bhakra beas management board - world bank · 2016. 7. 14. · environmental audit report – bbmb....

68
Bhakra Beas Management Board Environmental Audit Report – BBMB March 2010 Plot No. 6-B, Sector 19-B Madhya Marg, Chandigarh-160 019 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Upload: others

Post on 27-Jan-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

  • Bhakra Beas Management Board

    Environmental Audit Report – BBMB

    March 2010

    Plot No. 6-B, Sector 19-B Madhya Marg, Chandigarh-160 019

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    wb350881Typewritten TextE2407

  • Environmental Audit Report – BBMB

    CHAPTER 1

    CONTEXT

    1.1 Power Generation at BBMB (Bhakra Beas Management Board): BBMB hydro projects were constructed between 1955 and 1978. These projects comprise Bhakra Dam on river Sutlej with Power

    Stations on left and right banks (1325 MW), irrigation channel with two canal power houses (155 MW),

    Pong Dam on river Beas with a power station (396 MW). In addition, the projects include a diversion dam

    on river Beas to divert its water to river Sutlej through a 38 KM long water conductor system in the form

    of tunnels, open channel, balancing reservoir and Dehar power station (990 MW) at the tail1.

    The annual power generation from these power stations is between 10,000 to 14,000 GWh.BBMB hydro

    projects are connected to the Northern Grid... Importantly, the BBMB hydro projects provide invaluable

    peaking power and serve as sources of emergency & black start power to the Northern Grid of India.

    1.2 Power Deficit and Power Generation Options: The equipment at BBMB power houses have been in successful operation for more than thirty years. There is a huge shortage of peaking power.

    Further, the Northern Grid - a key beneficiary of the power generated from the power houses of BBMB -

    remains deficit with respect to the power requirements. Following options can be considered at National

    level to tide over the issues related to power shortages

    Option 1 : to construct fossil fuel based new power houses to meet the power demand. This option will

    however lead to emission of pollutants including carbon dioxide and generation of undesirable residues

    such as fly ash. Fossil fuel being a non-renewable resource will also get depleted.

    Option 2 : to explore construction of additional hydropower units. This option will lead to issues such as

    finding new sources of hydropower generation , gestation time of the hydro plants, resettlement of people

    in the submerged area, heightened seismicity hazard (for reservoir based high gravity dams) and string of

    ecological impacts – especially in the downstream areas.

    Option 3 : to carry out up-gradation of existing equipment through Renovation, Modernization and

    Upgradation (RM&U). This option will leave least environmental and social impacts both at national and

    regional levels..

    1 Refer to Figure 2.2 in Chapter 2 for more details.

    1

  • Environmental Audit Report – BBMB

    BBMB has decided to undertake R,M&U option so as to create additional power generation capacities in

    the grid.

    1.3 Clean Development Mechanism: Adoption of RM&U measures leading to added power

    generation capacity at the BBMB power houses would lead to reduction of carbon dioxide emissions

    (Green House Gas –GHG) at the grid level as it would substitute the power that would have otherwise

    been generated through fossil fuel based power plants.. The RM& U option adopted by BBMB has been

    developed as a CDM (Clean Development Mechanism) project under the Kyoto Protocol of the UNFCCC

    (UN Framework Convention on Climate Change)

    The carbon revenues earned from the CDM project would be used to overcome the barriers that BBMB

    faces towards implementation of the R,M& U activity. The RM&U project can become a showcase for the

    hydro & fossil based power houses in India to follow. The additional power available in the Northern Grid

    through R,M&U activity would ensure reduced detrimental environmental impacts and enhanced

    economic development in the industrial, agriculture and the commercial sectors.

    1.4 Proposed Activities under CDM project at BBMB:

    The RM&U work includes the following activities:

    • Replacement of existing generation equipments (turbine runner, generator, generator transformer and

    allied systems) with energy efficient ones; and

    • Providing a state-of-the-art control, instrumentation and protection system for better monitoring.

    A total capacity addition of 90.0 MW is envisaged through these RM&U activities, whose basic objectives

    are:

    • To increase the capacity and energy generation with upgraded turbine runners for more

    effective utilization of Sutlej-Beas river waters

    • To ensure safe, reliable and economic electricity production by the replacement of worn-out,

    deteriorated or obsolete electrical, mechanical, instrumentation

    The role of BBMB in this project will be in the following capacities:

    • Project Operator

    • Owner of the site and project

    • Owner of the emission reductions

    • Seller of the emission reductions

    1.5 Applicability of World Bank’s Environmental and Social Safeguards: Undertaking RM & U

    activities to generate additional power is the most environmentally sound and socially acceptable option. In

    2

  • Environmental Audit Report – BBMB

    fact, upgrading of existing turbines is essentially an efficiency enhancement measure that leads to reduced

    carbon dioxide emissions and has benefits towards climate change. However, despite above, it still

    becomes imperative to examine the projects as well as BBMB as an institution in the context of World

    Bank’s Environmental and Social Safeguards.

    Table 1.2 lists the relevant environmental and social safeguards in the context of the RM & U projects.

    Table 1.2: Environmental and Social Safeguard Policies of the World Bank Triggered by the

    Proposed RM & U Projects at BBMB

    Safeguard Policies Triggered Yes No

    Environmental Assessment (OP/BP 4.01) X Natural Habitats (OP/BP 4.04) X Forests (OP/BP 4.36) X Pest Management (OP 4.09) X Physical Cultural Resources (OP/BP 4.11) X Indigenous Peoples (OP/BP 4.10) X Involuntary Resettlement (OP/BP 4.12) X Safety of Dams (OP/BP 4.37) X Projects on International Waterways (OP/BP 7.50) X (see Section 1.6.1) Projects in Disputed Areas (OP/BP 7.60) X

    Except the safeguard on Environmental Assessment (OP/BP 4.01) and Dam Safety, no other

    Environmental and Social Safeguards are triggered in this project. A separate report has been prepared to

    examine the Dam safety safeguard and the present report is limited to the environmental issues. Section

    1.6.1 below reports on the applicability of OP 7.5 for the sake of completeness.

    1.6.1 Applicability of the Exceptions to External Notification Requirements of OP 7.50: According

    to paragraph 7 of OP 7.50, there are exceptions to the Bank’s requirement that the other riparian states be

    notified about the project. According to paragraph 7(a) of OP 7.50, the exception applies:

    “… (a) For any ongoing schemes, projects involving additions or alterations that require

    rehabilitation, construction, or other changes that in the judgment of the Bank

    (i) will not adversely change the quality or quantity of water flows to the other riparians; and

    (ii) will not be adversely affected by the other riparians’ possible water use.

    This exception applies only to minor additions or alterations to the ongoing scheme; it does not

    cover works and activities that would exceed the original scheme, change its nature, or so alter or

    expand its scope and extent as to make it appear a new or different scheme. In case of doubt

    regarding the extent to which a project meets the criteria of this exception, the executive directors

    representing the riparians concerned are informed and given at least two months to reply. Even if

    projects meet the criteria of this exception, the Bank tries to secure compliance with the requirements

    of any agreement or arrangement between the riparians. ”

    3

  • Environmental Audit Report – BBMB

    The project team has assessed the project components in the context of OP 7.50 and concludes that

    exception to the external notification requirements of OP 7.50, set forth in paragraph 7(a) of OP 7.50, is

    fully applicable to this project for the reasons mentioned below:

    • The project does not envisage any alteration in flows of water through the turbines from the

    original scheme. The capacity enhancement (uprating) is proposed to be achieved through

    replacement of existing generation equipment with more energy efficient ones without any

    changes to water flows.

    • The project works are small compared to the original scheme, are meant to support the

    rehabilitation of the original scheme

    • The project lies between existing upstream and downstream regulation structures in what is

    effectively a long cascade of river development and thus is not expected to impact the other

    riparians.

    Thus, given the nature of works envisaged under the proposed project: (a) the project will not adversely

    affect the quality or quantity of water flows to other riparians; (b) it will not be adversely affected by other

    riparians’ water use either; and (c) it does not change the nature of the scheme, or so alter or expand its

    scope and extent as to make it appear as a new or different scheme. Therefore, the exception to the

    external notification requirements of OP 7.50, set forth in paragraph 7(a) of OP 7.50, is fully applicable to

    this project.

    1.7 Environmental Audit -Focus and Approach: Since the projects and project sites already exist

    on the ground with a long history of operations, the environmental examination is more akin to an

    Environmental Audit2 rather than Environmental Impact Assessment (EIA). Box 1.1 below explains the

    spirit and scope of an Environmental Audit.

