on 20th September, 2017 Page 1
SOUTHERN REGIONAL POWER COMMITTEE
BENGALURU
Agenda for the 67th Meeting of Protection Coordination
Sub-Committee of SRPC to be held on 20th September, 2017
1. Introduction
2. Confirmation of Minutes of last PCSC meeting
Confirmation of minutes of 66th
Protection Coordination Sub-Committee meeting held
on 17.08.2017.
3. Grid Occurrences
3.1 Grid Disturbances (GD), Grid Incidences (GI), and trippings due to failure of Auto-
reclosing (A/R), and mal-operation of PLCC equipment that occurred during the
period July - August, 2017 given at Annexure-I would be discussed in the PCSC
meeting.
Constituents are requested to furnish the following information in respect of the
above grid occurrences to have fruitful discussions.
(a) Single line diagram of the station with switching devices, CT, PT and relay
details.
(b) Cause of the tripping & Remedial Action taken
(c) Relay setting details
Constituents are requested to bring/ furnish full particulars of the tripping
events pertaining to their system.
3.2 In compliance of Regulations 5.2 (r) of IEGC, the Constituents are required to
furnish the following information in respect of Grid Occurrences within 24 hrs of
occurrence of the same to SRLDC/ SRPC:
(a) First Information Report (FIR)
(b) Event Logger (EL) output
(c) Disturbance Recorder (DR) output
(d) Trip event analysis report (with pre and post fault system conditions)
Non-furnishing of tripping details (FIR/DR/EL/TR) for the period 01.15.2017 –
15.07.2017 had been brought to Constituents’ notice vide letters (i) No. SRPC/
SE-III/ PCSC/ 2017/4681 - 85 dated 22.06.2017, (ii) No. SRPC/ SE-III/ PCSC/ 2017/
3892 - 96 dated 07.07.2017, and No. SRPC/ SE-III/ PCSC/ 2017/ 4837 - 41 dated
18.08.2017. Non-compliance in this regard would be discussed in the meeting.
4. Submission of Reports/Compliance by Constituents
4.1 Status of implementation of pending Protection Coordination
Sub-Committee (PCSC) Recommendations
Status of implementation of pending PCSC recommendations (up to 66th
PCSC
meeting) given at Annexure-II may please be sent latest by 15.09.2017.
Agenda for the 67th Meeting of PCSC scheduled to be held on 20th September, 2017 Page 2
4.2 Remedial measures for "Transmission Elements under Forced Outage"
· The Constituents are requested to furnish the remedial measures/ action
taken by them for the tripping events as circulated vide our emails.
(Annexure-III)
· The tripping events are based on the daily reports at SRLDC website
http://srldc.in/ DailyReport.aspx under the menu: Reports->Daily->
"TL under Forced Outage")
4.3 Certificate for Healthiness of Batteries
· As per the MoP direction given in pursuant to recommendations of the
Enquiry Committee (NEW grid disturbance on 30th
& 31st
July, 2012), RPC’s
are required to obtain from their respective Constituents the monthly
certificate for healthiness of batteries, installed at 220 KV and above voltage
level Substations (for power supply to Relays, RTUs and PLCC equipment) and
furnish the same to CEA/ MoP.
· With reference to above, the Constituents have been requested to submit the
certificate on healthiness of batteries on monthly basis (i.e. status for a
month shall be sent by the 7th
day of the following month) to SRPC
Secretariat.
· The sought status for the month of August, 2017 is awaited from the
following SR-Constituents:
TSGENCO (Hydro), TANGEDCO, TANTRANSCO, PED, PGCIL (SR-I),
NPCIL (MAPS), NTECL, UPCL, JSWEL & NTPL
5. Revised Over Voltage Relay (OVR) Gradings for certain 400 kV & 765 kV lines
After issuance of new OVR gradings for 400 kV and 765 kV transmission lines of
southern region in April, 2017 (issued vide SRPC letter no: SRPC/ SE-III/ OVR/ 2017/
2023-53 dated 17.04.2017), certain reconfigurations took place (i) in the 400 kV system
belonging to APTRANSCO, TSTRANSCO and PGCIL (SR-I), and (ii) 765 kV system of
PGCIL (SR-I) in the past few months, which necessitated revising OVR gradings for the
transmission lines emanating from corresponding stations.
In this regard, necessary studies (Annexure-IV) have been carried out to arrive at
proper OVR gradings for these lines. Accordingly, APTRANSCO, TSTRANSCO and
PGCIL (SR-I) are directed to implement the new/ revised OVR gradings given at
Annexure-V pertaining to their respective systems with immediate effect.
6. Implementation of Protection Suite / Protection Management System (PMS)
for Southern Region
To familiarize SR-Constituents about the modus operandi of subject project execution,
kick-off meetings with M/s PRDC Pvt. Ltd. (Executing Agency) have been arranged as per
the following schedule (Letters in this regard have already been addressed to all
concerned vide our letter no: SRPC/ SE-III/ PMS/ 2017/ 4884 – 978 dated 24.08.2017):
Agenda for the 67th Meeting of PCSC scheduled to be held on 20th September, 2017 Page 3
Date & Time Venue Constituent Utilities
21.09.2017
from 10:00 hrs
Conference Hall of
SRPC Secretariat,
Bengaluru
Kerala, CPSUs and IPPs as indicated in
above referred letter
22.09.2017
from 10:00 hrs
Conference Hall of
SRPC Secretariat,
Bengaluru
Andhra Pradesh, Telangana, Karnataka,
TamilNadu, and Puducherry as
indicated in above referred letter
In the said meetings, the following would be presented by the Executing Agency:
· Introduction on the project
· Scope of the work: Different works and deliverables involved in the project will be
presented.
· Methodology: In this section clear methodology will be presented on how to go
about different works and complete them in stipulated time. Methodology for
following will be explained:
Ø Data collection and Database updating for SCADA validation, Geographical
diagram for the Southern states, plan for data collection, relay data extraction
from substations and Bus breaker model for all the substations.
· Case Study of data collection and database modelling, bus-breaker modelling
conducted for few substations in Bengaluru.
· Expectations from SR Constituents
· Time-lines and Deliverables of the project
· PRDC project team
· Discussions
7. Other Protection Issues, if any, with the permission of the Chair
8. Sending Agenda items for the PCSC meetings
As per the Guidelines of CEA/MOP, it has been decided to conduct the PCSC meetings
on monthly basis. It is requested that Agenda Items for the PCSC meetings, if any, may
please be sent latest by 5th
working day of the month to SRPC Secretariat to compile
and circulate the same so as to have fruitful discussions in the PCSC meetings.
9. Date of next PCSC meeting
It is informed that the 68th
meeting of PCSC will be held on 26th
October, 2017
(Thursday) from 10:30 hrs onwards in the Conference Hall of SRPC Secretariat,
Bengaluru.
*****
Grid Occurrences to be discussed in the 67th Meeting of PCSC scheduled to be held on 20th September, 2017 1/5
Grid Occurrences - 67
For all tripping events involving failure of substation equipment, Constituents are requested to
kindly furnish the SLD or equivalent pictorial representation showing (i) Location of the fault,
and (ii) Bus-bar arrangement/ Configuration of feeders and other connected equipment with
proper CB positions (OPEN/ CLOSE) at the time of occurrence of the fault.
I. Details of Grid Disturbances:
Sl. No.
Details of Event Date & Time Reason Remarks Category
1
Complete outage of
230kV Mettur
substation of Tamil
Nadu
13-07-2017
at 10:33 hrs
Flashover occurred during
transferring Unit-I (GT-I)
from main breaker to
transfer breaker
Gen loss
570 MW GD-1
2
Complete outage of
230kV Karamadai
substation
01-08-2017
at 3:40 hrs
Triggering incident was B-
phase PT failure in 230kV
Bus at Karamadi. Bus bar
protection operated
resulting in tripping of all
the connected elements
------ GD-1
3
Complete Outage of
230kV Tharamani
Subsation of
TANTRANSCO
02-08-2017
at 11:55 hrs
Jumper cut between bus
isolator and CT on Y-phase
of 230kV Tharamani –
Sholinganallur feeder
leading to operation of bus
bar protection.
Load loss
236MW GD-1
4
Complete Outage of
400kV Coastal energen
power Station
09-08-2017
at 17:54 hrs
400kV Coastal Energen -
Tuticorin PS Ckt-1 & 2
tripped due direct trip
receive in PLCC Channel-2.
Running units of Coastal
Energen also tripped due to
tripping of the evacuating
lines.
Gen loss
554 MW GD-1
5
Complete Outage of
220kV Nagjheri Power
House.
11-08-2017
at 19:51 hrs
while desynchronizing Unit-
3, R-phase of Generator
Circuit Breaker did not open
due to mechanical problem.
LBB of Unit-3 CB and this
tripped all the six lines
Gen loss
440 MW GD-1
6
Complete Outage of
400kV Coastal energen
power Station
19-08-2017
at 11:09 hrs
400kV Coastal Energen -
Tuticorin PS ckt-1&2 got
tripped due direct trip
receive in PLCC Channel-2.
Running units of Coastal
Energen also tripped due to
tripping of the evacuating
lines. There was no tripping
of breakers at Tuticorin PS
end.
Gen loss
325 MW GD-1
Grid Occurrences to be discussed in the 67th Meeting of PCSC scheduled to be held on 20th September, 2017 2/5
II. Details of Grid Incidents:
Sl. No. Details of Event Date & Time Reason Category
1 Tripping of 400 kV
RTPP-Chitoor line-2
2-07-2017
2017 at
00:27 & 1:08
hrs
line tripped on operation of over-voltage
stage-1 protection at RTPP and direct trip
received at Chittoor
GI-2
2
Tripping of 765/400kV
ICT-2 at Vemagiri
substation
03-07-2017
at 10:34 hrs
ICT-2 at Vemagiri GIS tripped on
maloperation of PRV-2 of Spare
transformer unit
GI-2
3
Tripping of 400/220kV
ICT-1 at Uruvakonda
substation
04-07-2017
at 2:01 hrs
ICT-1 tripped o mal-operation of Tie LBB
protection GI-2
4 Tripping of 765/400kV
ICT-2 at Kurnool
04-07-2017
at 15:06 hrs
765/400kV ICT-2 tripped due to mal-
operation of 86B trip relay GI-2
5 Tripping of HVDC
Bhadravati Pole-1
07-07-2017
at 10:59 hrs
Pole-1 tripped due to PC1 INTERNAL
MINOR ALARM WEST - ALARM. Pole
protection extended trip without any
protection operation.
6 Tripping of HVDC
Bhadravati Pole-1
09-07-2017
at 14:43 hrs
Pole protection initiated trip without any
protection operation
7 Tripping of 400kV
JSWEL - Guttur line
09-07-2017
at 18:02 hrs
& at 02:05
hrs on 24-07-
2017
line tripped on operation of over-voltage
stage-1 protection at Guttur end and
direct trip was received at JSW.
GI-2
8 Tripping of 400/220kV
ICT-1 at SVChatram
14-07-2017
at 19:03 hrs
400/220kV ICT-1 at S.V.Chatram tripped
on operation of Low impedance REF
protection during R phase to earth fault
in 400kV Alamathy-SVChatram line-2
GI-2
9 Tripping of HVDC
Talcher Kolar Pole-1&2
23-07-2017
at 17:07 hrs
Auxilliary supply failure at Talcher end led
to tripping of valve cooling pumps of
HVDC which in-turn led to tripping of
HVDC pole-1&2 at Talcher and emergency
switch off signal (ESOF) was sent to Kolar
end. Load relief in SR due to SPS
operation was 564 MW.
10 Tripping of 400/110KV
Alamathy ICT-2
24-07-2017
at 9:13 hrs
ICT-2 tripped due to suspected mal-
operation of high impedance REF
Protection
GI-2
11
Tripping of 400kV
Vijayawada TPS –
Malkaram and
Vijayawada TPS –
Suryapet
29-07-2017
at 19:33 hrs
Triggering incident was failure of Y-phase
CT occurred in 400kV VTPS-Malkaram
feeder at VTPS end.
GI-2
Grid Occurrences to be discussed in the 67th Meeting of PCSC scheduled to be held on 20th September, 2017 3/5
12 Tripping of HVDC
Gazuwaka Pole-1
03-08-2017
at 12:16 Hrs
Gazuwaka Pole-1 tripped due tomal-
operation of power supply card leading to
the stalling of the valve base electronics
13
Tripping of 400 kV
NCTPS – Vallur-2 and
NCTPS-Manali
04-08-2017
at 02:01 hrs
R-phase to ground fault occurred in
400kV NCTPS – Manali line. bus bar
protection of Bus-1 got operated at
NCTPS
GI-2
14 Tripping of 220 kV
Kaiga-Kadra line
11-08-2017
at 14:29 hrs
line tripped on B-phase to earth fault in
zone-1 from Kadra GI-1
15
Tripping of 400/220 kV
ICT-3 at N’Sagar
substation
13-08-2017
at 20:51 hrs
Mal-operation of ICT differential
protection GI-2
16 Tripping of 400/220 kV
ICT -3 at Nagarjunsagar
22-08-2017
at 10:21 hrs Mal-operation of 86B trip relay GI-2
17 Tripping of 400 kV
Kolar-Thiruvalam line
26-08-2017
at 1:58 hrs
hrs & 2: hrs
on 27-08-
2017
line tripped due to operation of
overvoltage protection at Kolar and direct
trip was received at Thiruvelam end.
considerable difference between R, Y and
B phase voltages
GI-2
18
Tripping of 400kV
Maheshwaram-
Narnoor line
30-08-2017
at 10:11 hrs
86B relay mal-operation at
Maheshwaram caused tripping of line and
direct trip was received at Narnoor
GI-2
19 Tripping of 400/220 kV
ICT-2 at Nellore
31-08-2017
at 05:05 hrs
ICT-2 tripped due to mal-operation of
differential relay. GI-2
III. Details of Trippings due to Failure or Non-operation of Auto-Reclose:
Sl. No. Element Date & Time Reason
Category
1
Tripping of 400kV
Gajwel - Bhoopalapalli
line
22-07-2017
at 13:13 hrs
line tripped on B-Phase to earth fault.
Auto-reclose was successful at
Bhoopalapally end and breaker tripped at
Gajwel.
GI-2
2 Tripping of 400kV
Neyveli-Salem line
06-08-2017
at 17:04 hrs
Y-phase to earth fault. Auto reclose was
successful at Salem end
GI-2
3
Tripping of 400kV
N’sagar- Cudappah
line-1
07-08-2017
at 12:20 hrs
R-phase to earth fault. Auto-reclose was
not attempted.
GI-2
4
Tripping of 400kV
Khammam-Asupaka
09-08-2017
at 19:43 hrs
B-phase to earth fault. Line did not
attempt auto-reclose at Khammam end
due to direct trip receive from Asupaka
end.
GI-2
5 Tripping of 400kV 15-08-2017 B-phase to earth fault. Direct trip was
Grid Occurrences to be discussed in the 67th Meeting of PCSC scheduled to be held on 20th September, 2017 4/5
Somanahalli-Bidadi
line-2
at 03:16 hrs sent from Bidadi to Somanahalli during
auto-reclose dead time
GI-2
6
Tripping of 400kV
N'Sagar-Cudappa line-1
19-08-2017
at 3:48 hrs
Y-phase to earth fault. Auto-reclose was
successful at N’sagar and breaker at
tripped at Cudappa end
GI-2
7
Tripping of 400kV
Tirunelveli-Kanarpatti
line
31-08-2017
at 21:58 hrs
R-phase to earth fault had occurred in
line. Breakers got tripped at Tirunelveli
and did not attempt auto-reclose.
GI-2
IV. Details of Trippings due to PLCC mal-operation:
For the following events, concerned Constituents are requested to furnish the remedial action
taken to resolve the issue involved to [email protected] latest by 16.09.2017
Sl. No. Element Date & Time Reason
Category
1
Tripping of 400 kV
Ghanapur-Mamidapalli
line
01-07-2017
at 15:49 hrs
Line tripped at Mamidapalli end only on
direct trip receive. Line was in service
from Ghanapur end.
GI-2
2
Tripping of 400kV
Khammam-Kalpakka
line-2
03-07-2017
at 9:24 hrs
Line tripped on direct trip receive at
Kalpaka end and line was in service from
Khammam
GI-2
3
Tripping of 400kV
Nellore-Thiruvelam
line-2
03-07-2017
at 14:20 hrs
line tripped on DT receipt at Thiruvallam
end only and was in service from Nellore
end
GI-2
4
Tripping of 400kV
Khammam-Kalpakka
line-2
07-07-2017
at 12:03 hrs
line tripped at Kalpakka end only on
direct trip receive and was in service from
Khammam
GI-2
5 Tripping of 400kV
Guttur-Hiryur line-2
22-07-2017
at 15:03 hrs
line tripped at Guttur end only and was in
service from Hiryur. I
GI-2
6
Tripping of 400kV
Ghanapur-Mamidapalli
line
24-07-2017
at 19:35 hrs
&
25-07-2017
at 16:24 hrs
line tripped at Mamidapalli end only on
direct trip receive and line was in service
from Ghanapur.
GI-2
7 Tripping of 400kV
Kaiga-Guttur line-2
25-07-2017
at 5:24 hrs
line tripped at Guttur end only on direct
trip receive and line was in service from
Kaiga.
GI-2
8
Tripping of 400kV
Khammam-
Mamidapalli line-2
31-07-2017
at 13:55 hrs
line tripped at Mamidapalli end on direct
trip receive and was holding from
Khammam
GI-2
9
Tripping of 400kV
Malkaram-Hyderabad
line
31-07-2017
at 15:44 hrs
line tripped at Malkaram end on direct
trip receive and was holding from
Hyderabad
GI-2
10
Tripping of 400kV
Mamidapalli-Dindi line-
2
31-07-2017
at 14:03 hrs
line tripped at Dindi end on direct trip
receive and was holding from
Mamidapalli.
GI-2
11 Tripping of 400kV
Ghani-Narnoor line-1
07-08-2017
at 11:05 hrs
line tripped at Narnoor end only on direct
trip receive and line was in service from
Ghani.
GI-2
12 Tripping of 400kV
Nizamabad-Dichipally
07-08-2017
at 17:12 hrs
line tripped on DT receipt at Dichipally
and was in service from Nizamabad
GI-2
Grid Occurrences to be discussed in the 67th Meeting of PCSC scheduled to be held on 20th September, 2017 5/5
13
Tripping of 400kV
Kalpakka-Gazuwaka
line-1&2
16-08-2017
at 14:40 hrs
line tripped at Kalpaka end only due to
Direct trip receipt at Kalpaka
GI-2
14 Tripping of 400kV
Cudappa-Chitoor line
19-08-2017
at 3:49 hrs
Line tripped at Cudappa end on direct trip
receive & was in service from Chittoor
end
GI-2
15
Tripping of 400kV
Ramagundam-
Ghanapur line-4
20-08-2017
at 1:47 hrs
line tripped on operation of over-voltage
stg-1 protection at Ghanapur end . Line
was holding from Ramagundam as no
direct trip was received from Ghanapur
GI-2
V. Forced outage of lines due to Over Voltage:
(i) Tripping of 400kV Uravakonda-Jamalamadugu line-2
It was noted that the line had frequently tripped (as given below) on operation of Over
Voltage Protection at Uravakonda in the past two months. Further, Direct Trip was also not
received at Jamalamadugu end, and line was hand tripped in all cases.
Sl. No. Date & Time of tripping Reason
1 24-07-2017 at 2:01 hrs Over Voltage Stg-1 at Uravakonda
2 27-07-2017 at 2:01 hrs Over Voltage Stg-1 at Uravakonda
3 29-07-2017 at 20:28 hrs Over Voltage Stg-1 at Uravakonda
4 07-08-2017 at 02:00 hrs Over Voltage Stg-1 at Uravakonda
5 12-08-2017 at 00:24 hrs Over Voltage Stg-1 at Uravakonda
6 19-08-2017 at 02:30 hrs Over Voltage Stg-1 at Uravakonda
7 23-08-2017 at 05:15 hrs Over Voltage Stg-1 at Uravakonda
8 24-08-2017 at 02:58 hrs Over Voltage Stg-1 at Uravakonda
à APTRANSCO is requested to present reasons for frequent tripping of the line on
OVR, Stage-I protection, and corrective action taken to sort out the issues involved.
(ii) Tripping of Maheswaram-Narnoor line:
It was noted that the line had frequently tripped (as given below) on operation of Over
Voltage Protection at Narnoor in the past two months. Direct trip was received at
Maheswaram end. However, operation of OVR, Stage-I protection could not be validated
with the submitted DR of Narnoor station.
Sl. No. Date & Time of tripping Reason
1 06-08-2017 at 08:02 hrs Over Voltage Stg-1 at Narnoor
2 12-08-2017 at 2:02 hrs Over Voltage Stg-1 at Narnoor
3 13-08-2017 at 16:32 hrs Over Voltage Stg-1 at Narnoor
4 19-08-2017 at 2:30 hrs Over Voltage Stg-1 at Narnoor
5 21-08-2017 at 1:43 hrs Over Voltage Stg-1 at Narnoor
6 23-08-2017 at 5:15 hrs Over Voltage Stg-1 at Narnoor
7 25-08-2017 at 16:11 hrs Over Voltage Stg-1 at Narnoor
à APTRANSCO is requested to present reasons for frequent tripping of the line on
OVR, Stage-I protection, and corrective action taken to sort out the issues involved.
*****
Meeting No /
Index
Details of Event Date & Time Reason PCSC Recommendations Utility responsible for
Implementation
Status of Recommendations
as on 06.09.2017
Remarks
Pending Implementation of PCSC Recommendations (up to 66th Meeting)
Complete outage of 220kV Yerraguntla
substation and tripping of running Units
at Rayalaseema TPS
52/I/2 (GD) PendingMail received on 27-07-2016:
1.The drop out relays of reducer oil pumps time setting was increased for
all mills.So there will not be any trip under transient low voltage condition.-
---Complied
2.The recommendation regarding 2 sec time delay will be implemented
during unit shut down and will be intimated immediately after
implementation.------Pending
APGENCO 1. APGENCO to check associated logic for lube oil pump for correct
operation under transient low voltage conditions at Rayalaseema TPS,
Unit-1.
2. APGENCO to keep appropriate time delay/ fault ride through
delay (typically 2 sec) in VFD speed sensor relay at all its generating
Units including Rayalaseema TPS Units.
HV B-Ph Current transformer of 100MVA Power
Transformer -1 failed resulting into a bus fault on
220KV Bus-1. Unit-1 and Unit-5 at RYTPS tripped
during the fault at Yerraguntla substation
21-02-2016 at
10:39 hrs
Andhra Pradesh
APGENCO to furnish a report on the remedial action implemented
w.r.t. overreaching of Krishnapatnam end distance relays during the
tripping of 400 kV Nellore (PG) - NPS line-1
APGENCO Yet to be informed Pending57/II/9 Tripping of 400 kV Nellore (PG) - NPS
line-1, 400 kV Krishnapatnam-Nellore
(AP) lines -1&2 and 400kV NPS -
MEPL line
18-07-2016 at
19:05 hrs
Triggering incident was snapping of Y phase
conductor in 400kV Nellore (PG) - NPS line-1.
Distance relay at Krishnapatnam end over-reached in
Zone-1, and resulted in tripping of 400kV
Krishnapatnam – Nellore (AP) lines - 1&2 from
Krishnapatnam end. Distance relay at MEPL over-
reached and resulted in tripping of MEPL-NPS line
from MEPL end.
Yet to be informed Pending
APTRANSCO mail dated on 31-08-2016:
To avoid the unwanted malopeartions due to the external LBB trip
initiation from PGCIL, Vide letter Dt: 04-08-2016, APTRANSCO has
requsted the PGCIL to arrange the Master trip relay and breaker contacts
of ICT-1 &2 LV side to enable the internal LBB feature in the Busbar
protection scheme at 220kV Gooty Switching station. Waiting for the
PGCIL response.
APTRANSCO mail dated on 15-11-2016:
To avoid the unwanted maloperations due to the external LBB trip
initiation from PGCIL, vide letter Dt: 04-08-2016, ARTRANSCO has
requested the PGCIL to arrange the Master trip relay and breaker contacts
of ICT-1&2 LV side to enable the internal LBB feature in the Busbar
protection scheme at 220kV Gooty Switching station. Waiting for the
PGCIL response.
APTRANSCO mail dated on 20-12-2016:
Waiting for the PGCIL response.
APTRANSCO mail dated 04.03.2017 & 24.05.2017.
SRPC is requested to coordinate with PGCIL in takind necessary action.
Pending
Tripping of 400kV Krishnapatnam-
Nellore line-1
Line tripped on B-phase to earth fault and auto-
reclose was successful at Nellore(AP) end and un-
successful at Krishnapatnam end
APGENCO
56/II/13 Tripping at 220kV Gooty Substation of
APTRANSCO
24-06-2016 at
16:04 hrs
LBB protection got operated for 400/220kV ICT-2
breaker which had resulted in tripping of 220kV Bus-
2 at 220kV Gooty Substation
1. APGENCO/ SDSTPS to correct logic and ensure healthiness of A/R
scheme employed for transmission lines emanating from SDSTPS,
and furnish an action taken report to PCSC forum.
