bill walter & lenn vincent january 11, 2017 · bill walter & lenn vincent january 11, 2017...
TRANSCRIPT
1government contracting
@DHG_GovConSubcontract Closeouts: A High Priority
Bill Walter & Lenn VincentJanuary 11, 2017
Issues in Focus Webinar
Series
2government contracting
@DHG_GovConYour Presenters
Bill WalterDixon Hughes Goodman [email protected]
RADM Lenn Vincent (ret.)The Subcontract Management [email protected]
3government contracting
@DHG_GovConAgenda
• What is a Subcontract?
• Close-out Process
• Why the Hub-Bub?
• Systemic Issues & Challenges
• Helpful Hints
4government contracting
@DHG_GovCon
What is a Subcontract?
5government contracting
@DHG_GovConDefinition
• The FAR contains many definitions of “Subcontract”:
– FAR 3.502 - a contract or contractual action entered into by a prime contractor or
subcontractor for the purpose of obtaining supplies, materials, equipment, or
services of any kind under a prime contract.
– FAR 3.10 - any contract entered into by a subcontractor to furnish supplies or
services for performance of a prime contract or a subcontract.
– FAR Part 12 - includes, but is not limited to, a transfer of commercial items
between divisions, subsidiaries, or affiliates of a contractor or subcontractor.
– FAR 15.4 - (except as used in 15.407-2) [dealing with make or buy programs]
also includes a transfer of commercial items between divisions, subsidiaries, or
affiliates of a contractor or a subcontractor
– FAR 44.101 - means any contract as defined in Subpart 2.1 entered into by a
subcontractor to furnish supplies or services for performance of a prime contract
or a subcontract. It includes but is not limited to purchase orders, and changes
and modifications to purchase orders.”
6government contracting
@DHG_GovConSubcontracts are “Different”
• Like price and contract type, terms and conditions are a risk-sharing
mechanism:– Price agreement alone does not define the business arrangement.
– The price must be associated with agreement on the terms and conditions.
• There is no privity of contract between the subcontractor and the
government.– FAR 42.505(b)(1) requires the Government to recognize that there is no privity between the
government and the subcontractor.
– However, the government requires the flow down of terms and conditions to comply with law.
– The prime contractor flows down the mandatory terms and conditions to comply with its
obligations under the prime contract.
• Subcontracts under a government prime contract are a hybrid of industry
commercial clauses and FAR clauses, which implement federal acquisition
law and regulations.
• The primary governing body of law in the subcontracting environment is
commercial contract law (not the FAR or federal law).
• This generally takes the form of state enacted versions of the Uniform
Commercial Code (UCC).
7government contracting
@DHG_GovConRelationships - Stakeholders
• PCO
• Program Office
• Oversight – DCAA/DCMA
• Congress/Agency/Etc.
Government
• Contract Manager
• Program Manager
• Subcontract Administrator
• Accounting & Finance
Prime Contract
• Program Manager
• Subcontract Manager
• Accounting & FinanceSubcontract
8government contracting
@DHG_GovConRelationships - Perspectives
• Prime Contractor
– Contractual relationships are often rocky, and hard to manage, but
subcontracting is critical for success in the global market place
– The value proposition is based on technical expertise, international market
and global customer knowledge
• Subcontractor
– The prime-subcontractor relationship is critical and growing in importance in
a dynamic global market shaped by fewer opportunities as a result of
declining budgets and a much tougher business environment
– May not want to share sensitive information with a potential competitor
– Primes must resist unfairly shifting risk to subcontractors… better
risk/reward balance
• Government
– Both prime and subcontractor must stay focused on the “main thing”
– Deliver high quality products and services at cost and within the agreed
schedule
– Strong teaming and collaboration… no surprises
9government contracting
@DHG_GovCon
• The majority of activities that occur at the Subcontract level
• Public, Private, Commercial, Large, Medium, Small, and Foreign Companies
can affect closing out the Subcontract
The Iceberg Effect
10government contracting
@DHG_GovCon
Close-Out Process
11government contracting
@DHG_GovConWhat is a Contract Close-Out?
• Prime – an administrative process
– Begins after contract is physically complete
• All products delivered, inspected and accepted
• All services performed and accepted
– Close-out complete when:
• All administrative actions completed
• All disputes are settled
• Final payment has been made
• Subcontract – many parallels?While the formal process begins when the contract is complete, the informal process begins with contract award and managed throughout the contract
12government contracting
@DHG_GovConRegulation - FAR 4.804
• Prime - Close-out of contract files
– Close-out by PCO
– Close-out by ACO
– Close-out by paying office
– Physically completed contracts
– Procedures for closing out files
• Subcontract – parallels?
13government contracting
@DHG_GovConFAR 4.804-1 Close-out by PCO
• Prime:
– Time standards:
• Simplified Acquisition – Closed when completed
• Firm fixed price – within 6 months
• Contracts requiring indirect cost rates – 36 months
• All other contracts – 20 months
– Procedures – standard or quick closeout
– Do not Close-out:
• Contracts in litigation or under appeal
• Terminated contracts where actions are open
• Subcontract – parallels?
14government contracting
@DHG_GovConFAR 4.804-4 Physically Completed
• Prime - A contract is considered to be
physically complete when:
– All deliveries are made and the Government
has inspected and accepted the supplies
– All services are performed and the
Government has accepted these services
– All option provisions, if any, have expired; or
– The Government has given the contractor a
notice of complete contract termination.