    Box 1.1 Environmental Audit and Environmental Impact Assessment- a comparative analysis3

    2 Also referred in some cases as Environmental Due Diligence (EDD) – especially when transfer of assets is involved.

    3 http://www.gdrc.org/uem/eia/eia-audit.html

    4

    http://www.gdrc.org/uem/eia/eia-audit.html

  • Environmental Audit Report – BBMB

    Environmental impact assessment is the mandatory assessment of the compliance of planned activities,

    such as planning documents, programmes and projects, with environmental protection requirements

    with the principles of sustainable development, with the aim of determining the optimum solution.

    On the other hand, environmental audit is the assessment of the compliance of environmental

    administration and performance of an operating business with environmental protection requirements,

    sound environmental practice in general, and the principles of sustainable development.

    Environmental auditing is mandatory only in cases stipulated by law.

    Environmental audits are being used as a tool and an aid to test the effectiveness of environmental

    efforts at local level. An environmental audit is a systematic, independent internal review to check

    whether the results of environmental work tally with the targets. An environmental audit also focuses

    on whether the methods used to achieve goals are effective. To be more precise the work of an

    environmental audit is a study of documents and reports to see whether there are any deviations

    between targets and results. This is done by interviewing key people in the organisation. An

    environmental audit will confirm whether or not the environmental targets have been attained.

    During a typical environmental audit, a team of qualified inspectors (either employees of the

    organization being audited or contractor personnel), conducts a comprehensive examination of a plant

    or other facility to determine whether it is complying with environmental laws and regulations. Using

    checklists, audit protocols , relying on professional judgment and evaluations of site-specific

    conditions, the team systematically verifies compliance with applicable requirements. The team may

    also evaluate the effectiveness of systems in place to manage compliance and assess the environmental

    risks associated with the facility's operations.

    The Environmental Audit in the case of BBMB’s RM&U projects was therefore targeted to assess

    • Environmental compliance,

    • Environmental Management System on an organization wide basis and

    • BBMB’s institutional capacity and commitment to environment

    The Environmental Audit thus aimed to ascertain:

    5

  • Environmental Audit Report – BBMB

    • BBMB’s understanding and sensitivity to the environmental issues and whether appropriate

    actions are taken to manage these issues

    • BBMB’s status on Environmental Compliance and whether a system is in place to monitor and

    audit the same

    • BBMB’s human resources for environmental management, adequacy and capacity

    To conduct Environmental Audit as per above, meetings were held with top management and concerned

    BBMB officials. Visits were made to the project sites and concerned staff at BBMB was interviewed,

    especially the Environmental Officers (EOs). In addition, documents concerning consents/authorization

    were accessed and reviewed. Supporting data on environmental monitoring was also looked into. As

    BBMB has implemented Environmental Management System (EMS) as per ISO 14001, the EMS

    documentation formed an important basis for Environmental Audit. Training programs and training related

    arrangements and facilities were also examined from capacity building perspective. Figure 1.1 explains

    the overall approach that was followed.

    1.8 Limitations: There are certain limitations to this Environmental Audit report that should be noted.

    • The focus of the Environmental Audit was limited to the CDM project sites and did not cover all

    the BBMB projects.

    • There were limited site visits

    • The Audit was performed solely based on the secondary data and information provided by BBMB.

    No primary and independent data are generated through third party monitoring to verify the data

    provided.

    However these limitations should be acceptable given the project context, low environmental and social

    sensitivity and BBMB’s record on meeting compliance with environmental regulators such as Pollution

    Control Boards (PCBs). The compliance records have been satisfactory.

    Further, BBMB has implemented Environmental Management System (EMS) as per ISO 14001. The

    practice and records of internal and external audit of EMS provide a basis for independent assessment and

    lend credence to the information provided. The Environmental Audit therefore focused on the assessment

    of EMS to understand organization wide commitment and management capacity at the BBMB. This

    assessment has been satisfactory.

    1.9 Structure of the Report: The report is developed across six chapters. Chapter 1 sets the context.

    Chapter 2 provides an overview of BBMB, its mandate, assets under management and the socio-economic

    6

  • Environmental Audit Report – BBMB

    and environmental implications. The various environmental management related initiatives undertaken by

    BBMB are described in Chapter 3 with an introduction to the EMS approach that has been adopted. The

    EMS approach has now set an overarching framework at BBMB that is driven through policy, objectives

    and targets rather than practicing a project limited ad-hoc approach. Chapter 4 therefore details the EMS

    system at BBMB, its structure and operation with supporting details in various annexes. Chapter 5

    describes the social welfare related initiatives undertaken by BBMB that are interlinked to environmental

    issues and demonstrate BBMB’s proactive community commitments. Finally, overall observations and

    recommendations are summarized in Chapter 6 for BBMB’s consideration.

    7

  • Environmental Audit Report – BBMB

    CHAPTER 2

    BACKGROUND: ABOUT THE BHAKRA-BEAS MANAGEMENT BOARD

    2.1 History and Evolution: Bhakra-Beas River Valley Development Projects formed a major part of

    the master plan formulated for the optimum utilisation of waters from three rivers viz. Sutlej, Beas and

    Ravi which came to the exclusive share of India as per Indus Water Treaty concluded with neighbouring

    Pakistan in the year 1960. Originally, the Bhakra-Beas River Valley Development Projects were the joint

    ventures of erstwhile Punjab and Rajasthan State Governments.

    2.2 Constitution: However, on reorganisation of the erstwhile state of Punjab on 1st November, 1966, the

    Bhakra Management Board (BMB) was constituted under section 79 of the Punjab Reorganisation Act,

    1966 for the administration, maintenance and operation of Bhakra Nangal Project on 1st October 1967.

    Construction of Beas Projects, a joint venture of States of Punjab, Haryana and Rajasthan was entrusted to

    Beas Construction Board according to Punjab Reorganisation Act. The Beas Project Works, on

    completion, were transferred by Government of India from Beas Construction Board (BCB) to Bhakra

    Management Board as per Section 80 of the Punjab Reorganisation Act, 1966 and the Bhakra Management

    Board was renamed as Bhakra Beas Management Board (BBMB) w.e.f. 15th May 1976.

    Partner State Governments and their State Electricity Boards form the key partners and stakeholders of

    BBMB. The BBMB consists of a whole time Chairman, two whole time Members (appointed by the Govt.

    of India) and one representative each from the states of Punjab, Haryana, Rajasthan and Himachal Pradesh

    besides two representatives from Govt. of India (One each from Ministry of Power and Ministry of Water

    Resources).

    2.3 Vision, Mission and the Mandate: Box 2.1 below states the Vision and Mission statement of

    BBMB

    Box 2.1 Vision and Mission statement of BBMB

    Vision Statement:

    “To lead and be a trend setter in the power sector in establishing high standards in operation, maintenance,

    renovation and modernization of hydel projects, transmission, canal systems and to exploit new hydro

    power potential to optimally utilize the existing infrastructure and resources.”

    Mission Statement:

    “To keep our systems running efficiently at minimum cost.”

    8

  • Environmental Audit Report – BBMB

    The mandate or the functions of BBMB which are specified in Section 79(1) and (3) of Punjab

    Reorganization Act are as under:

    1. To administer, operate and maintain Bhakra-Beas Projects, Beas-Satluj Project and Pong Dam.

    2. To regulate the supply of water from Satluj, Beas and Ravi rivers to the States of Punjab, Haryana,

    Rajasthan and Delhi.

    3. To regulate the supply of power from Bhakra Nangal and Beas projects to the States of Punjab,

    Haryana, Rajasthan, Himachal Pradesh and Chandigarh.

    4. Any other function as Central Government may assign after consultation with the Governments of

    States of Haryana, Punjab, and Rajasthan4.

    2.4.1 Assets Constructed, Presently Managed and Assets Improved: The BBMB projects were begun on the basis of the Indo-Pak Indus River Treaty allowing for the exclusive use of the river

    waters of Ravi, Beas and Sutlej to India. The projects were initiated as early as 1948 and

    substantially completed around 1966. The main dams/barrages forming a part of the BBMB

    Master Plan were:

    • Bhakra-Nangal on River Sutlej

    • Pong-Pandoh on River Beas

    • Thein on River Ravi

    Among these, the Bhakra Dam was the most significant project

    BBMB functions to distribute waters of the three rivers as well generate and distribute the generated hydro

    power to the states of Punjab, Haryana, Rajasthan, Himachal Pradesh and to the independently

    administered Union Territories of Delhi and Chandigarh in Northern India.

    Figure 2.1 shows the location of the influence area states covered by BBMB and Figure 2.2 is the Master

    Plan of River Satluj, Beas, Ravi and Connected Main Canals.

    4 In the year 1999, the Government of India entrusted additional functions of providing and performing engineering and related technical consultancy services in fields of HEPs and irrigation projects.

