Confidential Name and Signature of bidder: Signature Page 1 of 44 1 1 BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs Random Sample size : a ) 5 % of each lot ready for dispatch covering all the types of MPDs in the lot, where it is mentioned “ physically check for sample size” . b) Wherever “confirmation by TPIA” is sought, the random sample size can be decided by the TPIA to his satisfaction. TECHNICAL SPECIFICATIONS OF MPDs SR NO TENDER REQUIREMENT REQUIREMENT OBSERVATION / COMMENTS/ RESULTS of TPIA during Inspection 1 TYPE: High Hose Version Dispensers without pumping Unit suitable for Submersible Pumps. Submersible pumps are not in Vendor’s Scope Physically check for sample size 1.a MODEL NAME : Model name to be as per following details. Physically check for sample size Item: 2 PROD X 4H X 4 DISP (STD Duty ) MPD without printer, Minimum Width 1.2m Physically check for sample size

Upload: doantram

Post on 11-Apr-2018

247 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 1 of 44

1

1

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

Random Sample size : a ) 5 % of each lot ready for dispatch covering all the types of MPDs in the lot, where it is mentioned

“ physically check for sample size” . b) Wherever “confirmation by TPIA” is sought, the random sample size can be decided by the TPIA to his satisfaction.

TECHNICAL SPECIFICATIONS OF MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

1 TYPE: High Hose Version Dispensers without pumping Unit suitable for Submersible Pumps. Submersible pumps are not in Vendor’s Scope

Physically check for sample size

1.a MODEL NAME : Model name to be as per following details.

Physically check for sample size

Item: 2 PROD X 4H X 4 DISP (STD Duty ) MPD without printer, Minimum Width 1.2m

Physically check for sample size

Page 2: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 2 of 44

2

2

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

and display on the edges.

Item: 2 PROD X 4H X 2 DISP (Std Duty), 3 PROD X 6H X 2 DISP (Std Duty), 4 PROD X 8H X 2 DISP DISP (Std Duty) and 1PROD X2HX2 DISP with Printer (Heavy Duty) On Either Sides i.e. total two printers per MPD.

Physically check for sample size

1.b

Inlet Connection shall be 38 mm for all MPDs except Heavy Duty. For Heavy Duty Inlet connection would be between 38mm to 50mm However the delivery flow rates as referred in 2.a. should be achievable with FE PETRO / RED JACKET or equivalent make STPs of .75 HP.

Physically check for sample size

2 DELIVERY RATE

2.a

Minimum 30 litres/minute per nozzle when one side and one product in operation. Minimum 60 litres/minute per nozzle when

Physically check for sample size

Page 3: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 3 of 44

3

3

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

one side and one product in operation for Heavy Duty.

3 METERING UNIT 3.a Positive Displacement Type, with two or four

Piston with Integrated or Separate Pulse Generator. The shaft connecting pulser and metering unit should be in one piece without any transmission gears .

Confirmation by TPIA

3.b

Working Pressure – MAX 3.50 KG/SQ.CM for all MPDs

Confirmation by TPIA

3.c ACCURACY +15 ml to 0 ml at delivery rate of 10 lpm to the maximum capacity of the pump for 5 litre measure .

Physically check for sample size

Page 4: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 4 of 44

4

4

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

3.d Two consecutive readings out of three reading should be within accuracy limit.

Physically check for sample size

3.e All measuring units should be electronically calibrated only. Metering unit accuracy shall be adjusted by electronic head in the range as per W&M laws. The electronic calibration must be possible only when W&M seal is broken.

Confirmation by TPIA

3.f The range of calibration in ml in both plus as well as on minus side.

Confirmation by TPIA

3.g Accuracy of the Meter shall be +/- 0.3% or better.

Physically check for sample size

4 HOSE

4.a 4 M long – 19 MM FOR S.D And 25 MM for HD Nozzles.