• Subcontract – parallels?
15government contracting
@DHG_GovConFAR 4.804-5 Close-out Procedures
• Review contract fund status
• 15 point checklist for close-out
• Prepare contract completion statement
– Subcontract file
– Communication with Customer
16government contracting
@DHG_GovCon15 Points – Non-financial Issues
1. Disposition of classified material is completed
2. If a final patent report is required, may proceed
with contract closeout.
3. Final royalty report is cleared
4. There is no outstanding value engineering
change proposal
5. Plant clearance report is received
6. Property clearance is received
17government contracting
@DHG_GovCon15 Points - Financial Issues
7. All interim or disallowed costs are settled
8. Price revision is completed
9. Subcontracts are settled by the prime
contractor
10.Prior year indirect cost rates are settled
11.Termination docket is completed
12.Contract audit is completed
18government contracting
@DHG_GovCon15 Points - Final Documents
13.Contractor’s closing statement is completed
14.Contractor’s final invoice has been submitted
15.Contract funds review is completed and
deobligation of excess funds occurs
19government contracting
@DHG_GovCon
Why all the Hub-Bub?
20government contracting
@DHG_GovConContract Closeout – Systemic Issues
• 2005 DoD Public meeting
• Industry identified 23 areas of comment and/or
recommendation
• #8 was Subcontracts – included:
– Closeout Plan for Subcontracts (DPAP said no)
– Require the Use if Quick Closeout Procedures for Subcontracts
(DPAP said FAR 42.202 states Prime is responsible for
managing subs under existing regs)
– Waiver of Subcontract Assist Audits (DPAP will review)
– Requirement for Audit Coordination between Prime and DCAA
(DPAP will review)
– Use of 3rd Party Auditors to Complete Subcontractor Assist
Audits (DPAP said no)
21government contracting
@DHG_GovConFinal Rule
• August 20, 2009 Proposed Rule to update FAR
made following changes to FAR 52.216-7 for
subcontracts:
– Spelled out requirements for incurred cost submission:
• Schedule J – Subcontract information
• Optional Schedule D – List where prime is a flex-priced sub
– Added subparagraph 5) “The completion invoice or
voucher shall include settled subcontract amounts and
rates. The prime contractor is responsible for settling
subcontractor amounts and rates included in the
completion invoice or voucher and providing status of
subcontractor audits to the contracting officer upon
request.”
22government contracting
@DHG_GovConFactors Affecting SubK Closeout
External
• Funding
– Amount
– Expiration
• Sub final rates not
completed
• Pending legal matters
• Business system review
status
• Open REA/Claim
• Gov’t Challenges
Internal
• Subcontract document not
clear
• Privity
• Policy / Procedure
• Document retention
• SubK data requirements
• Subcontractor compliance
• Tax or other financial
implications
23government contracting
@DHG_GovConQuick-Closeout Procedure
• “The contracting officer responsible for contract
closeout shall negotiate the settlement of direct and
indirect costs” in advance of the determination of final
direct costs and indirect rates if:
– The contract or order is physically complete
– The amount of unsettled direct costs and indirect costs is
relatively insignificant – ($1M or 10% of SubK)
– The contracting officer performs a risk assessment and
determines that the use of the quick-closeout procedure is
appropriate
– Agreement can be reached on a reasonable estimate of
allocable dollars
24government contracting
@DHG_GovConSubcontractor Delays
• Indirect rates not settled
• Accounting challenges
• Gov’t Property not dispositioned
• Final acceptance not obtained
• Unresolved Forms 1
• Missing:
– Patent or royalty reports
– Contract release
– Classified material
– Open final price re-determination
25government contracting
@DHG_GovConPrime Delays
• Reconciling different accounts –
Accounting vs. Subcontractor
• Access to subcontractor records / waiting
on final rates
• Waiting for funds
• Fee withholdings
• Waiting for final voucher
• Final payment not made
26government contracting
@DHG_GovConJoint Delays
• Overhead rate negotiation pending
• Disallowed costs pending
• Pending contract modifications
• Warranty actions
• Appeals and litigation
• Contract terminations in process
27government contracting
@DHG_GovConWhy does it take so long?
• DCAA ICS Backlog - improving
• Finding records
• Complex funding and associated
reconciliation
• Confirm and verify ALL requirements are
met
• Closeout is the lowest priority
• Determination of award and incentive fees
28government contracting
@DHG_GovConWhat can you do?
• Be proactive - Plan ahead
– The first time you talk to the subcontractor
shouldn’t be when you are trying to settle the
subcontract price
• Accounting Process
• Admin Process
– Close-out Checklist
– Tool Box
Rates –Interim / Final
29government contracting
@DHG_GovConWords of Advice
• Be prepared
• Communicate internally
• Communicate with Subcontractor
• Communicate with Government
• Provide leadership and decision making
• Be prepared to take some risk
30government contracting
@DHG_GovConNavigating Around Reluctance
• Natural aversion to take risk
• Trust but verify
• Business case often not substantiated
• Lack of quick closeout experience
• “Washington Post” test
31government contracting
@DHG_GovConQuestions?
32government contracting
@DHG_GovCon
Join us next month on Wednesday, February 8th
Issues in Focus Webinar Series