2. APGENCO/ SDSTPS to configure DR’s of line protection relays
for a post triggering period of 2 sec to capture complete A/R
operation at their SDSTPS.
Yet to be informed Pending63/III.1 28-02-2017 at
05:16 hrs
1. APGENCO/ SDSTPS to correct logic and ensure healthiness of A/R
scheme employed for transmission lines emanating from SDSTPS,
and furnish an action taken report to PCSC forum.
2. APGENCO/ SDSTPS to configure DR’s of line protection relays
for a post triggering period of 2 sec to capture complete A/R
operation at their SDSTPS.
Tripping of 400kV Krishnapatnam-
Nellore line-2
R-phase to earth fault had occurred in line. Auto
reclose was successful at Nellore, however
protection at Krishnapatnam end issued a 3 phase
trip
APGENCO63/III.3 02-03-2017 at
4:55 hrs
1.APTRANSCO to check the healthiness of the connecting cable
between Gooty (PGCIL) and Gooty (APTRANSCO), and replace it,
if required.
2.APTRANSCO to ensure that the distributed architecture employed
in implementing busbar protection at their Gooty 220 kV SS does not
introduce any unwarranted delays in transmitting the triggering
signals to the Central Unit.
APTRANSCO
Annexure-II
Page 1 of 33
63/II.2 Tripping of 400 kV K.V. Kota-Suryapet
line
01-03-2017 at
20.05 hrs
Line tripped on operation of over-voltage protection
at K.V Kota and Direct Trip was received at Suryapet
1. APTRANSCO to furnish (i) FIR & TR for tripping events as
per SRLDC provided formats; and (ii) DR & EL within 24-hrs of
occurrence of tripping event in line with IEGC Regulation 5.2
(r).
2. APTRANSCO to adopt new OVR gradings for KV Kota
feeders, and confirm the same.
APTRANSCO Status vide APTRANSCO mail dated on 28-06-2017:
1. FIR furnished & DR configured
Pending
63/II.16 Multiple Trippings at 220kV Vizag
Switching Station (VSS) of APTRANSCO
27-03-2017 at
10:16 hrs
Bus-2 bus bar protection operated at 220kV VSS
end, resulting in the tripping of all the elements
connected to bus-2
1. APTRANSCO to furnish a detailed report on the reasons for LBB/
BBP operation at 220 kV VSS for a fault on 220 kV Gangavaram
feeder and remedial action taken to prevent recurrence of such
events.
APTRANSCO Yet to be informed Pending
64/II/1 Tripping of 400/220KV 315MVA ICT-
1and 230kV elements at 400kV Vemagiri
substation of APTRANSCO
09-04-2017
at 12:31 hrs
Suspected mal-operation of Busbar protection had
caused tripping of 220kV Bus-1 at Vemagiri.
APTRANSCO to furnish a report on the remedial action taken along
with single line diagram of 400/220 kV Vemagiri SS indicating fault
location and CB's involved and protections operated.
APTRANSCO Yet to be informed Pending
64/II/2 Tripping of 400/220 kV ICT’s – 2 & 3 at
400 kV Ghani substation of APTRANSCO
10-04-2017
at 17:29 hrs
ICT’s – 2 & 3 got tripped due to operation of 220 kV
Bus-2 busbar protection at 400/220KV Ghani
substation.
APTRANSCO to furnish single line diagram of 400/ 220 kV Ghani SS
clearly indicating (i) bus-configuration, (ii) location of fault, (iii)
breakers involved and type of protections operated.
APTRANSCO Status vide APTRANSCO mail dated on 28-06-2017:
Single line diagram sent vide mail dated : 27.06.2017.
Pending
64/III/1 Tripping of 400 kV Uravakonda-
Jammalamadugu line-1
02-04-2017 at
17:58 hrs
R-phase to earth fault and line did not auto-reclose.
Fault clearing time - 500ms
For the line under consideration, APTRANSCO to check & ensure
healthiness of carrier protection and make Auto-Reclosure
functional.
APTRANSCO Status vide APTRANSCO mail dated on 28-06-2017:
Carrier aided protection scheme has been tested end to end and rectified the
problem.
Pending
64/III/5 Tripping of 400kV Krishnapatnam-
Nellore line-2
11-04-2017 at
2:41 hrs
Line tripped on Y-phase earth fault. Line auto-
reclosed at Krishnapatnam and did not auto-reclose
at Nellore-AP (Manubolu).
For the line under consideration, APTRANSCO to look into reasons
for A/R failure at Nellore-AP (Manubolu) end, and furnish a report
on the remedial action taken.
APTRANSCO Status vide APTRANSCO mail dated on 28-06-2017:
The ABB make REL 670 type main-2 distance relay seen the fault as R-
Y phase to phase fault. Hence A/R is not operated. For the similar incident
on 07.06.2017, the operation of A/R is successful.
Pending
64/III/6 Tripping of 400kV Krishnapatnam-
Nellore line-1
12-04-2017 at
2:51 hrs
Line tripped on Y-phase earth fault. Line auto-
reclosed at Krishnapatnam and did not auto-reclose
at Nellore-AP (Manubolu).
For the line under consideration, APTRANSCO to look into reasons
for A/R failure at Nellore-AP (Manubolu) end, and furnish a report
on the remedial action taken
APTRANSCO Status vide APTRANSCO mail dated on 28-06-2017:
The ABB make REL 670 type main-2 distance relay seen the fault as R-
Y phase to phase fault. Hence A/R is not operated. For the similar incident
on 07.06.2017, the operation of A/R is successful.
Pending
64/III/10 Tripping of 400kV Krishnapatnam –
Nellore_AP line-1
13-04-2017 at
4:38hrs
Y-phase to earth fault. Line auto-reclosed from
Krishnapatnam end and did not auto-reclose from
Nellore-AP end
For the line under consideration, APTRANSCO to look into reasons
for A/R failure at Nellore-AP (Manubolu) end, and furnish a report
on the remedial action taken.
APTRANSCO Status vide APTRANSCO mail dated on 28-06-2017:
The ABB make REL 670 type main-2 distance relay seen the fault as R-
Y phase to phase fault. Hence A/R is not operated. For the similar incident
on 07.06.2017, the operation of A/R is successful.
Pending
Tripping of 400 kV Khammam - KTPS
line-2
The issue was discussed in PCSC-58 meeting held on 18.10.2016, when
PCSC forum agreed to de-link the implementation of the Item from the
scope of Protection Audit Recommendations (PAR), and pursue it as part
of PCSC Recommendations.
TSGENCO mail dated 30-05-2017
Procurement of Differential Protection relays is under process and the
work will be completed by the end of November 2017.
TSGENCOProvision of line differential protection for Jurala line 1 & 2 (line length-1.45 KM) feeders at 220 kV Jurala HPS [Carry-Over from Protection Audit Recommendations]58 Pending
24-12-2016 at
10:52 hrs
Line tripped on B-phase to earth fault. First fault was
persistent for 380 ms. Auto-reclose was successful at
Khammam end during 1st fault. 2nd fault occurred
during re-claim time of breaker hence Khammam end
breakers also got tripped.
1. TSGENCO to implement the SRPC agreed philosophy for Power
Swing Blocking in all distance relays on the feeders emanating from
KTPS.
2. For the line under consideration, TSGENCO to consult relays
OEM to migrate to new versions of Firmware (from to 4.72.01) and
Pset (to 4.70.02).
line tripped on direct trip receive at Gajwel and was
holding from Hyderabad
06-10-2016 at
12:16 hrs
Pending
Telangana
TSGENCO TSGENCO mail dated 30.03.2017:
1. According to SRPC phylosphy power swing block settings are changed
to ALL ZONES BLOCK EXCEPT ZONE1.
---------- Completed
2. M/s. Siemens is requested to depute the service Engineer to update the
firm ware of existing SIPROTEC relays in 400KV switch yard. This work
will be completed on or before 15.04.2017. -------------- Pending
Pending61/III/5
63/III.2 02-03-2017 at
1:57 hrs
1. APTRANSCO to check and ensure correctness of A/R operation
for the lines emanating from their Nellore-AP (Manubolu) SS.
2. APTRANSCO to configure DR’s of line protection relays for a
post triggering period of 2 sec to capture complete A/R operation at
their Nellore-AP (Manubolu) SS.
APTRANSCO Status vide APTRANSCO mail dated on 28-06-2017:
1.The ABB make REL 670 type main-2 distance relay seen the fault as Y-
B phase to phase fault. Hence A/R is not operated. For the similar incident
on 07.06.2017, the operation of A/R is successful.
Pending
Tripping of 400 kV Gaiwel-Hyderabad
line
59/IV/3 TSTRANSCO mail dated on 21-12-2016:
(i) Letter is been given to field for conducting end to end testing of 400kV
Gajwel-Ghanapur line.
(ii) Healthiness of PLCC system components will be checked while
conducting end to end testing.
TSTRANSCO
Tripping of 400kV Krishnapatnam-
Nellore line-1
Line tripped on B-phase to earth fault and line auto-
reclosed from Krishnapatnam end but did not auto-
reclose from Nellore-AP end.
For the line under consideration, the following shall be carried out by
TSTRANSCO in coordination with PGCIL (SR-I):
(i) End-to-end communication for DT/ permissive & other signals
may be ensured by testing at both the ends.
(ii) Healthiness of PLCC system components (hardware and software)
at both ends shall be checked and faulty components shall be repaired/
replaced.
Annexure-II
Page 2 of 33
65/II/8 Tripping of 400/220 kV Hyderabad ICT-
4 and 220 kV lines at Hyderabad
substation
10-05-2017 at
2:39 hrs
Operation of busbar protection due to fault in 220 kV
Bus at 220kV Hyderabad Substation
TSTRANSCO to investigate the reasons for BBP operation for 220
kV Bus-2, and furnish a report on the remedial measures taken.
TSTRANSCO Yet to be informed Pending
PendingFor the line under consideration, TSTRANSCO to carry out the
following in coordination with TSGENCO:
(i) Healthiness of PLCC system components (hardware and software)
at both ends shall be checked and faulty components shall be repaired/
replaced.
(ii) End-to-end communication for DT/ permissive & other signals
may be ensured by testing at both the ends.
(iii) Frequency bandwidth tuning of PLCC link for faithful
transmission of signals shall be carried out.
62/IV/5 Tripping of 400 kV Gajwel-
Bhoopalapalli line-1
16-02-2017
at 15:00 hrs
TSGENCO /
TSTRANSCO
TSTRANSCO mail dated on 31-05-2017:
1. Letter is been given to field for conducting end to end testing of 400kV
Gajwel-Bhoopalpalli-1 line.
Line tripped at Bhoopalapally on DT receive and was
holding from Gajwel.
TSTRANSCO mail dated on 31-05-2017:
1. Letter is been given to field for conducting end to end testing of 400kV
Gajwel-Ghanapur line.
replaced.
Annexure-II
Page 3 of 33
KPCL
38/GD/3.5 Pending
Mail received on 28-05-2015:
1. Main-2 relays already installed and commissioned.
2. DC fuses are intact. Till date no such incidence occurred.
3. Possibility of DC-1 & DC-2 arrangement and splitting of DC will be
reviewed.
Mail received on 07-07-2015 , 21-10-2015 and 23-11-2015:
1. Completed.
2. Completed.
3. Possibility of DC-1 & DC-2 arrangement and splitting of DC will be
reviewed.
Status received vide KPCL mail dated 14.06.2017:
1. Completed.
2. Completed.
3. Providing 2 separate DC sources is under process
Pending
Mail recieved on 28-05-2015:
1) e-NIT floated on 28.07.2014 for procurement of Numerical distance
relays & GPS. As there is change in scope of work and quantity of relays
by more than 25%, which is not permitted as per KTPP act. Hence, tender
cancelled and refloated on 05.05.2015 with revised scope of work and
revised PQR.
2. However, as per the recommendations of PSAG, Relays were
temporarily rearranged, replaced and wired up. testing & commissioning
shall be completed with the assistance of KPTCL.
Mail recieved on 07-07-2015:
1. Cover -1 of the bid is scheduled for open eing on 25.06.2015.
2. As per the recommendations of PSAG, Relays were temporarily
rearranged. testing & commissioning completed with the assistance of
KPTCL.
Mail recieved on 07-09-2015:
NIT floated on 5.5.15 through e-portal. Bid evaluation completed.
Obtaining of Administration approval to place P.O is in progress.
However, as per therecommendationsof PSAG-10, Relays
weretemporarilyrearranged.Testing & commissioning completed with the
assistanceofKPTCL.
Mail recieved on 21-10-2015:
NIT floated on 5.5.15 through e-portal. Bid evaluation completed. LOA's
issued to M/s Schneider Electric Infrastructure Ltd. on 08.10.2015.
Mail recieved on 23-11-2015:
LOA's issued to M/s Schneider Electric Infrastructure Ltd. on 08.10.2015.
Engineering work is in progress.
Status informed during Special Meeting held on 03.06.2016:
LOA’s issued to M/s Schneider on 08.10.2015. Inspection of relays
completed and received at site. DI issued for all balance materials except
furnitures.
Status received vide KPCL mail dated 14.06.2017:
Numerical Distance Protection relays commissioned on 12.04.2017
for all 4 lines at Kadra PH.
Installation, Testing and commissioning of Numerical Distance Protection
Relays for all the 4 outgoing lines is completed in all respect at Kodasalli
power house.
KPCL1. The PCSC forum requested KPCL to speed up the installation of
Numerical Distance Protection relay in Kadra –Kaiga and
Kodasalli –Kaiga.
2. The PCSC forum requested KPCL to submit the implementation
status of PSAG-10 recommendations within a week’s time.
A fault had occurred in 220 kV Kadra and Kodasalli.
As A result, de-energization of 220kV bus occurred at
Kadra and Kodasalli.
13-11-2014 at
19:31hrs
1. KPCL to make functional the Main2 (EPAC) relay with the
help of KPTCL at the earliest.
2. KPCL to investigate the reason for DC fuse fail during
transient fault in 220kV Kadra-Kodasalli line including the testing/
checking of DC supply cables, breaker control cables, and trip coils.
3. KPCL to ensure supply for Main-1& Main-2 protections, Trip
Coils (TC1, TC2) from separate battery banks.
Triggering incident was B-phase to earth fault had
occurred in 220kV Kadra-Kodasalli line. Line tripped
from Kodasalli end only. 220kV Kaiga-Kadra tripped
in Zone-3 from Kaiga end. Tripping of evacuating
lines caused bus shut down at Kadra hydro station.
GD-1 at Kadra and Kodasalli hydro
power station
16-02-2015 at
12:56 hrs
GD-1 at 220kV Kadra power Station of
KPCL
41/I/1
Annexure-II
Page 5 of 33
49/II/15
54/II/4 Tripping of 400 kV Raichur TPS-
Mahboobnagar line
05-04-2016 at
10:23 hrs
Line tripped on operation of Backup impedance
protection of line reactor. Direct trip was received at
Mahboobnagar end.
KPCL to keep the functioning of the concerned electro-mechanical
back-up impedance protection relay under observation, and replace it
with a spare at the earliest.
KPCL Status received vide KPCL mail dated 10.07.2017:
The electro-mechanical back-up impedance protection relay is in service.
However, Budgetary offer obtained for the retrofitting of Line reactor
protection with Numerical relay and is under process
Pending
54/II/9
Pending
PendingStatus informed during Special Meeting held on 03.06.2016:
1. Hot line washing was done previously.tender process is on for silicon
coating of insulators.
Status received vide mail dated 10-07-2017:
1. Off line water washing is being carried out whenever the Unit or Line is
under shutdown. Silicon coating for Unit#8 main & tie breakers carried
out in Sep'16 and same is under observation. Till today in order and good
condition. For remaining breakers, since it is big order, approval for the
same is under process.
2. Static / Electromechanical relays are existing in all 1 to 7 units. Breaker
flash over protection feature will be enabled (if available) in the numerical
relays which will be retrofitted in phased manner during R&M works.
KPCL1. KPCL to carry out hot-line washing of RTPS-connected lines
regularly to avoid trippings due to fog and dust.
2. KPCL may see the feasibility of providing breaker flashover
protection at RTPS, and implement the same if possible.
54/I/4 220 kV Nagjheri - Bidnal line tripped on B-E fault at
12:28 Hrs. At the same time, five running generating
units (1, 2, 3, 4 & 6) at Nagjheri tripped on operation
of Generator Transformer’s back-up Over Current &
Earth Fault protection.
Pending
1. KPCL to revise the settings of GT’s back-up O/C and E/F
protections considering their individual contribution to solid bus fault
at 220 kV bus of Nagjheri PH.
2. KPCL to upload/ make available various tripping files
(FIR/DR/EL/TR) for all tripping involving their stations in
compliance of IEGC Regulation 5.2 (r).
14-04-2016 at
12:29 hrs
Tripping of Nagjheri Generators Pending
Trippings at 220kV Raichur TPS
KPCL
Running Unit-4, 5 and Unit-8 and 400kV RTPS-
Yeramaras TPS feeder got tripped due to de-
energization of both 400kV Bus-1&2 at Raichur TPS
12-11-2015 at
00:30 hrs
Y-ph Pole of Tie-breaker of Unit-4 at RTPS failed.
Unit-4 got tripped on operation of Generator
Differential, Reverse power & LBB protection.
Operation of LBB protection led to tripping of BUS-2
at RTPS
46/II/21
Status received vide KPCL mail dated 10.07.2017:
1. i) Silicon coating for Unit#8 main & tie breakers carried out in Sep'16
and same is under observation. Till today in order and good condition. For
remaining breakers, since it is big order, approval for the same is under
process. ii) Hot line
water washing stopped and off line water washing is carried out whenever
the 400 KV Unit or line is under tripped condition / Shutdown condition.
2. Static / Electromechanical relays are existing in all 1 to 7 units. Breaker
flash over protection feature will be enabled (if available) in the numerical
relays which will be retrofitted in phased manner during R&M works.
KPCL13-04-2016 at
21:12 hrs
1.KPCL to undertake the following remedial measures to avoid
breaker flashovers:
(i) Replacing all porcelain insulators with composite insulators
(ii) Carrying out hot-line water washing of all insulators on regular
basis.
(iii) Applying Room Temperature Vulcanizing (RTV) Silicone high
voltage insulator coatings to all bus-connected ceramic insulators of
equipment like CT, PT, CB, Isolators etc.
2.KPCL to take steps to provide dedicated breaker flashover
protection to all breakers at Raichur TPS at the earliest.
Tripping of 400kV Raichur TPS Bus-2
Mail received on 21-10-2015:
1) Anti-pumping contactors of all the nine 220KV Lines are in circuit and
tested periodically during AOH works of lines along with other protections.
2) Completed.
3) Possibility to use both the 220kV buses as main bus under normal
operation is under review.
Mail recieved on 23-11-2015:
1) Completed
3) Two bus operation for 220kV buses : In place of existing CT switching
relays, High speed manual heavy duty change over switch of sufficient
current capacity will be retrofitted to all feeders at 220kV station and same
will be operated manually during changeover of feeder by one bus to the
other and this arrangement may facilitate to put both buses in service. Time
required for this retrofit is around 90days . However, this work will be
taken up only after retrofitting of electromagnetic relays with numerical
relays for Main-2 protection of all 220kV lines, for which work is in
progress.
Status received vide mail dated 10-07-2017:
1) Completed.
2) Completed.
3) Two Bus operation for 220kV bus is being carried out whenever
required. However scheme for tripping of one bus during LBB/fault and
maintaining the other bus intact by tripping B/C breaker will be taken up in
R&M works.
KPCL1. KPCL to check the operation of anti-pumping relay on 220 kV side
and keep it in healthy condition.
2. KPCL to provide manual reset to the 220 kV side master trip relay.
3. KPCL to use both the 220 kV buses as main buses under normal
operation, and should go for single bus operation only during
emergencies.
07-06-2015 at
01:35 hrs
Trippings at Raichur TPS
Status received vide KPCL mail dated 14.06.2017:
1. GT backup overcurrent & earth fault settings are revised as per the
recommendations of our head office CEED,Bangalore, copy of letter
enclosed.
2. FIR/DR/EL/TR are being uploaded in the recent incidences as all the
main-2 relays are replaced with new numerical relays
Annexure-II
Page 6 of 33
55/II/1
56/I/2 Complete outage of 220kV Sedam
Substation of KPTCL.
19-06-2016 at
15:27hrs
220kV Sedam-Humnabad-2 tripped at Sedam on
Distance protection, Zone-2. Sedam-RTPS-1 &2 lines
tripped at RTPS end only. 220kV Tandoor inter-state
line was hand tripped due to incoming supply failure
KPCL to disable GFC protection on all lines emanating from their
generating stations.
KPCL Status received vide KPCL mail dated 10.07.2017:
As per the reccomndations of KPTCL in Feb'16 the settings are done with
a time delay of 2 secs.
Pending
57/II/3 Tripping of 400/220 kV ICT-2 at Raichur
TPS
07-07-2016 at
3:32 hrs
ICT-2 tripped on operation 400/220KV ICT-2 was
tripped on operation of 220KV side Instantaneous
over current protection during B-phase to earth fault
in 220kV RTPS-Sedam-II line.
KPCL to review appropriately the high-set of ICT’s back-up O/C
protection at their 220 kV RTPS so that they do not operate for a
normal through fault.
KPCL Status received vide KPCL mail dated 10.07.2017:
The settings will be reviewed in co-ordination with KPTCL & OEM.
Pending
Status received vide KPCL mail dated 14.06.2017:
1. On 09.09.2016 at STRP,Two units were running(Unit-3 & Unit-4.It is to
clarify that, Station tripped due to spurious operation.LBB relay in Unit-4
and not due to operation of Unit-3 LBB as indicated in PCSC
recommendations .Unit-3 which was in service tripped as a consequence of
LBB Protection.How ever, following actions performed in both Units.
a) Trip coil-1 and Trip coil-2 circuit (including cable from protection panel
KPCL
Pending06-09-2016
at 14:40 hrs
31-05-2016 at
17:21 hrs
Direct Trip was sent from YTPS to RTPS and BTPS
01-05-2016 at
21:44 Hrs
LBB of 220kV Kodasalli breaker at Kadra end got
operated which resulted in tripping of Bus at Kadra
and in turn led to tripping of all elements
KPCL Status received vide KPCL mail dated 10.07.2017:
1) Zero-sequence compensation feature is already enabled in all the
differential relays of transformers. ---Completed
2) Referred to OEM for the tripping of line on SOTF protection.
3) Action has been taken to retrofit the protection relays of tie bays of
Mahbubnagar and Munirabad line to enable Auto-reclosure function.
(i) KPCL to check settings of LBB protection in all relays from which
it was implemented, and ensure that their configuration, logic, and
timing are in order at their 220 kV Kadra PH.
(ii) KPCL to furnish details regarding the existing LT auxiliary
supply arrangement at their 220 kV Kadra PH, and take steps to
provide a suitable Auto-Main-Fail (AMF) panel for DG set to effect
its auto-starting in case of failure of LT supply.
(iii) KPCL to ensure time-sync of all relays (DR’s & EL’s) with GPS
at their 220 kV Kadra PH.
(iv) KPCL to provide stand-alone Event Logger at their 220 kV
Nagjheri PH.
KPCL
Pending
KPCL Status received vide KPCL mail dated 14.06.2017:
1. All logics checked and found normal. LBB timing checked and found
200msec as per KPTCL MRT recommendation. - Completed
2. Work Under Progress
3. New GPS System commissioned along with new numerical and
synchronised with GPS system - Complied
4. Work Under Progress
Status received vide KPCL mail dated 14.06.2017:
1. DEF settings in lines are made as per recommendations of CE(RT) &
R&D, KPTCL, Bangalore & EE(RT), KPTCL Hubli.
High set operation of DEF relays is disabled at Kodasalli end.
2. All these guidelines are incorporated by KPTCL during the replacement
of line protection relays.
3. New stand alone event logger is to be procured since spares for old stand
alone event logger are obsolete.
KPCL (i) KPCL to disable high-set operation of DEF relays
(ii) KPCL to block DEF relays whenever corresponding distance
protection relays pick up at Kodasally end on Nagjheri – Kodasalli
lines, and
(iii)KPCL to provide stand-alone Event Logger at their 220 kV
Nagjheri PH.
Bus dead occurred at 220kV Nagjheri PH due to
tripping of evacuating lines.
Pending
Tripping of 400kV Bellary TPS-
Yeramarus TPS line and
400kVYeramarus TPS - Raichur TPS
line
PendingYet to be informed55/II/19
Pending
31-08-2016 at
12:47hrs
(i) KPCL to ensure the integrity of the connecting cable/ conductor
from Generating Unit-3 to its corresponding GT breaker at their STR
PH.
(ii) KPCL to ensure the healthiness of Manual Current Regulator
(MCR) of Unit-3’s AVR at their STR PH.
(iii) KPCL to ensure the healthiness of AVR’s of all Units of STR
PH.
Spurious operation of LBB protection of line feeder
had led to tripping of 220 kV bus at Sharavathy Tail
Race power house.