Physically check for sample size

Page 5: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 5 of 44

5

5

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

4.b To be of petrol resistant type of superior quality suitable for Petrol blended with Ethanol Of Max10%

Enclose test report from manufacturer

Page 6: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 6 of 44

6

6

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

4.c Hose shall be hard wall only confirming to BS EN 1360 Type III /UL 330 or Equivalent

Confirmation by TPIA

4.d Hose hook (Material SS304 SGHC(JIS G 3302 / plastic material of adequate strength &longevity) to be provided to hold the hose in position so as to prevent it from rubbing against the ground.

Confirmation by TPIA

4.e i. Colored Hoses for only 4x8x2 MPDs 1st Hose: Yellow for Speed 2nd Hose: Green for Petrol 3rd Hose: Black for Hi-Speed 4th Hose: Blue for HSD. ii. For all other MPDs, all Hoses would be Black in color.

Physically check for sample size

5 NOZZLE

5a. Pressure sensitive auto cut-off Unleaded MS- 13/16” spout for STD Duty of ZVA/ OPW/ TATSUNO/CATLOW(USA) make with BPCL logo embedded on NOZZLE COVER . For Heavy Duty, Pressure sensitive Auto

Physically check for sample size

Page 7: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 7 of 44

7

7

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

CutOff nozzle would be 15/16” or 1” size ZVA/OPW/TATSUNO/CATFLOW(USA) make with BPCL Logo embedded on Nozzle Cover. Nozzle Cover Color : 2X4X4 MPD : 1st Nozzle-Yellow 2nd Nozzle – Green 2x4x2 MPD: 1st Nozzle-Green 2nd Nozzle – Blue 3x6x2 MPD: 1st Nozzle- Yellow 2nd Nozzle – Green 3rd Nozzle- Blue 4x8x2 MPD: 1st Nozzle- Yellow 2nd Nozzle – Green 3rd Nozzle- Black 4th Nozzle-Blue

Page 8: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 8 of 44

8

8

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

1x2x2 MPD 1st Nozzle – Blue

6 REGISTER UNIT

6.a

MOTHERBOARD WITH MICROPROCESSOR/ MICROCONTROLLER

Electronic microprocessor control and display unit for 1 to 4 hydraulic modules with non volatile memory.

Physically check for sample size

6.b

All power handling devices including transformer and power correction / protection will be on separate board ( Power/ SMPS card ) so as to enable replacement of only power/SMPS card in the event of any power related failures. BPC has installed high quality UPS at all their ROs, from which power is fed to electronics of MPDs. Hence warranty and post warranty AMC will cover all items including all electronics. In nut

Physically check for sample size

Page 9: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 9 of 44

9

9

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

shell, all spares during warranty and post warranty AMC will be on vendor’s account, regardless of the reason for such spares failure. All exceptions to this rule is listed in Service Level Contract appended.

7

DISPLAY

7.a Liquid Crystal Display Capable of withstanding temperatures ranging from -20 Degree C to +80 Degree C .It must be visible during day and also at night with backlighting .

Enclose Test reports from Manufacturer

Page 10: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 10 of 44

10

10

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

7.b 1)LCD screens to be provided to display Volume, Amount, Unit Price and Density for all MPDs. The characters/digits shall be displayed in black and the background shall be white. Volume and amount will be displayed on a common bigger screen with character height of minimum 40 mm. 2)Density Display for the product of active Hose only. 3)Density input through keypad (security level L1) or POS.

4)“The Unit rate of each product available on MPD should be visible before commencement of dispensing fuel .However, during dispensing operation ,only Unit rate of product of active hose must be on display” 5) In case of power failure display

should remain at least for 30 seconds. No external battery should be used for back up.

Confirmation by TPIA

Page 11: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 11 of 44

11

11

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

7.c 1)The size of the characters displayed product should be as follows: Amount: 40 mm Volume: 40 mm Unit Price: 25 mm Density: 25 mm Amount and volume will be on a common screen with character height of min 40 mm. 2) The configuration of the display shall be as under:

o Amount: 99999.99 Rs o Volume: 99999.99 lts o Unit Price: 999.99 Rs/lt o Density: 999.9 kg/m3

Physically check for sample size

Page 12: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 12 of 44

12

12

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

7.d The Electronic Display should have masking of readings allowed up to 30 ml.

