bhel turbine manual
DESCRIPTION
technical information about 220MW turbineTRANSCRIPT
-
Improving Efficiency & Reliability
ofSTEAM TURBINEThrough R & M
BY:AMITABH SRIVASTAVASR.DGM, BHEL HARDWAR
-
IN THE PRESENT POWER SECTOR SCENARIO
FOCUS IS ON ENHANCING EFFICIENCY RELIABILITY STRICTER POLLUTION NORMS COST REDUCTION
-
RESULTING TO ENHANCED EMPHASIS ON
=> REDUCTION IN GENERATION COST
HIGH EFFICIENCY OF TG CYCLE LOWER EQUIPMENT COST SHORTER GESTATION PERIOD REDUCED MAINTENANCE TIME
=> INCREASED RELIABILITY => MINIMIZING ENVIRONMENTAL HAZARDS
-
IMPROVEMENT IN STEAM TURBINE PERFORMANCEPOSSIBLE BY1. IMPROVED BLADE PROFILEREDUCTION IN THE AERODYNAMIC FLOW LOSSES e.g.PROFILE LOSSSECONDARY FLOW LOSSTIP LEAKAGE LOSSMORE UNIFORM FLOW DISTRIBUTIONCONTD..
-
IMPROVEMENT IN STEAM TURBINE PERFORMANCEPOSSIBLE BY .contd...2. OPTIMISED FLOWPATH3. IMPROVEMENT IN SHAFT SEALING SYSTEM4. REDUCTION IN PRESSURE DROPS5. REDUCED FRICTION LOSSES 6. OPTIMISATION OF INLET & EXHAUST SECTION7. OPTIMISED EXHAUST LOSS
-
DEVELOPMENT OF PROFILES FOR CYLINDRICAL TURBINE BLADEST4 PROFILE HAS 1% LOWER PROFILE LOSSES COMPARED TO T2 PROFILE.
NEWLY DEVELOPED TX HAS 0.2% LOWER PROFILE LOSSES COMPARED TO T4 PROFILE.
-
CONSIDERATIONS IN RETROFITTING & UPGRADATION OF OLDER SETS COST EFFECTIVENESS MODIFICATIONS IN TURBINE INTERNALS ONLY INCREASE IN POWER OUTPUT WITH MINIMUM CHANGES OUTER CASING, PIPINGS, VALVES, PEDESTAL FIXING ARRANGEMENT , STEAM PARAMETERS & FOUNDATION DETAILS REMAIN UNALTERED SHORTEST POSSIBLE OUTAGE TIME
-
RETROFITTING & UPGRADATION OF OLDER SETSPRE-REQUISITEIDENTIFY THE UNITPRESENT LEVEL OF PERFORMANCERESIDUAL LIFE ASSESSMENT STUDY OF CRITICAL COMPONENTSANALYSIS OF HISTORY & OPERATING DETAILS
-
RETROFITTING & UPGRADATION OF OLDER SETSMAJOR MODIFICATIONS IN GUIDE & MOVING BLADE (LATEST STATE OF ART PROFILE)STEAM FLOWPATHROTORS & INNER CASINGS OF TURBINESHAFT SEALINGS [ADVANTAGE IN HEATRATE / OUTPUT CAN BE WORKED OUT ON CASE TO CASE BASIS]3 DS BLADE(HPT/IPT)TWISTED PROFILE BLADE (HP/IPT)BANANA TYPE BLADE (LPT)
-
Retrofitting of HP Turbine with STATE OF ART REACTION BLADING
-
210 MW STEAM TURBINE (IMPULSE DESIGN SET-LMW) HP TURBINE
-
EXISTING 210 MW HP TURBINE WITH IMPULSE BLADINGPROPOSED NEW DESIGN WITH LATEST STATE OF ART BLADING210 MW STEAM TURBINE (IMPULSE DESIGN SET) HP TURBINE
-
PROPOSED NEW DESIGN WITH LATEST STATE OF ART BLADING
-
HP TURBINEEXISTINGIMPULSE BLADING ( PRESSURE DROP ONLY IN STATIONARY BLADES)EFFICIENCY : 83.6 % (FOR NEW MACHINE)EFFICIENCY FOR EXISTING CONDITION : ~ 80%NEWREACTION BLADING ( PRESSURE DROP IN STATIONARY AS WELL AS MOVING BLADES
EFFICIENCY : 86.5 %
-
ACTIVITIES INVOLVED
REMOVAL OF EXISTING HP ROTOR, LINERS AND DIAPHRAGMSINSTALLATION OF NEW LINERS FITTED WITH STATIONARY BLADES AND NEW HP ROTORFITTING DIMENSIONS ARE TO BE MEASURED DURING PREVIOUS OVERHAUL AND LINERS ARE MACHINED ACCORDINGLY.REMOVED HP ROTOR AND DIAPHRAGMS CAN BE USED AS SPARE FOR OTHER SETS
-
THE RETROFIT CAN BE DONE WITHIN NORMAL OVERHAUL PERIOD.