9-09-2016 at
11:19 hrs
Complete outage of 220 kV Sharavathy
Tail Race PH
Pending
15-04-2016 at
15:36 hrs
KPCLDuring testing of retrofitted distance protection in
400kV Raichur-2 feeder, LBB protection trip DC got
extended to Bus trip. This resulted in tripping of
220kV bus at RTPS and all connected 220 kV
elements. Unit-4 which is connected to 400 kV Bus
got tripped due to tripping of Station Utility
Transformer that is connected 220 kV bus
1.KPCL to properly configure the distance relays at YTPS end on
both YTPS – BTPS line and YTPS-RTPS line with specific focus on
reaches and timings of Zone-2, Zone-3, and Zone-4 (reverse).
2.KPCL to ensure the healthiness of Direct Trip circuits and relay
coils at YTPS.
3.KPCL to ensure time sync of DR’s and EL’s at YTPS with GPS.
Triggering incident was failure of R-phase CT of
400/220kV ICT-1. 400kV YTPS-RTPS line got
tripped from YTPS end. 400kV RTPS-
Mehaboobnagar line tripped on a B-phase to earth
fault.
Complete outage of 220 kV Nagjheri PH
of KPCL.
Multiple tripping at 400 kV Raichur TPS
Station
Status received vide KPCL mail dated 10.07.2017:
Two Bus operation for 220kV bus is being carried out whenever required.
However scheme for tripping of one bus during LBB/fault and maintaining
the other bus intact by tripping B/C breaker will be taken up in R&M
works.
54/II/13
58/I/2 (GD)
58/I/5 (GD)
Complete outage of 220 kV Kadra power
station of KPCL
1.KPCL to enable zero-sequence compensation feature, if not already
done, in all differential relays of transformers at RTPS.
2.KPCL to examine in detail the reasons for SOTF operation at RTPS
end for the fault on RTPS-Veltoor line, and if required relay
(configuration) settings at RTPS end may be suitably got revised with
the help of their OEM.
3.KPCL to take steps to enable auto-reclose for the Tie-CB’s in the
dias containing Munirabad and Veltoor (Mehboobnagar) at RTPS.
58/I/3 (GD)
Tripping of Units at Raichur TPS In view of the availability of two buses along with healthy bus-
coupler at 220 kV RTPS, KPCL is recommended to put in service the
double-bus operation at 220 kV RTPS by suitably distributing loads
within 15 days.
Annexure-II
Page 7 of 33
a) Trip coil-1 and Trip coil-2 circuit (including cable from protection panel
to GCB Marshaling Box)of GT Breakers of Unit 03 and 04 checked found
ok.
b) Integrity of Connecting cable/conductor from Generating unit no.3 and
also to its corresponding GT Breakers inspected and found ok.
c) Regarding Spurious operation of Unit No.04 LBB relay and its
timer.Checked the operation of the LBB overcurrent relay with its external
Timer for repeated correct operations, it was found that LBB Timer was
giving correct timing operation for 1 in 3 operations only i.e. for one of the
operation it was operating within 40ms compare to set value(200ms) hence
declared as faulty and the same has been replaced with new one later
operation of the new Timer checked and found ok.operating for >200mse
only. With this cause for spurious operation of LBB and resulting in
complete outage of STRP has been identified and solved -----
Completed
2. In Unit -3,MCR is working satisfactorily.it is to clarify that problem was
existing in Unit No.4 AVR manual channel reference value of Generator
.The Same has been replaced with spare one. Manual channel AVR is
found to be Ok. ------Completed
3. All the units AVR's Healthyness checked and found Ok. -
-----
Completed
4. Presently at GPH,no stand alone Event logger exists. Since the subject
requirement pertains to all the Generating units and in view of
Standardization of the complete system, Networking of numerical relays
carried out and events are availble in networking system..
(i) KPCL to check and correct configuration settings of LBB
protection in all relays from which it was implemented, at their 220
kV Varahi PH.
(ii) KPCL to provide stand-alone Event Logger at their 220 kV STR
PH.
KPCLLBB protection operated and caused bus shut down at
Varahi PH
Pending
21-01-2017
at 00:38 hrs
12-09-2016 at
14:47 hrs
KPCL
Partial disturbance occurred in central Kerala grid due
to overloading and tripping of 220 kV lines. Loss of in-
feed to 220 kV Kalamassery, 220 kV Brahmapuram,
220 kV Ambalamugal, 220 Pallom & 220 kV Kochi
occurred. Generation at Neriamangalam, Panniar,
Chengulam and Pallivasal also got affected during the
incident.
(i) SLDC, KSEB to put in place proper mechanism to ensure adequate
load-generation balance is maintained in their control area at all
times, and due vigilance is exercised in operating an already depleted
transmission network.
(ii) KSEB to put UFR in service at New Pallom end on 220 kV New
Pallom – Amabalamugal line as part of Kudankulam Regional
Islanding Scheme.
KPCL
Status received vide mail dated 10.07.2017:
1. Furnishing FIR & TR of the tripping events as per the formats provided
by SRLDC.
4. Refered to OEM for the tripping of Tie CB of Munirabad line on SOTF
protection.
Pending
Status received vide mail dated 14.06.2017:
LBB Protection system is in Bus bar Protection Panel.The Configuration
settings are checked.They are as follows.
Minimum operating primary current is 160A
Stage I:Issue of Retrip to the feeder is 100ms after the action of main
distance protection Relay/initiation of LBB.
Stage II:Bus bar LBB Trip -200ms.
Total time of LBB trip is 300ms from the time of occurrence of Line Fault.
Disturbance in Kerala system Yet to be informed Pending
(i) KPCL to adopt the following VT fuse-fail logic for all 220 kV
lines emanating from NPH:
“Under VT fuse fail condition, distance protection shall normally be
kept blocked. However, upon detection of a fault (sensed by negative
sequence component), blocking of distance protection shall give rise
to operation of its inherent Over-Current protection set with a definite
time delay of 500 msec”.
(ii) KPTCL/ KPCL to revise Zone-2, Zone-3 and Zone-4 (reverse)
timings of DPR of all 220 kV lines emanating from Nagjheri PH in
line with Ramakrishna Committee guidelines.
Triggering event was the fault on 220 kV Nagjheri
–Kodasalli line-2. Both buses of 220 kV Nagjeri
power station of KPCL got
de-energized.
62/I/1 KPCL Status received vide mail dated 14.06.2017:
1. Already settings are discussed with EE(RT), Hubli and soon relays will
be tested for VT fuse fail condition.
2. Timings of Zones were set as per the recommendations of CE(RT) &
R&D, KPTCL, Bangalore & EE(RT), KPTCL, Hubli.Regarding revision
of timings will be carried out in co- ordination with EE(RT), KPTCL,
Hubli.
Pending
16- 03-2017 at
01:18 hrs
Bus-2 B-Ph differential bus bar protection operated
at 400 kV RTPS end, tripping all the main breakers
connected to Bus-2
1. KPCL to start furnishing FIR and TR of their tripping events as
per the formats provided by SRLDC.
2. KPCL to check earth-mat resistance for 400 kV switchyard and
ensure that it is within prescribed limits.
3. KPCL to set right operation of SER in C&I Control Room of Unit-
4.
4. KPCL to furnish action taken w.r.t. tripping of Tie-CB of
Munirabad line on SOTF protection. OEM report, in this regsrd, may
be furnished.
PH.
(iv) KPCL to provide stand-alone Event Logger at their 220 kV STR
PH.
15-09-2016 at
14:06 hrs
63/II.10 Multiple trippings at 400 kV RTPS
substation of KPCL
58/I/7 (GD) Complete outage at Varahi Hydro Power
Station
58/I/6 (GD)
Complete outage of 220 kV Nagjheri
substation of KPCL
Annexure-II
Page 8 of 33
65/II/9 Tripping of 400/220 kV ICT-1 at BTPS 13-05-2017 at
19:41 hrs
ICT-1 got tripped on operation of LV side earth fault
protection during R-phase to earth fault in 220 kV
BTPS-Lingapur line
1. KPCL to review the need for providing separate non-directional
sensitive earth fault protection for ICT’s at their BTPS station, and
take steps to disable the same.
2. For 220 kV BTPS –Lingapura line, KPCL to resolve issues relating
to PLCC carrier communication, and put A/R into service.
KPCL Yet to be informed Pending
65/III/2 Tripping of 400 kV Hiryur-BTPS line-1 06-05-2017
at 14:01 hrs
Y-phase to earth fault had occurred in line. Direct
trip was sent from BTPS to Hiryur end.
KPCL to introduce suitable delay (say, 3 sec) for UVR tripping, and
disable sending of DT to the other end on UVR operation at their
BTPS station.
KPCL Yet to be informed Pending
1. PCSC forum recommended KPTCL to replace the old static
distance protection relays with numerical relays.
2. PCSC forum also requested KPTCL to provide a broken conductor
alarm indication in Control Room.
3. Standing instruction needed to be given to the all substation
personnel for not changing the relay settings without approval of
RT/MRT wing.
Fault had occurred in 220kV
Mahalingapura-Narendra line-2. Due to the failure of
relay operation at Mahalingapura, breakers at remote
end tripped which resulted in bus dead condition.
PendingMail received on 27-05-2015 (KPTCL) & 29-07-2015:
1.Existing Back up relays will be replaced by numerical type distance
relays.Procurement is in tendering stage.
2. Completed.
3. Completed.
KPTCL Mail recieved on 23-01-2016:
1. Existing back up relays will be replaced by Main-2 protection. LOI
issued M/s Alstom for taking up the works.
KPTCL Mail Recieved dated 25-05-2016:
Under the Scope of R&U. The work will be taken up by M/s Alstom
shortly.
KPTCL Mail Recieved dated 25-04-2017:
1. ALSTOM make P442 type Numerical relays are supplied to the site,
replacement of M-1 relays(OPTIMHO) by new relays will be taken up
shortly
KPTCL25-10-201438/GD/3.1 GD-1 at Mahalingapura Substation of
KPTCL
66/ III/ 1 For the line under consideration, KPCL to carry out the following:
(i) End-to-end communication for DT/ permissive & other signals
may be ensured by testing at both the ends.
(ii) Healthiness of PLCC system components (hardware and software)
at both ends shall be checked and faulty components shall be repaired/
replaced.
R-phase to earth fault had occurred in line. Line did
not auto-reclose from both ends.
05-06-2017 at
19:48 hrs
Tripping of 400 kV BTPS-YTPS line KPCL Yet to be informed Pending
Annexure-II
Page 9 of 33
Mail received on 27-05-2015 & 29-07-2015:
1. C&R panels of 500MVA ICT 1&2 will be replaced under scheduled
R&M works.
2. O&M personnel are instructed to take sufficient care in order to avoid
unwarrented trippings. --- Completed.
KPTCL mail received on 23-01-2016:
1. New C&R panels(with numerical relays) erected for 500MVA ICT-1
&2 under R&M work, which will be commissioned shortly.
KPTCL mail received on 25-05-2016:
1. New C&R panels(with numerical relays) erected for 500MVA ICT-1
&2 under R&M work, which will be commissioned shortly.
KPTCL mail received on 25-04-201:
1. New CRPs mounted in bay KIOSK commissioned under R&M works.
Triggering incident was B-phase to earth fault in
220kV Ambewadi- Nagzari line-1. B-pole of breaker
did not open at Ambewadi end. LBB protection not
available at Ambewadi end. All elements tripped on
Zone-2 from remote ends.
40/I/1
220kV Sedam-
Tandur line
Line tripped on Yphase to earth fault from both the
ends
20-12-2014
at 22:20 hrs
Pending
KPTCL Pending
39/I/5 Tripping of 400/220kV
ICT-2 at Hoody
substation of KPTCL
Suspected mal-operation of 220kV side Rphase
over current relay
01-12-2014
40/IV/1 Pending
KPTCL1. PCSC forum recommended KPTCL to replace the relay with a
different make.
2. KPTCL was also requested to train the O&M personnel
adequately before performing any maintenance works to avoid such
unwanted trippings.
1. Till the completion of R&M works for bus bar and LBB protection,
KPTCL shall explore the possibility of having split bus operation at
Ambewadi and submit the details of the same to PCSC forum.
2. KPTCL shall provide the details of the tripping of Supa hydro
station connected downstream from 110 kV bus.
22-12-2014 at
21:22 hrs
Mail received on 28-04-2015:
1. In view of operating 220kV Ambewadi SS in split bus mode, action is
being taken up by KPTCL. Problem in the 220kV bus coupler breaker is
attended and isolator overhauling work is under progress. Spilt bus
operation at Ambewadi will be made possible at the earliest.
2. ICT Protection system at Ambewadi and trippings occured at Supa GS
during the instance is checked up and remedial measures already furnished
in this regard.
---- Completed
Mail recieved on 29-07-2015:
1. Action is being taken by KPTCL for operating Ambewadi in split bus
mode. Problem in bus coupler breaker is attended.Isolator overhaulling
work is completed.PTs are already provided to 220kV Bus-II. After
commissioning of Bus-II PTs, Ambewadi can be operated in split bus
mode. Pending works will be completed within a months time.
KPTCL mail recieved on 23-01-2016:
1. Bus-II PTs yet to be commissioned.Planned to complete before end of
April-2016.
KPTCL mail recieved on 25-04-2017:
1. Yet to be attended
GD-1 at 220kV Ambewadi Station of
KPTCL
KPTCL was requested to explore the possibility of providing A/R
feature to this line and submit the remedial measures to the PCSC
forum.
Mail recieved on 29-07-2015:
Carrier protection is being restored for 220kV Sedam-Tandoor line at
Sedam end. After restoring the carrier protection , AR will be enabled.
KPTCL mail recieved on 23-01-2016:
Carrier protection is being restored for 220kV Sedam-Tandoor line at
Sedam end. After restoring the carrier protection , AR will be enabled.
KPTCL mail recieved on 25-05-2016:
SEE,SCADA to update the latest status
KPTCL mail recieved on 28-06-2016:
Action is being taken to restore carrier protection.AR will be enabled once
carrier signal is restored.
KPTCL
Annexure-II
Page 10 of 33
Pending
PendingKPTCL
Complete outage of 220kV Ambewadi
substation of KPTCL
42/I/2 (GD)
27-09-2015 at
4:23:17 hrs
Fault in 220kV Ambewadi-Nagjheri line-2
KPTCL
KPTCL
48/I/2 (GD) All connected 220kV lines and transformers were
taken on 220kV North bus as South bus was under
shut down for conversion of strung bus to rigid bus
and isolator replacement under R&M works. Failure
of HV side Y phase CT of 150MVA Transformer-3
occurred at Peenya Substation which resulted in
operation of Differential and HV REF protection. The
failure of CT also resulted in a 220kV bus fault in
North Bus.
42/I/1 (GD)
41/I/4
Complete outage of 220kV Sedam
substation of KPTCL
15-02-2015 at
14:24 hrs
Complete outage of 220kV Peenya
Substation in Karnataka
R-Phase to ground fault occurred on 220kV Sedam-
Shahpur line. Fault not cleared from Sedam end due to
stuck-breaker condition. While the Sedam- Sahapur
line tripped from Shahapur end in Zone-1, the other
220 kv lines from Sedam tripped at remote ends in
Zone-2. This caused complete outage of 220kV Sedam
substation.
KPTCL
Mail received on 27-05-2015:
1. Bus Bar protection will be provded under R&U.
2. A/R yet to be enabled.
Mail received on 29-07-2015:
1. Procurement of Bus bar and LBB protection is in the final tendering
stage.
2. Action is being taken to restore the carrier protection for 220kV Sedam-
Tandoor line. AR will be enabled after restoration of PLCC.
KPTCL to revise distance relay settings at Nelamangala end for 220
kV Nelamangala – Hebbal - Peenya line – 1 for the effective line
length of 17 km. These new settings can be appropriately reviewed as
and when the tie-arrangement at Hebbal is done away with.
1. KPTCL to provide Bus Bar protection and LBB protection at
Sedam S/s and furnish the status of their implementation to PCSC
forum.
2. KPTCL to implement A/R feature on 220 kV Sedam-Tandur inter-
state line.
Mail received on 28-04-2015:
Procurement of Bus bar and LBB protection is in the final tendering stage.
2. Action is being taken to restore the carrier protection for 220kV Sedam-
Tandoor line. AR will be enabled.
Mail received on 29-07-2015:
1. Procurement of Bus bar and LBB protection is in the final tendering
stage.
2. Action is being taken to restore the carrier protection for 220kV Sedam-
Tandoor line. AR will be enabled after restoration of PLCC.
KPTCL mail received on 23-01-2016:
1. Bus bar protection panels pocured and erected at Sedam. Wiring ,
testing ,commissioning is being taken up.Planned to complete by April
2016.
2. Action is being taken to restore the carrier protection for 220kV Sedam-
Tandoor line. AR will be enabled after restoration of PLCC.
Pending
KPTCL mail received on 25-05-2016:
Presentl 220kV Nelamangala -Hoody(i.e. nelamangala-Peenya-Hebbal -
Hoody line is made LIILO at Yelahanka sub station and breaker at
Peenya is kept open, necessary modification in distance relay settings
adopted for new configuration.
Pending
PendingKPTCL mail received on 23-01-2016:
Will be complied in a months time.
30-09-2015 at
10:41 hrs
Outage of 220kV Ambewadi station in
Karnataka
12-03-2015 at
7:51 hrs
Fault occurred in 220kV Sedam-Shahpur line
48/I/3 (GD) KPTCL to fast-track providing A/R on all 220 kV lines emanating
from Ambewadi SS to prevent Station shut-down on temporary faults.
06-08-2015 at
4:51 hrs
220kV RTPS-Lingasugur line-2 tripped at TPS end on
operation of distance
protection zone-1. 400/220kV ICT-2 got tripped on
operation of earth fault
protection. 220kV RTPS-Lingasugur line-1&3 tripped
on distance protection zone-2 and zone-3
respectively. Due to tripping of ICT-2, the running
units got overloaded and it was mentioned that under
frequency occurred as units are on load control. The
Units got tripped on under frequency.
KPTCL to activate non-directional Over Current protection with a
time delay of 600-800 msec for Fuse
failure condition at Lingasugur.
KPTCL Status received vide KPCL mail dated 10.07.2017:
LV earth fault relay had an additional default E/f setting having a definite
time which resulted in tripping of ICT-2 and the same was rectified and
already complied.
Pending
1. KPTCL shall provide A/R feature on Ambewadi – Ponda 220 kV
D/C inter-state line.
2. Till the completion of R&M works for bus bar and LBB protection,
KPTCL shall explore the possibility of having split bus operation at
Ambewadi and submit the details of the
same to PCSC forum.
Tripping of Unit-1&2
along with 400/220kV
ICT-2 at Raichur TPS
Complete outage at 220kV Sedam
Substation of KPTCL (GD-1)
220kV Ambewadi-Nagjheri line-2 tripped on B-phase
to earth fault. This resulted in loss of supply to 220kV
Ambewadi bus. 220kV Ambewadi-Ponda line-1&2
were hand tripped after deenergization of bus at
Ambewadi.
KPTCL
1. KPTCL to provide Bus bar and LBB protections for 220 kV
bus at Sedam S/s.
2. KPTCL to implement A/R feature on 220 kV Sedam-Tandur
inter-state line.
27-01-2015 at
8.00 hrs
Mail received on 29-07-2015:
1. Procurement of Bus bar and LBB protection is in the final tendering
stage.
2. Action is being taken to restore the carrier protection for 220kV Sedam-
Tandoor line. AR will be enabled after restoration of PLCC.
47/II/13
Annexure-II
Page 11 of 33
52/I/3 (GD) Complete outage of 220kV Shimoga
substation
22-02-2016 at
15:03 hrs
220kV Bus Bar protection operated during failure of
R phase CT in DVG-2 line bay.
KPTCL to operate 220 kV Shimoga on multi-bus operation under
normal conditions, put it on single-bus operation only under
emergency conditions.
KPTCL KPTCL Mail received dated 25-04-2017:
Replacement of existing BBP by new BBP with 4 zone protection is being
taken up under R&U.
Pending
56/II/6 Tripping of 220kV Ambewadi-Ponda
(Xeldam) line-1
10-06-2016 at
13:33 hrs
Line tripped on Y-E faut due to DPR, Z1 operation KPTCL to keep A/R for Ambewadi – Ponda (Xeldam) line-1 in
service with immediate effect.
KPTCL Yet to be informed Pending
59/II/13 Tripping of 220 kV Bidadi (PG) - Bidadi
lines - 1&2
02-10-2016 at
10:32 hrs
Line-2 tripped in DPR, Zone-2 and Line-1 tripped on
operation of E/F protection from Bidadi end.
KPTCL to resolve PLCC carrier communication issues on 220 kV
Bidadi – Bidadi-PG D/C lines, and subsequently restore Zone-2
timing to normal values.
KPTCL Yet to be informed Pending
53/I/1
1.KPTCL to take steps to provide busbar protection at their 220 kV
Chikkodi inter-regional substation, and furnish a time-line for the
same.
2.KPTCL to review distance protection settings for 220 kV Chikkodi
– Kudachi line.
3.KPTCL to furnish equipment failure report of the current incident to
PSE&TD Division of CEA with a copy marked to SRPC.
Yet to be informedKPTCL
KPTCL Mail received dated 25-05-2016:
SEE, RTC, Bangalore to update the status
KPTCL Mail received dated 28-06-2016:
Providing numerical bus bar protection to 400kV buses and GPS time
synchronising equipment at Guttur is considered under R&U. Work is
awarded to M/s Alstom, execution will be taken up shortly.
KPTCL Mail received dated 25-04-2017:
GPS and accessories will be supplied during May 2017, expected to
complete the work within a month after supply of materials
For the line under consideration, the following shall be carried out by
KPTCL in coordination with
PGCIL (SR-II):
(i) End-to-end communication for DT/ permissive & other signals
may be ensured by testing at both the ends.
(ii) Healthiness of PLCC system components (hardware and software)
at both ends shall be checked and faulty components shall be repaired/
replaced.
KPTCL
KPTCL
Yet to be informed
KPTCL
Line tripped at Hiryur end due to direct trip receive
and was holding from Guttur
KPTCL Mail received dated 25-05-2016:
SEE, RTC, Bangalore to update the status
Multiple tripping at 400kV Guttur sub-
station
17-01-2016 at
18:53 hrs
49/I/1.3 (GD) 1. KPCL to provide A/R on all 220 kV lines emanating from Nagjheri
PH.
2. KPTCL to provide A/R on all 220 kV lines emanating from
Ambewadi SS.
Failure of Lightning Arrestor of Y-phase Line Reactor
of 400kV Guttur-Hiriyur line-1 and line tripped on
distance protection Zone-1. Bus-bar protection of
400kV Bus-2 at Guttur substation also got operated
during the event sensing this through fault. 400/220
kV ICT-1 & 2 at Guttur, 400kV Kaiga-Guttur-2,
400kV
Guttur-Narendra-2, 400kV Guttur-Hiriyur-2 and
400kV Guttur-Munirabad which are on 400kV Bus-2
got tripped during the incident. 400kV Guttur-
Narendra-1 which was on Bus-1 also tripped at the
same time.
220kV Peenya-Nelamangala-3 tripped on B-E fault at
both ends. At the same time, 220kV Peenya-
Nelamangala-4 tripped on R-Y fault only at
Nelamangala end, and was in service from Peenya
end. Due to tripping of these two lines, 220kV Peenya-
Nelamangala-2 tripped on overcurrent protection.
KPTCL to furnish a report on the tripping of 220 kV Peenya-
Nelamangala line-4 Nelamangala detailing the remedial measures
taken including the settings adopted for Z1B (Zone extension) and
Power Swing Block.
Pending220kV Nagjheri-Ambewadi line-1 tripped at 13:33
hrs due to B phase to earth fault. Ambewadi was
radially fed from Nagjheri power station through
220kV Nagjheri-Ambewadi line-2. Tripping of this
line caused 220kV Bus shut down at Ambewadi and
remaining lines and transformers were hand tripped
Pending
Pending
Pending 1. KPTCL to configure all DR’s and EL’s at 400 kV Guttur SS so
that they will also get triggered for BBP operation.
2. KPTCL to ensure time-synchronization of all DR’s and EL’s with
GPS at their 400 kV Guttur SS.
KPTCL
Triggering incident was failure of B-ph PT of 220kV
Bus-2 (western bus) at 220KV Chikkodi substation.
220KV Chikodi- Belgaum-I line tripped on DEFR
(Inst), 220KV Chikkodi-Kudachi line tripped on
Distance protection and also 100MVA transformer-2
tripped on E/F protection.
Tripping of 400 kV Guttur-Hiryur line-1 10-10-2016 at
3:15 hrs
Complete outage of 220kV Ambewadi
Substation of KPTCL
29.10.2015 at
14:34 hrs
Complete outage of 220kV Peenya
Substation of KPTCL
01-07-2016 at
03:03 hrs
Tripping of 220 kV Chikkodi-Mudshingi
and 220 kV Chikkodi-Talandage lines
51/II/21
16-03-2016 at
11:39 Hrs
57/II/1
59/IV/4 Yet to be informed Pending
Annexure-II
Page 12 of 33
62/II/3 Tripping of 220 kV Bus 2 and connected
elements (220kV HAL #1 and 2, 400/220
kV ICT- 1, 2 and 220/66 kV ICT-2) at
400/220 kV Hoody substation of KPTCL
(Load loss : 590 MW)
09-01-2017 at
23:06 hrs
Failure of R-phase CT of 220/ 66 kV transformer-2 at
220kV Hoody end resulted in a bus fault in 220kV
Bus-2. Fault was cleared by backup protection of
ICT's (220kV lines were being radially operated) due
to absence of busbar protection
1. KPTCL to provide Busbar protection at their 220 kV Hoody SS at
the earliest.