Physically check for sample size

8 COMMUNICATION PORT

8.a The unit shall have an RS 485 port for communication with POS/OPT/any Automation system. For makes that support Current Loop as the default mode of communication, one RS 485 port shall also be provided with an option to switch to RS 485 output or back to Current Loop (using jumper settings). Vendor to ensure that communication port remains protected when connected to FCC of DOMS, POSTEC or any other make of repute for automation purposes.

Physically check for sample size

Page 13: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 13 of 44

13

13

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

The communication to the local printers (when installed at a later date) shall be through RS 232. The printer shall work independent of the automation system. The receipt printing should be done by activating a button provided on the pump, the communication should be directly between the pump controller board and the local printer board, using RS232. This will ensure receipt printing whether there is automation or not

Page 14: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 14 of 44

14

14

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

8.b 1) The below requirement is applicable only for 2×4×2, 3x6x2, 4x8x2 and 1x2x2 MPDs :

i) A prompt should appear on the LCD screen or Key pad of the DU to enter the Vehicle Number (alphanumeric), before printing of the cash memo. Cash memo must depict Vehicle Number (alphanumeric). ii)If prompt is on LCD, all details of last transaction should reappear after Vehicle number is entered or skipped

2) The above are not applicable for 2×4×4

3) If Vehicle number is skipped, cash Memo must depict “ Not entered” against Vehicle number

Physically verify using POS terminal available with manufacturer for the sample size.

Page 15: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 15 of 44

15

15

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

9 COMMUNICATION PROTOCOL

Page 16: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 16 of 44

16

16

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

9.a For pumps working with POS or RO automation, following data must be available from dispenser on request from POS using an industry standard protocol or proprietary protocol:

o The delivery data, i.e., delivery amount and delivery volume message that provides updated information in real time as to the current delivery, amount marked upon the Microcontroller and volume delivered at Microcontroller respectively. If not possible, at least one of these data will be transferred on real time basis, while other data will be transferred at the end of each delivery. The data transmitted to the host are identical to those displayed on the Microcontroller.

o The overall total volume, i.e. the total number of liters delivered by each Microcontroller

o The overall total amount, i.e. the total number of monetary units counted Microcontroller.

o All density, price, calibration records. o Preset value entered on the key pad should

be transmitted to POS at the beginning of transaction.

Physically verify using POS terminal available with manufacturer for the sample size.

Page 17: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 17 of 44

17

17

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

9.b o The communication protocol should

recognize the floating decimal.

o The protocol shall support remote

change of unit rates for all products in the MPD. This is in order to enable remote price change of products through Automation System.

Physically verify using POS terminal available with manufacturer for the sample size.

9.c Pre-delivery status signals required are:

o Host generated block ( authorization from POS)

o Product identification o Nozzle out

Physically verify using POS terminal available with manufacturer for the sample size.

Page 18: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 18 of 44

18

18

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

9.d Error status signals required:

o Display 1,2 connectivity error o Totaliser o Single sensor error o Twin sensor error

These error signals are illustrative only, and not exhaustive

Physically verify using POS terminal available with manufacturer for the sample size.

9.e Under delivery status required for MPDs are: o Nozzle out

Physically verify using POS terminal available with manufacturer for the sample size.

Page 19: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 19 of 44

19

19

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

9.f

POS commands to Microcontroller to work as under:

Command from POS: Action by Micro Controller

1)Recognize change in the nozzle position from IN to OUT: Activation of Delivery starts procedure. 2)Emergency Block delivery : Delivery fuel to be blocked at microcontroller 3)Preset amount to be delivered Memorization of “Preset by POS” function, 4)Preset volume to be delivered : Memorization of “Preset by POS” function,

Physically verify using POS terminal available with manufacturer for the sample size.

Page 20: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 20 of 44

20

20

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

5)Unit price setting: Memorization of price received from POS visualization of new price received & activation of procedure of writing new price 6)Motor enable/disable : Suspends/ resumes delivery. 7) Density values entered in three digits + one decimal (in Kg/m 3) : The values entered from POS must be displayed on MPD on the LCD screen.