PAY BACK PERIOD IS LESS THAN 3 YEARS ACTIVITIES INVOLVED
-
A. Reference data for ORIGINAL brand new turbineReference Heat Balance Diagram TCD - 210 - 33 - 2, Regime No. 1 Rated parametersMain steam Flow 662 T/hMain Steam Pressure 130 ataMain Steam Temperature 535 Deg CHot reheat Temperature 535 Deg CCondenser Vacuum 0.1042 ataTG Heatrate 2062 kCal/kWh
-
B. Expected present performance level (210 MW Original rating)Considering deterioration due to ageing as per ASME-PTC-6Report 1985Expected Power outputwith 662 T/h main steam flow and rated parameters 202.4 MW
Expected TG Heatrate with 662 T/h main steam flowand rated parameters 2164 kCal/kWh
-
EXPECTED PERFORMANCE IMPROVEMENT IN THE EXISTING IMPULSE DESIGN SET DUE TO HP TURBINE REFURBISHMENTINCREASE IN POWER OUTPUT : 8.6 MWIMPROVEMENT IN HEATRATE : 4% (FROM EXISTING PERFORMANCE LEVEL OF THE SET WITH RATED STEAM PARAMETERS & THROTTLE STEAM FLOW)
-
EXPECTED PERFORMANCE IMPROVEMENT IN THE EXISTING IMPULSE DESIGN SET DUE TO HP TURBINE REFURBISHMENT
Sheet1
BRAND NEW SETEXPECTED PRESENT DETERIORATED CONDITIONUPGRADED HPT
OUTPUT (MW)210202.4 (3.6% DECREASE)211 (4.2% INCREASE)
HEAT RATE (KCAL/ KWh)20622164 (4.9% INCREASE)2077 (4.02% IMPROVEMENT)
Sheet2
Sheet3
-
COMPARISONGAIN WITH UPRATED HPT:
ADDITIONAL GEN. OF MU = MW X1000 X HRS.X PLF
= 8.6 X 1000 X 8000 X 0.80 = 55.04 MU
ADDITIONAL GEN. OF REVENUE @ RS 2/= PER UNIT
= 55.04 X 2 = RS 11 CR
-
200/210 MW IMPULSE DESIGN SET(LMW)
-
EXISTINGAFTER RETROFIT
-
WORK INVOLVED IN RETROFIT OF LP TURBINE
WORK TO BE DONE AT SITE:
CUTTING OF DEFLECTORS / RIBS & BLANKING THE SPACE IN LP CASING TO FACILITATE REMOVAL OF BAUMEN STAGE.MODIFICATION OF STRUCTURE AT THE EXHAUST END OF LPC TO FACILITATE INSTALLATION OF DIFFUSOR.CONTD.