    9

  • Environmental Audit Report – BBMB

    Figure 2.1: States Benefiting from the Bhakra Nangal Project

    10

  • Environmental Audit Report – BBMB

    RAJASTHAN

    CHANDIGARH

    DELHI

    Beas (Pong) Dam

    Pandoh Dam

    Ranjit Sagar(Thein) Dam

    Bhakra Dam

    Nangal Dam

    Harike H/W

    Sutlej River

    Ropar H/W

    MadhopurH/W

    Sirhind Canal

    Anandpur Sahib H/ChannelNangal H/Channel

    Tajewala H/W

    Madhopur Beas Link

    Beas

    Sutle

    j Li

    nk

    Bhakra BeasNation’s Pride

    Ghaggar H/W

    Bikaner

    Jaisalmer

    Manak Escape

    International BorderState Boundary

    RiverCanal/ Branch

    Legend:

    Dam/ HW

    N

    Head BML

    Har. Con. Pt. RD 1,60,000’

    HR. Con. Pt. RD 3,90,000’

    UTTAR PRADESH

    J & K

    HARYANA

    PUNJAB

    HIMACHAL PRADESH

    Ferozepur Feeder’

    Wazirabad Barrage

    Okhla Barrage

    Figure 2.2: Master Plan of River Satluj, Beas, Ravi and Connected Main Canals.

    Bhakra Nangal Project:

    The Bhakra Dam was the first multi-purpose project of Free India. It was dedicated to the Nation on the

    22nd of October in 1963 by Pundit Nehru. Key features of the Bhakra dam are:

    Height of the dam 225.55 m (740 feet) (from the deepest foundation)

    Type of dam Concrete straight gravity

    Length at top 1700 feet Elevation at top of dam (above mean

    sea level) 1700 feet

    Name of reservoir Govind Sagar Area of reservoir 168.35 sq.km Length of reservoir 96.56 km Catchment area 56,980 sq km Gross Storage capacity of Reservoir 9621 million m3

    11

  • Environmental Audit Report – BBMB

    Key features of the Bhakra Dam power Houses are:

    Left Bank Power House

    Installed capacity 5 x 108 MW = 540 MW

    Type of turbine Vertical shaft

    Right Bank Power House

    Installed capacity 5 x 157 MW = 785 MW

    Type of turbines Vertical shaft

    Nangal Dam and Nangal Hydel Channel

    A barrage at Nangal called “Nangal Dam” for diversion of Satluj Water to Irrigation Channels through a

    65 km long Nangal Hydel Channel was constructed in 1954.

    Canal Power Houses

    Power generation at Ganguwal (77.65 MW) and Kotla (77.65 MW) Canal Power Houses had commenced

    in 1955 and 1956 respectively.

    Beas Satluj Link Project (Beas Unit – I)

    • This was the first Inter-linking River Project.

    • Beas Unit-I i.e. the Beas Satluj Link Project had been completed in 1977. It diverts 3.80 MAF of

    Beas Waters to Satluj and generates 990 MW of power at Dehar Power Plant. The Schematic

    View of the Beas Unit – I is shown in Figure 2.3.

    12

  • Environmental Audit Report – BBMB

    Figure 2.3: Schematic View of the Beas Unit – I

    Beas Project (Beas Unit – II)

    Beas Unit –II is the Pong Dam which was completed in 1974. It is also a big storage dam and the main

    source of water to the desert lands of Rajasthan. 396 MW of power is generated here. The key features of

    the Pong Dam are:

    Height of Dam 132.59 m (435 ft.)

    Gross Storage capacity of

    Reservoir

    8570 million m3

    Area of Reservoir 260. sq. Km.

    BBMB Reservoirs

    There are two big storage Reservoirs namely, ‘Gobind Sagar’ and ‘Maharana Partap Sagar’ which provide

    irrigation and drinking water to Punjab, Haryana, Rajasthan, Delhi and Chandigarh. Drinking water is also

    supplied to Himachal Pradesh.

    13

  • Environmental Audit Report – BBMB

    BBMB Hydro Power Plants

    Sr.

    No.

    Name of the Plant Original Installed Capacity Installed Capacity after

    RM&U

    1 Bhakra Left Bank 450 MW 540.00 MW

    2 Bhakra Right Bank 600 MW 785.00 MW

    3 Ganguwal Power Plant 77.65 MW 76.39 MW

    4 Kotla Power Plant 77.65 MW 77.34 MW

    5 Dehar Power Plant 990 MW 990.00 MW

    6 Pong Power Plant 360 MW 396.00 MW

    TOTAL 2555.30 MW 2864.73 MW

    BBMB Transmission Network (as shown in Figure 2.4)

    Lines Sub-Stations (Nos.) Lines Length (Ckt.

    km.)

    400 KV 3 574

    220 KV 17 2995

    132 KV 2 22

    66 KV 2 115.5

    Total 24 3706.5

    14

  • Environmental Audit Report – BBMB

    Figure 2.4: BBMB Transmission Network

    2.5 Environmental and Economic Benefits Accrued to BBMB Projects: All the three river valley projects managed by BBMB i.e. Bhakra-Nangal, BSL Project and Beas Dam Project were planned and

    executed before 1978, i.e. much before Environmental Impact Assessment (EIA) was made mandatory by

    the Government of India5. Hence, no EIA report is available on the BBMB projects.

    The environmental benefits of the projects have been however accounted on gross terms. For example the

    Bhakra-Nangal Project (BNP) has generated about 248 billion kWh of energy between 1955 and 2005. An

    equivalent thermal power would have consumed 161 million tons of coal and would have produced more

    5 Ministry of Environment and Forests vide Notification on EIA of 1994 made Environmental Impact Assessment mandatory for the Environmental Clearance of Large Hydel projects

    15

  • Environmental Audit Report – BBMB

    than 50 million tons of ash content. Environmental impacts of handling and disposal of such quantities of

    fly ash, especially on the counts of air emissions, land occupation and soil/water degradation were thus

    avoided had a coal based thermal route was taken for generation of power.

    Some of the significant socio-economic benefits of BBMB projects are listed below. Many of these

    benefits provide reduced risks, conservation and protection to the environment in the catchment of BBMB.

    • Bhakra and Beas Projects, being multi-purpose projects involving power and irrigation, have ushered

    in India’s well-known ‘Green Revolution’; the assured irrigation supply for the Green Revolution was

    provided by canals from BNP as well as tube wells energized from the power generated by BNP.

    Combined together, these two aspects of BNP had a major role in the food grain production in Punjab

    and Haryana – between the 1960s and 2000, productivity for wheat and rice in terms of kg/Ha has

    nearly tripled for both states. At the present time, the average wheat yield in Punjab is the highest for

    any state in India, with Haryana taking second place. Only these two states in India have crossed a

    yield of over four tons per Ha, a fact credited to BBMB projects

    • In 1951, only 42 out of 11,947 villages in Punjab had electricity. With the help of power generation

    from Bhakra, Punjab and Haryana were the first States in India to provide electricity to every village

    in the year 1975-76.

    • The Bhakra and Beas Reservoirs have been shown to save the regional ecology from devastating

    floods. While flood control was not a primary objective of the project, it has proved to be a boon for

    the areas and population in the downstream areas of river Sutlej. Since commissioning till date,

    average daily inflows of more than 90,000 cusec were received in 16 years. Bhakra absorbed all the

    floods except in two years i.e. in 1978 and 1988 when average daily discharge of more than 50,000

    cusec were made from Bhakra Dam. Bhakra Dam has also been absorbing floods up to 6,00,000 cusec.

    Similarly, the flash floods in 1997, 2000 and 2005 in the Sutlej brought about large-scale devastation

    in Himachal Pradesh, but had no effect in Punjab

    .

    • With the help of power generation from Bhakra-Nangal Project, the region underwent large-scale

    industrialization. Nangal Fertilizers factory was among the earliest of these which received Power

    directly from Bhakra Power Houses. The refugees settled in BNP Command area soon developed

    industrial enterprises. Ludhiana, Jalandhar and Amritsar in Punjab and Faridabad, Ballabhgarh and

    Sonepat in Haryana were developed as major industrial centres. In addition to big industries, a large

    number of small-scale industries have also come up in this area. In Punjab alone, the number of

    small-scale industries has grown to around 2,00,000, employing nearly a million people.

    16

  • Environmental Audit Report – BBMB

    • These reservoirs have also provided a source of tourism. Every year, about 3 lakh tourists visit the

    Gobind Sagar Lake which was formed upstream of the Bhakra dam as a major tourist attraction.

    • BBMB project reservoirs serve as important sources of fish production as well. On an average, over

    1,100 tones of fishery products are raised and sold by the local fishermen each year. The Gobind Sagar

    reservoir has in fact created history by maintaining the highest per unit fish production in large

    reservoirs for the last two decades in the country. 1,400 direct and 1,500 indirect jobs have been

    generated to run these operations.