10 PRINTERS

10.a 1). 2x4x2,3x6x2,4x8x2 and 1X2X2 MPDs should be provided and supplied with Two inbuilt Thermal Printers i.e. one on either side. 2 ) Above is not applicable/ required for 2x4x4 MPDs

Physically check for sample size

Page 21: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 21 of 44

21

21

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

10.b The RS 232/RS485 com port of the MPD shall enable communication with printers.

Physically check for sample size

10.c The printers is to be provided 1.2m above Ground level.

Physically check for sample size

10.d Printer specs and Cash Memo template would be as per purchase order specifications.

Physically check for sample size

1 10.e The printer should allow one re-print of the ticket; the second copy shall be marked as “COPY/DUPLICATE”. The required format of the ticket/cash memo is enclosed with the printer specs.

Physically check for sample size

Page 22: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 22 of 44

22

22

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

11 PULSE & SAFETY FEATURE

11.a

Pulser resolution of 10ml per pulse should consist of two/three pairs of photoelectric two sensors.

Confirmation by TPIA

1 11.b

Pump to give error message and stop functioning if sensor (s) fail OR Alternate Technology – Any failure of sensor should give an error message, stopping sales

Confirmation by TPIA

11.c They are to be flame proof/ explosion proof if they are placed with in the hazardous area.

Confirmation by TPIA

11.d

If uni-directional pulsar is not used, and there is a situation of reverse movement in pulsar, the pump should display an error message and stop dispensing.

Confirmation by TPIA

11.e There should be provision for sealing of the entire pulsar unit

Physically check for sample size

Page 23: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 23 of 44

23

23

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

12 TOTALISER

12.a Electro-mechanical and Electronic Totaliser are both to be provided for each meter

Physically check for sample size

12.b Electro-mechanical totalisers to have sealing arrangement. Integrity of Electro mechanical Totaliser shall be ensured through fool proof sealing system. Details as per vendor’s offer.

Confirmation by TPIA

12.c Both Electro-mechanical and Electronic Totalisers should be irreversible type. The Electro-mechanical Totaliser including it’s gear train must be in tamper proof enclosure with sealing Arrangement.

Confirmation by TPIA

12.d 7 DIGIT without decimal form Electromechanical Totaliser.

Confirmation by TPIA

Page 24: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 24 of 44

24

24

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

12.e Electro mechanical totaliser should be readable from outside without removing the panel/doors

Confirmation by TPIA

12.f Minimum 12 digits including two decimal digits Electronic Totaliser for all MPDs 2×4×2, 2X4X4 ,3x6x2 4x8x2 and 1x2x2 MPDs

Confirmation by TPIA

12.g In case, Vendor has provided additional fail safe Electronic Totalizer in place of Electro Mechanical Totalizer, Fail safe Electronic Totaliser to be checked for Electronic Totalizer functionalties.

Confirmation by TPIA

13 PRESET

Page 25: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 25 of 44

25

25

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

13.a Required as a standard feature for all the MPDs. Preset would be for Volume (ltrs) and Value (In Rs)

Confirmation by TPIA

13.b

1.Preset shall have least count of 1 Litre by Volume and Rs 10/- by amount. 2. 3 pre-set keys in addition to all numeric keys in the key pad will be provided for fixed amount as well as volume configurable at site. This is required for three most frequent transactions.

Confirmation by TPIA

13.c Solenoid Valve shall be of Two stages/ Proportional stages. Vendors to confirm the Cut-off level of the first stage.

Physically check for sample size

14 OPERATING ENVIRONMENT

Page 26: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 26 of 44

26

26

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

14.a Pump shall be capable of operating in tropical conditions & in open atmosphere without over head canopy. Humidity of max. 95% and ambient temperature of -20 to +500c.

Confirmation by TPIA

15 SECURITY AND CONTROLS

15.a History of last 10 electronic calibrations shall be stored in the CPU Memory of the ERA and shall be recalled on the pump display. There shall also be an option for printing the same using the local printer. The microcontroller must also be capable of communicating the details to a POS terminal/Automation System when the unit is automated.

