bill palazzi, transport for nsw
TRANSCRIPT
Rail Safety in NSW Investing in technology to improve commuter
safety and service reliability
Bill Palazzi Technical Manager
Advanced Train Control Systems Programme
25 March 2014
Safety and performance:
traditional enemies?
2
Diagram from JJC Bradfield, Proposed Electric Railways for the City of Sydney, 1916
Capacity calculations assume dwell times of 30 second, including train
deceleration and acceleration.
• If able to be achieved, this is dependant on open train doors, alighting and
boarding while the train is moving, etc.
This is not a safety regime that would be acceptable in today’s railway.
Drivers of the current ATP
programme
• Waterfall Rail
Accident and Report
of the Special
Commission of
Inquiry
• Safety benefit for
customers
• Enabler for future
capacity
improvements
The journey thus far …
4
DATE ACTIVITIES
2006 • Recommendation that RailCorp implement an ATP system
2008 • ETCS Pilot Trial Complete
2010 • Funding approved for first ATP Package
2011 • Contract for supply of first package awarded to Alstom
• ATP works begin on Main North Line
2012 • Contract for installation of equipment on Oscar trains awarded to Alstom
• RailCorp System Testing 1
• Consolidated Train Operating System (TOS) rollout
2013 • RailCorp System Testing 2
2014 / 2015 • Oscars Fleet Rollout
• Trackside Rollout
• ATP Passenger Service between Wyong and Asquith (excluding Gosford)
2017 • Completion of Approval Package 1
Scope and rollout strategy
Approval Package 1 (AP1)
Tangara
Approval Package 2 (AP2)
Oscar
Millennium Waratah
5
Why revisit the strategy?
6
• The second stage of investment in ATP (Approval
Package 2) needs to be taken forward.
• ATP is a safety requirement for network but it would also
be desirable to leverage off this investment for
performance as well as safety.
• Need to provide for higher performance at train
frequencies of 20 per hour on key corridors. Advanced
systems will be a key component in achieving this.
• Need for replacement of large, life expired signalling
installations.
• Technology has changed.
Plan for Sydney’s Rail Future
7
Introduction of Automatic Train Operations
8
Objective of any Rail Systems
initiative
• Any strategy for rail systems must align with the vision
for Sydney’s Rail Future and contribute to TfNSW’s
Strategic Business Requirements:
– Safety – enhance and maintain safety for passengers, staff and
others
– Cost – reduced project, operational and maintenance costs
– Capacity – optimise the capacity of the network, to meet service
requirements
– Carbon – move towards intelligent systems that optimise train
movements to reduce energy consumption
– Customer Satisfaction – improve reliability, provide a platform
to support initiatives such as consolidated control.
9
System Options
Existing (train stops)
Intermittent ATP +
Resignal
Intermittent ATP Overlay
Continuous ATP Overlay
Increasing automation of train management
System defined by existing signalling. ATP simply takes
the place of trainstops.
Existing system is optimised to achieve full benefits of
ATP – for example, removal of overlaps, removal of
signals possible (if in-cab).
Continuous ATP +
In-Cab + moving block
Continuous ATP +
In-Cab + ATO + moving
block
Continuous ATP +
In-Cab + ATO + moving
block + ATR / ATS
Moving block results in minimal trackside equipment (no track circuits required).
Control of trains by
driver. SPAD protection is
reactive (trainstops).
Driver drives, but speed
profile enforced by the system. Authority
from lineside signals.
Driver may be present but automatic
operation is possible, to
limits enforced by
ATP.
Driver drives, but speed
profile enforced by the system. Authority
from lineside or in-cab.
Driver may be present but automatic
operation is possible, plus
dynamic regulation of
trains.
Incr
eas
ing
eff
icie
ncy
of
sign
allin
g ar
ran
gem
en
ts
Continuous ATP Overlay +In-Cab + ATO
Continuous ATP +
Resignal
Continuous ATP +
In-Cab + ATO + Resignal
Continuous ATP +
In-Cab + ATO + virtual blocks
Continuous ATP +
In-Cab + virtual blocks
Fixed blocks remain, but are augmented using virtual
blocks to provide increased capacity.
