BILL OF QUANTITY

Bill of Quantity

Name of work:Construction of Security Wall Approach Road, Maingate, security hut at 132KV S/S bindaki, distt.-fatehpur. Sl.No.Item of workUnitQty.RateAmount

123456

1.Excavation in foundation in ordinary soil (Loam Clay or sand) including lift upto 1.5 m and lead upto 30m and including filling, watering and ramming of excavated earth into the trenches or into the space between the building and insides of the foundation trenches or into the plinth and removal and disposal of surplus earth as directed by the engineer-incharge upto a distance of 30m from the foundation trenches. (SOR4.01)Cu.M480.0057.6027,648.00

(Rs. Fifty Seven and Paise Sixty Only)

2.Concrete with 40mm Stone ballast, coarse sand (F.M. 1.8 to 2.5) and cement in proportion 12:6:1 in foundations and under floors including supply of all materials, labour and tools and plants etc. required for proper completion of the work. (SOR-5.02)Cu.M 86.50 2578.00 2,22,997.00

(Rs. Two Thousand Five Hundred Seventy Eight Only)

3.As above item No. 2 but with 40mm brick ballast as per SOR- No. 5.01.Cu.M.26.001931.0050,206.00

(Rs. One Thousand Nine Hundred Thirty One Only)

4.Cement Concrete with 2cm gauge approved hard stone ballast, coarse sand (F.M. 1.8 to 2.5) and cement in proportion of 1:2:4 including supply of all materials, side shuttering if required and T&P etc. required for proper completion of work. (SOR-5.06)Cu.M2.203636.007,999.20

(Rs. Three Thousand Six Hundred Thirty Six Only)

##2##

Construction of Security Wall Approach Road, Maingate, security hut at 132KV S/S bindaki, distt.-fatehpur. Sl.No.Item of workUnitQty.RateAmount

123456

5.RCC work with cement approved coarse sand (F.M. 1.8 to 2.5) and 2 cm gauge graded approved hard stone ballast in proportion 1:2:4 in lintels of doors and windows, excluding supply of reinforcement and its bending but including its fixing and binding the same with 24 B.W.G. G.I. binding wire and including necessary centering and shuttering etc. and also including cost of all materials, binding wire, labour and T&P etc. required for proper completion of the work (binding wire to be supplied by the contractor free of cost.) (SOR-5.10)Cu.M. 0.404156.00 1,662.40

(Rs. Four Thousand One Hundred Fifty Six Only)

6.Same as above in Item No.-5 but for slabs in 1:1.5:3 proportion. (SOR-5.24) Cu.M. 2.255205.00 11,711.25

(Rs. Five Thousand Two Hundred Fine Only)

7.Same as above in Item N.-5 but for lighter beams i.e. having span upto 6m. (SOR-5.12) Cu.M. 21.305181.00 1,10,355.30

(Rs. Five Thousand One Hundred Eighty One Only)

8.Same as above in Item No.-5 but for RCC raft foundation and footings. (SOR-5.15) Cu.M.44.203892.001,72,026.40

(Rs. Three Thousand Eight Hundred Ninety Two Only)

9.Same as above in Item No.-5 but in RCC columns in 1:1.5:3 proportion.

(SOR-5.17) Cu.M.60.205713.003,43,922.60

(Rs. Five Thousand Seven Hundred Thirteen Only)

10.First class brick (class-150) work in 1:6 cement and coarse sand (F.M. 1.8 to 2.5) mortar in foundation and plinth including supply of all materials, labour, T&P etc. required for proper completion of work.

(SOR-6.01)Cu.M.196.002150.00 4,21,400.00

(Rs. Two Thousand One Hundred Fifty Only)

##3##

Construction of Security Wall Approach Road, Maingate, security hut at 132KV S/S bindaki, distt.-fatehpur. Sl.No.Item of workUnitQty.RateAmount

123456

11.Same as above in item no. -10 but in super structure including necessary cutting and moulding of bricks as required and also including honeycomb brick work, thickness of wall not to be less than 1 brick thick. (SOR-6.01 + 6.07 + 6.08) Cu.M. 196.90 2378.004,68,228.20

(Rs. Two Thousand Three Hundred Seventy Eight Only)

12.2.5 cm thick damp proof coarse with cement concrete consisting of one part cement, 1.5 parts approved coarse sand and 3 parts of approved 13mm graded stone grit and also including water proofing material as ordered by the Engineer-Incharge in the proportion as specified by the manufacture. (SOR-7.02) Sq.M. 2.30165.10 379.73

(Rs. One Hundred Sixty Five and Paise Ten Only)

13.S/F of 32 mm thick single leaf flush door shutter (Boiled water resistance, phenol maldehide resin bonded, hot pressed factory made) commercial quality to I.S. 2202 part -1 (1983) ISI marked including fixing of wooden cleats and stoppers and including fixing and adjustment of hinges, including supply of all labour materials and T&P required for work. (SOR.-8.80a)Sq.M 1.60975.00 1,560.00