Confirmation by TPIA

15.b The microcontroller and ICs connected to Microcontroller shall be surface Mounted on to the PCBs. Other ICS and Circuits not directly effecting Microcontroller can be Non surface Mounted.

Confirmation by TPIA

Page 27: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 27 of 44

27

27

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

15.c The manufacturer should have his mark on the mother board for identification. It shall be mounted on the structure through a screw/ bolt and the whole mounting will be a sealed wire system with manufacturer’s seal on it.

Physically check for sample size

15.d Display of Software version: The pump software version should be readable on the LCD screen as and when required

Physically check for sample size

Page 28: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 28 of 44

28

28

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

15.e Minimum 3 levels of security required for accessing various functions through the MPD keypad/Remote Control as below. 1. Level1 for density, Shift totalizer clearance

2.Level2 for Price, Auto to manual to Mode and for History of all price & Density changes with date and time for last 5 entries

3.Level3 for software changes etc. only with manufacturer 4.Level 3 can control all Levels below.

Physically check for sample size

15.f The output going from Pulsar unit to Pump controller card should be secured so as to prevent manipulation of pulsar signals.

BPCL desires pulsar encrypted feature. Refer Vendor’s confirmation.

Enclose Test report from manufacturer.

Page 29: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 29 of 44

29

29

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

15.g Rate change through password Control- History of last 5 rate changes shall be stored in the CPU Memory of the ERA and shall be recalled on the pump display through keypad /Remote control. There shall also be an option for printing the same using the local printer (when installed at a later date). The microcontroller must also be capable of communicating the details to a POS terminal/ Automation System when the unit is automated.

Physically check for sample size

15.h Tamper proof electronics to avoid unauthorized programming/ replacement of components. Details to be provided.

Physically check for sample size

15.i Stand Alone and Auto mode: The MPD should be able to be taken to auto or stand alone mode through MPD’s keypad/ Remote Control and the access will be with higher level of security.

Physically check for sample size

15.j Software programming should not be altered by any agency. However in case of updates, the same would be approved by BPCL Retail Eng (HQ) Dept.

Confirmation by TPIA

Page 30: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 30 of 44

30

30

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

15.k BPCL expects the vendor to ensure that the pump software/microcontroller program and Level 3 or Highest level pass word remains strictly confidential. Vendor to ensure tight security with suitable internal processes to prevent the software from being disclosed to any outside party. BPCL reserves the right to debar the vendor for all future tenders in the event where BPCL has discovered that the same has come into the possession of any undesired person or agency. In such case, vendor shall load new software or replace the manipulated motherboard with new motherboard free of charge as per BPCL’s requirement without any cost to BPCL.

Physically check for sample size

Page 31: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 31 of 44

31

31

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

15.l Each MPD should be provided with a Red color Mushroom type “STOP” button –one each on Front and Rear panel. All the power to the MPD including dispensing should stop , except display which should remain for minimum 30 seconds.

Physically check for sample size

16 PAINTING SS surface will not be painted. Non SS

surfaces to be coated as under:

a) External surface of bottom panel (front and rear) and “MPD Top Fascia” to be finished for pasting of screen printed vinyl .

b) All external surface, other than (a) above, will be 50 micron pure polyester powder coated white.

Physically check for sample size

17 STATUTARY LOCAL APPROVALS

17.a Valid Model Approvals from Weights & Measure Verify and

Page 32: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 32 of 44

32

32

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

and Certification / Approvals from Chief Controler Of Explosives, Govt Of India.(Vendor to enclose Model Approvals & CCOE approval copies for offered models)

enclose required approvals alongwith report

17.b Quality Assurance Plan by Vendor

Verify and enclose QAP

17. c Vendor to confirm that in all Models the position of

CARD READER IN DISPENSER (CRIND )will remain same. (Except 2x4x4 model)

Physically check for sample size

18 OTHER REQUIREMENTS

Page 33: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 33 of 44

33

33

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

18.a Tray for keeping vehicle fuel tank cap of 75 mm diameter Stainless Steel/Nylon Glass Filled tray fixed on the front and rear bottom panel

Physically check for sample size

18.b MPDs should be provided with reusable filters of 70 to 80 micron size. Lower micron is also acceptable provided flow rate is not compromised.