2. KPTCL to furnish an Equipment Failure Report on CT failure to
CEA with a copy marked to SRPC.
KPTCL KPTCL mail received dated 25.04.2017:
Numerical BBP is being provided under R&M works
Pending
64/II/9 Tripping of 400/ 220 kV ICT-2 and 3 at
Hoody substation of KPTCL
26-04-2017 at
15:40 hrs
ICT-2 tripped on suspected mal-operation Oil surge
relay of B-phase Transformer. ICT-3 tripped due to
overloading.
KPTCL to put in place a suitable SPS at their 400/ 220 kV Hoody SS
that takes care of over-loading of the other ICT when one ICT out of
ICT’s – 2 & 3 trips at the earliest, and furnish the details of
implemented SPS to PCSC forum.
KPTCL Yet to be informed Pending
65/II/17 Tripping of 400/220 kV ICT - 1 & 3 at
Hoody substation of KPTCL
(Load Loss: 750 MW)
26-05-2017 at
12:30 hrs
R phase limb of ICT-1 bank pre-close supervision
contact of trip coil -2 had arc over. ICT-3 got tripped
on over-loading
KPTCL to furnish compliance report on the recommendations given
in PSAG-18 meeting to PCSC forum.
KPTCL Yet to be informed Pending
Complete outage of 220kV Ambewadi
station of KPTCL and 220kV Nagjheri
of KPCL
Complete outage of 220kV Nagjheri
power station and 220kV Ambewadi
substation of KPTCL
51/I/3
KPCL/KPTCL
KPTCL Pending
ICT-3 tripped due to operation of back-up earth fault
protection during fault in 220kV RTPS-Raichur line-
1.
KPCL/ KPTCL to check the ICT’s back-up (high-set) protection
settings, and ensure that they operate with a time delay of 100 msec.
KPCL/ KPTCL
Yet to be informed
Ambewadi Narendra line-2 tripped on fault and
220kV ambewadi Narendra line-1 tripped due to over-
loading. Running Units at Nagjheri also tripped during
the event due to tripping of evacuating lines
PendingStatus informed during Special Meeting held on 03.06.2016:
1. KPTCL informed that the matter had been taken up with concerned Line
Operation and Maintenance wing to carry out corridor clearance and
maintenance as per schedule to avoid frequent line faults in this corridor. A
letter had also been addressed to Chief Engineer, Bhagalkot zone, to ensure
lines in & around Kali complex are maintained in healthy condition. ---
Completed
2. KPTCL assurd that the final modified SPS would be implemented at
Nagjheri PH at the earliest. ------ Pending
3. KPCL informed that Nagjhari- Kodasalli Lines 1 & 2 had been kept in
service since 23.05.2016 @ 08.06hrs. ---- Completed
KPTCL Mail received dated 28-06-2016:
Modifications to be carried in Nagzari SPS logic is submitted to
SRLDC/SRPC for verification and approval
Status received vide KPCL mail dated 14.06.2017:
1. Will be reviewed in consultation with EE(RT), KPTCL, Hubli.
2. Both the lines are in charged condition.
KPTCL mail received dated 25.04.2017:
Numerical BBP is being provided under R&M works
KPTCL to provide numerical Busbar Protection at their 220 kV
Somanahalli SS at the earliest.
Tripping of 400 kV Neelamangala-
Hoody line-1
KPTCL to carry out the following for the line under consideration:
(i) Healthiness of PLCC system components (hardware and software)
at both ends shall be checked and faulty components shall be repaired/
replaced.
(ii) End-to-end communication for DT/ permissive & other signals
may be ensured by testing at both the ends.
PendingTripping of 220 kV South Bus and
connected elements (220kV HSR, 220kV
Nagnathpura, 220 kV Harohalli, 220 kV
Subramanyapura, 220 kV Tataguni, 220
kV Mallur and 400/220kV ICT-2 and 3)
at 400/220kV Somanhalli substation of
KPTCL
(Load loss: 850 MW)
20-01-2017 at
14:34 hrs
Triggering incident was fault in 66 kV Somanahalli -
Bannerghatta line and fault was cleared by operation
of Back-up OCR at Somanahalli end.
15-02-2017
at 13:44 hrs
Line tripped at Hoody end on direct trip receive and
was holding from Neelamangala end.
Tripping of ICT-3 at Raichur Substation Pending
1. KPCL to furnish a report on the reasons for Unit-6 tripping at
Nagjheri PH.
2. KPCL/ KPTCL to modify suitably the SPS at Nagjheri Power
House such that it would also factor in the over loading of Ambewadi-
Narendra lines.
3. KPCL to put 220 kV Kodasalli - Nagjheri D/C lines into service if
more than 200 MW generation from Kali Complex (with Nagheri
Contribution not less than 50 MW) is ensured on sustained basis.
Pending
15-03-2016 at
12:28 hrs
KPTCL Mail received dated 28-06-2016:
Modifications to be carried in Nagzari SPS logic is submitted to
SRLDC/SRPC for verification and approval
Status received vide KPCL mail dated 14.06.2017:
1. Tripped since there was evacuation problem and there were only two
lines NA-1 and NA-2
2. Will be reviewed in consultation with EE(RT), KPTCL, Hubli.
3. Both the lines are in charged condition.
KPTCL Mail Recieved dated 25-05-2016:
SEE,SCADA to update the status of healthiness of carrier protection of
220kV RTPS-Raichur 1 &2 lines
KPTCL Mail Recieved dated 28-06-2016:
Details sought from KPCL for review of ICT's back up (high set) proection
settings as suggested. KPCL is yet to furnish the details required to give
53/I/3 (GD)
62/IV/4
62/II/5
18-03-2016 at
14:40 hrs
22-02-2016 at
12:36 hrs
KPCL/ KPTCL 1. To avoid tripping of transmission lines on transient faults, KPCL/
KPTCL is recommended to carry out periodic patrolling of lines, and
ensure their proper maintenance by carrying out jungle/ bushing
clearance and trimming of tree branches within the RoW of
transmission lines as per the SRPC transmission line patrolling
guidelines (available under the menu item "All Uploads ! Operation
! Miscellaneous ! Transmission Line Patrolling Protocol /
Guidelines for Southern Region" on SRPC website).
2. KPCL/ KPTCL to review operation of SPS at NPH for
functionality (reduction of generation with tripping of evacuating
lines) and healthiness.
3. KPCL to put 220 kV Kodasalli - Nagjheri D/C lines into service if
more than 200 MW generation from Kali Complex (with Nagheri
Contribution not less than 50 MW) is ensured on sustained basis.
220kV lines from Nagjheri power house started
tripping from 11:00 hrs due to fault in lines. The
sequence of tripping is shown in SOE list. At 12:33
hrs, 220kV Narendra-Ambewadi lines-1&2 got
tripped which resulted in loss of evacuation path to
Nagjheri station resulting in tripping of running Units
and complete outage at Nagjhheri power station.
220kV Ambewadi station also got de-energized due to
tripping of source feeders i.e. 220kV Narendra-
Ambewadi-1&2 and 220kV Nagjheri-Ambewadi-
1&2.
53/II/1
KPTCL
Annexure-II
Page 13 of 33
56/I/3 Complete outage of 220kV Ambewadi
Substation of KPTCL.
24-06-2016 at
20:57hrs
B phase to earth fault had occurred in 220 kV
Ambewadi-Ponda line-2. Fault was cleared by
tripping of feeders from remote end
1.KPCL & KPTCL to furnish an action taken report on the
recommendations given by PSAG-16 to PCSC forum.
2.KPTCL to keep A/R for Ambewadi – Ponda line-2 in non-auto
mode (i.e., only 3-ph trip should get extended on occurrence of a fault)
till the line is closed from Ponda end.
KPCL/KPTCL Yet to be informed Pending
TANTRANSCO mail dated 12.04.2017:
1. The recommendation will be ensured. AR logic will be configured in
Distance Protection relay itself instead of BCU. OEM has been addressed.
2. Post triggering period of 2 sec. to cover AR operation in DR time scale
will be provided.
TANTRANSCO mail dated 01.06.2017 & 15.06.2017:
1. The recommendation will be ensured. AR logic will be configured in
Distance Protection relay itself instead of BCU. OEM has been addressed.
Main-1 & 2 relays will be replaced for the requirement of more output
contacts for AR logic implementation.
2. Post triggering period of 2 sec. to cover AR operation in DR time scale
is being provided.
TANTRANSCO mail dated 04.08.2017:
1. The recommendation will be ensured. AR logic will be configured in
Distance Protection relay itself instead of BCU. OEM has been addressed.
Main-1 & 2 relays will be replaced for the requirement of more output
contacts for AR logic implementation.
2. Post triggering period of 2 sec. to cover AR operation in DR time scale
is provided. ----- Completed
TANGEDCO1. TANGEDCO to take properly configure A/R logic at NCTPS-II in
that in case of unsuccessful auto-reclsoure, three-phase trip shall be
given along with A/R block.
2. TANGEDCO to configure all protection relays DR’s time scale at
NCTPS-II for a post-triggering period of 2 sec to capture events such
as complete A/R operation.
R-phase to earth fault due to de-capping of insulator.
Auto-reclose attempt was unsuccessful.
22-02-2017 at
06:16 hrs
Tripping of 400 kV NCTPS-S.V.Chatram
line-2
62/V/3
Pending
Pending
Tripping of running Units & 230kV
feeders at Tuticorin TPS of TANGEDCO
(Gen Loss: 640 MW)
62/II/7 TANGEDCO
TANTRANSCO TANTRANSCO vide their mail dated 24.06.15 informed that different
relays in Main-I & Main-II would be ensured at the earliest.
Mail recieved on 24-07-2015 ,19-02-2016 and 24-03-2016:
Different relays in Main-I & Main-II will be ensured.
Mail received on 27-04-2016:
TANTRANSCO: Not feasible in the existing SAS sub stations. Hence,
exemption may be given for these sub stations.
Mail received on 20-05-2016 ,16-06-2016,25-07-2016 & 24-09-2016 :
As discussed in the 52nd PCSC meeting, Swapping of Relays between two
stations is not feasible in the existing SAS sub stations. Hence, exemption
may be given for these sub stations.
Status received vide mails received on 10-11-2016 & 20.12.2016 &
12.04.2017 & 01.06.2017 & 15.06.2017 & 04.08.2017:
Different make Relays will be ensured for Main-I & II relays at Alamathy
TANGEDCO mail dated 15.04.2017:
1) New Relay is tested and ready for replacement.Now all 5 units are in
service.The relay will be replaced when lesser units are in service. ---
Pending
2.a)Steps are taken to renovate & mordernization of all the control panel
into Numerical based control panels. --- Pending
2.b) Since 230 KV indoor switchyard has no spare space providing dual
CT`s is not fessible. -- Completed
3) Procurement of EL & DR is under progress. --- Pending
TANGEDCO mail dated 26.04.2017:
1) Check zone New Relay is replaced on 17.04.2017 -- Completed.
2. Pending
3. Pending
settings as suggested. KPCL is yet to furnish the details required to give
the revised settings.
Status received vide mail dated 10-07-2017:
As requested by EEE (protection), CEERT, KPTCL, the details were sent
to through e-mail dtd. 08.08.2016. After receipt of reply from KPTCL will
be implemented accordingly.
Tamil Nadu
1. TANGEDCO to replace existing Check-Zone relay with a new one
possessing required performance.
2. TANGEDCO to take steps to provide numerical busbar protection
at their 220 kV Tuticorin TPS. TANGEDCO may also explore
providing dual CT’s (on either side) for all B/S breaakers at the time
of commissioning of numerical BBP, if there were no space
constraints.
3. TANGEDCO to take steps to provide for standalone Event Logger
(EL) and standalone Disturbance Recorder (DR) with automatic
downloading facility to a centralized server.
Failure of Bus Section-I Y-ph CT resulted in
operation of bus-bar protection for Bus Sections -I &
II. Running Units#1, 4 and 5, 230 kV Kayathar,
230kV Kudankulam, 230kV Sterlite, Station
Transformer-1, 2 & 3 got tripped during the incident.
Unit – 2 & 3 were not in service.
25-01-2017 at
22:36 hrs
Pending
29-03-2015 at
15:29 hrs
43/II/5 Line-2 tripped on R-phase to earth fault.
Line autoreclosed at SVChatram end and failed to
reclose at Alamathy end. Bphase to earth fault in line-
1. Line tried for A/r but due to permanent fault line
did not reclose. ICT tripped on operation of over flux
protection.
TANTRANSCO was requested to swap the relays between two
stations, so that
Main-1 and Main-2 will be of different make at each station.
Tripping of 400kV
Alamathy-
SVChatram line-1&2
and 400/230kV ICT
at S.V.Chatram
Annexure-II
Page 14 of 33
05-09-2015 at
14:04 hrs
TANTRANSCO to take suitable measures like installing more stub-
towers along 230 kV OK Mandapam – Myvady line to avoid
excessive sag due to over-loading.
TANTRANSCO48/I/1 (GD) PendingComplete outage of 230kV Palladam, 230 kV
Othakalmandapam S/s, 230 kV Coimbatore S/s, 230
kV Thudialur and 230 kV Sadayapalayam S/s
Disturbance in 220kV Tamilnadu system
Different make Relays will be ensured for Main-I & II relays at Alamathy
end.
TANTRANSCO Mail received on 19-02-2016, 24-03-2016 and 27-04-
2016:
230kV Othakalmandapam - Myvadi feeder will be made LILO at Kongal
Nagar. Line restringing will be carried out along with the above proposal.
Mail Received on 20-05-2016 ,16-06-2016,25-07-2016 & 24-09-2016:
230kV Othakalmandapam - Myvadi feeder will be made LILO at Kongal
Nagar. Line restringing will be carried out along with the above proposal.
Status received vide mails received on 10-11-2016 & 20.12.2016 &
12.04.2017 & 01.06.2017 & 15-06-2017 & 04.08.2017:
230kV Othakalmandapam - Myvadi feeder will be made LILO at Kongal
Nagar. Line restringing will be carried out along with the above proposal.
Annexure-II
Page 15 of 33
51/I/1 (GD)
12-05-2016 at
12:15 hrs
55/I/1 (GD)
TANTRANSCO mail received on 24-03-2016:
CMR relay for extending LBB protection was released and LBB extended
from Distance Protection relay directly. CT is not available in the Bus
Coupler bay for zone segregation. However, during commissioning of third
ICT, Bus section Breaker will be provided for zone segregation. Numerical
BBP relay will be provided.
Status received vide mails recieved on 27-04-2016 and 20-05-2016 ,16-
06-2016, 25-07-2016, 24-09-2016,10-11-2016 & 20.12.2016 &
12.04.2017 & 01.06.2017 & 15-06-2017:
CT is not available in the Bus Coupler bay for zone segregation. However,
during commissioning of third ICT, Bus section Breaker will be provided
for zone segregation. Numerical BBP relay will be provided.
Status received vide mail dated 04.08.2017:
Contract awarded for providing third ICT & Bus modification works to
accomodate bus coupler bay. Numerical BBP relay has been provided and
tesing under progress.
Pending
TANTRANSCO
TANTRANSCODifferent type and Make of distance protection relays to be provided for Main-I & Main-II protection for 230kV feeders at 400 kV Sunguvarchathiram & 230 kV Sunguvarchathiram
Substation [Carry-Over from Protection Audit Recommendations]
Mail recieved on 25-07-2016 & 24-09-2016:
TANTRANSCO: Auto Transformer-2 HV side Bus isolator 'C'-phase
support insulator of 230kV Southern Bus was replaced and Bus Bar
Protection scheme was restored on 12.05.2016.
Status received vide mails received on 10-11-2016 & 20.12.2016 &
12.04.2017 & 01.06.2017 & 15-06-2017 & 04.08.2017:
CT is not available in the Bus Coupler bay for zone segregation. CT latch
relay is to be provided for all bays for zone segregation.
Complete outage of 230kV Madurai S/s
(Chekanaurani) of TANTRANSCO
Pending
TANTRANSCO 1. TANTRANSCO to provide split-bus operation with bus
sectionalizer CB for their 230 kV Madurai (Chekanurani) SS.
2. TANTRANSCO to provide two main-zone operation for the
numerical BBP that is being commissioned.
3. TANTRANSCO to examine the feasibility of providing Re-Trip
feature for the LBB protection, and accordingly take steps for
implementing the same.
Fault had occurred in 230kV Madurai-Sembatty line.
Trip from distance relay was not extended to breaker
due to protection DC fail. LBB protection got
operated resulting in a busbar trip at 230kV Madurai
substation. All elements got tripped as there is a
single bus operation at 230kV Madurai S/s
19-01-2016 at
11:56 hrs
Complete outage of 230 kV
Gummidipoondi Station of
TANTRANSCO
Flashover of Auto Transformer- 2 HV
B-phase Isolator supporting insulator of 230kV
Southern Bus occurred at Gummidipoondi station. At
the time of fault, Bus bar protection relay was not in
service for pre-commissioning testing of Auto
Transformer-2. All feeders got tripped due to
operation of zone-2 protection from remote ends.
The issue was discussed in PCSC-58 meeting held on 18.10.2016, when
PCSC forum agreed to de-link the implementation of the Item from the
scope of Protection Audit Recommendations (PAR), and pursue it as part
of PCSC Recommendations.
Status received vide mails dated 10.01.2017 & 12.04.2017 &
01.06.2017 &15-06-2017 & 04.08.2017:
Different make Relays will be provided for Main-I & II relays at
Sunguvarchatram end in a phased manner.
TANTRANSCO
58
TANTRANSCO Mail received on 19-02-2016 and 24-03-2016:
Revision of Bus Bar Protection setting was carried out. The stabilizing
voltage setting was raised from 410 to 450 volts. After completing the
necessary test, the bus bar protection put in to service on 29.12.2015.
Mail Received on 27-04-2016 ,16-06-2016,25-07-2016 & 24-09-2016:
Revision of Bus Bar Protection setting was carried out. After completing
the necessary test, the bus bar protection put in to service on 29.12.2015.
Mail received on 10-11-2016 & 20.12.2016:
Provision of Bus Coupler bay arrangement was included in the
Upgradation works proposed and the same was sanctioned by MoP through
PSDF.
Numerical relay allotted and being commissioned.
Mail received on 20-02-2017:
Numerical BBP relay was commissioned on 02.02.2017
Status received vide mail dated 12.04.2017 & 01.06.2017 & 15-06-
2017:
Numerical BBP relay was commissioned on 02.02.2017.
Provision of Bus Coupler bay arrangement was included in the
Upgradation works proposed and the same was sanctioned by MoP through
PSDF.
Status received vide mail dated 04.08.2017:
Numerical BBP relay was commissioned on 02.02.2017.
Provision of CT in Bus Coupler bay is arranged and zone segregation will
be provided.
Pending
Pending
TANTRANSCO to take steps to provide double-bus operation at
their 230 kV Gummidipoondi SS.
1. TANTRANSCO to examine the feasibility of providing two main-
zone operation for bus bar protection by exploring various alternatives
like replacing existing bus-coupler CB with a hybrid bus-coupler CB
that comes with inbuilt CT, replacing existing BBP relay with another
suitable relay that supports two main-zone operation, and implement
the same.
Busbar protection got operated for a fault in 230kV
Mywadi-Anaikadavu line
21-12-2015 at
6:28 hrs
Complete outage of 230kV Mywadi
station of TANTRANSCO
50/I/3 (GD)
Annexure-II
Page 16 of 33
14-09-2016 at
11:13Hrs
Bus Bar Protection (Zone-2) of 230 kV Bus-B got
operated at Alamathy Station during fault in 230 kV
Alamathy-Korattur feeder.
58/II/17 Mail received on 10-11-2016 & 20.12.2016:
1. The Bus Bar Protection scheme will be tested for healthiness including
the CT circuits.
2. High impedance BBP relay will be replaced by Numerical relay.
Status received vide mails dated 10.01.2017 & 12.04.2017 &
01.06.2017 & 15-06-2017:
1. The Bus Bar Protection scheme was tested for healthiness including the
CT circuits. AREVA make CTs in Alamathy SS are having different
kneepoint voltage for the cores. CT cores of higher knee point voltage has
been choosen for BBP in 230kV Korattur, 230kV OPG-1 & 230kV OPG-2
feeders on 29.11.2016. ---- Completed.
2. High impedance BBP relay will be replaced by Numerical relay. ---
TANTRANSCO Pending1. TANTRANSCO to check the healthiness of BBP relay by
conducting stability test, and take appropriate remedial action like
increasing voltage settings, ensuring the healthiness of CT’s, using
CT’s with similar characteristics (equal saturation effects & equal
winding resistances) etc. at their 230 kV Alamathy SS.
2. TANTRANSCO to replace the existing high-impedance BBP relay
with its low-impedance/ numerical variant so as to accommodate
variation in CT characteristics at their 230 kV Alamathy SS.
Bus Bar Protection (Zone1) of 230kV Bus-A got
operated at Alamathy Station during fault in 230 kV
Alamathy-OPG-1 feeder.
15-09-2016 at
22:14 hrs
Multiple tripping at 230 kV Alamathy
Station
Annexure-II
Page 17 of 33
64/1/4 Complete outage of North Chennai TPS
STG-1
26-03-2017
at 23:14hrs
Tripping of evacuating lines due to fault led to
tripping of running Unit at NCTPS Stg-1
1. TANTRANSCO to take steps to complete insulator replacement
works on the 230 kV lines owned by them in NCTPS area within 6
months.
2. TANTRANSCO to take steps to implement A/R on all 230 kV lines
emanating from NCTPS-I at the earliest.
TANTRANSCO Status received vide mails dated 04.08.2017:
1. All the Porcelain insulators were replaced with Polymer insulators in
230kV NCTPS-I - Tondiarpet feeders - 1 & 2.
2. AR will be implemented on all 230kV lines emanating from NCTPS-I.
Pending
65/II/1 Tripping of 220 kV Idukki –Udumalpet
line
05-05-2017 at
17.02 hrs
Line tripped due to B-N and R-N fault in line 1. TANTANSCO to correctly configure A/R logic at Udumalpet so
that in the event of 3-ph trip being given during A/R dead-time, the
relay will not try for auto-reclosure.
2. TANTRANSCO to keep A/R dead-time as 1 sec for all 220 kV &
above transmission lines.
TANTRANSCO Status received vide mails dated 04.08.2017:
1. AR logic configuration will be checked for correct operation.
2. In all the 400kV feeders, AR dead time is kept at 1 sec. The same will
be implemented in all 230kV feeders.
Pending
2. High impedance BBP relay will be replaced by Numerical relay. ---
Pending,
Status received vide mails dated 04.08.2017
1. Completed
2. High impedance BBP relay will be replaced by Numerical relay.
66/I/1 Complete outage of 230 kV Kadaperi
Substation of TANTRANSCO.
21-06-2017 at
17:43 hrs
230kV Kadaperi –Sriperumpudur Line-1, 230 kV
Kadaperi – Kalivanthupattu tripped due to Y-N and B-
N fault. 230kV ICT - 1, 2 & 3 and other 230kV feeders
were hand tripped.
44/I/1 (GD) Complete outage of Idukki Hydro Power
Station (GD-1)
28-04-2015 at
12:30 Hrs
Mail received on 31-07-2015:
1. Reducing the sensitivity of REF protection of Unit # 4, 5, 6 at Idukki
PH: - Generation wing is planning to purchase new transformer
management relays with low impedance REF protection. Purchase
procedures initiated. ---------Pending
2. The replacement/ repair of faulty breakers are under the consideration of
Generation wing. Breakers will be replaced / repaired in a phased manner.
Unit #3 breaker was replaced with available breaker from the 220kV
IDMD feeder. The 220kV CBs of unit #2 and unit #3 will be replaced with
in two months.
3. No abnormalities were noticed in the PLCC equipment at New Pallom
station. It is kept under observation.
Mail recieved on 30-10-2015:
1. Purchase procedures is still in progress.
2. Replaced.
3. PLCC equipment Tested and found OK.
Mail recieved on 03-03-2016:
1. Even though repeated plans to have a joint inspection with M/s.ABB
who is the OEM of the relay panel for replacing the relays with numerical
ones, the same could not become successful. Finally, the inspection has
been fixed on 15.03.2016. It has been planned to replace existing REF
protection with low impedance ones after retrofitting the numerical ones of
OEM.
Mail recieved on 25-05-2016:
1.Generation wing is planning ti provide low impedance REF protection by
retrofitting numerical ABB make transformer management relay in the
existing panel. ---- Pending.
2.Faulty breaker of Unit3 has been replaced. ---- Completed.
1. TANTRANSCO to restore cut communication link on 230 kV
Kadaperi – KV Pattu line in a week’s time.
2. TANTRANSCO to review Zone-2 time settings on 230 kV Kadaperi
– SP Budur lines 1 & 2 in line with Ramakrishna Committee
recommendations.
3. TANTRANSCO to correct A/R logic such that in the event of
another fault during A/R dead-time, A/R 3-ph trip with A/R block
shall be attempted. Further, if the carrier communication medium
becomes not available, A/R shall be blocked and 3-ph trip shall be
attempted.