(Rs. Nine Hundred Seventy Five Only)

14.Approximate cost of chromium polished iron fittings with screws for doors, window etc. (SOR-8.58) Sq.M. 1.60160.00 256.00

(Rs. One Hundred Sixty Only)

##4##

Construction of Security Wall Approach Road, Maingate, security hut at 132KV S/S bindaki, distt.-fatehpur. Sl.No.Item of workUnitQty.RateAmount

123456

15.Mild steel or iron work in heavy sizes such as trusses built up gates, door frames, records, racks roof work gates etc. wrought to required form including holes rivetting or welding where necessary and also fixing in proper position and alignment including supply of steel bolts nuts wastage etc. and their fixing required for proper completion of the work, including cost of steel (which shall be arranged by the contractor). (SOR-9.03) M.T. 8.6061277.00 5,26,982.20

(Rs. Sixty One Thousand Two Hundred Seventy Seven Only)

16.Mild steel or iron in plain work such as reinforced concrete or reinforced brick work (when not included in an over all rates) wroght to required shape as necessary including bending for proper completion of the work and including supply of steel its wastage, bend, hooks and authorized overlapping shall be measured (steel shall be arranged by the contractor). (SOR-9.05) M.T. 10.2559134.00 6,06,123.50

(Rs. Fifty Nine Thousand One Hundred Thirty Four Only)

17.12mm thick plaster with cement mortar in proportion 1:4 cement and coarse sand of 2.5 fineness modulus over brick work minimum thickness not to be less than 10 mm including supply of all materials, labour and T&P etc. required for proper completion of the work. (SOR-11.08)Sq.M. 2760.0081.50 2,24,940.00

(Rs. Eighty One and Paise Fifty Only)

##5##

Construction of Security Wall Approach Road, Maingate, security hut at 132KV S/S bindaki, distt.-fatehpur. Sl.No.Item of workUnitQty.RateAmount

123456

18.Add for extra labour and materials for plaster over rough face of one brick thick wall. (SOR-11.15)Sq.M. 853.007.00 5,971.00

(Rs. Seven Only)

19.Providing (12x15mm) section groove in plaster at the junction of ceiling & walls, including all material, labour and T&P etc. required for proper completion of the work. (SOR-11.19)R.M. 2772.004.80 13,305.60

(Rs. Four and Paise Eighty Only)

20.S/F water proof craft paper in double layer with grease in between over 4cm thick C.c. 1:1:5:3 in cement, coarse sand & 12mm gauge stone grit. (C.C. 1;1:5:3 shall be paid separately )

(SOR-10.13)Sq.M. 2.9540.80 120.36

(Rs. Forty and Paise Eighty Only)

21.2 cm thick cement plaster in dado or skirting in 1:2 consisting of one parts of cement and two parts of approved coarse sand laid in panels finished with 3mm floating coat of neat cement or cement and marble dust in ratio of 5:1 including supply of all materials, labour & T&P etc. required for proper completion of the work. (SOR-11.16)Sq.M. 1.00134.00 134.00

(Rs. One Hundred Thirty Four Only)

22.6 mm thick plaster with 1:3 cement and coarse sand mortar including labour, materials and T&P etc. required for proper completion of the work. (SOR-11.20)Sq.M. 19.6067.70 1,326.92

(Rs. Sixty Seven and Paise Seventy Only)

##6##

Construction of Security Wall Approach Road, Maingate, security hut at 132KV S/S bindaki, distt.-fatehpur. Sl.No.Item of workUnitQty.RateAmount

123456

23.2.5 cm. thick 1:2:4 plain cement concrete floor with cement, approved coarse sand and 2cm graded approved stone ballast laid in panels finished with 3mm floating coat of neat cement or cement and marble dust in ratio of 5:1 as specified and removing any overlapping mortar at the joints of the panels if any and giving them a uniform finish including supply of all materials, labour and t&P etc. required for proper completion of the work. (SOR-12.02)Sq.M. 19.10134.00 2,559.40

(Rs. One Hundred Thirty Four Only)

24.Painting or varnishing new iron work in small areas or new wood work with one coat of ready mixed priming paint and two coat of approved superior quality ready mix paint Luxol or equivalent brand or varnish including supply of all materials, labour and T&P etc. required for proper completion of the work. Paint to be used should conform to the I.S. 103-1950. (SOR-13.01 + 13.02) Sq.M. 338.8053.80 18,227.44

(Rs. Fifty Three and Paise Eighty Only)

25.Finishing walls with water proof cement paint of approved made like Super Snowcem or equivalent quality on new work first coat as primer coat and second and third coat to give an even shade including supply of all materials, labour and T&P etc. required for proper completion of work.

(SOR-13.07 + 13.08) Sq.M. 2708.0043.90 1,18,881.20

(Rs Forty Three and Paise Ninety Only)

##7##

Construction of Security Wall Approach Road, Maingate, security hut at 132KV S/S bindaki, distt.-fatehpur. Sl.No.Item of workUnitQty.RateAmount

123456

26.2.5 cm thick cement concrete consisting of one part cement 1.5 part coarse sand and 3 parts of 13mm graded stone aggregate on the bearing under slab and coping of walls and columns as per direction of engineer-incharge.