Physically check for sample size

18.c i) The Dispensers should be provided with Swivels, Shear valves and single use safe breakaway couplings . ii) Breakaway couplings should be at top

Physically check for sample size

18.d MPDs and its components should be suitable for fuel with 10% Mix Ethanol. Viton/ equivalent seals and not NBR seals to be used. All the rubber components coming in contact with the fuel will be of Viton/ equivalent Material.

Physically check for sample size

18.e Please note that All Rubber Components Physically check

Page 34: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 34 of 44

34

34

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

which are in direct contact with the Product must be made of "Viton" (except hose)

for sample size

18.f MPD bottom panel and MPD Top Fascia

should be provided with 3M or Avery vinyl with screen printed graphics or silk screen directly printed on metal body . The graphic design will be provided by BPCL. Vendor to give five years warranty for loss of colour and gloss not below 80% level.

Physically check for sample size

18.g The bottom door panels should be removable type and not to be hinged with main body. The nozzle support should be fixed on main body and not on the bottom door panels.

Physically check for sample size

18.h Provision is to be made to retrofit ‘CRIND’ at a future date. Opening size should be of size 22 cm width , 20.5 cm height and 25 cm depth on either side of the MPD. Blanking plate on opening to be provided This CRIND could be even located in place of printer installed on MPD.

Physically check for sample size

Page 35: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 35 of 44

35

35

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

18.i MPD Top should have a fascia. The shape of

the fascia should be wave type. (Drawing and photographic sample attached on page 42,43,44 of this Annexure).

Physically Check

19 PACKING/MARKING

19.a PACKING: Dispensers / Pumps to be covered with polythene covers and packed in a wooden box / crate to withstand multiple loading/ unloading and transportation from :- Overseas factory to Indian ports by ship Ports to storage locations by road Storage location to retail outlets by road NOTE : 1.Packing should capable to withstand rough

Physically check for sample size

Page 36: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 36 of 44

36

36

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

sea weather for a minimum period of 4 to 6 months and should be commensurate with best commercial export practices. All packing shall be done in such a manner as to reduce the volume as much possible. Fragile articles should be adequately packed with special packing materials depending on type of materials. 2.All delicate surface and electrical equipment and other heavy article should be carefully protected and painted with protective paint/ compound and wrapped to prevent rusting and damage. 3.All mechanical and electrical equipment and other heavy articles should be securely fastened to the bottom of the case and shall be blocked and braced to prevent movement. 4.Attachments and spare parts of equipments and all small pieces shall be packed separately in wooden cases with adequate protection inside the case and wherever possible should be sent along with the main equipment. Each item shall be tagged so as to identify it with the main equipment and part

Page 37: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 37 of 44

37

37

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

number and reference number shall be indicated. 5. All protrusions shall be suitably protected and opening shall be blocked by wooden covers. 6. Wherever required equipment/materials shall be packed in polythene bags and silica gel or similar dehydrating compound shall be put inside the bags to protect them. 7. Pipes/tubes made of stainless steel, copper etc. Shall be packed in wooden cases irrespective of sizes. 8 The supplier shall be held liable for all damages or breakages to the goods due to the defective or insufficient packing as well as for corrosion due to insufficient packing. 9. Detailed packing list in waterproof envelope shall be inserted in each package together with equipment/materials. One c o p y of "detailed packing list", shall be fastened outside of the package in water proof envelop and covered by the metal cover. Marking: 1.each package shall be marked on four sides,

Page 38: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 38 of 44

38

38

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

with proper paint/indelible water proof inks as follows: Packing slip (with minimum following details ) To, M/S BHARAT PETROLEUM CORPORATION LTD. DESTINATION: MUMBAI/DELHI/CHENNAI/KOLKATA SHIPPING MARK: BPCL (M) MUMBAI PURCHASE ORDER NO ..............DATE ............. ITEM NO OF P.O………..MODEL NO……………... ITEM DESCRIPTION AS PER PO………………….. NETWEIGHT..........KGS.GR.WT.............. KGS COUNTRY OF ORIGIN .................................. SHIPPER’S NAME : …………………………….