    Box 2.2 lists some of the salient economic indicators attributable to BBMB projects.

    Box 2.2: Salient Economic Indicators Attributable to BBMB Projects

    Bhakra Nangal Project:

    New area irrigated: 26 lakh Ha

    Area where irrigation improved: 9

    lakh Ha

    Number of towns electrified: 128

    Number of villages electrified:

    13,000

    Annual increase in food grains:

    15.78 lakh tonnes

    Cost of annual agricultural

    produce: Rs. 465 crores

    Cost of out-turn from major

    industries: Rs. 635 crores

    Beas Project Unit – I (Beas Sutlej

    Link):

    Annual irrigation: 3.26 lakh Ha

    Annual increase in food grains:

    223.6 thousand tonnes

    Cost of annual agricultural

    produce: Rs. 100 crores

    Beas Project Unit – II (Beas Dam

    at Pong):

    Annual irrigation: 1.6 million Ha

    Annual increase in food grains: 2

    million tonnes

    Cost of annual produce: Rs. 350

    crores

    Clearly, the economic indicators show a significant positive impact of BBMB projects on the economy of

    the participating States.

    BBMB has been following all the environmental compliance related requirements with the concerned

    authorities by undertaking prevention, control and monitoring measures. In addition to the requirements of

    Environmental Compliance, BBMB has adopted an Environmental Management System (EMS as per ISO

    14001) on a proactive basis supported with an Environmental Management Plans (EMP). This EMP is

    17

  • Environmental Audit Report – BBMB

    implemented and improved on a continual basis to ensure that environmental aspects (issues) are identified

    and addressed through appropriate institutional and budgetary provisions.

    On the whole, it can be said that BBMB Projects have brought about socio-economic upliftment of the

    region by way of enhanced industrialization & employment opportunities, better energy and irrigation

    facilities, ecological protection and improvement due to non-devastation possible by flood control

    measures. A balanced view on economic, environmental and social scorecard of BBMB’s development

    effectiveness therefore shows a positive result.

    18

  • Environmental Audit Report – BBMB

    CHAPTER 3

    MANAGEMENT OF ENVIRONMENTAL ISSUES / ASPECTS AT BBMB

    3.1 Key Environmental Issues: As no new construction activities are executed by BBMB under the

    present project activity, the environmental issues/aspects for BBMB are limited mainly to the operation of

    various existing assets, utilities and supporting infrastructure. The key activities and linked environmental

    issues cover the following as depicted in Table 3.1

    Table 3.1 Environmental Issues/Aspects in BBMB Operations

    Activity Environmental issue/aspect

    Management and disposal of silt in reservoirs

    impact on land and agriculture

    Minor repairs, reconstruction for strengthening etc Construction and demolition waste

    Lake tourism activities Contamination of water

    Fabrication and Maintenance of machinery

    impact on soil and water due to release of oil,

    lubricants;

    noise,

    packaging waste

    worker health and safety

    Townships

    Generation of sewage

    Generation of solid waste

    Generation of biomedical waste from hospitals

    All the impacts cited above are mitigable and not significant if managed effectively especially to meet the

    compliance requirements as per the applicable laws and regulations.

    3.2 Impact Mitigation and Enhancement Measures: BBMB has been addressing the impacts cited

    in Table 3.1 through various mitigation as well as enhancement measures. These include

    19

  • Environmental Audit Report – BBMB

    • practicing good housekeeping and training at the project sites (e.g. through waste prevention and

    management). In addition, BBMB has been checking encroachments along the roads to stop

    choking of drains, supply lines, sewer lines etc. as a preventive measure.

    • raising awareness. BBMB has been implementing ‘Awareness Programmes’ among BBMB

    employees to plant trees/plants around their residences/colonies.

    • creation of requisite pollution control facilities (e.g. providing environmental infrastructure at

    townships)

    • implementing environmental enhancement measures through stakeholder partnerships (e.g. joint

    aforestation with communities and construction contractors)

    • carrying out monitoring and control (e.g. ensuring environmental compliance and permits with

    Pollution Control Boards (PCBs)

    • conducting environmental impact assessment (EIA) where there is a public interest, issues are

    complex and identification of mitigations is not obvious

    • Remaining in touch with PCBs for latest guidelines, innovations, instructions in the environment

    field. Participate in seminars, publish papers relating to the steps undertaken and results gained

    and to conduct pilot studies, if found necessary.

    It may be thus observed that the strategies adopted by BBMB are wide encompassing covering prevention,

    control and conservation supported by physical, institutional and policy measures. Some of the specific

    mitigation and enhancement measures implemented by BBMB are listed in the sections below.

    3.2.1 Impact Mitigation Measures: On the townships, following measures have been taken towards

    building and operating required environmental infrastructure.

    • Sewage management at BBMB townships: BBMB has three major residential townships at Nangal,

    Sundernagar and Talwara. At Nangal, which is the largest township, a Sewage Treatment Plant (STP)

    of 1.5 million gallon per day capacity is in operation. Sundernagar, Pandoh and Slapper townships also

    have STPs. There is no STP at Talwara where the sewage is treated with bleaching powder. However,

    regular testing of sewage quality is carried out from labs.

    • Hospital waste management in BBMB hospitals: There are three 100-bedded hospitals in the townships

    of BBMB, at Nangal, Talwara & Sundernagar. Hospital waste is disposed off as per prescribed norms.

    20

  • Environmental Audit Report – BBMB

    Clearance for treatment/disposal of bio-medical waste has been obtained from PPCB for Nangal &

    Talwara Hospitals.

    • Solid waste management: BBMB has prepared solid waste management plans for its safe and scientific

    disposal around the project areas as compliant with the applicable MSW (management and handling

    rules). These plans are currently under implementation.

    3.2.2 Environmental Enhancement Measures: Apart from mitigations and management measures,

    BBMB has carried out environmental improvement projects and programmes. Highlights of these

    initiatives are described below.

    • Adjacent to the “Greenland Project”, a ‘Rock Garden’ on the pattern of Nek Chand Rock Garden of

    Chandigarh has been established on 20 acres of land at Talwara under the able guidance of Padam Shri

    Nek Chand Ji. It is important to note that the Rock Garden was established with Beas Project

    wastes.

    21

  • Environmental Audit Report – BBMB

    BBMB has identified green belts & development of parks, nurseries, gardens in the spare land of BBMB.

    Here, aforestation programmes are taken up in partnership with communities and drawing support from

    construction contractors.

    BBMB has prepared ‘Catchment Area Treatment’ and ‘Fringe Area Treatment’ Plans and is implementing

    these plans in coordination with Himachal Pradesh Govt. Authorities.

    3.2.3 Environmental Monitoring: BBMB monitors the effectiveness of mitigation measures through

    environmental monitoring activities that are conducted in and around project locations as well as

    townships. Monitoring activities include

    • Monitoring of water quality at reservoirs and drinking water supplies

    • Ambient air and workspace noise monitoring

    3.2.4 Conduct of Environmental Impact Assessment: In some cases where the impacts need to be

    assessed on a more scientific basis, or if grievances are reported by the affected people, then BBMB has

    conducted Environmental Impact Assessment (EIA) on its own.

    These EIA studies are not stipulated under the EIA Notification but are conducted to resolve issues on a

    more rational and scientific basis. One such example is the EIA of BSL project that was commissioned by

    BBMB in 2000. This case is illustrated in the section below to underscore the proactive approach of

    BBMB in managing the environmental issues.

    3.2.4.1 Case of EIA Study of the BSL Project

    BBMB decided to engage NEERI, Nagpur for the EIA and EMP studies of BSL Project in 1999, because

    of the grievances received by affected people on account of the accumulation and disposal of silt. Public

    representative bodies/Non Government Organizations (NGOs) of the area, other Himachal Pradesh Govt.

    departments were also made stake-holders in the study. The ‘Final Report’ of the Institute was received in

    December 2000. Figure 3.1 shows the project location.

    22

  • Environmental Audit Report – BBMB

    Figure 3.1 Beas Satluj Link (BSL) Project

    The NEERI report was discussed in the 176th meeting of BBMB held on 12th November 2001 in which it

    was decided to implement the short-term mitigation measures as recommended at a cost of Rs. 182.8 lakhs.

    Table 3.2 shows the actions taken by BBMB against specific environmental issues as identified in this

    project.