(SOR-7.02-0.25xSOR-11.18) Sq.M134.80154.5520,833.34

(Rs. One Hundred Fifty Four and Paise Fifty Five Only)

27.Ist Class bricks on edge floor laid dry joints sand filled, including preparation of base to proper slope and its ramming including supply of all materials, labour and T&P etc. required for proper completion of the work as SOR-12.08. Sq.M. 800.00206.00 1,64,800.00

(Rs. Two Hundred Six Only)

28.Laying C.C. Road slab 15cm thick consisting of 1 cement 2 approved coarse sand 4 approved stone ballast 2cm gauge over prepared sub grade after its rectifications and bringing it to proper camber and including supply of all materials, labour and T&P etc. required for proper completion of the work, finished to required template as per directions of the Engineer-in-Charge but excluding cost of Metal required for the rectification of the sub grade. (SOR-18.13) Cu.M. 120.004,516.005,41,920.00

(Rs. Four Thousand Five Hundred Sixteen Only)

29.Filling of 20mm wide 80/100/150 deep joint coarse sand and saw dust mixed with hot bitumen etc. complete. (SOR-18.20) RM320.0029.109,312.00

(Rs. Twenty Nine and Paise Ten Only)

##8##

Construction of Security Wall Approach Road, Maingate, security hut at 132KV S/S bindaki, distt.-fatehpur. Sl.No.Item of workUnitQty.RateAmount

123456

30.Brick on edge pavement on pateries with Ist Class bricks laid dry joint filled with local sand including preparation of base to proper slope and its ramming spreading layer of 1cm depth of local sand over the sub grade and including supply of all material, labour and T&P etc. required for proper completion of the work (Straight over burnt brick to be used) (SOR-18.09) Sq.M. 308.00199.0061,292.00

(Rs. One Hundred Ninety Nine Only)

Total 41,57,080.80

( Rs. Forty One Lac Fifty Seven Thousand Eighty and paise Eighty Only)

J.E.

S.d.O. Panki Computer executive Engineer

Terms & Conditions :

1.PPC cement of ISI specification shall be arranged by the Contractor as his own cost of approved brand like ACC/Jaypee/Prism/Diamond/Maihar/Birla/Bangur or equivalent.

2.Cement shall be consumed as per consumption statement.

3.Contractor has to make his own arrangement for mixture machine and vibrator for cement concrete work, No. concrete shall be allowed without above equipment.

4.All section of steel i.e. M.S. Angle Iron. Ribbed or steel bars, M.S. Flat, Tee, M.S. round plain bar etc. of standard specification shall be supplied by the contractor for work. He will also submit test certificate along with supply of steel. However, if required, steel shall be got tested again at cost of contractor for which he will make all arrangements. The steel should confirm ISI specification. The weight of all steel section shall be taken as per standard I.S.I. code. Measurement of steel shall be done as per standard sectional weight.

5.The work shall be carried out as per U.P.P.W.D., U.P.P.T.C.L. specifications.

6.No extra payments shall be made for dewatering if required as per site conditions.

7.Sufficient water shall be arranged by the contractor at his own cost for the completion of the work. If Corporations water is used, water charge @ 1.50% shall be deducted on cement consuming items.

8.Before Unloading any constructional materials at site the same shall have to be first inspected by the Engineer-in-charge/representative. Any sub-standard material found at site shall be got shifted by the Contractor at his own cost.

9.Any item can be deleted or may vary up to any extent subject to + 25% of the total cost of work.

10.10% settlement allowance shall be deducted in earth filling work. No deduction shall be made on confined area such as under floors, under roads, slabs etc.

11.The work can be divided in two or more contractors.

12.In case, if steel is available in departmental store, the same shall be issued to the contractor @ prevailing schedule of rate + 10% of the rate.

13.Contractor shall use his own template. However, if templates are available at Corporation store, the same shall be given to the contractor for use. But contractor shall bear the expenses to & fro cartage of templates from the store of Electricity Civil Transmission Division, at Panki or other places. If the Contractor fails to return the templates within one month after completion of the work, the same shall be recovered from his bills @ Rs. 28.00 per Kg.

14.In case if the quantity is not mentioned in one category of work, the same can be executed by the other category of work.

15.All the drawings related to the work shall be given at site by the Junior Engineer at the time of construction of work.

16.Total Cost of Bill of Quantity

Rs. 41,57,080.80 To be filled by the Tenderer

Note : Struck out the word not applicable.

I/We ________________________ resident of ________________________________ __________________________________ submit my/our Tender at the under noted percentage above/below. The rates mentioned in the bill of quantities.

1.In Figure ______________________________% below/above/At Par.

2.In words ______________________________ % below/above/At Par.

(SIGNATURE of TENDERER)