[email protected] www.pro6managers.nl Biggest problems and challenges during execution of Projects in The Netherlands Simon Kolkman MSc

Upload: dangthuan

Post on 21-Jun-2018

227 views

Category:

Documents


0 download

TRANSCRIPT

[email protected]

Biggest problems and challenges during executionofProjects inTheNetherlands

Simon Kolkman MSc

Outline

1. Introductionq Dutchbuildingprojects and legal

frameworks2. Biggest problems by buildingphase

q ProcurementandContractingq Designandworkplanningq Executionanddelivery

3. Conclusions and Questionq Atthe end..

SIDiR2017Disclaimer- Pointofview- notintendedasalegalandcompleteacademicevaluation

Leadsgrowth to moreproblems inbuildingprojects?

SIDiR2017

Utility building(%CAGR) Housing (%CAGR) Infrastructure (%CAGR)

Compoundannualgrowthrate(CAGR)isthe mean growthrate inperiod

• Morebuildingprojects inmajorurban

surroundings

• Increasing technical and legal complexity

(environmentalcodes)

• Grow ofPublic-Private-Cooperation

• Increasing transfersof(financial)risks to

contractors

• Moreintegrated contracts (D&C/DB(F)M)

Morecomplexity and integrated contractmodels

SIDiR2017

30%

12% 44%

14%

Dutchcontractmodels- comparisonFIDIC

D&C- Silverbook DB(FM)- Yellow/silverbook

RAW- Redbook Other- different

ChangeinManagementand Contractmodels

SIDiR2017

- Earlierandintegralcooperationclientandcontractor- Resultandperformancebasedmanagement- Highermanagementstandards(faster,better,cheaper,

morecontrolled)

- Morerisksandresponsibilitytowardcontractor- Moreextensiveandmutilatedcontracts- Tension between Dutchlaw principles and contracts

(disproportionate vs clear responsibilities)

1. ProcurementandContracting– Contracting - models and content– Procurement - effective– MEATand Risks – bestbidding

2. Designandworkplan(ning)– Requirements– partobligation– Projectmanagement– (un/over)controlled– VerificationandValidation– (ap)prove

3. Executionanddelivery– Executingplan– (uncontrolled)deviations– VerificationandValidation– (ap)prove– Delivery– fitfor purpose

Biggest problems/challenges by buildingphase:

SIDiR 2017

Biggest problems and challenges:• Contracting – models and content

– Deviatefromthestandard,unbalancedriskallocationorinsufficient quality contract.

• Procurement – choice procedure– UnsuitableProcurementprocedure,misfit

informationandcommunicationneeds– TimetoTendertoshort

• MEATand Risks – bestbid(ding)?!– Overestimation ofbidding by client ornot

wellmotivated awarddecision– Unclear orunrealistic riskdistribution

1.ProcurementandContracting

SIDiR 2017

Bestbidding also realistic?

SIDiR2017

Biggest problems and challenges:• Requirements– partobligation

– Obvious,unclearorconflictingrequirements/information

• Projectmanagement– (un/over)controlled– Misfitprescribedmanagement

specificationandprojectneeds,badlyexecutedorlackofcooperation

• VerificationandValidation– (ap)prove– Lackoffproveofperformance,disputeof

misunderstandingaboutdeliveredquality(contractvsclient)

2.Designandworkplan(ning)

SIDiR2017

• Testsituation - Deltares independentinstituteforappliedresearchinthefieldofwaterandsubsurface

• ProjectWapenveld-Veessen• High-waterprogramm- morespace for

rivers – prefend flooding

Howto Verify - 1:100year operarational enfunctional?

SIDiR2017

Biggest problems and challenges:• Executingplan– (uncontrolled)deviations

– Obviousunreliable information,unexpectedsoil conditions oropportunisticplannedandbadlyexecutedwork

• VerificationandValidation– (Ap)prove– Failing to achieve required (MEAT)results or

dispute about evidence ofresults (validationofthe verification)

• Delivery– Fitfor purpose– Buildingitwellbutnottherightproduct,

disputeaboutdeliveredresults(productorprocess)

3.Executionanddelivery

SIDiR2017

Good ornot good enough?

SIDiR2017

• Thecooperationdirectlycomesunderpressureandthejointinterestwillvanishwithalltheescalationconsequences:– Legally– Cooperation

• Itisthenthechallengetoquicklyfinishsuchproblems(orplacethemoutsidetheproject)toreturntoagoodcollaborationtocompletetheprojectwell:– Mutualunderstandingcontract– predictable

escalation(followtheprocedures)– GoodProjectmanagementandSystemsEngineering– Investmentinde-escalationandjointtrust

And what’s the challenge when things gowrong?

SIDiR2017

Conclusions enrecommendations

SIDiR2017

• Morecomplexbuildingprojectsneedsnewcontractmodels

• Butcontractmodelsdonotchangethewayprojectsareexecutedà peopledo.

• Preventinglegalissuesinprojectispossiblethrough:– mutualunderstandingofthecontract– earlyde-escalationandgoodProjectmanagement

practiceandmethodslikeSystemsEngineering.

• Andspecialattentionshouldalsobegiventobehaviourandcooperationduringtheproject.

Questions

SIDiR2017

[email protected]