    Table 3.2 EIA and EMP for BSL Project

    Short-term Measures Issue Identified Action Taken by BBMB Flow of Beas River downstream of Pandoh Dam

    Minimum daily inflow in River Beas at Mandi

    town should be 5% of minimum daily flow

    upstream of Pandoh Dam. After accounting for all

    the Khads/River/Rivulets confluencing with the

    River Beas in the reach between Pandoh Dam and

    Mandi and flowing under normal present

    condition, the short fall, if any, may be made up

    by release of water from Pandoh Dam.

    BBMB started maintaining the minimum daily inflow

    in river Beas at Mandi equal to 5% of the minimum

    daily inflow upstream of Pandoh Dam as

    recommended by NEERI and also started sending the

    data to H.P. Pollution Control Board, Shimla

    regularly.

    23

  • Environmental Audit Report – BBMB

    Minimum Environmental Flow in River Beas

    The Himachal Pradesh Govt. vide Notification

    dated 16.07.2005 and revised Notification dated

    09.09.2005 ordered to release the minimum flow

    downstream of Diversion Dams throughout the

    year at a threshold value of not less than 15% of

    the minimum inflow observed in the lean season.

    Accordingly, BBMB started releasing the minimum

    stipulated flow as desired vide above said

    notifications from Pandoh dam from September,

    2005. This step of BBMB is noteworthy as it

    demonstrates its environmental sensitivity while

    compromising on generation of power.

    In 2006, PSEB and NHPC filed writ petitions in

    the Hon’ble High Court Shimla challenging the

    notifications issued by H.P. Govt. regarding

    release of 15% minimum flow downstream

    throughout the year. The Hon’ble Court has

    stayed the impugned notifications qua petitioners

    only.

    However, BBMB has decided not to approach the

    Court of law for this issue.

    Road along Baggi Sundernagar Hydel Channel

    (tarring of one side of road along Hydel Channel).

    12 km metalled road was constructed along

    Sundernagar Hydel Channel. It has provided an all-

    weather means of transportation to the adjoining

    villages.

    24

  • Environmental Audit Report – BBMB

    Design & Maintenance of Cross-over Bridges:

    Seasonal cross over bridges on Suketi Khad

    needed to be improved using engineering

    concepts and proper maintenance.

    All the 22 Nos. temporary steel foot bridges on Suketi

    Khad were improved/fabricated during

    September/October 2002. These bridges are removed

    during monsoon and re-installed thereafter in the non-

    monsoon months and maintained by BBMB.

    (Before)

    (After)

    Organised promotion of fish production in Suketi

    Khad and its tributaries: Construction of fish seed

    ponds and fish propagation in the area delineated

    specifically for the artificial fish needed.

    Revised project proposal regarding ‘Promotion of

    fisheries in the riparian area of Suketi khad &

    adjacent streams’ was received from the Director of

    Fisheries (HP) in Sept. 2003. The administrative

    approval of Rs. 72 lakhs accorded by BBMB and the

    demand draft amounting to Rs. 36.00 lakhs (1st

    instalment) was released Oct. 2003. Fishery Dept. is

    still executing the 1st phase. Deposition of the silt in agriculture land: Silt-

    affected agricultural land needs to be made

    productive by adopting one-time farm

    management for restoration of land environment.

    The Scheme was not found techno-economically

    feasible & practicable by the HP Govt.

    25

  • Environmental Audit Report – BBMB

    Compensation to the farmers for the subsequent

    damage to crop and land, if any, with the help of

    revenue Dept. along the current line of practice.

    BBMB pays the compensation to the farmers for the

    damaged crops and the land, if any, with the help of

    Revenue Authorities of HP.

    Provision of cattle troughs: Possibility of

    providing cattle throughs along the Suketi Khad

    may be explored and implemented, if possible.

    BBMB earmarked Rs.4.40 lakhs for providing 22 no.

    troughs along Suketi Khad to provide clean drinking

    water to the animals for which the land was proposed

    to be provided by HP Govt. Lately, the Department

    of Animal Health/Breeding withdrew this demand, as

    from 2004 onwards clean water is available in the

    khad for animals during lean months.

    Long-term Measures

    Issue Identified Action Taken by BBMB W.R.D.T.C., University of Roorkee collaborated

    with NEERI to evolve the most techno-economic

    and viable solution for the safe disposal of silt

    from Balancing Reservoir.

    The various options were studied and following

    recommendations were made:

    • Reduction in silt load at Pandoh Dam

    • Increase in dredging rate

    • Disposal of silt

    Reduction in silt load at Pandoh Dam:

    Flushing of Pandoh Dam is done regularly by BBMB

    during high flood periods.

    Increase in dredging rate:

    2nd Dredger was procured and commissioned during

    the monsoon season of 2004.

    3rd Dredger has also been procured and has been put

    into operation from July, 2007.

    Disposal of silt:

    The Expert Committee’ meant for suggesting long-

    term option for disposal of silt was formed by

    CPCB & MoEF in 2004,which has suggested

    an Action Plan for disposal of Silt in 2005. The

    Action Plan is under implementation by BBMB.

    CAT Plan for BSL Project was also suggested by the

    Expert Committee, which has been prepared by HP

    Forest Dept. and is under scrutiny by the Expert

    Committee.

    Apart from the measures listed above, it was also decided in the said meeting to undertake certain long

    term measures that were organization-wide and not limited to the BSL project. These measures included

    the following

    26

  • Environmental Audit Report – BBMB

    • Providing guidelines to Chief Engineers on conducting regular meetings with stakeholders of

    environmental projects and the public for redressal of their problems/grievances and to maintain

    harmony with them

    • Setting up of fully equipped central laboratories at all project stations for conducting silt analysis,

    chemical and bacteriological tests for checking the performance of potable water, treatment plants,

    sewage treatment plants etc.

    • Environmental Upgradation of Power Plants and Project Colonies by having ‘ISO 14000

    Certification’

    3.3 Adoption of Environmental Management System (EMS) along with Quality Management

    System (QMS) : While the implementation of monitoring, mitigative and environmental enhancement

    projects helped BBMB in identification and resolution of specific environmental issues, adoption of an

    Environmental Management System (EMS) as per ISO 14001 standard on an organization-wide basis was

    considered as a useful and effective strategy. This recommendation in fact resulted from the EIA study

    conducted at the BSL project described above. Section 3.3.1 below describes the EMS approach.

    3.3.1 Environmental Management System (EMS): Figure 3.2 shows a typical process followed in

    the EMS starting from formulation of Environmental Policy to Management Review.

    Environmental Policy

    PlanningEnvironmental aspects

    Legal and otherrequirements

    Objectives and targetsEnvironmental management

    programs

    Implementation and Operation

    Structure & ResponsibilityTraining, Awareness &

    CompetenceCommunication

    EMS documentationDocument Control

    Operational ControlEmergency Preparedness

    and response

    Checking and Corrective Action

    Monitoring and measurement

    Non-conformance and corrective and preventive

    actionsRecords

    EMS Audits

    ManagementReview

    ContinualImprovement

    Figure 3.2 Elements of EMS as per ISO 14001

    27

  • Environmental Audit Report – BBMB

    It may be observed that the elements of EMS essentially follow the cycle of Plan-Do-Check and Act

    leading to continual improvement guided by BBMB’s Environmental Policy.

    In the EMS approach the issues identified in Table 3.1 form Environmental Aspects. These aspects get

    analyzed in the context of legal requirements considering normal, ab-normal as well as emergency

    situations. A legal register provides a basis towards checking environmental compliance.

    The Environmental Management Plan (EMP) as well as Emergency Preparedness and Response Plan

    (EPRP) are evolved according to the significance of environmental aspects. Accordingly, the

    responsibilities are allocated across the organization, supported by required training to the concerned staff.

    All procedures to be followed are documented with document upkeep guidelines.

    The EMP and EPRP are implemented as per the set objectives and targets. Accordingly, implementation

    plans are prepared and budgets are allocated for implementation. Monitoring of the EMP and audit of the

    “system” are carried out to check the effectiveness of measures undertaken. If there are any shortfalls or

    non-conformities then corrective actions are undertaken. A management review meeting is held to report

    the findings and take further directions. The objectives and targets are revisited based on the performance,

    new issues if any and emergent organizational needs and aspirations. The entire system of addressing and

    resolving environmental issues is thus systematic and not ad-hoc. The system is measurable and subject to

    internal and external audit process supported by institutional development (training), documentation

    (records) and a Management Review.

    EMS (ISO 14001) at BBMB was considered to lead to following advantages

    • EMS provides a robust and internationally understood framework right from identification of

    environmental issues/aspects, mitigation/enhancement measures, allocation of responsibilities,

    monitoring and control

    • EMS is driven by management policy, management review and management support that provides

    apex level treatment to environmental issues

    • EMS is based on continual improvement is subject to internal and external audit and is

    documented

    • EMS requires that human resources in the entire organization as well as its stakeholders are made

    aware to the general as well as specific environmental issues, objectives and targets that are to be

    met

    28

  • Environmental Audit Report – BBMB

    Clearly, the various environmental mitigation and enhancement measures undertaken by BBMB today (see

    sections 3.2) fall in the systems and programmatic approach of ISO 14001 EMS. This form assures that

    environmental issues are identified and dealt with in a systematic manner on an organization wide basis.