-
MODIFICATION OF STRUCTURE AT THE STEAM INLET END OF LPC TO FACILITATE INSTALLATION OF 1ST STAGE OF GUIDE BLADES.WORK INVOLVED IN RETROFIT OF LP TURBINEWORK TO BE DONE AT SITE:
-
A. Reference data for ORIGINAL brand new turbineReference Heat Balance Diagram TCD - 210 - 33 - 2, Regime No. 1 Rated parametersMain steam Flow 662 T/hMain Steam Pressure 130 ataMain Steam Temperature 535 Deg CHot reheat Temperature 535 Deg CCondenser Vacuum 0.1042 ataTG Heatrate 2062 kCal/kWh
-
B. Expected present performance level (210 MW Original rating)Considering deterioration due to ageing as per ASME-PTC-6Report 1985Expected Power outputwith 662 T/h main steam flow and rated parameters 202.4 MW
Expected TG Heatrate with 662 T/h main steam flowand rated parameters 2164 kCal/kWh
-
EXPECTED PERFORMANCE IMPROVEMENT IN THE EXISTING SET DUE TO LP TURBINE REFURBISHMENT
INCREASE IN POWER OUTPUT : 10.1 MWIMPROVEMENT IN HEATRATE : 102 KCAL / KWH (FROM EXISTING PERFORMANCE LEVEL OF THE SET WITH RATED STEAM PARAMETERS & THROTTLE STEAM FLOW)
-
COMPARISON
Sheet1
DESCRIPTIONUNITSTEAM TURBINEWITH UPGRADEDGAIN
BRAND NEWLIKELY PRESENT DETERIORATED PERFORMANCE LEVELHPTLPTWITH UPGRADED HPT% INCREASE (WRT PRESENT LEVEL)WITH UPGRADED LPT% INCREASEWITH UPGRADED HPT & LPT% INCREASE
PLANT DATA
RATED CAPACITY OF TG-SETMW210204212.5212.52.51.22.51.2
LOADING WITH 662 T/HR STEAM FLOWMW210204211.5212.573.438.5415.57.5980392157
HEAT RATE OF STKCAL/KWH2062214020762057.764382.341993.75.6
GENERATION
NO OF UNITS GENERATEDMU1471 (ASSUMING PLF OF 80%)1429 (ASSUMING PLF OF 80%)1482 (ASSUMING PLF OF 80%)1489 (ASSUMING PLF OF 80%)533.70%604.20%1137.9
BENEFIT
SELLING PRICE PER UNITRS / KWH2.32.32.32.32.3NA2.3NA2.3NA
REVENUE GENERATEDRS CRORE338.33328.67340.9342.4712.233.72%13.84.20%267.9
Sheet2
BRAND NEW STEXPECTED PRESENT DETERIORATED CONDITIONUPGRADED LPT
OUTPUT (MW)210202.4212.5
HEAT RATE (KCAL / KWH)206221642066
ADDITIOAL GEN (MU)NANA64.64
Sheet3
-
COMPARISONGAIN WITH UPRATED LPT:
ADDITIONAL GEN. OF MU = MW X1000 X HRS.X PLF
= 10.1 X 1000 X 8000 X 0.80 = 64.64 MU
ADDITIONAL GEN. OF REVENUE @ RS 2/= PER UNIT
= 64.64 X 2 = RS 12.93 CR
-
COMPARISON
Sheet1
DESCRIPTIONUNITSTEAM TURBINEWITH UPGRADEDGAIN
BRAND NEWLIKELY PRESENT DETERIORATED PERFORMANCE LEVELHPTLPTWITH UPGRADED HPT% INCREASE (WRT PRESENT LEVEL)WITH UPGRADED LPT% INCREASEWITH UPGRADED HPT & LPT% INCREASE
PLANT DATA
RATED CAPACITY OF TG-SETMW210204212.5212.52.51.22.51.2
LOADING WITH 662 T/HR STEAM FLOWMW210204211.5212.573.438.5415.57.5980392157