2. Additional marking such as “ Handle with care” “This side up”, “Fragile” or any other additional indication for protection and safe handling shall be added depending on the type of material. All cases will have warning signs on the outside denoting ‘Center of gravity and sling mark’

Page 39: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 39 of 44

39

39

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

3.Name plate on each of the MPDs (02 nos. name plates on each MPDs- one on each side ) with minimum following details.

a. Purchase Order Number /date: b. Model No: c. Sr. No: d. Mfg. Date: e. Mfg. by M/s: f. Date verified and stamped by W&M legal

Metrology: g. CCOE certificate: h. Capacity: i. W&M no:

20 JUNCTION BOXES

20.a There will be two separate junction boxes inside MPDs; one for electrical input catering to MPD electronics, lights etc. and another to terminate the MPD communication cable. The location of the junction boxes shall be in the bottom enclosure of the MPD.

Physically check for sample size

20.b Physically check

Page 40: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 40 of 44

40

40

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

The communication cable between the MPD controller card and the second Junction Box should be pre-wired, terminated with suitable FLP glands. A duly plugged opening to be provided on the JB to allow entry of communication cable from POS.

for sample size

21 REQUIRED STANDARDS AND CERTIFICATIONS

21.a The electronic and electric circuit of MPDs must conform to UL 87 or ATEX CE or equivalent standards. BPC would like these standards to be certified to this extent. Only exception to UL 87 would be motor trigger linked with nozzle instead of having a separate activation mechanism for motor.

Physically check for sample size

21.b The power condition in India calls for a high degree of noise insulation for electronic and communication circuitry in the dispensing units. BPC would prefer to have CE standards followed in this regard. The equivalent US standards may also be

Physically check for sample size

Page 41: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 41 of 44

41

41

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

SR NO

TENDER REQUIREMENT

REQUIREMENT

OBSERVATION/ COMMENTS/

RESULTS of TPIA during Inspection

acceptable. 21.c

All Measuring Units should be OIML certified or equivalent.

Physically check for sample size

21.d The pulsar unit should adhere to CE standards. RS 485 should be Optically/Magnetically/ Capacitively isolated

Physically check for sample size

NOTEs A. In addition to above, TPIA shall also verify the following for the specified sample size:

1. Segment check facility. 2. Automatic zeroing with respect to on/off operation. 3. Checking for internal component configuration, workmanship and finish. B. TPIA Report should also cover the following. 1. Witness Stuffing of cleared/inspected MPDs wooden Boxes/Crates in Containers. TPIA report should provide Container No details ,

No of MPDs, SR NO of MPDs in each container 2. Based on successful completion Sample check and Random check, full offered LOT can be cleared for Dispatch. Report should

provide all Sr Nos of MPDs in the LOT with Configuration and also list of SR Nos of MPDs selected for Sample and Random Check of MPDs. TPIA should Stamp all MPDs in the cleared LOT at an easily accessible but discreet place with an identification Mark. The location of Marking and identification Mark should be mentioned in the TPIA report.

Page 42: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 42 of 44

42

42

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

Photographic Sample of MPD Top Fascia.

TOP FASCIA

Page 43: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 43 of 44

43

43

BHARAT PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs

Sample Drawing : The dimensions as mentioned in the drawings below can vary to some extent, but the overall profile (shape and size) of the Top Fascia should be maintained. The same will be approved by BPCL during FAT. The height of the fascia at the centre should be 220 mm. For 2X4X4, 3X6X2 and 4X8X2 (fig in mm)

Page 44: BHARAT PETROLEUM CORPORATION LTD. … PETROLEUM CORPORATION LTD. ANNEXURE- VI THIRD PARTY INSPECTION CHECKLIST SCOPE of THIRD PARTY INSPECTION AGENCY (TPIA) FOR MPDs b) Wherever “confirmation

Confidential Name and Signature of bidder:

Signature Page 44 of 44