    3.3.2 Integration of EMS with QMS: BBMB considered implementation of EMS ISO 14001 in

    tandem with Quality Management System (QMS) as per ISO 9001. Not many organizations have followed

    such a strategy. Following have been the benefits of the integrated approach.

    • As both EMS and QMS follow the cycle Plan-Do-Check-Act Simultaneous consideration of EMS

    and QMS led to optimization over documentation, work instructions and maintenance of the

    systems

    • Integration of quality and environment allowed mainstreaming of sustainability in BBMB’s

    business operations.

    With such an implementation, BBMB became the first hydropower management company in India that has

    obtained QMS 9001 and EMS ISO 14001 certifications.

    Figure 3.3 describes the evolution of EMS based approach to environmental management at BBMB. It

    may be observed that BBMB has gradually moved from Level I approach to Level III over a period of time

    moving towards a proactive, systemic, organization wide and business integrated environmental

    management system.

    BBMB’s efforts at environmental management have been appreciated by juries at independent

    organizations. The Greentech Foundation, declared BBMB as the winner of the Gold Award in the

    hydropower sector “for outstanding achievement in environmental management” for 2007.6

    6 Greentech Foundation based in New Delhi, India is a non-profit organization established to promote education, training, research and dissemination of knowledge, advancing the scientific, technical and practical aspects of industrial safety, environment management, climate change, pollution control, hazardous/non-hazardous waste management, water treatment, water pollution, noise pollution, eco tourism, and occupational health, fire, safety and security.

    "Greentech Environment Excellence Awards" and "Greentech Safety Awards", coveted awards in the Indian corporate world, are presented every year to various organizations/companies for outstanding achievements in the field of OHSAS industrial fire safety and security, and environmental management. Past winners from the domain of environmental excellence include Hindustan Petroleum Corporation Limited, Aditya Birla Group, Tata Chemicals Limited, etc. Source: http://greentech.org/

    29

    http://greentech.org/

  • Environmental Audit Report – BBMB

    Mitigation Measures

    Environmental Issues

    Environmental Issues

    Mitigation Measures

    Preventive and Enhancement

    Measures

    Environmental Issues

    Environmental Management System as

    per ISO 14001

    Preventive and Enhancement

    Measures

    Mitigation Measures

    Quality Management System as per ISO

    9000

    Training , Awareness and Competence

    Internal and External Audits

    Management Review

    DocumentationMonitoringBudgeting

    Project limited Reactive Approach

    Proactive Comprehensive

    but Project limited Approach

    Proactive System based

    Organization wide Business Integrated

    Approach

    Level ILevel II Level III

    Figure 3.3 Levels of Environmental Management and Evolution at BBMB

    As the EMS at BBMB has become today the principal driver for environmental management, the

    Environmental Audit focused on the structure, implementation and operation of the Environmental

    Management System. Chapter 4 describes the evolution, scope and content of BBMB’s EMS.

    30

  • Environmental Audit Report – BBMB

    CHAPTER 4

    ENVIRONMENTAL MANAGEMENT SYSTEM (EMS) AS PER 14001 AT BBMB

    4.1 Motivation for EMS Approach: From using a management approach geared towards tackling

    grievances and/or complaints in an ad hoc manner, BBMB recognized the need to adopt an anticipatory

    and methodological mechanism in the form of its organization-wide Environmental Management System,

    i.e. EMS as per ISO 14001.

    Further, it is notable that BBMB is the only organization of its kind in India to have obtained not just an

    EMS but also a QMS Certification for both its Power and Irrigation Wings7. In an effort to formalize its

    commitment to the environment and deliverance of quality to its customers, BBMB decided to opt for both

    systems of certification (see Section 4.4 for the Environmental and Quality Policy of the organization).

    4.2 Phased Certification of EMS: The Environmental Management System covers major activities

    of BBMB. The EMS at BBMB was certified in two phases – Phase I and Phase II.The majority of the

    utilities were certified in Phase II. Phased approach for the organization of the size and spread of BBMB

    was appropriate but in addition it provided an avenue of “learning while doing”. It may be observed that

    the CDM project site was implemented in Phase II.

    4.3 EMS Scope and Linkages with QMS : The EMS covers major activities of the BBMB at

    corporate as well as project locations, with the following Chief Engineers nominated as Management

    Representatives by the Chairman, BBMB for the scope of work under their jurisdiction:

    Irrigation Wing Power Wing

    Bhakra Complex: Chief Engineer, Bhakra

    Dam, BBMB, Nangal Township

    Bhakra Complex and Pong Power House:

    Chief Engineer, Generation, BBMB, Nangal

    Township

    Unit I - Beas Sutlej Link Project: Chief

    Engineer, BSL Project, BBMB, Sunder

    Nagar

    Dehar Power House and System Operation

    Activities: Chief Engineer, System Operation,

    BBMB, Chandigarh

    7 The National Hydroelectric Power Corporation Ltd. (NHPC), India is an ISO 14001:2004 certified company in the sector of hydropower development alone.

    31

  • Environmental Audit Report – BBMB

    Irrigation Wing Power Wing

    Unit II - Beas Dam: Chief Engineer, Beas

    Dam, BBMB, Talwara

    Transmission System: Chief Engineer,

    Transmission System, BBMB, Chandigarh

    Certain activities of the EMS and QMS converge, thus requiring common procedures/formats.

    Recognizing this, with some strategic planning and coordination, BBMB has combined the two

    management systems to further the objectives of both QMS and EMS. Thus, BBMB has aligned the

    common management elements in the form of “Common Management System Documents” (see

    Annexure 1). This aspect is important as it fully mainstreams environmental considerations in BBMB’s

    business operations.

    4.4 BBMB Organization Chart8: BBMB is one of the organizations designated as a “Statutory

    Body” under the ambit of the Ministry of Power, Government of India. Any environment-related

    regulations / legislations are conveyed to BBMB by the Ministry of Environment and Forests (MoEF) of

    the Government of India through the Ministry of Power.

    BBMB is headed by a full-time Chairman and two full-time Members i.e. Member (Irrigation) and

    Member (Power), who head the Irrigation and Power Wings of BBMB respectively. The Financial Adviser

    and CAO heads the Finance and Accounts Wing of the Board.

    The Secretary and Special Secretary assist the Chairman and the full-time Members of BBMB in the

    normal working of the Board.

    Other than the two full-time Members, BBMB’s Board also includes six other Members as listed below:

    Member, Govt. of India Jt. Secy (H) Govt. of India,

    Ministry of Power, New Delhi.Member, Govt. of India Commissioner (Indus) Govt. of India.

    Ministry of Water Resources New DelhiMember, Punjab Secretary to Govt. of Punjab,

    Irrigation and Power Department Chandigarh.

    8 Source: (a) BBMB: The Board – Organizational Hierarchy at http://bbmb.gov.in/english/menu1.asp (b) Annual Report of the Ministry of Power (2005-2006) at http://www.mycii.org/library/annual%20reports-government.htm

    32

    http://bbmb.gov.in/english/menu1.asphttp://www.mycii.org/library/annual%20reports-government.htm

  • Environmental Audit Report – BBMB

    Member, Haryana Financial Commissioner and

    Principal Secretary to Govt. of Haryana,

    Department of Irrigation ChandigarhMember, Rajasthan Secretary to Govt. of Rajasthan,

    Department of Irrigation JaipurMember, Himachal Pradesh Principal Secy. to Govt of Himachal Pradesh,

    MPP and Power Department Shimla

    After the Members, Power and Irrigation in the organisational hierarchy of the Power and Irrigation

    Wings, are the Chief Engineers (Power) and Chief Engineers (Irrigation). The Chief Engineers (Power)

    head the offices of System Operation, Transmission Systems and Generation. Similarly, there are three

    posts of Chief Engineer for the Irrigation Wing – one each for the Bhakra Dam, Beas Dam and Beas-Sutlej

    Link.

    The Chief Engineers are followed by Superintending Engineers / Directors, Senior Executive Engineers /

    Deputy Directors and Assistant Engineers.

    Figures 4.1(a) and 4.1(b) illustrate the organizational hierarchy at BBMB. The EMS at BBMB recognizes

    this organizational structure and reflects the same in its procedures and documentation.