HEAT RATE OF STKCAL/KWH2062214020762057.764382.341993.75.6
GENERATION
NO OF UNITS GENERATEDMU1471 (ASSUMING PLF OF 80%)1429 (ASSUMING PLF OF 80%)1482 (ASSUMING PLF OF 80%)1489 (ASSUMING PLF OF 80%)533.70%604.20%1137.9
BENEFIT
SELLING PRICE PER UNITRS / KWH2.32.32.32.32.3NA2.3NA2.3NA
REVENUE GENERATEDRS CRORE338.33328.67340.9342.4712.233.72%13.84.20%267.9
Sheet2
BRAND NEW STEXPECTED PRESENT DETERIORATED CONDITIONUPGRADED HPTUPGRADED LPTUPGRADED HPT & LPT
OUTPUT (MW)210202.4211212.5214
HEAT RATE (KCAL / KWH)20622164207720662047
ADDITIOAL GEN (MU)NANA55.0464.6474.24
Sheet3
-
COMPARISONGAIN WITH UPRATED HPT & LPT:
ADDITIONAL GEN. OF MU = MW X1000 X HRS.X PLF
= 11.6 X 1000 X 8000 X 0.80 = 74.74 MU
ADDITIONAL GEN. OF REVENUE @ RS 2/= PER UNIT
= 74.74 X 2 = RS 14.848 CR
-
TECHNICAL PROPOSALFOR R & M OF 210 MW STEAM TURBINES (KWU DESIGN) OF TUTICORIN TPS
-
CROSS SECTIONAL VIEW OF 210 MW STEAM TURBINE
-
EXISTING DESIGN: HP Turbine:HP ROTOR : WITH MOVING BLADES OF T2 PROFILE
INNER CASING: WITH STATIONARY BLADES OF T2 PROFILE
INLET INSERTS: WITH 580X9 MM BUTTRESS THREADS
EXHAUST ELBOWS: WITH SERRATED GASKET.
-
210 MW STEAM TURBINE (REACTION DESIGN SET-KWU) HP TURBINERETROFITTING 210 MW REACTION TURBINE WITH IMPROVED BLADING
-
HP INLET INSERTSBREECH NUTHP OUTER CASING
-
HP INLET INSERTSHP INLET INSERTS (OLD DESIGN):HP OUTER CASING & BREECH NUTS THREAD SIZE : 580X9 MM
HP INLET INSERTS (NEW DESIGN):HP OUTER CASING & BREECH NUTSTHREAD SIZE : 580X20 MM
-
IMPROVEMENTS IN PROPOSED DESIGN:HP MODULE:
INNER CASING & HP ROTOR WITH OPTIMISED HIGHLY EFFICIENT T4 PROFILE BLADING.
ADVANTAGE:INCREASED EFFICIENCY
-
IMPROVEMENTS IN PROPOSED DESIGN: (CONTD.)HP MODULE (CONTD.):
MODIFIED HPT INLET INSERTS WITH BUTTRESS THREADS OF SIZE 580X20 MM IN HP OUTER CASING & BREECH NUTS.ADVANTAGE:EASE IN ASSEMBLY & DISMANTLING.
-
IMPROVEMENTS IN PROPOSED DESIGN: (CONTD.)HP MODULE (CONTD.):
MODIFIED HP EXHAUST ELBOWS WHICH HAVE U-RING IN PLACE OF SERRATED GASKET.ADVANTAGE:ENHANCED RELIABILITY.
-
HP EXHAUST ELBOWSExhaust ElbowHP OUTER CASING
-
HP EXHAUST ELBOWS
-
HP EXHAUST ELBOWSU-RING
-
SCOPE OF SUPPLYFOR HP TURBINE:
COMPLETELY ASSEMBLED HP MODULE WITH T4 PROFILE BLADING ALONGWITH MODIFIED HP INLET ASSEMBLY & HP EXHAUST ELBOWS.
-
210 MW STEAM TURBINE (REACTION DESIGN SET-KWU)IP TURBINERETROFITTING 210 MW REACTION TURBINE WITH IMPROVED T4 PROFILE BLADINGADVANTAGE:IMPROVED PERFORMANCE.
-
SCOPE OF SUPPLY (CONTD.)FOR IP TURBINE:
IP INNER CASING & IP ROTOR WITH T4 PROFILE BLADING.A SET OF HPR-IPR & IPR-LPR COUPLING BOLTS.NECESSARY KEYS ETC.