Continuous ATP +
In-Cab + ATO + virtual
blocks+ ATR /ATS
Continuous ATP Overlay + In-Cab + ATO
ATR /ATS
Continuous ATP +
In-Cab + ATO + Resignal +
ATR /ATS
Scope of existing ATP project
Scope of proposed L2 trial
To be implemented on NWRL
Likely progression
Variants of ETCS L1
Variants of ETCS L2
Variants of ETCS L3 /
CBTC
10
Long term vision for systems
Anticipated benefits
Strategic Business
Requirement
Advanced Train Control Systems
Contribution
Safety • SPAD protection
• Overspeed protection
• Maintenance worker safety
Cost Simplified trackside infrastructure leads to
• Lower capital costs
• Lower operational and maintenance costs
Capacity • Consistency in train behaviour
• Reduced platform re-occupation times
• Increased capacity
Carbon • Optimised energy consumption for trains
• Reduced energy consumption by trackside
infrastructure
Customer
Satisfaction
• Higher performance / higher reliability services
• Lower operational impact during project work
• Reduced journey times 11
SPAD protection
12
Overspeed protection
13
Simplified trackside infrastructure
14
… by the use of
cab signalling
Simplified trackside infrastructure
15
Level 2 ATP requires:
• Train detection (track circuits
or axle counters)
• Balises (for odometry
correction)
• Point machines and
detection
Level 3 ATP requires:
• Balises (for odometry
correction)
• Point machines and
detection
• But – also requires on-board
train integrity management
Cab signalling
16
Benefits will include:
• Lower capital costs – typically put at 40% or less of the equivalent
conventional arrangement
• Lower maintenance costs
• Less need for workers to be trackside = higher levels of safety
Variability in train behaviour
17
Redfern to
Central Wynyard to
Milsons Point
Town Hall to Wynyard
Central to
Town Hall
The current level of
variability in train
behaviour can mean
over a minute
difference in travel time
in individual sections
Wynyard
Town Hall
Central
Redfern
Through the core of the
network, one slower
train can result in
several minutes
additional travel time,
equivalent to the loss of
one or more paths
braking distance overlapsighting
Emergency braking applied by trainstop if necessary, to stop train within overlap
Line speed
Stopped
Normal operation at service braking, to stop at red signal
Train must clear this overlap before the
signal shown red will change to yellow
One clear block(= braking distance)
Track blocks regulate train separation but also
demonstrate train integrity
Increasing capacity
18
Traditional signalling with trainstops
ATP Level 2 (Continuous ATP)
braking distance
Line speed
Stopped
ATP enforces normal operation at service braking, to ensure
train stops at block point
ATP
Train must move to next block before following
train’s movement authority can be extended
Data radio communication to
trains
Signals removed, blocks represented in on-board system
Block point
ATP
overlapone clear block‘Sighting distance’ eliminated by continuous
update via radio
Minimum separation between following trains
Minimum separation between
following trains
Reducing platform reoccupation
times
19
• Modelling suggests that re-spacing of
blocks through core areas can reduce
platform reoccupation times
Source – David Morton, Siemens,
presentation to WCRR 2013 Sydney
Closely spaced blocks
at the rear of the
platform, to provide an
updated movement
authority to the
following train as soon
as possible.