TANTRANSCO Yet to be informed Pending
220 kV breaker of unit-3 at Idukki Power
house flashed and bus differential protection
acted. All Generators (6Nos.) along with all
220 kV feeders tripped during the incident.
1. KSEB to reduce sensitivity of REF protection appropriately at
Idukki PH.
2. KSEB to replace/ repair the faulty breaker.
3. KSEB to check the PLCC equipment at New Pallam and inform the
remedial measures taken to PCSC forum.
Kerala
Pending
(Recommendat
ion No.1)
KSEB
66/ III/ 2 Tripping of 400 kV Alamathy-
SV.Chatram line-1
06-06-2017 at
22:03 hrs
R-phase to earth fault had occurred in line. Auto-
reclose was successful at Alamathy and breaker got
tripped at S.V.Chatram
1. TANTRANSCO to take up firmware issue of D60 relays with their
OEM, and get them upgraded appropriately.
2. TANTRANSCO to check the resistive reach settings of SV Chatram
end relays for the line under consideration.
TANTRANSCO Yet to be informed Pending
Annexure-II
Page 18 of 33
Pending
66/I/3 Complete outage of 220 kV Pothencode
substation of KSEB
11-07-2017 at
9:40 hrs
220 kV Buses – 1 & 2 got tripped due to operation of
busbar protection due to bus fault.
To ensure similar kind of events do not recur, KSEBL is
recommended to carry out the following:
1. Alignment issues w.r.t. the dedicator 89C isolator between Bus-1 &
Bus-3 and 89C isolator of Trivendrum-2 feeder between Bus-2 and
Bus-3 shall be immediately attended to.
2. Bus-Coupler CB between Bus-1 & Bus-2 shall be brought into
service at the earliest. Till this is done, Bus-Tie Isolator between Bus-
1 & Bus-2 shall be made use of as an additional parallel path to effect
changeover of Bus-1 connected elements on to Bus-2 or vice versa.
The respective connected source elements (transformers) can also be
de-energized before effecting required bus-changeover operations.
3. Since the required no. of breakers have not been provided to
smoothly effect various bus change-over operations, thermo-vision
cameras shall be used periodically to detect issues w.r.t. isolators &
breakers so as to take appropriate corrective action in time.
KSEB Yet to be informed Pending
23-08-2016
at 11:20 hrs
Triggering incident was conductor snapping in 110 kV
Kalamassery- Kaloor feeder
KSEB to take steps to provide the following at their 220/ 110 kV
Kalamassery SS:
1. Busbar protection at 110 kV level
2. Connecting 220 kV and 110 kV sides on to a common earthmat
3. Redundant DC supply for both protection (220 V) and
communication (48 V) applications
4. Stand-alone Event Logger
KSEB KSEB Mail received vide dated 17.01.2017:
1. 110 kV bus bar protection progressing ----Pending
2. Connection of 220kV earth mat and 110 kV plate earthing system
completed.---- Completed
3. Redundancy of 110V DC system in progress. Complete independent
redundancy is not practical for the time being. 48 V DC redundancy was
already there. ----Pending
4. Instead of stand alone event logger, SCADA system of 110 kV feeder is
expected to be completed by the end of 2017. SCADA system of 220kV
side will be taken up after that ----Pending
58/I/1 (GD) Complete outage of 220 kV Kalamassery
Substation
2.Faulty breaker of Unit3 has been replaced. ---- Completed.
3.PLCC equipments in the feeder were checked and found OK. ------
Completed.
Annexure-II
Page 19 of 33
08-05-2016at 4:57
hrs
Tripping of 400kV Hyderabad - N’sagar
line
55/II/5 Line tripped on operation of over-voltage protection at
Hyderabad end and Direct Trip was received at
N’sagar. Over-voltage, Stg-2 operation was observed
in EL of Hyderabad station.
1.PGCIL (SR-I) to properly configure EL’s at Hyderabad station
with time-scale resolution up to msec; further, DR’s should also be
configured for showing both Analog and Digital data with properly
defined X-axis and Y-axis scales.
2.PGCIL (SR-I) to follow the FILE Naming Nomenclature provided
by SRPC in naming various tripping files (FIR/DR/EL/TR) being
uploaded in SRLDC’s Tripping Monitor System (TMS) portal.
Yet to be informedPGCIL (SR-I)
PGCIL (SR-I & SR-II)
Pending
Annexure-II
Page 20 of 33
55/II/9 Tripping of HVDC Gazuwaka pole-2 19-05-2016 at
11:41 hrs
Pole tripped on operation of differential current
protection of east side of Pole-2
PGCIL (SR-I) to take up the issue of differential protection operation
of converter transformer on low voltage fluctuations with their OEM,
and submit a detailed report on it.
PGCIL (SR-I) Yet to be informed Pending
56/II/11 Tripping of HVDC GazuwakaPole-2 19-06-2016 at
5:20 Hrs
HVDC Pole-2 got tripped on operation of Bus
differential protection
PGCIL (SR-I) to get the tripping of HVDC Pole-2 tripping on Win-
Bus differential protection thoroughly investigated for correctness of
operation, and submit a report thereon.
PGCIL (SR-I) Yet to be informed Pending
56/III/7 Tripping of 400 kV Khammam-N’sagar
line-1
05-06-2016 at
22:41 hrs
Line tripped on B-phase to earth fault. Line auto-
reclosed successfully at N’sagar and failed to auto-
reclose at Khammam
1.PGCIL (SR-I) to configure DR & EL at N’sagar (Tallapalli) end so
that full operation of A/R is captured.
2.PGCIL (SR-I) to investigate the reasons for non-operation of A/R of
Tie-CB at N’Sagar end, and resolve them suitably.
PGCIL (SR-I) Yet to be informed Pending
58/II/13 (GI) Tripping of 400 kV Raichur-Gooty line-1
and 400 kV Gooty-Tumkur line-2
01-09-2016 at
5:17 hrs
400kV Gooty-Raichur line tripped at Gooty end only
and was holding from Raichur. 400kV Gooty-Tumkur
line-2 tripped on over voltage.
PGCIL (SR-I) to check the operation of OVR relays at their Gooty
SS, and properly configure lines’ DRs & ELs so that events pertaining
to OVR (Stage-I & Stage-II) operation (START & TRIP) get
explicitly recorded.
PGCIL (SR-I) Yet to be informed Pending
58/II/14 (GI) Tripping of 400 kV Gooty-Tumkur line-2 02-09-2016 at
21:56 hrs
Line tripped on operation of over-voltage protection at
Gooty end and Direct Trip was received at Tumkur
PGCIL (SR-I) to check the operation of OVR relays at their Gooty
SS, and properly configure lines’ DRs & ELs so that events pertaining
to OVR (Stage-I & Stage-II) operation (START & TRIP) get
explicitly recorded.
PGCIL (SR-I) Yet to be informed Pending
61/II/4 Tripping of HVDC Gazuwaka Pole-2 05-12-2016
at 15:03 hrs
Pole-2 tripped due to tripping of AC filter banks
which was due to voltage disturbance in eastern bus at
Gazuwaka.
PGCIL (SR-I) to refer the instant trippings to their OEM to ensure
that the settings adopted for pole trippings for low-voltage, power
swing, and ferro-resonance phenomena are in order and have been set
properly. A copy of the OEM’s reply in this regard shall be furnished
to PCSC forum.
PGCIL (SR-I) Yet to be informed Pending
62/II/4 Tripping of 400 kV Gazuwaka-Vemagiri
(PG) line and 400kV Vemagiri(PG)-
Nunna line
18-01-2017 at
22:03 hrs
400 kV Gazuwaka - Vemagiri (PG) line and 400 kV
Vemagiri (PG) - Nunna line got tripped due to Direct
Trip receive at Gazuwaka and Vijayawada
respectively
PGCIL (SR-I) to configure triggering of DR & EL for SF6 gas
compartment Zone trip with suitable legend.
PGCIL (SR-I) Yet to be informed Pending
63/II.11 Tripping of 765 kV Vemagiri-Srikakulam
line-1 and 765/400kV ICT-1 at Vemagiri-
PG SS
16-03-2017 at
10:23 hrs
Line-1 and ICT-1 which are in the same diameter got
tripped due to operation of Tie bay gas
compartment trip
1. Since tripping of elements on Gas Compartment Trip has been
observed frequently in the past few months at 765/ 400 kV
Vemagiri SS, PGCIL (SR-I) shall furnish a comprehensive report
detailing the remedial measures taken including OEM’s suggestions
to prevent their occurrence.
PGCIL (SR-I) Yet to be informed Pending
Tripping of 400 kV Ramagundam-
Warangal line
PGCIL (SR-I)
64/II/14
12-09-2016 at
12:03 hrs
Line tripped on Direct Trip receipt at Ramagundam
end and line was holding from Warangal end.
Yet to be informed
Yet to be informed
For the line under consideration, the following shall be carried out
by PGCIL (SR-I) in coordination with NTPC-Ramagundam:
I)End-to-end communication for DT/ permissive & other signals may
be ensured by testing at both the ends.
II)Healthiness of PLCC system components (hardware and software)
at both ends shall be checked and faulty components shall be
repaired/ replaced.
PGCIL (SR-I) Pending62/II/1
Pole-1 got tripped due to failure of auxiliary supply
changeover. 400kV Jeypore-Gazuwaka line-2 got
tripped on operation of over-voltage protection.
Pole-2 east shunt reactor got failed and this in turn
resulted in tripping of HVDC pole-2 due to Pole-2 Y
block activation. 400kV Jeypore-Gazuwaka line -1
also got tripped during the incident.
28-Apr-17 Pole-1
at 8:44 hrs and
Pole-2 at 9:07 hrs
Tripping of HVDC Gajuwaka Pole-1&2
and 400 kV Jeypore-Gazuwaka line-1&2
PGCIL (SR-I) Yet to be informed Pending1. PGCIL (SR-I) to provide fully automatic supply-changeover
scheme for Pole-1 auxiliaries at the earliest.
2.PGCIL (SR-I) to furnish a detailed report on the reasons for East
Shunt Reactor failure including remedial action taken. OEM report in
this regard also shall be shared.
05-01-2017
at 13:05 hrs
Tripping of 400kV Gazuwaka - Vemagiri
(PG) line and 400 kV Vemagiri (PG ) -
Nunna line
1. PGCIL (SR-I) to ensure time-sync of all protections relays at their
Vemagiri, Gajuwaka, and Vijayawada substations.
2. PGCIL (SR-I) to check OVR settings for correctness of operation
along with proper drop-off to pick-up ratio (> 0.97), and configure
OVR_START event in the corresponding Relay/ BCU Event Logger for
all 400 kV lines emanating from their Vemagiri (PG) SS.
Pending58/IV/1
400 kV Gazuwaka-Vemagiri (PG) line tripped on Y-E
fault. However, for 400 kV Gazuwaka-Vemagiri (PG)
line, Direct Trip was received at Gazuwaka after
250ms of occurrence of fault and fault was
persistent for 250ms. Then, Over-Voltage, Stage-1
protection operated from Vemagiri (PG) end in 400
kV Vemagiri (PG) - Nunna line and tripped it
Annexure-II
Page 21 of 33
64/III/16 Tripping of 76 5kV Kurnool-Nellore PS
line-2
27-04-2017 at
22:22 hrs
R-phase to earth fault had occurred in line. Auto-
reclose was successful at Kurnool end and breaker at
Nellore PS end tripped and did not attempt for auto-
reclose.
For the line under consideration, PGCIL (SR-I) to Configure Event
Logger (EL) to record events at msec level.
PGCIL (SR-I) Yet to be informed Pending
65/II/15 Tripping of HVDC Gazuwaka Pole-1&2 25-05-2017 at
09:45 hrs
HVDC pole-1 got tripped due to operation of South
filter inter zone protection and HVDC pole-2 got
tripped due to operation of differential protection
PGCIL (SR-I) to furnish detailed report on the events that led to
tripping of HVDC Poles – 1 & 2 including remedial measures taken
to PCSC forum. Further, the OEM report w.r.t. tripping of HVDC Pole-
2 shall also be furnished.
PGCIL (SR-I) Yet to be informed Pending
65/III/5 Tripping of 765 kV Raichur-Solapur line-
2
07-05-2017
at 19:18 hrs
Y-phase to earth fault. Auto-reclose was successful
at Solapur and breakers at Raichur end got tripped
PGCIL (SR-I) to configure Event Logger’s time-resolution up to
millisec level in all protection relays at their 765/ 400 kV Raichur SS.
PGCIL (SR-I) Yet to be informed Pending
55/II/7 Tripping of 400kV Kudgi PG (Narendra
New) - Narendra-PG line-2
18-05-2016 at
16:25 hrs
line tripped on B-phase to earth fault and line auto-
reclosed successfully from Narendra end. Line tripped
from Kudgi-PG due to operation of over-voltage stage-
1
PGCIL (SR-II) to properly configure dead-time of A/R (typically 1
sec) on all lines emanating from Narendra (PG) substation.
PGCIL (SR-II) Yet to be informed Pending
54/II/3 Tripping of 400kV Sriperambudur -
SV.Chartam and 400kV Nellore-
Sriperambudur line-1
05-04-2016 at
00:11 hrs
400kV Nellore-Sriperambudur line-1 tripped on a R-
phase to earth fault. 400kV Sriperambudur-
S.V.Chatram line tripped at Sriperambudur end only
on operation of over current protection
PGCIL (SR-II) to check and revise Pole Discrepancy Relay (PDR)
time setting appropriately based on the type of A/R scheme being
implemented at their 400 kV Sriperambudur SS.
PGCIL (SR-II) Yet to be informed Pending
54/III/3 Tripping of 400 kV Kalvindapattu-Vallur
line
10-04-2016 at
14:59 hrs
R-phase to earth fault had occurred in line. Auto
reclose attempt is unsuccessful/ auto-reclose could not
be established from provided DR/ EL.
PGCIL (SR-II) to furnish a report on the tripping event detailing the
reasons for unsuccessful A/R operation at Kalvindapattu end, and the
remedial action taken to restore A/R to normalcy.
PGCIL (SR-II) Yet to be informed Pending
55/II/17 Tripping of HVDC Talcher-Kolar pole-1 30-05-2016 at
09:49 Hrs.
Failure of main CT of AC filter (20C08A) occurred
and it in turn caused the operation of filter bank
differential protection. HVDC Pole-1 got tripped on
group Differential protection operation
PGCIL (SR-II) to take up the issue of Pole-1 tripping on Group
Differential Protection (Stage-II) due to multiple commutation failures
with their OEM, and furnish a report on it.
PGCIL (SR-II) Yet to be informed Pending
56/II/8 Tripping of HVDC Talcher-Kolar Pole-1 17-06-2016 at
16:35 Hrs
Talcher-Kolar HVDC Pole-1 got tripped on line fault
and Pole-2 went to ground return mode with 150MW
PGCIL (SR-II) to address & resolve DTPC and fibre-optic link
related issues raised by KSEB at Thrissur/ Madakathara substations,
and conduct a mock-test in coordination with KSEB to verify integrity
of signal transmission from Kolar to Thrissur/ Makadathara.
PGCIL (SR-II) Yet to be informed Pending
57/II/2 Tripping of 400 kV Mywady-Salem line-1
and 400 kV Mywady-Madurai line
PGCIL (SR-II) to furnish a report on the remedial action taken after
ascertaining the reasons for (i) non-opening of Main-CB of Mywady
– Madurai line at Mywady end on Tie-CB LBB operation, and (ii)
delay in sending DT to the remote ends after Tie-CB LBB operation.
65/III/10
03-07-2016 at
03:06 hrs
400kV Mywady- Madurai line tripped on a Y-phase
to earth fault due to agriculture fire. Tie-CB LBB
relay got operated at Mywady end and resulted in
tripping of Main breakers of 400kV Mywady-
Madurai and 400kV Mywady-Salem line-1 which are
in the same diameter.
PGCIL (SR-I) to sort out issues relating to A/R functionality/
operation for both Main-CB and Tie-CB at both Vemagiri and
Gajuwaka substations.
For the line under consideration, the following shall be carried out
by PGCIL (SR-I):
! End-to-end communication for DT/ permissive & other signals
may be ensured by testing at both the ends.
! Healthiness of PLCC system components (hardware and software)
at both ends shall be checked and faulty components shall be
repaired/ replaced.
Y-phase to earth fault. Auto-reclose was not
successful due to persistent fault. Vemagiri end had
sent a Direct Trip after un-successful Auto-reclose.
A/R attempt was observed in Gazuwaka end DR
after 3 phase trip
14-05-2017
at 16:54 hrs
Tripping of 400 kV Vemagiri - Gazuwaka
line
PGCIL (SR-I)
also got tripped during the incident.3.PGCIL (SR-I) to provide redundant AC auxiliary supply to both
Pole-1 & Pole-2 either by making use of tertiary of ICT-1 or from
external dedicated feeder
Yet to be informed Pending
PendingPGCIL (SR-II) Yet to be informed
Annexure-II
Page 22 of 33
58/II/3 (GI) Tripping of 400 kV Sriperambudur-
SV.Chatram line
14-08-2016 at
13:49 hrs
Line tripped at Sriperambudur end only on
operation of directional earth fault protection
(i) PGCIL (SR-II) to disable high-set of line DEFR’s, and
(ii) PGCIL (SR-II) to block line DEFR operation when DPR is in active
condition (has picked up) at their Sriperambudur SS.
PGCIL (SR-II) Yet to be informed Pending
58/II/5 (GI) Tripping of 400 kV Neyveli TS2-Pugalur
line and 400 kV Neyveli TS2-Neyveli TS2
EXP line
21-08-2016 at
10:35 hrs
Failure of Y-Ph tension insulator of tie feeder bay at
Neyveli TS2. Neyveli-Pugalur line tripped due to over
voltage at Neyveli TS2 and direct trip was received
at Pugalur.
PGCIL (SR-II) to check the operation of the DPR relays at Pugalur
end NLC TS2 - Pugalur line by trans-playing the event on another
healthy relay, and take suitable action including replacement of the
relay accordingly.
PGCIL (SR-II) Yet to be informed Pending
58/II/19 (GI) Tripping of 400 kV Madurai-Karaikudi
line
15-09-2016 at
03:02hrs
Line tripped on operation of OVR, Stage-I protection
at Karaikudi and Direct Trip was received at Madurai
PGCIL (SR-II) to check the operation of OVR relays at their 400 kV
Karaikudi SS, and properly configure lines’ DRs & ELs so that events
pertaining to OVR (Stage-I & Stage-II) protection operation (START
& TRIP) get explicitly recorded.
PGCIL (SR-II) Yet to be informed Pending
59/II/20 (GI) Tripping of HVDC Talcher-Kolar pole-1 10-10-2016 at
16:35 hrs
Pole-1 of HVDC Talcher-Kolar tripped due to receipt
of ‘’Pole block command from Talcher end due to
tripping Pole-1 DC filter at Talchar end. Pole 2 went
into metallic return mode after tripping of pole-1
PGCIL (SR-II) to check the correctness of non-operation of SPS
(Talcher –Kolar Trip Signal-1) in the instant case by comparing it
with the incident of tripping of HVDC Talcher-Kolar pole-1 on
05.10.2016, and furnish a report on it to PCSC forum.
PGCIL (SR-II) Yet to be informed Pending
59/II/24 (GI) Tripping of 400/220kV ICT-2 at
Somanahalli SS
24-10-2016 at
3:54 hrs
ICT-2 tripped on operation of Buchholz relay PGCIL (SR-II) to properly configure ICT protection relay DR so that
digital signals are recorded with proper names at their 400/220 kV
Somanahalli SS.
PGCIL (SR-II) Yet to be informed Pending
59/III/4 Tripping of 400 kV Salem -Udumalpet
line-2
13-10-2016 at
03:06 hrs
Line tripped on R-phase to earth fault. Line auto-
reclosed at Udumalpet end and did not reclose at
Salem
PGCIL (SR-II) to configure protection relay DR & EL for 400 kV
Salem -Udumalpet line-2 at Udumalpet end for proper time-scale
and A/R operation related events.
PGCIL (SR-II) Yet to be informed Pending
62/III/5 Tripping of 400 kV Tumkur – Bidadi line 17-02-2017
at 10:44 hrs
B-E fault. Line did not auto-reclose 1. PGCIL (SR-II) to properly configure A/R logic operation at Bidadi
end, and ensure it’s correct operation for a fault during reclaim
time.
2. PGCIL (SR-II) to ensure time-sync of protection relays with GPS at
both Tumkur and Bidadi substations.
PGCIL (SR-II) Yet to be informed Pending
62/III/6 Tripping of 400 kV Tumkur – Bidadi line 18-02-2017
at 10:36 hrs
B-E fault. Line did not auto-reclose PGCIL (SR-II) to properly configure A/R logic operation at Bidadi
end, and ensure it’s correct operation for a fault during reclaim
time.
PGCIL (SR-II) Yet to be informed Pending
62/V/1 Tripping of 400kV Vallur-Kalivandapattu
line-2
22-02-2017 at
4:55 hrs
Line tripped due to failure of R phase jumper. Two
faults observed from DR. 2nd fault cleared in 500ms
from Kalavindapattu end.
PGCIL (SR-II) to enable Trip on Reclose (TOR) at Kalavindapattu end
on all 400 kV lines emanating from it.
PGCIL (SR-II) Yet to be informed Pending
65/II/2 Tripping of 400 kV Kudgi (PG) - Tumkur
line-2 and Kudgi (PG) – Kudgi (NTPC) line-
1
06-05-2017 Kudgi (NTPC) feeder tripped at Kudgi (PG) end on
operation of distance protection R-N, Zone-1.
Tumkur feeder tripped at Kudgi(PG) end on
operation of NGR buchholtz relay.
1. PGCIL (SR-II) to sort out A/R related issues at Kudgi (PG) end on
400 kV Kudgi (PG) – Kudgi (NTPC) lines, and put A/R into service.
2. PGCIL (SR-II) investigate reasons for NGR Buccholtz trip on 400
kV Kudgi (PG) – Tumkur line-2, and furnish action taken report w.r.t.
rectifying the same.
PGCIL (SR-II) Yet to be informed Pending
58/II/16 (GI) Multiple tripping at 400 kV Kalpaka SS 06-09-2016 at
16:43 Hrs
Y-Pole breaker of Bus reactor-3 got failed during its
charging. This resulted in a bus fault in 400kV bus-1
resulting in tripping of 400kV elements connected to
Bus-1
PGCIL (SR-I) & PGCIL (SR-II) to review their Reverse Zone settings of
distance relays so as to bring them in line with Ramakrishna
Committee guidelines at all their substations in the southern region.
PGCIL (SR-I) & PGCIL
(SR-II)
Yet to be informed Pending
62/II/6 Tripping of 400 kV Trichy-Karaikudi line 21-01-2017
at 21:45 hrs
Line tripped on operation of over voltage protection
at Karaikudi end and direct trip was received at
Trichy. Voltage recorded in DR in antecedent
conditions were 245.4 kV, 243.2 kV, 253.6 kV
respectively
1. PGCIL (SR-II) to ensure OVR settings adopted for 400 kV lines at
Karaikudi SS are as per SRPC provided settings with a drop-off to
pick-up ratio > 0.97.
2. PGCIL (SR-II) to configure OVR_START event in the corresponding
Relay/ BCU Event Logger for all 400 kV lines emanating from their
Karaikudi SS.
PGCIL (SR-II) Yet to be informed Pending
Annexure-II
Page 23 of 33
NTECL400kV Vallur-Alamathy Line-2 got tripped from
Vallur end during failure of Y-phase LA in 400kV
Alamathy-Tiruvalam line. Protection at Vallur end
tried for an auto-reclose and gave a 3 phase trip.
NTECL, Vallur to furnish a report detailing the reasons for mal-
operation of Vallur end relays for a fault on Alamathy-Tiruvalam line-
1, and remedial measures taken to PCSC forum. In the report, their
preparedness for implementing line differential protection on Vallur-
Alamathy lines may also be indicated.
Tripping of 400kV Alamathy-Tiruvalam
line-1 and 400kV Alamathy-Vallur line-2
51/II/4 TANTRANSCO mail received on 24-03-2016:
3Ф Trip at 400kV Alamathy end due to DT received from vallur end for
BФ LAS bursted in Alamathy -Thiruvalam - 1 # at Alamathy end.
Mail received on 27-04-2016 and 20-05-2016:
3Ф Trip at 400kV Alamathy end due to DT received from vallur end for
BФ LAS bursted in Alamathy -Thiruvalam - Line-1 at Alamathy end.
Pending13-12-2015 at
22:42 hrs
Others
Annexure-II
Page 24 of 33
56/III/5 Tripping of 400 kV Neyveli TS-2-
Pugalur line
04-06-2016 at
16:36 hrs
B phase to earth fault occurred in line. Auto-reclose
had not operated at NLC TS-2 and DT was sent to
Pugalur end resulting in a 3 phase trip
NLC to review the necessity of providing Relay Definitive Trip, and
accordingly take steps to disable it on all lines emanating from their
generating stations.