-
WORK REQUIRED TO BE DONE AT SITE:[NOT INCLUDED IN THE SCOPE OF THIS TECHNICAL OFFER]
PERFORMANCE TESTING PRIOR & AFTER R & M.OVERHAULING.RLA STUDY.COMPONENTS IDENTIFIED DURING OVERHAULING/ RLA STUDY WHICH NEED REPLACEMENT
-
WORK REQUIRED TO BE DONE AT SITE: (FOR HP Turbine)REMOVAL OF OLD HP MODULE FROM ITS POSITION AFTER DISMANTLING OF HP INLET INSERTS AND HP EXHAUST ELBOWS.
OLD HP INLET ASSEMBLY (INLET INSERTS WITH BREECH NUTS) & HP EXHAUST ELBOWS ARE TO BE CUT FROM MS PIPES & CRH PIPES RESPECTIVELY.
-
WORK REQUIRED TO BE DONE AT SITE:(CONTD.)INSTALLATION OF NEW IMPROVISED HPT MODULE IN POSITION, CENTERING & ALIGNMENT.
WELDING OF HP INLET ASSEMBLY OF NEW MODULE WITH MAIN STEAM PIPES.
-
WORK REQUIRED TO BE DONE AT SITE:(CONTD.) HP EXHAUST ELBOWS ARE TO BE WELDED WITH CRH STEAM PIPES.
ASSEMBLY OF HP INLET INSERTS & HP EXHAUST ELBOWS TO BE COMPLETED.
-
WORK REQUIRED TO BE DONE AT SITE:FOR IP TurbineREMOVAL OF OLD IP ROTOR & IP INNER CASING.INSTALLATION OF NEW IP INNER CASING & IP ROTOR WITH T4 PROFILE BLADING, ITS CENTERING & ALIGNMENT.COMPLETION OF BOX UP OF IP Turbine.
-
CONDITION AFTER R & M OF HPT & IPT (UNDER RATED CONDITION):RATED PARAMETERS:At 100% MCR conditionMAIN STEAM FLOW : 641.3 T/HRMS/ HRH STEAM TEMP:535/535 DEG CMAIN STEAM PR: 150 ATABACK PR: 0.121 ATA
-
EXPECTED PRESENT PERFORMANCE:CONSIDERING DETERIORATION DUE TO AGING AS PER ASME-PTC-6 REPORT 1985 FOR AVERAGE LIFE OF 20 YEARS, FOLLOWING WILL BE EXPECTED PERFORMANCE AT 641.3 T/HR MAIN STEAM FLOW AND RATED PARAMETERS OUTPUT: 202.3 MW HEAT RATE: 2067 KCAL/KWH
-
COMPARISON OF PERFORMANCE:
BRAND NEW ST
EXPECTED PRESENT CONDITION
AFTER R & M of HPT & IPT
OUTPUT (MW)
210
202.3
209
(GAIN OF 3.3%)
HEAT RATE (KCAL/KWH)
1991
2067
1999.6
(GAIN OF 3.2%)
-
PAY BACK PERIOD1) REDUCTION IN OH PERIOD: 25 DAYSRESULTING TO
ADDITIONAL POWER GENERATION FOR 25 DAYS
YIELDING TO
GUAREENTED MINIMUM ADDITIONAL REVENUE:= 209MW x 1000 x 25DAYS x 24HRS x 0.80PLF x 2.00RS
=RS 20.06 CRORES
-
PAY BACK PERIODADDITIONAL ANNUAL REVENUE GENERATION DUE TO INCREASE IN OUTPUT & IMPROVED HEAT RATE:
= 6.7 MW x 1000 x 8000 HRS x 0.80 PLF x RS 2.00 = RS 8.576 CRORES PER YEAR
HENCE, PAY BACK PERIOD < 3 YEARS
-
PRESENT EXPECTED CONDITION:
OUT PUT = 202.3 MW (641.3T/HR)THEREFORE,OUT PUT = 210 MW (665.7 T/HR)FOR THIS FLOW : IT IS OPERATING NEAR TO VWO CONDITION WHICH IS NOT DESIRABLE.
-
EXPECTED CONDITION AFTER R&M:
OUT PUT = 209 MW (641.3T/HR)THEREFORE,OUT PUT = 216.95 MW (665.7 T/HR)FOR THIS FLOW : IT WILL BE OPERATING NEAR VWO CONDITION WHICH IS NOT DESIRABLE.