Direction of travel
Outcomes from modelling work
20
Target – 24tph
Modelling of ETCS L1 for
Sydney – max. 22tph
Modelling of ETCS L2 for
Sydney – max. 24tph
ThamesLink target for
L2 w.ATO – 24tph
Outcome of Line Capacity Study
with ATP/ATO – max. 26tph
Notional outcome –
30tph
No clear view on timing of a
high capacity version of L3
Examples exist worldwide of
capacity 30tph and above
Capacity limit under a
moving block system likely
to be as a result of corridor
and alignment parameters
Modelling of ETCS L2 in
Brisbane (90 sec dwell)
Area controlled by
Sydney Interlocking
Area controlled by North
Sydney Interlocking
Area controlled
by Strathfield
Interlocking
21
Upcoming asset renewals
necessary
Overlay approach to deployment
22
Train control location
Interlocking location
Trackside interface location
Signal
Track circuit boundary
Trainstop
Point machine
Main cables
Local cables
Existing signalling arrangement
Note – configuration is illustrative only
Train control location
Interlocking location
Trackside interface location
Signal
Track circuit boundary
Trainstop
Point machine
Main cables
Local cables
Overlay of new equipment, in shadow mode
Train control location
Interlocking location
Trackside interface location
New cabling to connect to existing
point machines
Axle counter headExisting (operational) signalling equipment shown in blackNew (shadow overlay) signalling equipment shown in red
Block lengths optimised for new
configuration
Passive balise
Overlay approach to deployment
23
Train control location
Interlocking location
Trackside interface location
Signal
Track circuit boundary
Trainstop
Point machine
Main cables
Local cables
Commissioning of new system
Train control location
Interlocking location
Trackside interface location
New cabling to connect to existing
point machines
Axle counter headNew (operational) signalling equipment shown in blackExisting (redundant) signalling equipment shown in green
Passive balise
Overlay approach to deployment
24
Overlay approach to deployment
25
Point machine
Final signalling arrangement after removal of redundant equipment
Train control location
Interlocking location
Trackside interface location
Axle counter head
Note – configuration is illustrative only Passive balise
Grade of Automation
Type of Train
Operation
Sets Train in Motion
Stopping Train
Door Closure
Operation in event of
Disruption
GoA1 ETCS L2With Driver
Driver Driver Driver Driver
GoA2ETCS L2 &
ATOWith Driver
Automatic Automatic Driver Driver
GoA3 Driverless Automatic AutomaticTrain
AttendantTrain
Attendant
GoA4Unattended
Train Operation
Automatic Automatic Automatic Automatic
Grades of Automation
26
Optimisation of energy
consumption with ATO
27
Source – David Morton, Siemens,
presentation to WCRR 2013 Sydney
• There are four driving phases: acceleration, cruising, coasting and
braking.
• The ATO algorithm optimizes the cruising and coasting phases.
Optimisation of energy
consumption with ATO
28
Source – UNISIG specification for ATO
with ETCS
Non-optimised
approach to a
station
Optimisation of energy
consumption with ATO
29
Source – UNISIG specification for ATO
with ETCS
Energy-optimised
approach to a station.
Estimates of the energy
saving possible range
between 10 and 40%.
Freight and mixed traffic
30
• System must be
seamless for freight
and mixed traffic.
• Interface to ATMS /
ICE.
• But - there will be
benefits for freight
and mixed traffic: • SPAD and
overspeed
protection
• Capacity –
increased paths
braking distance overlapsighting
Emergency braking applied by trainstop if necessary, to stop train within overlap
Line speed
Stopped
Normal operation at service braking, to stop at red signal
Train must clear this overlap before the
signal shown red will change to yellow
One clear block(= braking distance)
Track blocks regulate train separation but also
demonstrate train integrity
Increasing capacity – mixed traffic
impacts
31
Traditional signalling with trainstops
ATP Level 2 (Continuous ATP)
braking distance
Line speed
Stopped
ATP enforces normal operation at service braking, to ensure
train stops at block point
ATP
Train must move to next block before following
train’s movement authority can be extended
Data radio communication to
trains
Signals removed, blocks represented in on-board system
Block point
ATP
overlapone clear block‘Sighting distance’ eliminated by continuous
update via radio
In traditional signalling,
braking distance is set
within the system and
must allow for the worst
braked train at the highest
permissible speed.
With cab signalling,
each train’s braking
distance is based
on that train's
individual
characteristics
Capacity is optimised for mixed traffic as well!
System rollout: significant coming
events
• Pilot trial of ETCS L2 between Arncliffe and Oatley, likely to
commence in 2015?
• Subsequent network ‘events’ that may influence the potential next
stages of rollout:
2019 Commissioning of North West Rail Link
− Operational need to establish reliable high frequency services
to meet additional demand from NWRL between Sydney CBD
and Chatswood.
2020 Nominal life expiry of Sydney Interlocking.
2022 Nominal life expiry of Strathfield Interlocking
32
Summary
With modern train control systems, safety and performance no
longer have to be traditional enemies!
• In response to the release of Sydney's Rail Future, TfNSW is taking
the opportunity to revisit the systems strategy for Sydney, with a
focus on the strategic business requirements of Safety, Cost,
Capacity, Carbon and Customer Satisfaction.
• Adopting advanced Train Control Systems present an opportunity
for substantial benefits to the Sydney network.
• There is a fair bit of water to go under the bridge yet, but some of
the issues and strategies discussed in this presentation may form
part of the ultimate solution.
33
Questions?