NLC Direct trip triggering of DR wii be carried out at TS2 end during the next
planned shutdown of the Pugalur Ts2 feeder
Mail received on 22-02-2017:
Direct trip triggering of DR carried out at TS2 end for the TS2-Pugalur
feeder on 25-01-17
Pending
56/II/16 Tripping of 400 kV Gajwel-Singareni
line-2
30.06.2016 at
23:43 hrs
Tripped on 3-phase Trip at Gajwel end SCCL to configure Jaipur end relay’s EL properly so that the time-
stamp resolution is extended downwards up to milli-second level.
SCCL Yet to be informed Pending
62/III/2 Tripping of 400 kV Kaiga-Guttur line-1 06-02-2017
at 05:01 hrs
B-phase to earth fault. Line did not auto-reclose at
Kaiga end.
1. KGS to properly configure all relays DR’s time scale for a post-
triggering period of 2 sec to capture events such as complete A/R
operation.
2. KGS to ensure time-synchronization of all protection relays with
GPS in their 400 kV switchyard.
NPCIL (KGS) Yet to be informed Pending
Line tripped on B-phase to earth fault. Line auto
reclosed at Chandrapur end and did not reclose at
Ramagundam
57/II/4 1.Singareni TPS to furnish single line diagram of their switchyard
along with the Over Voltage Relay settings adopted for various
transmission lines, and to ensure that they are in line with the SRPC
provided gradings.
2.Singareni TPS to upload various tripping files (FIR/DR/EL/TR)
pertaining to a tripping event involving their station in SRLDC web-
portal within 24-hrs of occurrence of that event in compliance of
IEGC Regulation 5.2(r).
59/III/3
57/II/8 NTPC (Ramagundam)
10-07-2016 at
1:56 hrs
Line tripped at Ramagundam end on operation of over-
voltage protection. Dichipally end tripped due to
receipt of Direct Trip signal.
1.NTPC-Ramagundam to ensure correctness of operation of Over
Voltage relays by taking remedial measures like maintaining
healthiness of concerned CVT’s, setting drop-off to pick-up ratio at
0.97 & above, etc.
2.NTPC-Ramagundam to ensure time sync of their station’s DR & EL
with GPS.
3.NTPC-Ramagundam to sort out analog values indication &
overlapping issue of time-stamp in their station DR’s.
4.NTPC-Ramagundam to properly configure their EL’s so that events
are recorded with msec. resolution.
Tripping of 400 kV Ramagundam -
Chandrapur line -2
1.NTPC-Ramagundam to furnish remedial measures taken w.r.t. A/R
non-operation and unwarranted DT sending to other end.
2.NTPC-Ramagundam to configure protection relays DR’s such that
events get recorded for at leas
2000 msec post-triggering so as to cover complete A/R operation.
Tripping of 400 kV Ramagundam -
Dichipally line
16-07-2016 at
4:38 hrs
1.MAPS to furnish a detailed report on the tripping of SP Koil –
MAPS lines 1 & 2 at MAPS end with focus on the correctness of the
settings of Main-I & Main-II relays (for primary & back-up
protections) on both the lines.
2.MAPS to take steps to provide down-loading facility for DR & EL
from Main-I & Main-II relays on all 230 kV lines emanating from
MAPS.
3.MAPS, in co-ordination with SP Koil, to carry out PLCC end-to-
end testing, on SP Koil – MAPS lines 1 & 2, and ensure healthiness
of PLCC communication & carrier-aided protection.
4.MAPS to put in service Auto-Reclosure feature on all four 230 kV
lines emanating from MAPS by June, 2016.
PendingLine tripped on operation of Over-Voltage
protection at Singareni and Direct Trip was received
at Gajwel. DR & EL of Singareni was not furnished
Pending
Tripping of 400 kV Gajwel-Singareni line-
2
02-04-2016 at
17:08 hrs
NTPC-Ramagundam mail dated 09.03.2017:
1. Main-II relay replaced, Over voltage relays pickup to reset ratio is 0.98.
--- Completed
2. DR and EL are time synchronized with GPS clock.
-------- Completed
3.DR alalog overlaping issue is sloved. ---- Completed
4. ----- Pending
Yet to be informed
Pending
54/I/1 Complete outage of 230 kV S.P.Koil
Station of TANTRANSCO
B-phase CT failure occurred in 230 kV S.P.Koil -
MAPS line-1. Busbar protection got operated at
SP.Koil station. All elements except 230kV
Oragadam and 230kV Kalivandapattu got tripped at
230kV S.P.Koil station. ‘Y’ phase CT and support
insulators also got damaged.
27-09-2016 at
01:01 hrs
NPCIL (MAPS)
SCCL
PendingNTPC NTPC-Ramagundam mail dated 09.03.2017:
1. The relay will be checked in next opportunity, if required it will be
changed with new one.------------- Pending
2.DR time recording increased to 2 sec --------- Completed
Status revided vide MAPS mail dated 06.12.2016;
1. The settings given by M/s TANTRANSCO were adopted for Main –I &
Main- II relays for both the lines. The same settings were verified to be
same. Subsequently calibrated was done and no drift was observed.
--- Complied
2. From May 2016 onwards, the DR, EL and trip report are being sent by
mail to SRLDC, Bengaluru by MAPS.
--- Complied
3. Monthly maintenance of PLCC equipments is being done by M/s
TANTRANSCO. At present PLCC telephone is not working, it is being
followed up.
--- Complied
4. CVTs are planned to be procured from M/s TANTRANSCO by the end
of February 2017 and A/R will be implemented for all the lines emanating
from MAPS by July-2017 as discussed in the current SRPC meeting on
25/11/2016.
--- Pending
Annexure-II
Page 25 of 33
63/III.4 Tripping of 400 kV Gajwel-Singareni line-
2
07-03-2017 at
16:52 hrs
Line tripped on B-phase to earth fault. Line did not
auto-reclose.
1. SCCL to properly configure LBB logic for all line relays,
where A/R has been put into service, for 1-ph initiation based
on phase segregation (i.e., for the faulted phase) at their
Singareni TPS.
SCCL Yet to be informed Pending
64/II/8 Tripping of 400 kV Tirunelveli-
Kudankulam line-3
23-04-2017 at
05:56hrs
R-phase to earth fault had occurred in Tirunelveli -
Udumalpet line-2. During the incident, Tie-CB LBB
got operated at Tirunelveli end due to sluggish
operation, and tripped 400 kV Tirunelveli -
Kudankulam line-3
NPCIL (KKNPP) to configure DR’s & EL’s of protection relays at their
station for recording DT receipt event at their Kudankulam NPP.
NPCIL(KKNPP) Yet to be informed Pending
66/ II/ 17 Tripping of 400 kV Kudankulam-
Tirunelveli line-2
25-06-2017
at14:48 hrs
Line tripped on operation of overvoltage protection
at Kudankulam
66/ II/ 18 Tripping of 400 kV Kudankulam-Madurai
line
25-06-2017 at
15:02 hrs
Line tripped on operation of overvoltage protection
at Kudankulam
66/ II/ 20 Tripping of 400 kV Tirunelveli-
Kudankulam line-2
26-06-2017 at
1:38 hrs
Line tripped on operation of Over Voltage protection
at Kudankulam and Direct Trip was received at
Tirunelveli
Yet to be informedTripping of 400kV Kaiga-Guttur line-2 Line tripped on Y-phase to earth fault. Line auto-
reclosed from Guttur end and failed to re-close from
Kaiga end
1. NPCIL (KGS) to furnish an action taken report on the
reasons for A/R lock-out, and remedial action taken to rectify
the same.
2. NPCIL (KGS) to configure DR’s of line protection relays
for a post triggering period of 2 sec to capture complete A/R
operation at their Kaiga GS.
3.NPCIL (KGS) to furnish FIR & TR for tripping events as
per SRLDC provided formats.
27-03-2017 at
7:06 hrs
63/III.8 NPCIL (KGS) Pending
1. KKNPP to disable external electromagnetic type OV relays
provided in their 400 kV lines, and provide the same from the
corresponding main protection relays.
2. KKNPP to check the healthiness of line CVT’s in view of sensing of
very high voltages by them even though the grid voltage is normal
around the tripping event.
NPCIL(KKNPP) Yet to be informed Pending
Annexure-II
Page 26 of 33
34/I/6
01-01-2015 at
13:38 hrs
1. Bus bar protection shall be provided by asset owner ( i.e
KPTCL).
2. Settings for main distance protection & Overcurrent protection
shall be examined and reviewed.
3. Time synchronization of the Substation shall be ensured.
As reported directional over current relay of ICT’s
operated due to snapping of line jumper in 220kV
Lingapur line.
400kV Raichur TPS-Raichur(PG) line-
1&2, 400kV Raichur-Mahboobnagar,
Unit#7 and ICT-2 at RTPS tripped
during the incident. B phase to earth
fault had occurred in 400kV Raichur
TPS-Raichur line-1
1. KPCL to review REF setting (DMT or IDMTL) for unit-7 by first
week of April, 2015 and inform the same to PCSC forum.
2. TSTRANSCO to furnish Mehaboobnagar’s DR and EL and the
reasons for distance relay operation at their end within a week’s time.
3. PGCIL (SR-I) to rectify the issues relating to A/R operation, relay
reach (Z2), reverse reach (Z4) and SOTF auxiliary contacts within a
week’s time, and submit the actions taken to PCSC forum.
16-07-2014 Pending
(with KPTCL)
Tripping of 400
kV TALAGUPPA
– HASSAN line
40/II/3
Multiple tripping at Raichur TPS of
KPCL
42/II/18
400/220 kV ICT-1 & 2 at
MUNIRABAD
09-03-2015 at
06:36 hrs
On account of R-phase to earth fault, line tripped at
Hassan end due to operation of distance Zone-2 and
non-receipt of carrier. From D.R of Talaguppa end it
is observed that fault had occurred in Yphase.
1. PGCIL and KPTCL to ascertain the reason for the phase
discrepancy in the relay operation and take suitable remedial
measures.
2. KPTCL to check the PLCC operation at Talaguppa end and submit
the report to the PCSC forum.
Multi-Utilities
Pending (with
KPCL)
KPCL/
TSTRANSCO/
PGCIL (SR-I)
PGCIL (SR-II)/ KPTCL
KPTCL/
PGCIL (SR-I)
Mail recieved on 28-04-2015:
End to end testing of PLCC has been done and problem in the PLCC is
atttended.
Mail received on 27-05-2015 (KPTCL) & 29-07-2015:
End to end testing of PLCC has been done and problem in the PLCC is
atttended. Phase discrepancy in the relay operation is to be checked jointly.
Mail recieved on 02-09-2015 from PGCIL (SR-II):
Problem is in identification of phases at Talguppa end. To be rectified by
M/s KPTCL.
Mail recieved on 28-06-2016 from KPTCL:
The matter is reffered to the concerned Operation and maintance wing to
set right the mismatch of phases in 400kV Talaguppa-Nelamangala and
Talaguppa-Shantigrma lines at Talaguppa in cordination with PGCIL .
1. Yet to be informed by KPCL. ---- Pending
2. Mail received on 26-05-2015 from TSTRANSCO:
It is found that the main-2 ABB make REL316 type distance relay was
defective and same was replaced with MICOM P444 by M/s.PGCIL on
23.04-2015. After replacement of main-II, DR can be extracted from this
relay. For EL in to service, some field winding is pending which is being
taken up in this month. -- Complied with
3.
PGCIL mail recieved on 27-04-2016:
End to end PLCC tunning carried out.
PGCIL (SR-I) RVMD 14.07.2016:
Relay settings of all the stations in SRTS-1 were derived as per
Ramakrishna Commettee recomendations and implemented. - Complied
with.
Pending
(with KPTCL)
Mail recieved on 27-05-2015 (KPTCL):
1. KPTCL has taken action to provide bus bar protection to 220kV buses.
2. Over current relay Settings of ICTs to be reviewed by PGCIL.
Mail received on 29-07-2015 (KPTCL):
Initial Tendering stage
KPTCL Mail recieved on 23-01-2016:
Detailed estimate prepared for taking up the work. CEE, Transmission
Zone, Gulbarga will take up necessary procurement and further execution.
----------------------------------------------------------------------
1. Pending from KPTCL side.
2. Complied with as per PGCIL (SR-I) RVMD 14.07.2016, which stated
that "Relay settings of all the stations in SRTS-1 were derived as per
Ramakrishna Commettee recomendations and implemented."
3. Pending from KPTCL side.
Annexure-II
Page 27 of 33
Tripping of Unit 1 at NCTPS 24-05-2015
at 19:13 hrs
ID Fan trip
Tripping of Unit 1 at MEPL 24-05-2015
at 19:13 hrs
Coal Mill tripped
Tripping of Unit 1 at
Krishnapatnam
24-05-2015
at 19:17 hrs
Generator Protection operated
Tripping of Unit-8 at RTPS 24-05-2015
at 19:19 hrs
Tripped on Overvoltage.
Complete outage of Krishnapatnam TPS
1. All Tripped units, viz., Krishnapatinam, MEPL, Raichur, NCTPS
to submit a detailed report on this event including the remedial
measures taken to PCSC forum.
2. KPCL to check the excitation system of Unit 8 of RTPS, and
submit the remedial measures taken to PCSC forum.
KPCL/ MEPL/
APGENCO/ TNEB
Pending (with
KPCL)
APGENCO letter dated 18.03.2016:
1.SOE and SLD are attached. The DR of 405 CB is not generated during
the incident. Now the problem is identified and rectified.
--------- Completed
2.All the 3 lines i.e CHTR-2, MNBL-I & II tripped in zone
protection. The fault was in Blind zone i.e P2 side of CT, where it was
covered under Bus fault by the time fault moved on to P1 side when the
fault comes under STUB/TEED zone after 330msec all the feeders expect
CHTR-1 tripped in Zone-II and total fault persisted for 500msec before the
405 TIE CB opens and clear the fault. As a remedial the STUB protection
operation also checked and found OK.-------Completed
3.The Time Sync was missed on the day and found there was problem with
LAN Timer same was rectified. Now found OK.
-----------Completed
4.Now the DR Time scale changed to 1 sec for Pre fault and 3 sec for Post
fault and STATE of events are corrected wherever found wrong/or
misguiding during analysis.---------Completed.
5.
PGCIL-SR1 RVMD 27-04-2016:
Procurement of differential protection for 400kV NPS-NLR D/C and
400kV RCR-RTPS-D/C is under tendering.
PGCIL-SR1 RVMD 14-07-2016:
The proposal for procurement of Line differential Protections for 400kV
Raichur - RTPS-1 & 2 and 400kV Nellore - NPS - 1 & 2 lines has been
approved and tender is under technical evaluation
Pending with
PGCIL (SR-I)
08-09-2015 at
18:20 hrs
As per FIR submitted, CT damage observed in
Chitoor-Main bay (404). Main breakers connected to
bus-1 (401, 404, 407, 410) got tripped on operation of
bus bar protection. Unit-1 tripped on operation of
MFT. Unit-2 was not in service
44/I/3
47/I/2 1. APGENCO to furnish to PCSC forum (i) A3-size Single Line
Diagram of SDSTPS, and (ii) the sequence of events with time stamp
showing the protection that opened Tie-CB (405) at SDSTPS.
2. APGENCO to review STUB/TEED protection in all dias at
SDSTPS and ensure that they are configured for instantaneous
operation.
3. APGENCO to properly configure the STATE of the tripping events
so that they get recorded appropriately like TRIP/ OPERATED in
their corresponding Event Loggers.
4. APGENCO to ensure time sync of all DR’s and EL’s at SDSTPS.
5. PGCIL (SR-I) to provide line differential protection for 400 kV
NPS –Nellore-PG lines 1 & 2.
TANGEDCO vide their mail dated 07.07.2015 informed that as per the
discussion and recommendation of 44th meeting of PCSC held on
28.05.2015, a time delay of 2 Sec had been introduced for the above
tripping for all the ID fans at NCTPS-II.
MEPL vide their mail dated 14.09.2015 informed that they had
implemented 2 seconds delay for under voltage tripping of all Drag Chain
Feeder Conveyors. And this has been done for both the Units.
APGENCO letter dated 18.03.2016:
The unit not tripped on Generator protection but tripped on Economiser
inlet flow protection consequent to tripping of TDBFP on lube oil pressure
low.Before tripping , dip in voltage was observed in the LT system which
caused tripping od lube oil pumps.After the incident,Changeover scheme on
under voltage of LT System was reduced from 80% with 2 sec delay to
40% with 200msec delay
APGENCO/
PGCIL (SR-I)
Annexure-II
Page 28 of 33
PGCIL (SR-I) / KPTCL 1. For Gooty –Nelamangala line, PGCIL (SR-I) and KPTCL to
provide 3-ph trip logic at their respective ends upon detection of
PLCC link failure during dead-time of A/R operation.
2. PGCIL (SR-I) to make GPS functional at Gooty SS, and ensure
time-sync of various DR’s and EL’s with it (GPS).
3. PGCIL (SR-I) /KPTCL to furnish reason for the operation of
Backup impedance protection of the line reactor at Nelamangala end
and the remedial measures taken to PCSC forum.
1.PGCIL (SR-I) to furnish Action Taken Report on the findings of
OEM on relay mal-operation at NPS end on 400 kV NPS – NCCK
line to PCSC forum.
2. PGCIL (SR-I) to appropriately configure Station Event Logger at
NPS to record events at msec interval.
3. PGCIL (SR-I) to carry out PLCC end-to-end testing in coordination
with TPCIL for 400 kV NPS –TPCIL line.
4.PGCIL (SR-I), MEPL, SEL, TPCIL & NCC to take steps to provide
line differential protection at their respective ends on all 400 kV lines
(except Gooty line) emanating from Nellore Pooling Station, and
furnish an action plan to implement the same.
Pending
PGCIL (SR-I) mail received on 27-04-2016:
1. The firmware of REL670 is being upgraded. ------- Completed.
2. The recording of events in msec interval is being taken up with OEM.
Henceforth, for analysis purpose, we will provide larm list which has msec
time stamp. -------- Completed.
3. End to end testing of PLCC code transmision and tuning of channels
carried out. ------- Completed.
4. Procurement of differential protection for 400kV NPS-NLR D/C and
400kV RCR-RTPS-D/C is under tendering. The legends modified in
Event/alarm list. Provision of diff. rel;ay for all short lines emanating from
NPS is being taken up with our corporate. -------- Pending.
PGCIL(SR-I) RVMD 14-07-2016:
The proposal for procurement of Line differential Protections for 400kV
Raichur - RTPS-1 & 2 and 400kV Nellore - NPS - 1 & 2 lines has been
approved and tender is under technical evaluation
1.
PGCIL RVMD 27.04.2016:
A/R blocked due to failure of PLCC link. The defective PLCCcards
replaced at Neelamgala end.
PGCIL RVMD 14.07.2016:
A/R blocked due to failure of PLCC link. The defective PLCCcards
replaced at Neelamgala end. End to end testing of PLCC carried out and
PLCC link is healthy. ------ Pending
2. Gooty end Time syc unit is replaced with new one and commissioned. ----
---- Completed.
3. Yet to be informed by KPTCL. --- Pending
Running units at Thermal Powertech power Station
tripped due to tripping of 400kV Nellore pooling
station (NPS)-TPCIL line and 400kV Nellore pooling
station (NPS)-ECC line
30-12-2015 at
06:02hrs
R-phase to earth fault had occurred in Line. Line did
not auto-reclose from both ends. It was mentioned that
Y&B pole breakers at Neelamangala tripped on
operation of pole discrepancy and backup impedence
protection for line reactor got operated.
31-07-2015 at
11:44 hrs
220kV Kadra-Karwar lines-1&2 tripped
on earth fault in B-phase in zone-2.
Kaiga-Kadra line tripped at Kaiga end
only on operation of directional eath
fault protection.
12-11-2015 at
00:20 hrs
Complete outage of TPCIL power station 50/I/2
50/II/8
47/II/7 Tripping of 220kV Kadra-Karwar lines -
1&2 and 220kV Kaiga-Kadra line
Tripping of 400kV Gooty-Nelamangala
line
1. KPTCL/ KPCL to see the possibility of implementing Weak Infeed
logic with Echo feature enabled by Under
Voltage (27) element on Kadra-Karwar lines 1 &2, and implement the
same if feasible.
2. NPCIL to time-coordinate Kaiga’s DEFR settings with (i) Zone-2
settings at Kaiga, and (ii) primary protections of the lines emanating
from Kadra and Kodasalli.
3. KPCL to ensure time-sync of EL’s, and healthiness of the Fault
Locators at Kadra.
PendingPGCIL (SR-I),
MEPL, SEL, TPCIL,
NCC
KPTCL/ KPCL/ NPCIL
(KAPS)
1.
Mail recieved on 25-05-2016 from KPTCL:
Availability of week end infeed with eco feature to be confirmed by
SEE,RTC,Hubli --- Pending.
2.
Mail recieved on 03-12-2016 from NPCIL(KGS):
The 200 ms Definite time DEFR element in both Kaiga Kadra and Kaiga
Kodasally lines were disabled. IDMT DEFR is retained. The 200 ms
Definite time back up o/c element in both Kaiga Kadra and Kaiga
Kodasally lines were disabled. IDMT is retained.
------ Completed.
3. Yet to be informed by KPCL
Status received vide KPCL mail dated 14.06.2017:
1. Since PT blasted (B phase) at Karwar end, resistive over reach occurred.
hence Backup protecion operated at Kadra end (zone-2 not sensed) ---
Pending.
3.Newly commissioned micom P444 relay time synchronised with GPS
------ Completed.
Pending (with
KPTCL)
Annexure-II
Page 29 of 33
52/I/8 Complete outage of 400kV NTPL station
and CEPL Stations
14-03-2016 at
01:36 hrs
Running Units at NTPL and Coastal Energen power
station got tripped due to tripping of evacuating lines.
NTPL and PGCIL (SR-II) to furnish compliance report of the
recommendations given by PSAG-15 Committee that held its meeting
on 12-13 April, 2016 at NTPL, Tuticorin.
PGCIL (SR-II)/
NTPL
NTPL mail received on 19.05.2016:
All General Recommendations will be done in the second week of June
2016 ---------- Complied by NTPL.
Yet to be informed by PGCIL (SR-II)
Pending
[with PGCIL
(SR-II)]
56/III/4 Tripping of 220 kV Sedam-Tandur line 03-06-2016 at
21:52 hrs
Line tripped on B-phase to earth fault. Auto-reclose is
not enabled for line.
KPTCL and TSTRANSCO to fast-track providing A/R on 220 kV
Sedam – Tandur line, and furnish an action plan of providing the same
by next PCSC meeting (PCSC-57).
KPTCL/
TSTRANSCO
Yet to be informed Pending
For the line under consideration, the following shall be carried out by
TSTRANSCO and PGCL (SR-I) in co-ordination:
i.End-to-end communication for DT/ permissive & other signals may
be ensured by testing at both the ends.
ii.Healthiness of PLCC system components (hardware and software)
at both ends shall be checked and faulty components shall be repaired/
replaced.
PGCIL (SR-I)/
TSTRANSCO
Yet to be informed
Pending
1.TSTRANSCO and SCCL to check drop-off to pick-up ratio of OV
relay and ensure that it is kept at 0.97 & above.
2.TSTRANSCO and SCCL to configure respective end ‘s DR & EL
so that they get triggered on OVR protection, and record relevant
events.
3.SCCL to configure Jaipur end relay’s EL properly so that the time-
stamp resolution is extended downwards up to milli-second level.
TSTRANSCO/
SCCL
Yet to be informed
PGCIL mail received on 27-04-2016:
Being pursued with APTRANSCO
APTRANSCO mail dated on 22-06-2016:
AS maintenance being carrired out by PGCIL(SR-1), the required relay
replacement (wiring/programming) may also be carried out by PGCIL(SR-
1).
PGCIL RVMD 14.07.2016:
1. The CB problem has been attended by POWERGRID by using OEM
M/s BHEL services & POWERGRID's O&M spares.
------ Completed.
2. Being pursued with APTRANSCO to replace the faulty Event Logger at
Vijayawada (Nunna) SS. -------- Pending
APTRANSCO mail dated on 31-08-2016 & 04.03.2017 & 24.05.2017:
As maintenance being carrired out by PGCIL(SR-1), the required relay
replacement (wiring/programming) may also be carried out by PGCIL(SR-
1).
Yet to be informed
PGCIL (SR-I)/
APTRANSCO
1. PGCIL (SR-I), in co-ordination with APTRANSCO, to address the
problem with CB at the earliest opportune time.
2. APTRANSCO to take steps to replace the faulty Event Logger at
Vijayawada (Nunna) SS.
Pending
Line tripped due to operation of over voltage
protection at Vijayawada end and Direct Trip was
received at Sattenapalli end
25-12-2015 at
3:01 hrs
Tripped on 3-phase Trip at Gajwel end30.06.2016 at
23:43 hrs
19-06-2016 at
15:27hrs
220kV Sedam-Humnabad-2 tripped at Sedam on
Distance protection, Zone-2. Sedam-RTPS-1 &2 lines
tripped at RTPS end only. 220kV Tandoor inter-state
line was hand tripped due to incoming supply failure
Tripping of 400kV Sattenapalli-
Vijayawada line
56/I/2
51/II/6
Complete outage of 220kV Sedam
Substation of KPTCL.