    4.5 Environmental Policy of BBMB: The major projects of BBMB are established in natural

    surroundings. BBMB is committed to preserve clean, green and serene environment of the projects and

    their surroundings. The Environmental Policy Statement dated 11 June, 2009 and approved by the

    Chairman; has been an affirmation of BBMB’s commitment to9:

    • Ensure safe and environmentally sound practices for the management of dams, reservoirs, canals,

    water conducting system and related infra-structure, power houses, substations and townships.

    • Generate and promote green and clean hydro-electric power.

    • Efficient waste management.

    • To promote Clean Development Mechanism (CDM) projects in the organisation.

    • Prevent environmental degradation in accordance with prevailing international / national

    standards, practices, technology and laws.

    9 Note: The Environmental Policy Statement has been framed in compliance with requirements of ISO 14001:2004 Clause 4.2

    33

  • Environmental Audit Report – BBMB

    34

    • Setting-up of appropriate environmental objectives, targets and their achievements as per

    Environmental Management Plans (EMP) ensuring their continual improvement.

  • Environmental Audit Report – BBMB

    Figure 4.1 (a): BBMB Board Members

    MEMBER, MINISTRY

    OF WATER RESOURC

    ES GoI

    MEMBER, MoP (JT.

    SEC.), GoI

    MEMBER, IRRIGATIO

    N

    (FULL-TIME)

    MEMBER, POWER

    (FULL-TIME)

    FINANCIAL

    ADVISOR & CAO

    MEMBER, PUNJAB

    (DEPT. OF IRR. /

    POWER)

    MEMBER, RAJASTHAN(DEPT. OF IRR. / POWER)

    MEMBER, HARYANA (DEPT. OF

    IRR. / POWER)

    MEMBER, H.P.

    (DEPT. OF IRR./

    POWER)

    MINISTRY OF ENVIRONMENT AND

    MINISTRY OF POWER

    BBMB BOARD

    CHAIRMAN, BBMB

    SECRETARY AND SPECIAL SECRETARY

    **: Other bodies under the ambit of the MoP include: (a) Damodar Valley Corporation (b) Power Trading Corporation India Ltd., (c) National Power Training Institute, (d) Central Power Research Institute, (e) Bureau of Energy Efficiency and various Central Public Sector Undertakings.

    In case of BBMB, the MoP does not concern itself with matters relating to irrigation.

    35

  • Environmental Audit Report – BBMB

    36

    DY. FA & CAO

    SNR.ACCTS.

    OFFICERS

    BBMB FINANCE AND ACCOUNTS WING

    FINANCIAL

    ADVISOR & CHIEF

    ACCOUNTS

    BBMB IRRIGATION WING

    MEMBER, IRRIGATI

    ON

    (FULL-TIME)

    CHIEF ENGINEER

    , BEAS DAM*

    CHIEF ENGINEER

    ., BEAS-SUTLEJ*

    CHIEF ENGINEER, BHAKRA

    Superintending Engineer / Director

    Senior Executive Engineer/Deputy

    Assistant Engineer

    CHIEF ENGINEER, TRANSM. SYSTEM*

    CHIEF ENGINEER

    , GENERA-

    CHIEF ENGINEER, SYSTEMS

    OPS*

    BBMB POWER WING

    MEMBER, POWER

    (FULL-TIME)

    Engineers/Dy. Directors

    Engineers/Directors, Sr.

    head the respective offices followed by

    *: Chief Engineers

    Superintending

    Engineers. The and Assistant

    Executive

    Superintending Engineer / Director

    Assistant Engineer

    Senior Executive Engineer/Deputy

    Figure 4.1(b): Organizational Hierarchy at BBMB

  • Environmental Audit Report – BBMB

    • Water conservation and rain water harvesting.

    • Eco friendly / Bio-tech projects.

    • Community services in peripheral area of the Project in Environmental Sector.

    The policy statement is thus proactive and guides preventive, mitigative as well as enhancement related

    measures in addressing the various environmental issues.

    4.5.1 Quality Policy of BBMB: The Quality Policy Statement dated 27 May, 2009 and approved by the

    Chairman states:

    BBMB is committed to maintain its position as the leader and a trend setter in power sector for

    establishing high standards in operation & maintenance of hydel projects, transmission system and canal

    systems. BBMB will also continue to renovate, modernize and upgrade its generating units to optimally

    utilize the river waters and to improve reliability and efficiency.

    BBMBshall encourage adoption of energy conservation measures within the organisation besides

    propagating the message to other stakeholders as well.

    BBMB’s “Mission is to keep our systems running efficiently at minimum cost.”

    This shall be achieved by building up and sustaining our acquired values-“discipline,hard work

    ,operational excellence and professionalism.”

    We shall ensure continual improvement in processes, methods,procedures and resources aswell asfull

    compliance to applicable statutory and regulatory requirements.

    4.6 Environmental Objectives at BBMB: The following are the environmental objectives laid down

    as part of the EMS at BBMB:

    • Minimization of environmental degradation in the management of power houses, transmission

    system and related operations, dams, reservoirs, canals, water conducting system, related infra-

    structure, related electro-mechanical/hydro-mechanical equipment ,townships , hospitals, schools

    and related infrastructure.

    • Adoption of latest techniques and good practices to prevent environmental degradation.

    • To ensure appropriate system of waste management and its disposal.

    • Improving the green cover at project/ work sites.

    • Advance planning for tackling of potential environmental disasters.

    • Material substitution and technology absorption for improving the state of environment.

    • To create and improve awareness on environment related issues within and outside the

    organization including suppliers, contractors and local community.

    • To implement and create awareness on clean development mechanism projects in the organisation.

    • To promote the rain water harvesting and water conservation measures.

    37

  • Environmental Audit Report – BBMB

    • To promote use of natural resources.

    • To improve the environment of the local people by community services in environment, health,

    and education fields.

    These objectives have been reflected in the EMS documentation of BBMB. The Environmental

    Management Programmes (EMPs) are formulated at relevant level for fulfilment of these objectives and

    progress monitored periodically.

    4.7 Activity Specific Environmental Goals at BBMB: Activity Specific Environmental Goals are

    defined separately for all major support works / areas of general nature for example Administrative offices

    and educational establishments, Townships/ colonies, Hospitals/ dispensaries, Guest Houses etc. These are

    documented and maintained at the level of relevant works / areas. Listing of these goals is provided below.

    A strategy of setting goals for areas is important as area specific EMPs get evolved and budgeted for

    implementation.

    4.7.1 Environmental Goals - Administrative Offices and Educational Establishments

    • Electricity conservation.

    • Water conservation.

    • Encourage computerization - as a step towards paperless offices.

    • Recycling of paper/ waste stationary.

    • Disposal of solid waste in environmental friendly manner in consonance with the relevant rules

    and acts.

    • Carrying out awareness campaigns about energy and water conservation.

    4.7.2 Environmental Goals – Township /Colonies

    • Providing clean drinking water, sanitation, garbage disposal and other civic amenities by having

    proper storage, collections, treatment, transportation and disposal of solid/liquid waste generated

    in residential/non residential areas.

    • Proper upkeep of common areas, parks etc. by following proper horticulture practices and waste

    material utilization in ‘Theme Parks’.

    • Provide and maintain green cover through plantation of trees and plants in and around the

    surroundings of colonies/township areas.

    • Have a proper, adequately manned complaint centres to promptly attend to the

    complaints/grievances of residents with regard to water, sanitation, garbage related issues and

    continual improvement of the system thereof.

    • Carrying out awareness campaigns about energy and water conservation.

    38

  • Environmental Audit Report – BBMB

    4.7.3 Environmental Goals – Hospital/Dispensaries

    • Creating awareness amongst public / patients about hygiene, cleanliness and disease protection by

    following contemporary environmental friendly practices.

    • Safe collection, treatment, transportation and disposal of solid/liquid and bio-medical waste in

    conformity to the relevant environmental acts and rules.

    • Proper linen management, laboratory sterilization techniques for equipment and material used in

    the day to day hospital functioning.

    4.7.4 Environmental Goals – Guest Houses

    • Providing proper amenities to maintain hygiene, cleanliness in rooms / kitchen and common

    surrounding areas of Guest Houses.

    • Proper housekeeping management and quick civic complaint attendance in day to day running of

    Guest Houses.

    4.8 Environmental Aspects and Methodology of Attaching Significance: The identification of

    environmental aspects and the methodology of attaching significance to them are documented in the

    BBMB EMS Manual through:

    • Procedure for Identification of Environmental Aspects and Evaluation of Their Significance

    (MR/EMS/P/01); see Annexure 3.

    • Guidelines for Evaluation of Environmental Aspects (MR/EMS/G/01); see Annexure 4.

