38 DONGYANG STRUCTURAL ENGINEERS GROUP

04 BIM Project in Korea

KOREA _ Asiana Hangar • Size : 5F, B1

• Gross Area : 27,443m²

• Architect : Keunjeong Architects

2 0 1 4 Dong Yang Structural Engineers Group

• Constructing Simulation

2 0 1 4 Dong Yang Structural Engineers Group

Top Rail

Hangar Door Hangar Door : Heavy Equipment Simulation

Pre - Construction

2 0 1 4 Dong Yang Structural Engineers Group

42 DONGYANG STRUCTURAL ENGINEERS GROUP

43 DONGYANG STRUCTURAL ENGINEERS GROUP

04 BIM Project in Korea

Pusan Haeundae Resort - Land Mark Tower

Size : 84F, B5

Gross Area : 660,077㎡

Architect : Samoo

44 DONGYANG STRUCTURAL ENGINEERS GROUP

Pusan Haeundae Resort Land Mark Tower

– Belt Wall Proposal

• SRC System

• Steel System

• RC System

45 DONGYANG STRUCTURAL ENGINEERS GROUP

04 BIM Project in Korea

D- Tower – Reinforced Concrete Rebar Model

Size : 24F & 2 Tower, B8

Gross Area : 1,053,939㎡

Architect : Samoo

46 DONGYANG STRUCTURAL ENGINEERS GROUP

Revit Basic Model

Alplan Re-bar Model

D- Tower – Reinforced Concrete Rebar Model

47 DONGYANG STRUCTURAL ENGINEERS GROUP

04 BIM Project in Korea

F K I – the Federation of Korean Industries Tower

Size : 50F, B6

Gross Area : 170,104㎡

Architect : ASGGE, Changjo

2 0 1 4 Dong Yang Structural Engineers Group

First Phase Model

2 0 1 4 Dong Yang Structural Engineers Group

FKI – the Federation of Korean Industries : Podium

Create vertical planes from

architectural division Vertical planes and new free surface i

ntersection

2 0 1 4 Dong Yang Structural Engineers Group

is the first non-rotated rib 15

0

4

8 11 14

Study Construction from Various Rib - Plan

2 0 1 4 Dong Yang Structural Engineers Group

Analysis - Robot

Revit Structure

BIM Model & Analysis Model

2 0 1 4 Dong Yang Structural Engineers Group

53 DONGYANG STRUCTURAL ENGINEERS GROUP

04 BIM Project in Korea

• Size : 3F, B1

• Gross Area : 3,688m²

• Architect : Asymptote

Ega Architects

The Arc

2 0 1 4 Dong Yang Structural Engineers Group

First Phase (Concept + SD)

– Rhino + Grasshopper & 2D CAD

2 0 1 4 Dong Yang Structural Engineers Group

Second Phase (DD+CD)

– Revit Structural

2 0 1 4 Dong Yang Structural Engineers Group

Analysis

MIDAS

Robot

SCIA

Transformation - Analysis

2 0 1 4 Dong Yang Structural Engineers Group

Construction Phase

– Tekla Structure & CATIA

Detailing

Advance Steel

Tekla

CATIA

2 0 1 4 Dong Yang Structural Engineers Group

60 DONGYANG STRUCTURAL ENGINEERS GROUP

04 BIM Project in Korea

2015 Gwangju Summer Universiade Swimming Pool

Size : 3F, B1

Gross Area : 88,506㎡

Architect : UI Architecture, Pos A&C

2 0 1 4 Dong Yang Structural Engineers Group

Alt 1

Alt 2 Revit Model

First Phase (Concept + SD)

– Rhino + Grasshopper

2 0 1 4 Dong Yang Structural Engineers Group

Second Phase (DD+CD)

– Revit Structural

Before After

2 0 1 4 Dong Yang Structural Engineers Group

Construction Phase

– Tekla Structure

64 DONGYANG STRUCTURAL ENGINEERS GROUP

해외 BIM 프로젝트

05

65 DONGYANG STRUCTURAL ENGINEERS GROUP

05 BIM Project in Overseas

Size : 4F

Gross Area : 9,960㎡

Architect : Arup

Saudi Arabia - King Abdulla Sports City – Multi-Purpose Sports Hall

2 0 1 4 Dong Yang Structural Engineers Group

Second Phase (DD+CD)

– Revit Structural

2 0 1 4 Dong Yang Structural Engineers Group

Revit Quantity

2 0 1 4 Dong Yang Structural Engineers Group

Construction Phase

– Tekla Structure