54/IV/2 Tripping of 400kV Ghanapur-
Mamidapalli line
56/II/16 Tripping of 400 kV Gajwel-Singareni
line-2
Line tripped at Mamidipally end only on Direct Trip
receipt from Ghanapur end
30-04-2016 at
16:40 hrs
KPTCL and TSTRANSCO to take steps to provide A/R feature on
220 kV Sedam – Tandur inter-state line at their respective ends at the
earliest.
KPTCL/
TSTRANSCO
Pending
Pending
Annexure-II
Page 30 of 33
R-phase to earth had occurred in 400kV BTPS-JSWEL
line and protection issued a 3 phase trip
64/I/1 Complete outage of North Chennai TPS
STG-2
24-04-2017
at 21:02hrs
Tripping of evacuating lines due to fault led to
tripping of Units
Pending
64/I/2 Complete outage of North Chennai TPS
STG-2
25-04-2017
at 18:27hrs
Tripping of evacuating lines due to fault led to
tripping of Unit
64/I/3 Complete outage of North Chennai TPS
STG-2
26-03-2017
at 21:09 hrs
Tripping of evacuating lines due to fault led to
tripping of running Unit at NCTPS Stg-2
64/III/2 Tripping of 400 kV Ghanapur-
Mamidapalli line
04-04-2017 at
19:01hrs
B-phase to earth fault. Line auto-reclosed from
Mamidapalli end and tripped from Ghanapur
For the line under consideration, PGCIL (SR-I)/ TSTRANSCO to (i)
rectify issues w.r.t. PLCC channels, (ii) restore PLCC carrier
communication, and (iii) put A/R into service at the earliest.
PGCIL (SR-I)/
TSTRANSCO
Yet to be informed Pending
Triggering incident was failure of CT in 110 kV
Villianur-Kurumbapet at Villianur substation. 230KV
Villianur – NLC2 and 230 kV Villianur - Pondy lines
got tripped from Pondy end (on operation of DEF)
and NLC end (on operation of Zone-3) respectively
resulting in loss of supply to 230 kV Villianur
substation
19-05-2017 at
12.35 hrs
Complete outage of 230 kV Villianur
Substation of Pondicherry
65/I/1 PED/ PGCIL (SR-II)/
NLCIL
1. PED to furnish an action taken report w.r.t. complying with the
protection audit recommendations.
2. PGCIL (SR-II) to review Zone-3 and DEF protection setting at
Pondicherry end 230 kV Pondicherry – Villianur and 230 kV
Pondicherry – Bahour line, and set them appropriately to achieve
required time-coordination with O/C protections of ICT’s at Villianur
SS.
3. NLCIL to keep DEF protection in blocked condition as long as
Distance Protection is active, and configure it to become active only
when distance protection does not pickup to avoid time-
coordination issues.
Yet to be informed
Pending
PendingYet to be informed
57/II/9 Tripping of 400 kV Nellore (PG) - NPS
line-1, 400 kV Krishnapatnam-Nellore
(AP) lines -1&2 and 400kV NPS -
MEPL line
18-07-2016 at
19:05 hrs
Triggering incident was snapping of Y phase
conductor in 400kV Nellore (PG) - NPS line-1.
Distance relay at Krishnapatnam end over-reached in
Zone-1, and resulted in tripping of 400kV
Krishnapatnam – Nellore (AP) lines - 1&2 from
Krishnapatnam end. Distance relay at MEPL over-
reached and resulted in tripping of MEPL-NPS line
from MEPL end.
PGCIL (SR-I), TPCIL, MEPL, SEL, SGPL, APTRANSCO,
APGENCO and SDSTPS to implement line differential protection on
all 400 kV transmission lines (of length less than 50 km) emanating
from Nellore PS, Nellore (PG) SS, and Nellore (AP) SS. [It may be
noted here that the cut-off length of 50 km has been specified with a
view to exclude only long transmission lines].
APGENCO/ PGCIL(SR-
I)/ TPCIL/MEPL/
SEL/SGPL/
APTRANSCO
56/IV/2 Tripping of 400 kV VTPS-Suryapet line Direct Trip was received at VTPS and line was
holding from Suryapet end
13-06-2016 at
16:55 hrs
APGENCO/
TSTRANSCO
1. TANTRANSCO and PGCIL (SR-II) to take steps to complete
insulator replacement works on the 400 kV lines owned by them in
Chennai area within 3 months.
1. JSWEL to follow file naming terminology provided by SRPC
for various tripping files uploaded in SRLDC’s TMS portal.
2.JSWEL to furnish reasons for AR-BLOCK observed during
the instant tripping and remedial action taken by them to
keep A/R in service.
3. KPCL to configure DR & EL properly to record OVR Stage-I
& Stage-II protections at their BTPS station.
14-03-2017 at
19:11 hrs
Tripping of 400 kV YTPS-BTPS line and
400 kV BTPS-JSWEL line
KPCL/JSWEL Yet to be informed Pending
For the line under consideration, the following shall be carried out by
APGENCO in coordination with TSTRANSCO:
1.End-to-end communication for DT/ permissive & other signals may
be ensured by testing at both the ends.
2.Healthiness of PLCC system components (hardware and software)
at both ends shall be checked and faulty components shall be repaired/
replaced.
Status received vide TANTRANSCO mail dated 15-06-2017 &
04.08.2017:
1. All the Porcelain insulators of 400kV NCTPS-II - Vallur feeders-1&2
were replaced with Polymer insulators by 20.05.2017.
2. Existing Porcelain insulators of all other 400kV feeders are being
replaced with Polymer insulators in a phased manner.
TANTRANSCO/
PGCIL(SR-II)
Pending
63/II.9
57/I/1 Complete outage of 220 kV Karwar
Substation of KPTCL
KPTCL/ KPCL/ NPCIL
(KAPS)
NPCIL(KGS) mail dated on 03-12-2016:
A.The 200 ms Definite time DEFR element in both Kaiga Kadra and
Kaiga Kodasally lines were disabled. IDMT DEFR is retained .
B. The 200 ms Definite time back up o/c element in both Kaiga Kadra and
Kaiga Kodasally lines were disabled. IDMT is retained.
------Completed
APTRANSCO mail dated on 20-12-2016:
Issue was addressed to the concerned for necessary action.
APTRANSCO mail dated on 24-05-2017:
Meeting was conducted and the relays procurement for all the locations is
under progress.
Pending
12-07-2017 at
11:36 hrs
Triggering incident was failure of R phase PT in Bus-
1 at 220kV Karwar substation. 220kV Kaiga-
Kodasalli tripped during the incident. Also bus shut
down occurred at Kadra and Kodasally stations.
1.NPCIL (KAPS) to disable DefiniteTime O/C relay, and put in its
place by IDMT O/C relay for backup protection on both 220 kV
Kaiga – Kadra line and 220 kV Kaiga – Kodasalli line at Kaiga end.
2.KPTCL to put bus bar protection in service at their 220 kV Karwar
SS at the earliest.
3.KPCL/ KPTCL to implement Weak In-feed Logic with Echo feature
enabled by Under Voltage (27) element on Kadra – Karwar lines 1 &
2.
4.KPTCL to furnish equipment failure report of the current incident to
PSE&TD Division of CEA with a copy marked to SRPC.
Annexure-II
Page 31 of 33
65/II/5 Tripping of 400 kV Ghanapur-
Mamidapalli line
08-05-2017 at
19:15 hrs
Line tripped at Ghanapur end only and was holding
from Mamidapalli. Ghanapur end protection had
sensed R-phase to earth fault
For the line under consideration, the following shall be carried out
by TSTRANSCO in coordination with PGCIL (SR-I):
1. End-to-end communication for DT/ permissive & other signals
may be ensured by testing at both the ends.
2. Healthiness of PLCC system components (hardware and
software) at both ends shall be checked and faulty components
shall be repaired/ replaced.
TSTRANSCO/ PGCIL
(SR-I)
Yet to be informed Pending
65/III/12 Tripping of 400 kV Srisailam-Dindi line-2 24-05-2017
at 15:02 hrs
R-phase to earth fault. Auto-reclose was successful
at Dindi and Zone - 1, 3-phase trip at Srisailam
Since all 400 kV lnies emanating from Srisailam LB are composite
feeders, APTRANSCO/ TSTRANSCO can keep A/R functionality
disabled at respective remote end stations under their control.
APTRANSCO/ TSTRANSCO Yet to be informed Pending
66/ II/ 5 Tripping of 400 kV Ramagundam -
Dichipally line, 400kV Nizamabad -
Dichipally line-1 and 400/220 kV ICT-1
05-06-2017 at
19:15 hrs
Triggering incident was fault in 400kV Nizamabad
GIS
1. TSTRANSCO/ NTPC to adopt proper Zone-2 time settings (say,
Ramagundam end � 500 msec; Dichipally end � 350 msec in line
with Ramakrishna Committee recommendations) on 400 kV
Ramagundam – Dichipally line and 400 kV Dichipally - Nizamabad
lines respectively.
2. For the 400 kV Dichipally - Nizamabad D/C line, TSTRANSCO, in
coordination with PGCIL (SR-I), to carry out the following:
(i) End-to-end communication for DT/ permissive & other signals
may be ensured by testing at both the ends.
(ii) Healthiness of PLCC system components (hardware and
software) at both ends shall be checked and faulty components
shall be repaired/ replaced.
NTPC-Ramagundam/
TSTRANSCO/ PGCIL (SR-I)
Yet to be informed Pending
66/ II/ 8 Tripping of 400 kV Khammam – KTPS
lines – 1 & 2
08-06-2017 at
18:32 hrs
Lines – 1 & 2 tripped on B-phase to earth faults 1. TSGENCO to keep uniform A/R dead-time of 1 sec on the lines
emanating from their KPTS station.
2. PGCIL (SR-I) to enable Trip-on-Reclose (TOR) functionality for
Zone-2 faults for Khammam – KTPS lines at Khammam end, if such a
feature is available in the concerned relay, and to configure it for
sending Direct Trip (DT) Command to KTPS end.
TSGENCO/
PGCIL (SR-I)
Yet to be informed Pending
65/I/2 Complete outage of 400kV Uravakonda
and Jammalamadugu Substations
31-05-2017 at
17.44 hrs
Triggering incident was tripping of 400 kV Kurnool-
PG - Narnoor line - 1 & 2 and 400 kV Narnoor-
Jamalamadugu line-2 which led to loss of supply to
400kV Uravakonda and Jamalamadugu. 400kV Gooty-
Narnoor, 400kV Narnoor-Jamalamadugu-1, 400kV
Srisailam-Narnoor, 400kV Uruvakonda-
Mahboobnagar-1&2 were out of service in
antecedent condition.
1. For 400 kV Ghani –Narnoor line, the following shall be carried out
by APTRANSCO:
(i) End-to-end communication for DT/ permissive & other signals
may be ensured by testing at both the ends.
(ii) Healthiness of PLCC system components (hardware and
software) at both ends shall be checked and faulty components
shall be repaired/ replaced.
2. PGCIL (SR-II) to take appropriate action w.r.t disabling non-
directional instantaneous I>4 protection that operates without
checking existence of stub. If required, the issue may be referred to
relays OEM for appropriate solution or the present relays may be
replaced with other relays with different styles that don’t have the
issue observed.
APTRANSCO/ PGCIL
(SR-II)
Yet to be informed Pending
Y-phase to earth fault. Neyveli TS2 end relay issued a
3-phase trip 220ms after issue of Y phase trip. Direct
Trip was sent to Pugalur end preventing auto-
reclose.
07-05-2017
at 19:55 hrs
PGCIL (SR-II)/ NLCIL Yet to be informed Pending
65/II/16 Tripping of 400 kV Kayathar-Karaikudi
line
25-05-2017 at
15:52 hrs
R-phase to earth fault had occurred in line. There
was Zone-2, 3 phase trip operation at Kayathar end
and Zone-1, 3 phase trip at Karaikudi end
For the line under consideration, the following shall be carried out
by TANTRANSCO in coordination with PGCIL (SR-II):
1. End-to-end communication for DT/ permissive & other signals
may be ensured by testing at both the ends.
2. Healthiness of PLCC system components (hardware and software)
at both ends shall be checked and faulty components shall be
repaired/ replaced.
PGCIL (SR-II)/
TANTRANSCO
Status received vide TANTRANSCO mail dated 04-08-
2017:
1. End to end communication for DT & other signals will be carried out in
coordination with PGCIL (SR-II).
2. PLCC system components at Kayathar end will be checked for
healthiness.
Pending
For the line under consideration, the following shall be carried out
by TSTRANSCO in coordination with NTPC-Ramagundam:
1. End-to-end communication for DT/ permissive & other signals
may be ensured by testing at both the ends.
2. Healthiness of PLCC system components (hardware and software)
at both ends shall be checked and faulty components shall be
repaired/ replaced.
Over Voltage Stage-1 had operated at Gajwel end.
Ramagundam end did not trip as Direct Trip was not
received from Gajwel end.
29-05-2017
at 00:07 hrs
Tripping of 400 kV Ramagundam -
Gajwel line
65/II/19 TSTRANSCO/ NTPC
(Ramagundam)
Yet to be informed Pending
Tripping of 400 kV Neyveli TS2-Pugalur
line
65/III/6 For the line under consideration, the following shall be carried out
by NLCIL in coordination with PGCIL (SR-II):
1. End-to-end communication for DT/ permissive & other signals
may be ensured by testing at both the ends.
2. Healthiness of PLCC system components (hardware and software)
at both ends shall be checked and faulty components shall be
repaired/ replaced.
Annexure-II
Page 32 of 33
66/ II/ 10 Tripping of 400/ 220 kV ICT’s – 3 & 4 at
Ramagundam STPS
11-06-2017
at 19:46hrs
Triggering incident was failure of 220 kV
B-phase LA in ICT-3 LV extension feeder (220KV line-
2) at Malayalapalli substation
1. NTPC to disable high-set of DEFR on the 220 kV lines emanating
from their Ramagundam STPS.
2. NTPC/ TSTRANSCO to provide Line Differential Protection (with or
without pilot) on 220 kV Ramagundam – Malayalapalli lines – 1 & 2
& 3.
NTPC-Ramagundam/
TSTRANSCO
Yet to be informed Pending
66/ IV/ 1 Tripping of 400 kV Vijayawada-Vemagiri
line-2
03-06-2017
at 16:09 hrs
Breakers at Vemagiri end tripped due to receipt of
Direct Trip and line was holding from Vijayawada
end.
PGCIL (SR-I)/ APTRANSCO to rectify DC leakage issues for the
APTRANSCO bays at Vijayawada SS, and ensure that PLCC carrier
communication is maintained healthy.
PGCIL (SR-I)/
APTRANSCO
Yet to be informed Pending
sending Direct Trip (DT) Command to KTPS end.
3. PGCIL (SR-I) to set right time-sync issues w.r.t. Khammam end
Event Loggers on Khammam – KTPS lines.
4. For 400 kV Khammam – KTPS line-1, PGCIL (SR-I), in coordination
with TSGENCO, shall carry out the following:
(i) End-to-end communication for DT/ permissive & other signals
may be ensured by testing at both the ends.
(ii) Healthiness of PLCC system components (hardware and
software) at both ends shall be checked and faulty components
shall be repaired/ replaced.
66/ IV/ 3 Tripping of 400 kV Vijayawada-VTPS line 07-06-2017
at 23:55 hrs
Line was holding from VTPS end and breaker at
Vijayawada end tripped on Direct Trip receipt.
For the line under consideration, APTRANSCO/ APGENCO, in
coordination with PGCIL (SR-I) to carry out the following:
(i) End-to-end communication for DT/ permissive & other signals
may be ensured by testing at both the ends.
(ii) Healthiness of PLCC system components (hardware and
software) at both ends shall be checked and faulty components
shall be repaired/ replaced.
APGENCO/ APTRANSCO/
PGCIL (SR-I)
Yet to be informed Pending
Annexure-II
Page 33 of 33
Sl.No. Element NameOutage
date/time
Revival
date/timeReason for Outage Sender/ Receiver Remedial Measures/ Actions taken
1 400 kV KAIGA - GUTTUR 1 06-02-2017/05:01:00 POLE DISCREPANCY NPCIL/ KPTCL
KGS:
The line tripped due to unsuccessful A/R and operation
of PDR at KGS end. The line was taken into service vide
CPCC-CP-02/110 and SRLDC-CR-02/154 codes.
2 400 kV KAIGA - GUTTUR 1 27-03-2017/15:38:00 27-03-2017/16:48:00 RELAY MALOPERATION NPCIL (KGS)/ KPTCL
KPTCL:
At Guttur end DPR operated in Z1, R phase, AR
unsucessful due to persistant fault. At Kaiga end DPR
operated in Zone-1, RN fault,145km; AR attempt is
observed from Kaiga end.
Reason: Transient fault. Stood OK after test charging.
KGS:
3 400 kV KHAMMAM - MAMIDIPALLY 2 08-05-2017/16:06:00 08-05-2017/17:49:00 R PHASE TO GROUND FAULTPGCIL (SR-I)/ TSTRANSCO/
APTRANSCO
PGCIL(SR-I):Tripped on operation of distance
protection. Line belongs to APTRANSCO.
TSTRANSCO: Tripped at both ends. Tripped on R-phase
to ground, Zone-1 indications, A/R acted and was
unsucessful at Mamidipally end.
APTRANSCO:
4 400 Kv VTPS - MALKARAM 1 22-05-2017/14:52:00 22-05-2017/18:58:00 B phase fault APGENCO/ TSTRANSCO
TSTRANSCO:
Trippedat both ends. Tripped on B-Phase to ground
and Zone-1 indications, A/R acted and was unsucessful
at Malkaram end.
5HVDC TALCHER - KOLAR POLE 1 AT
TALCHER01-06-2017/23:22:00 02-06-2017/00:11:00
DC DIFFERENTIAL PROTECTION
OPERATEDPGCIL (SR-II)/ PGCIL (ER-I)
PGCIL(SR-II):
Due to DC filter Diff relay operation at Talcher end
6 400 kV KOLAR - HOODY 2 06-06-2017/20:08:00 DUE TO HEAVY WIND PGCIL (SR-II)/ KPTCL
PGCIL (SR-2):
Hand Tripped due to Isolator problem at Hoody End
7400 kV PUGALUR -
KALAIVANTHAPATTU14-06-2017/12:37:00 14-06-2017/18:45:00 TRIPPED ON Y-N FAULT PGCIL(SR-II)
To-be-discussed
8 400 kV KAIGA - NARENDRA 2 07-07-2017/07:50:00 07-07-2017/09:08:00 TRIPPED ON R-Y Ph FAULT NPCIL / KPTCLTo-be-discussed
9 220 kV AMBEWADI - PONDA 1 16-07-2017/11:38:00 16-07-2017/12:08:00 DISTANCE PROTECTION KPTCL / GEDTo-be-discussed
Pending Remedial Measures/ Actions taken
for the Critical Tripping Incidents (as on 06.09.2017)
Annexure-III
Page 1 of 4
10 220 kV AMBEWADI - PONDA 2 20-07-2017/01:36:00 LINE FAULT KPTCL/ GEDTo-be-discussed
11 HVDC BHADRAVATHI POLE 1 21-07-2017/22:48:00 21-07-2017/23:53:00 INTERNAL MINOR ALARM PGCIL (SR-I)/ PGCIL (WR-I)To-be-discussed
12 400 KV GOOTY - TUMKUR - 1 22-07-2017/15:07:00 22-07-2017/15:45:00TRIPPED DURING OPGW
WORKSPGCIL (SR-I)/ PGCIL (SR-II)
To-be-discussed
13 400 Kv GAJWEL - BHOOPALAPALLY 2 22-07-2017/13:13:00 22-07-2017/13:36:00 B PHASE FAULT TSTRANSCO/ TSGENCO
TSTRANSCO: T
ripped at Both ends. Tripped on B-Phase to Ground and
Zone-1 indication at Gajwel end. Bhoopalapally end
auto reclosure acted and reclosed. Auto reclosure did
not act at Gajwel end. Non operation of Auto reclosure
at Gajwel end will be checked duly taking Line
Clearance on the feeder.
14 400 kV GUTTUR - HIRIYUR 2 22-07-2017/15:03:00 22-07-2017/15:53:00TRIPPED DUE TO RELAY MAL
OPERATIONKPTCL/ PGCIL (SR-II)
To-be-discussed
15 400 kV HASSAN - NEELAMANGALA 1 27-07-2017/17:00:00 TRIPPED DUE TO Y-N FAULT PGCIL(SR-II)/ KPTCLTo-be-discussed
16 400 kV KAIGA - GUTTUR 1 29-07-2017/13:21:00 29-07-2017/18:52:00TRIPPED DUE TO DISTANCE
RELAY MALOPERATIONNPCIL (KGS)/ KPTCL
To-be-discussed
17 400kV VTPS -MALKARAM 29-07-2017/19:33:00BUS BAR PROTECTION ACTED
DUE TO CT BLAST AT VTPSAPGENCO/ TSTRANSCO
TSTRANSCO: Tripped at both ends. Tripped on Direct
trip received indications at Malkaram end as Bus bar
acted at VTPS end due to blasting of Y Phase CT of
Malkaram feeder.
APGENCO:
18 400KV VTPS-SURYAPET 29-07-2017/19:33:00
BUS BAR PROTECTION
OPERATED DUE TO CT BLAST
AT VTPS
APGENCO/ TSTRANSCO
TSTRANSCO: Tripped at VTPS end only on Over Voltage
due to blasting of Y Phase CT of Malkaram feeder
(which is in same dia of Suryapet feeder). But as Direct
Trip was not received from VTPS end line did not trip at
Suryapet end.
APGENCO:
19 HVDC GAJUWAKA POLE 1 03-08-2017/12:16:00 03-08-2017/13:08:00 VALVE FAILURE PGCIL (SR-I)To-be-discussed
20 400 kV NEYVELI TS 2- SALEM 1 06-08-2017/17:04:00 06-08-2017/17:25:00 TRIPPED ON Y-N fault NLCIL / PGCIL (SR-II)To-be-discussed
21 400 kV CUDDAPAH - N P KUNTA 07-08-2017/12:20:00 07-08-2017/13:33:00 TRIPPED DUE TO R-N FAULT PGCIL (SR-I)To-be-discussed
22 400 KV NIZAMABAD- DICHPALLY-2 07-08-2017/17:12:00 07-08-2017/18:03:00 DT received at Dchipally end PGCIL (SR-I) / TSTRANSCO
TSTRANSCO: Tripped at Dichpally end only as Direct Trip
was received from Nizamabad end and there is counter
increment in PLCC Panel.
PGCIL(SR-I):
Annexure-III
Page 2 of 4
23 400 kV N'SAGAR - CUDDAPPA 1 07-08-2017/12:20:00 07-08-2017/13:31:00 TRIPPED DUE TO R-N FAULT PGCIL(SR-I)To-be-discussed
24765 KV NIZAMABAD -
MAHESHWARAM - 207-08-2017/00:16:00 07-08-2017/15:56:00 R-N FAULT PGCIL (SR-I)
To-be-discussed
25765 KV NIZAMABAD -
MAHESHWARAM - 207-08-2017/00:16:00 R-N FAULT PGCIL (SR-I)
To-be-discussed
26 400 Kv COASTAL - TTRNPS 09-08-2017/17:54:00 09-08-2017/18:11:00 RELAY MALOPERATION CEPL/ TANGEDCOTo-be-discussed
27 400 kV COASTAL - TTRNPS 2 09-08-2017/17:54:00 09-08-2017/18:40:00 RELAY MALOPERATION CEPL/ TANGEDCOTo-be-discussed
28 400 KV KUDGI PG - TUMKUR - 2 09-08-2017/14:13:00 09-08-2017/14:23:00 RELAY MALOPERATION PGCIL (SR-II)To-be-discussed
29 220 kV YERANDAHALLY - HOSUR 14-08-2017/11:35:00 14-08-2017/12:00:00TRIPPED DUE TO JUMPER AT
TOWER OPENEDKPTCL/ TANTRANSCO
TANTRANSCO: Temporary fault
30 220 kV PALAKKAD - KANJIKODE 2 14-08-2017/10:58:00 14-08-2017/14:24:00HOTSPOT IN CT TERMINAL
WORKKSEB
To-be-discussed
31 400 Kv BANGALORE - BIDADI 2 15-08-2017/03:15:00 15-08-2017/03:54:00 B-N FAULT PGCIL(SR-II)To-be-discussed
32 400 kV KALPAKKA - GAZUWAKA 2 16-08-2017/14:40:00 16-08-2017/14:53:00 DISTANCE PROTECTION APTRANSCO/ PGCIL(SR-I)To-be-discussed
33 400 kV KALPAKKA - GAZUWAKA 1 16-08-2017/14:40:00 16-08-2017/14:53:00 DISTANCE PROTECTION APTRANSCO/ PGCIL(SR-I)To-be-discussed
34 400/220 kV ICT-3 AT N'SAGAR 22-08-2017/10:21:00 22-08-2017/10:28:00TRIIPEED DUE TO RELAY
MALOPERATIONPGCIL(SR-I)
To-be-discussed
35 220 kV AMBEWADI - PONDA 2 22-08-2017/13:09:00 22-08-2017/14:02:00 EARTH FAULT relay operated KPTCL/ GED (WR)To-be-discussed
36 400 KV GOOTY - TUMKUR - 1 23-08-2017/11:44:00 23-08-2017/13:00:00 PHASE TO PHASE FAULT PGCIL(SR-II)To-be-discussed
37 400 kV MAHESHWARAM - NARNOOR 30-08-2017/10:11:00 30-08-2017/10:25:00 RELAY MALOPERATION PGCIL (SR-I)/ APTRANSCOTo-be-discussed
38 400/220 kV ICT-2 AT NELLORE 31-08-2017/05:05:00 31-08-2017/17:06:00 MOLOPERATION APTRANSCOTo-be-discussed
39 400kV KANARPETTY-TIRUNELVELI 31-08-2017/21:58:00 31-08-2017/23:03:00 TRIPPED ON R-N FAULT TANTRANSCO/ PGCIL (SR-II)To-be-discussed
40 400 kV MYSORE - KOZHIKODE 1 01-09-2017/16:28:00 01-09-2017/16:43:00 TRIPPED ON Transient fault PGCIL (SR-II)To-be-discussed
41 220 kV AMBEWADI - PONDA 1 01-09-2017/13:25:00 01-09-2017/13:54:00 DISTANCE PROTECTION KPTCL/ GEDTo-be-discussed
Annexure-III
Page 3 of 4
42 400 Kv NCTPS - SVCTM-II 01-09-2017/06:46:00 01-09-2017/17:09:00 B-N FAULT TANGEDCO/ TANTRANSCOTo-be-discussed
43 400/110 kV ICT 2 AT ALAMATHY 02-09-2017/16:04:00 02-09-2017/17:36:00 DIFFERENTIAL PROTECTION TANTRANSCOTo-be-discussed
44 400 Kv NELLORE - SPDR-1 03-09-2017/18:29:00TRIPPED ON B PHASE TO
GROUND FAULTPGCIL (SR-I)/ PGCIL (SR-II)
To-be-discussed
45 400kV KHAMAM - WARANGAL 03-09-2017/09:49:00 03-09-2017/11:52:00TRIPPED ON PRD MAL
OPERATIONPGCIL (SR-I)
To-be-discussed
46 220 kV AMBEWADI - PONDA 1 03-09-2017/12:53:00 03-09-2017/13:06:00 B-n fault KPTCL/ GEDTo-be-discussed
Annexure-III
Page 4 of 4
From Bus
NumberFrom Bus Name
To Bus
NumberTo Bus Name Ckt Id
Length,
km
Charging
'B' (pu)
Q' from
Line (B/2)
[= Q1]
Q' from Line
Reactor
[= Q2]
Net 'Q' from
Line
[= Q1 + Q2]
Power
Flow, MW
Order as
per
Criticality
New OVR
Grading (at
FROM BUS
end)
414010 KURNOOL 400.00 414001 GOOTY 400.00 1 84.19 0.4695 0.23475 0 0.23475 445.1 9 A
414010 KURNOOL 400.00 414031 KURNOOL-PG 400.00 1 9.88 0.07243 0.036215 0 0.036215 303.9 10 A
414010 KURNOOL 400.00 414031 KURNOOL-PG 400.00 2 9.88 0.07243 0.036215 0 0.036215 303.9 7 C
414010 KURNOOL 400.00 414036 JAMALAMADUGU400.00 1 100.86 0.73929 0.369645 0 0.369645 -35.9 5 E
414010 KURNOOL 400.00 414036 JAMALAMADUGU400.00 2 100.86 0.73929 0.369645 0 0.369645 -35.9 1 I
414010 KURNOOL 400.00 414041 GHANI 400.00 1 16.26 0.11919 0.059595 0 0.059595 -273.9 8 B
414010 KURNOOL 400.00 414041 GHANI 400.00 2 16.26 0.11919 0.059595 0 0.059595 -273.9 4 F
414010 KURNOOL 400.00 424003 GHANAPUR 400.00 1 226.5 1.2571 0.62855 0 0.62855 -163.7 2 H
414010 KURNOOL 400.00 424005 SRISAILAMLB 400.00 1 104.9 0.5749 0.28745 0 0.28745 -306.9 6 D
414010 KURNOOL 400.00 424021 MHSWRM-PG 400.00 1 175.01 0.97131 0.485655 0 0.485655 -331 3 G
414011 KALPAKKA 400.00 414009 GAZUWAKA 400.00 1 3.39 0.02061 0.010305 0 0.010305 -328.1 9 B
414011 KALPAKKA 400.00 414009 GAZUWAKA 400.00 2 3.39 0.02061 0.010305 0 0.010305 -328.1 6 D
414011 KALPAKKA 400.00 414012 SIMHADRI-I 400.00 1 3.72 0.02256 0.01128 0 0.01128 -345.4 12 A
414011 KALPAKKA 400.00 414012 SIMHADRI-I 400.00 2 3.72 0.02256 0.01128 0 0.01128 -345.4 10 B
414011 KALPAKKA 400.00 414012 SIMHADRI-I 400.00 3 3.72 0.02256 0.01128 0 0.01128 -345.4 7 D
Revised OVR Grading Studies for certain 400 kV Transmission Lines of Southern Region
1. Voltage - Time (OVR) Grading Matrix:
2. Study Results:
Annexure-IV (OVR-Studies)
Page 1 of 4
414011 KALPAKKA 400.00 414012 SIMHADRI-I 400.00 4 3.72 0.02256 0.01128 0 0.01128 -345.4 3 G
414011 KALPAKKA 400.00 414014 VEMAGIRI 400.00 1 166.93 1.0124 0.5062 0 0.5062 281.7 11 A
414011 KALPAKKA 400.00 414014 VEMAGIRI 400.00 2 166.93 1.0124 0.5062 0 0.5062 281.7 2 H
414011 KALPAKKA 400.00 414027 HINDUJA 400.00 1 7.35 0.04425 0.022125 0 0.022125 211.8 8 C
414011 KALPAKKA 400.00 414027 HINDUJA 400.00 2 7.35 0.04425 0.022125 0 0.022125 211.8 5 E
414011 KALPAKKA 400.00 424004 KHAMMAM 400.00 1 364 2.2076 1.1038 -0.5714 0.5324 152.3 1 I
414011 KALPAKKA 400.00 424020 ASUPAKA 400.00 1 131.07 1.60744 0.80372 -0.5714 0.23232 138.4 4 F
414042 K V KOTA 400.00 414027 HINDUJA 400.00 1 246 1.48092 0.74046 0 0.74046 -211.7 3 B
414042 K V KOTA 400.00 414027 HINDUJA 400.00 2 246 1.48092 0.74046 0 0.74046 -211.7 1 G
414042 K V KOTA 400.00 424016 SURYAPET 400.00 1 174.54 1.27938 0.63969 0 0.63969 122.6 4 A
414042 K V KOTA 400.00 424016 SURYAPET 400.00 2 174.54 1.27938 0.63969 0 0.63969 122.6 2 D
424003 GHANAPUR 400.00 414007 TALLAPALLI 400.00 1 155.26 0.86172 0.43086 0 0.43086 65.9 2 G
424003 GHANAPUR 400.00 414010 KURNOOL 400.00 1 226.5 1.2571 0.62855 0 0.62855 163.7 1 H
424003 GHANAPUR 400.00 424002 RSTPS NTPC 400.00 1 201.25 1.11694 0.55847 0 0.55847 -353.6 6 B
424003 GHANAPUR 400.00 424002 RSTPS NTPC 400.00 2 201.25 1.11694 0.55847 0 0.55847 -353.6 3 E
424003 GHANAPUR 400.00 424006 MAMIDIPALLI 400.00 1 46 0.2769 0.13845 0 0.13845 292.9 4 D
424003 GHANAPUR 400.00 424008 GAJWEL 400.00 1 72.95 0.4392 0.2196 -0.45351 -0.23391 -493.8 8 A
424003 GHANAPUR 400.00 424011 MALKARAM 400.00 1 54.9 0.3254 0.1627 -0.4535 -0.2908 134.6 7 A
424003 GHANAPUR 400.00 424021 MHSWRM-PG 400.00 1 56.15 0.31166 0.15583 0 0.15583 -361.1 5 C
424004 KHAMMAM 400.00 414007 TALLAPALLI 400.00 1 144.58 0.80242 0.40121 0 0.40121 160.8 8 C
424004 KHAMMAM 400.00 414007 TALLAPALLI 400.00 2 144.58 0.86938 0.43469 0 0.43469 173.5 4 F
424004 KHAMMAM 400.00 414007 TALLAPALLI 400.00 3 144.58 0.86938 0.43469 0 0.43469 173.5 2 H
424004 KHAMMAM 400.00 414008 NUNNA 400.00 1 114.78 0.637 0.3185 0 0.3185 170.2 5 E
424004 KHAMMAM 400.00 414011 KALPAKKA 400.00 1 364 2.2076 1.1038 -0.5714 0.5324 -152.3 3 G
424004 KHAMMAM 400.00 424006 MAMIDIPALLI 400.00 1 198 1.192 0.596 0 0.596 147.9 7 D
424004 KHAMMAM 400.00 424006 MAMIDIPALLI 400.00 2 198 1.192 0.596 0 0.596 147.9 1 I
424004 KHAMMAM 400.00 424010 WARANGAL 400.00 1 117.09 0.64985 0.324925 -0.4535 -0.128575 -280.4 10 A
424004 KHAMMAM 400.00 424012 KTPS-VI 400.00 1 67.76 0.4079 0.20395 0 0.20395 -281.3 9 B
424004 KHAMMAM 400.00 424012 KTPS-VI 400.00 2 67.76 0.4079 0.20395 0 0.20395 -281.3 6 D
424004 KHAMMAM 400.00 424020 ASUPAKA 400.00 1 131.07 0.78872 0.39436 -0.5714 -0.17704 -136.9 11 A
424006 MAMIDIPALLI 400.00 424003 GHANAPUR 400.00 1 46 0.2769 0.13845 0 0.13845 -292.9 5 A
424006 MAMIDIPALLI 400.00 424004 KHAMMAM 400.00 1 198 1.192 0.596 0 0.596 -147.9 3 D
424006 MAMIDIPALLI 400.00 424004 KHAMMAM 400.00 2 198 1.192 0.596 0 0.596 -147.9 1 G
424006 MAMIDIPALLI 400.00 424019 DINDI 400.00 1 74.91 0.41576 0.20788 0 0.20788 -49.8 4 B
424006 MAMIDIPALLI 400.00 424019 DINDI 400.00 2 74.91 0.41576 0.20788 0 0.20788 -49.8 2 E
424013 SHANKARPALLI400.00 424008 GAJWEL 400.00 1 105 0.58275 0.291375 0 0.291375 -280.1 4 D
Annexure-IV (OVR-Studies)
Page 2 of 4
424013 SHANKARPALLI400.00 424016 SURYAPET 400.00 1 231 1.39062 0.69531 0 0.69531 32.8 3 E
424013 SHANKARPALLI400.00 424016 SURYAPET 400.00 2 231 1.39062 0.69531 0 0.69531 32.8 1 H
424013 SHANKARPALLI400.00 424017 NARSARPUR 400.00 1 60.92 0.33811 0.169055 0 0.169055 -265 6 A
424013 SHANKARPALLI400.00 424022 MAHES-TS 400.00 1 83.99 0.5056 0.2528 0 0.2528 -178.3 5 B
424013 SHANKARPALLI400.00 424022 MAHES-TS 400.00 2 83.99 0.5056 0.2528 0 0.2528 -178.3 2 G
424016 SURYAPET 400.00 414013 VTS-IV 400.00 2 130.95 0.72645 0.363225 0 0.363225 37.9 5 B
424016 SURYAPET 400.00 414042 K V KOTA 400.00 1 174.54 1.27938 0.63969 0 0.63969 -122.6 6 A
424016 SURYAPET 400.00 414042 K V KOTA 400.00 2 174.54 1.27938 0.63969 0 0.63969 -122.6 2 G
424016 SURYAPET 400.00 424011 MALKARAM 400.00 1 135.56 0.8157 0.40785 0 0.40785 51.9 3 E
424016 SURYAPET 400.00 424013 SHANKARPALLI400.00 1 231 1.39062 0.69531 0 0.69531 -32.8 4 D
424016 SURYAPET 400.00 424013 SHANKARPALLI400.00 2 231 1.39062 0.69531 0 0.69531 -32.8 1 H
424019 DINDI 400.00 424005 SRISAILAMLB 400.00 1 73.02 0.40527 0.202635 0 0.202635 -50 4 A
424019 DINDI 400.00 424005 SRISAILAMLB 400.00 2 73.02 0.40527 0.202635 0 0.202635 -50 2 D
424019 DINDI 400.00 424006 MAMIDIPALLI 400.00 1 74.91 0.41576 0.20788 0 0.20788 49.8 3 B
424019 DINDI 400.00 424006 MAMIDIPALLI 400.00 2 74.91 0.41576 0.20788 0 0.20788 49.8 1 G
424020 ASUPAKA 400.00 414011 KALPAKKA 400.00 1 131.07 1.60744 0.80372 0 0.80372 -138.4 1 D
424020 ASUPAKA 400.00 424004 KHAMMAM 400.00 1 131.07 0.78872 0.39436 0 0.39436 136.9 2 A
424021 MHSWRM-PG 400.00 414010 KURNOOL 400.00 1 175.01 0.97131 0.485655 0 0.485655 331 1 F
424021 MHSWRM-PG 400.00 424003 GHANAPUR 400.00 1 56.15 0.31166 0.15583 0 0.15583 361.1 2 D
424021 MHSWRM-PG 400.00 424022 MAHES-TS 400.00 1 1.55 0.01132 0.00566 0 0.00566 410.8 3 B
424021 MHSWRM-PG 400.00 424022 MAHES-TS 400.00 2 1.55 0.01099 0.005495 0 0.005495 423.1 4 A
424022 MAHES-TS 400.00 424013 SHANKARPALLI400.00 1 83.99 0.5056 0.2528 0 0.2528 178.3 3 B
424022 MAHES-TS 400.00 424013 SHANKARPALLI400.00 2 83.99 0.5056 0.2528 0 0.2528 178.3 1 F
424022 MAHES-TS 400.00 424021 MHSWRM-PG 400.00 1 1.55 0.01132 0.00566 0 0.00566 -410.8 4 A
424022 MAHES-TS 400.00 424021 MHSWRM-PG 400.00 2 1.55 0.01099 0.005495 0 0.005495 -423.1 2 D
Annexure-IV (OVR-Studies)
Page 3 of 4
From Bus
NumberFrom Bus Name
To Bus
NumberTo Bus Name Ckt Id
Length,
km
Charging 'B'
(pu)
Q' from
Line (B/2)
[= Q1]
Q' from
Line
Reactor
[= Q2]
Net 'Q'
from Line
[= Q1 +
Q2]
Power
Flow, MW
Order as
per
Criticality
New OVR
Grading (at
FROM BUS
end)
337003 WARDHA-PG 765.00 427001 NIZAMABAD 765.00 1 291.2 7.74592 3.87296 -2.4 1.47296 755.32 A
337003 WARDHA-PG 765.00 427001 NIZAMABAD 765.00 2 291.2 7.74592 3.87296 -2.4 1.47296 755.31 E
427001 NIZAMABAD 765.00 337003 WARDHA-PG 765.00 1 291.2 7.74592 3.87296 -2.4 1.47296 -755.33 B
427001 NIZAMABAD 765.00 337003 WARDHA-PG 765.00 2 291.2 7.74592 3.87296 -2.4 1.47296 -755.31 E
427001 NIZAMABAD 765.00 427002 MHSWRM 765.00 1 240 6.4651 3.23255 -2.4 0.83255 635.82 C
427001 NIZAMABAD 765.00 427002 MHSWRM 765.00 2 240 0.01099 0.005495 -2.4 -2.394505 635.84 A
427002 MHSWRM 765.00 427001 NIZAMABAD 765.00 1 240 6.4651 3.23255 -2.4 0.83255 -635.82 A
427002 MHSWRM 765.00 427001 NIZAMABAD 765.00 2 240 0.01099 0.005495 -2.4 -2.394505 -635.81 E
Revised OVR Grading Studies for certain 765 kV Transmission Lines of Southern Region
1. Voltage - Time (OVR) Grading Matrix:
2. Study Results:
Annexure-IV (OVR-Studies)
Page 4 of 4
From Bus
NumberFrom Bus Name
To Bus
NumberTo Bus Name Ckt Id Length, km
Line Reactor VARS
at FROM BUS End
(pu)
New OVR Grading
(at FROM BUS end)
414010 KURNOOL 400.00 414001 GOOTY 400.00 1 84.19 0A
414010 KURNOOL 400.00 414031 KURNOOL-PG 400.00 1 9.88 0A
414010 KURNOOL 400.00 414031 KURNOOL-PG 400.00 2 9.88 0C
414010 KURNOOL 400.00 414036 JAMALAMADUGU400.00 1 100.86 0E
414010 KURNOOL 400.00 414036 JAMALAMADUGU400.00 2 100.86 0I
414010 KURNOOL 400.00 414041 GHANI 400.00 1 16.26 0B
1. Voltage - Time (OVR) Grading Matrix:
2. Over Voltage Relay Gradings:
Revised OVR Gradings for certain 400 kV Transmission Lines of Southern Region
Annexure-V (OVR-Gradings)
Page 1 of 5
414010 KURNOOL 400.00 414041 GHANI 400.00 2 16.26 0F
414010 KURNOOL 400.00 424003 GHANAPUR 400.00 1 226.5 0H
414010 KURNOOL 400.00 424005 SRISAILAMLB 400.00 1 104.9 0D
414010 KURNOOL 400.00 424021 MHSWRM-PG 400.00 1 175.01 0G
414011 KALPAKKA 400.00 414009 GAZUWAKA 400.00 1 3.39 0B
414011 KALPAKKA 400.00 414009 GAZUWAKA 400.00 2 3.39 0D
414011 KALPAKKA 400.00 414012 SIMHADRI-I 400.00 1 3.72 0A
414011 KALPAKKA 400.00 414012 SIMHADRI-I 400.00 2 3.72 0B
414011 KALPAKKA 400.00 414012 SIMHADRI-I 400.00 3 3.72 0D
414011 KALPAKKA 400.00 414012 SIMHADRI-I 400.00 4 3.72 0G
414011 KALPAKKA 400.00 414014 VEMAGIRI 400.00 1 166.93 0A
414011 KALPAKKA 400.00 414014 VEMAGIRI 400.00 2 166.93 0H
414011 KALPAKKA 400.00 414027 HINDUJA 400.00 1 7.35 0C
414011 KALPAKKA 400.00 414027 HINDUJA 400.00 2 7.35 0E
414011 KALPAKKA 400.00 424004 KHAMMAM 400.00 1 364 -0.5714I
414011 KALPAKKA 400.00 424020 ASUPAKA 400.00 1 131.07 -0.5714F
414042 K V KOTA 400.00 414027 HINDUJA 400.00 1 246 0B
414042 K V KOTA 400.00 414027 HINDUJA 400.00 2 246 0G
414042 K V KOTA 400.00 424016 SURYAPET 400.00 1 174.54 0A
414042 K V KOTA 400.00 424016 SURYAPET 400.00 2 174.54 0D
424003 GHANAPUR 400.00 414007 TALLAPALLI 400.00 1 155.26 0G
424003 GHANAPUR 400.00 414010 KURNOOL 400.00 1 226.5 0H
424003 GHANAPUR 400.00 424002 RSTPS NTPC 400.00 1 201.25 0B
424003 GHANAPUR 400.00 424002 RSTPS NTPC 400.00 2 201.25 0E
424003 GHANAPUR 400.00 424006 MAMIDIPALLI 400.00 1 46 0D
424003 GHANAPUR 400.00 424008 GAJWEL 400.00 1 72.95 -0.45351A
Annexure-V (OVR-Gradings)
Page 2 of 5
424003 GHANAPUR 400.00 424011 MALKARAM 400.00 1 54.9 -0.4535A
424003 GHANAPUR 400.00 424021 MHSWRM-PG 400.00 1 56.15 0C
424004 KHAMMAM 400.00 414007 TALLAPALLI 400.00 1 144.58 0C
424004 KHAMMAM 400.00 414007 TALLAPALLI 400.00 2 144.58 0F
424004 KHAMMAM 400.00 414007 TALLAPALLI 400.00 3 144.58 0H
424004 KHAMMAM 400.00 414008 NUNNA 400.00 1 114.78 0E
424004 KHAMMAM 400.00 414011 KALPAKKA 400.00 1 364 -0.5714G
424004 KHAMMAM 400.00 424006 MAMIDIPALLI 400.00 1 198 0D
424004 KHAMMAM 400.00 424006 MAMIDIPALLI 400.00 2 198 0I
424004 KHAMMAM 400.00 424010 WARANGAL 400.00 1 117.09 -0.4535A
424004 KHAMMAM 400.00 424012 KTPS-VI 400.00 1 67.76 0B
424004 KHAMMAM 400.00 424012 KTPS-VI 400.00 2 67.76 0D
424004 KHAMMAM 400.00 424020 ASUPAKA 400.00 1 131.07 -0.5714A
424006 MAMIDIPALLI 400.00 424003 GHANAPUR 400.00 1 46 0A
424006 MAMIDIPALLI 400.00 424004 KHAMMAM 400.00 1 198 0D
424006 MAMIDIPALLI 400.00 424004 KHAMMAM 400.00 2 198 0G
424006 MAMIDIPALLI 400.00 424019 DINDI 400.00 1 74.91 0B
424006 MAMIDIPALLI 400.00 424019 DINDI 400.00 2 74.91 0E
424013 SHANKARPALLI400.00 424008 GAJWEL 400.00 1 105 0D
424013 SHANKARPALLI400.00 424016 SURYAPET 400.00 1 231 0E
424013 SHANKARPALLI400.00 424016 SURYAPET 400.00 2 231 0H
424013 SHANKARPALLI400.00 424017 NARSARPUR 400.00 1 60.92 0A
424013 SHANKARPALLI400.00 424022 MAHES-TS 400.00 1 83.99 0B
424013 SHANKARPALLI400.00 424022 MAHES-TS 400.00 2 83.99 0G
424016 SURYAPET 400.00 414013 VTS-IV 400.00 2 130.95 0B
424016 SURYAPET 400.00 414042 K V KOTA 400.00 1 174.54 0A
Annexure-V (OVR-Gradings)
Page 3 of 5
424016 SURYAPET 400.00 414042 K V KOTA 400.00 2 174.54 0G
424016 SURYAPET 400.00 424011 MALKARAM 400.00 1 135.56 0E
424016 SURYAPET 400.00 424013 SHANKARPALLI400.00 1 231 0D
424016 SURYAPET 400.00 424013 SHANKARPALLI400.00 2 231 0H
424019 DINDI 400.00 424005 SRISAILAMLB 400.00 1 73.02 0A
424019 DINDI 400.00 424005 SRISAILAMLB 400.00 2 73.02 0D
424019 DINDI 400.00 424006 MAMIDIPALLI 400.00 1 74.91 0B
424019 DINDI 400.00 424006 MAMIDIPALLI 400.00 2 74.91 0G
424020 ASUPAKA 400.00 414011 KALPAKKA 400.00 1 131.07 0D
424020 ASUPAKA 400.00 424004 KHAMMAM 400.00 1 131.07 0A
424021 MHSWRM-PG 400.00 414010 KURNOOL 400.00 1 175.01 0F
424021 MHSWRM-PG 400.00 424003 GHANAPUR 400.00 1 56.15 0D
424021 MHSWRM-PG 400.00 424022 MAHES-TS 400.00 1 1.55 0B
424021 MHSWRM-PG 400.00 424022 MAHES-TS 400.00 2 1.55 0A
424022 MAHES-TS 400.00 424013 SHANKARPALLI400.00 1 83.99 0B
424022 MAHES-TS 400.00 424013 SHANKARPALLI400.00 2 83.99 0F
424022 MAHES-TS 400.00 424021 MHSWRM-PG 400.00 1 1.55 0A
424022 MAHES-TS 400.00 424021 MHSWRM-PG 400.00 2 1.55 0D
Annexure-V (OVR-Gradings)
Page 4 of 5
From Bus
NumberFrom Bus Name
To Bus
NumberTo Bus Name Ckt Id Length, km
Line Reactor VARS
at FROM BUS End
(pu)
New OVR Grading (at
FROM BUS end)
337003 WARDHA-PG 765.00 427001 NIZAMABAD 765.00 1 291.2 -2.4A
337003 WARDHA-PG 765.00 427001 NIZAMABAD 765.00 2 291.2 -2.4E
427001 NIZAMABAD 765.00 337003 WARDHA-PG 765.00 1 291.2 -2.4B
427001 NIZAMABAD 765.00 337003 WARDHA-PG 765.00 2 291.2 -2.4E
427001 NIZAMABAD 765.00 427002 MHSWRM 765.00 1 240 -2.4C
427001 NIZAMABAD 765.00 427002 MHSWRM 765.00 2 240 -2.4A
427002 MHSWRM 765.00 427001 NIZAMABAD 765.00 1 240 -2.4A
427002 MHSWRM 765.00 427001 NIZAMABAD 765.00 2 240 -2.4E
1. Voltage - Time (OVR) Grading Matrix:
2. Over Voltage Relay Gradings:
Revised OVR Gradings for certain 765 kV Transmission Lines of Southern Region
Annexure-V (OVR-Gradings)
Page 5 of 5