    BBMB has devised the Procedure MR/EMS/P/01 to ensure that:

    • “The environmental aspects of its activities, products and services within the defined scope of the

    environmental management system of BBMB which it can control and those that it can influence

    taking into account planned or new developments, or new or modified activities, products and

    services, with in defined scope of EMS are determined.

    • The environmental aspects are evaluated for their environmental impacts, actual or potential, so

    as to determine significant environmental aspects.

    39

  • Environmental Audit Report – BBMB

    • The information on environmental aspects is maintained and updated regularly taking into

    consideration new development, technologies or renovation and modernization or modifications.

    • Significant environmental aspects are taken into consideration in establishing, implementing and

    maintaining the EMS”10.

    Notably, step 6 of MR/EMS/P/01 states clearly the requirement to define countermeasures to tackle

    significant aspects through technological improvements and monitoring so as to keep such aspects “within

    limits”. The team nominated by the Management Representative (MR) continues to report to him and seek

    his inputs throughout the exercise. The schema for attaching significance is comprehensive.

    4.9 Environmental Management Programmes: Environmental Management Programmes (EMPs)

    are formulated at relevant functions and levels (divisional / directorate / circle / wing levels) for fulfilment

    of the environmental objectives and targets of BBMB’s EMS. EMPs lay down time-bound activities with

    clear responsibility and the means to achieve set objectives. Progress is monitored periodically. In

    specific, EMPs for the CDM project sites were reviewed and were found to be satisfactory.

    4.10 On-site and Off-site Disaster Management Plan: BBMB has established and maintains

    Procedure for Dealing with Environmental Emergencies (MR/ EMS/P/06) and Procedure for On-site

    Emergency Plan Preparation and Implementation (MR/ EMS/P/09) to:

    • Identify potential emergency situations, disasters and potential accidents that can have an impact

    on the environment, and its response mechanism for various types of emergencies such as floods

    and fire.

    • Respond to actual emergency situations and accidents and prevent or mitigate associated

    environmental impacts.

    BBMB periodically reviews and, where necessary, revises its emergency preparedness and response

    procedures, in particular, after the occurrence of accidents or emergency situations. Mock drills are also

    conducted to test the efficacy of emergency procedures.

    10 Source: BBMB EMS Manual ISO 14001:2004. BBMB/EM Issue 2, Released: December, 2005.

    40

  • Environmental Audit Report – BBMB

    4.11 Environmental Monitoring :A system exists for measurements of key characteristics of

    processes which can have significant environmental impact(s). Regular monitoring is carried out to ensure

    degree of control for continued compliance to applicable standards and criteria in accordance with the

    following established procedures:

    • Procedure for Control of Air Pollution (MR/ EMS/P/03)

    • Procedure for Control of Water Pollution (MR/ EMS/P/04)

    • Procedure for Waste Management (MR/ EMS/P/05)

    • Procedure for Environmental Guidelines and Controls During Operation and Maintenance (MR/

    EMS/P/08)

    The Procedures are provide for:

    • Documentation of information to monitor performance.

    • Operational controls, as applicable.

    • Conformity to environmental objectives and targets.

    • Calibration and maintenance of equipment used for measurements and monitoring and retention of

    necessary records.

    Most of the environmental monitoring at BBMB is currently outsourced to the laboratories that are

    recognized by the Pollution Control Boards (PCBs).

    There is a room to improve the environmental data management at BBMB. The data is presently recorded

    on hard copies (registers) in various formats and practice of electronic storage for the purposes of analyses

    and reporting is not followed. BBMB may consider setting up a suitable Environmental Management

    Information System (EMIS) that will help organize and interpret the data more effectively. An integration

    of EMIS with Geographic Information System may also be relevant. Such a system if web based will allow

    BBMB to share the data with stakeholders on 24x7 basis.

    4.12 Environmental Regulatory Compliance: BBMB has a systematic Procedure (MR/ EMS/P/02)

    for periodic evaluation of compliance to applicable environmental legal requirements and other applicable

    environmental requirement. Importantly, this procedure is anticipatory and provides a mechanism for

    combined evaluation of compliance to applicable legal requirements and other environmental

    requirements. This includes:

    • Routine sampling and testing of water, air, soil, noise levels etc. and ensuring conformity to laid

    down standards/ rules and regulations

    41

  • Environmental Audit Report – BBMB

    • Timely renewal of licenses, consents, authorizations, and filing of returns /statements/information

    etc.

    • Progress review for various environmental management programmes/objectives and targets /

    calling of records for review.

    • EMS internal audits.

    • On-site observations by Senior Officers during their inspections / visits to Projects/ Work sites.

    The records of the results of evaluation and compliance with legal requirements and other applicable

    requirements are kept with nominated Nodal Environmental Officers at BBMB.

    Environmental monitoring data generated at the CDM project sites was reviewed. The data showed

    conformity with the applicable standards.

    4.13 Organizational Aspects Including Training and Capacity Development: The overall human

    resource requirements of officers/officials are fulfilled mainly by transferring suitable persons from Partner

    States against their Share Quota. The officers in these States have been recruited / promoted based on the

    set criteria for educational qualification, experience and competence as defined in service rules of

    respective cadres of State Governments for different positions. A cadre of permanent BBMB officials also

    exists. Overall manpower planning shall be done keeping in view of the projected work / competence

    requirements and sanctioned norms.

    The Secretary/BBMB looks after Human Resource planning, deployment, promotions, transfers of officer

    cadre (Group A and B) in accordance with rules laid down by concerned State Governments and as per the

    direction of Chairman, BBMB.

    Special Secretary, BBMB looks after the pertinent issue of Rules and Regulations regarding the service

    conditions of human resources in BBMB. The policy decisions of the Board are dealt with by the Rules

    and Regulation Section. Although the administrative control of Group C and D employees vests with the

    respective HODs i.e. respective Chief Engineers (both Irrigation and Power Wing) in the field, FA and

    CAO for Finance Wing and Secretary for the concerned staff in Board Sectt., the general service

    conditions, pay and allowances, regulations and management of cadre are carried out by the office of

    Special Secretary.

    The induction of staff from the partner States i.e. Partner State Government and State Electricity Boards

    vis-à-vis direct recruitment of BBMB employees as per BBMB Regulations are also entrusted to the office

    of Special Secretary, BBMB. So far as the postings and transfers and other administrative decisions are

    concerned, the respective HODs exercise their power as per laid down statutes and procedures.

    42

  • Environmental Audit Report – BBMB

    Besides, the demands put forth by various recognised unions are processed and settled after due

    negotiations with their authorised representatives, for which the Special Secretary plays a pivotal role. The

    regular holding of general meetings and correspondence etc. are held as per labour laws and executive

    instructions.

    The Special Secretary has also been designated as Director, Grievances for BBMB as a whole. In this

    respect, a quarterly progress report indicating the position of pending grievances in respect of various

    administrations is compiled and sent to the Ministry of Power.

    Another important aspect of overall human resource planning is the maintenance of their competence

    levels. Regular upgradation of knowledge and skills of the employees is ensured through trainings both in-

    house and through external agencies.

    It is planned that continued competence be ensured for the personnel performing quality related functions,

    based on appropriate education, training, skills and experience as per the HRD policy.

    Training activities at BBMB are planned both at the level of Director/HRD, BBMB and at Chief Engineer

    levels. A procedure for manpower training is documented. A Training Institute has been established at

    Nangal for providing training to in-house and external agencies on various specialized areas related to

    Power and Irrigation sectors. This institute was visited during Environmental Audit.

    More information about environmental training modules conducted at BBMB is provided in section 4.13.2

    with observations.

    4.13.1 EMS Procedure for Training and Capacity Development: The EMS at BBMB aims to ensure

    that:

    • Necessary competence for personnel performing work relating to significant environmental

    impacts is determined and provided.

    • Wherever gaps are noticed, the same shall be made up through appropriate training or other

    alternative actions such as job rotation etc.

    • Effectiveness of the actions taken shall be evaluated.

    • Personnel are made aware of the relevance, importance and significant environmental aspects of

    their activities and their contribution in the achievement of environmental objectives.

    • Record of education, training, skills and experience shall be maintained.

    The Procedure for Training (MR/TRG/P/06) ensures that BBMB employees as well as contractors

    personnel are made aware of:

    43

  • Environmental Audit Report – BBMB

    • Importance of the conformity with environmental policy and procedures and with the

    requirements of EMS.

    • Significant environmental impacts, actual or potential, of their work and environmental benefits of

    improved personnel performance.

    • Roles and responsibilities in achieving conformity with environmental policy, procedures and

    EMS including emergency preparedness and response requirements.

    • Potential consequences of departure from specified operating procedures for control of various

    environmental impacts.

    Annexure 5 lists the Procedure for Training (MR/TRG/P/06) followed by BBMB as part of the EMS.

    4.13.2 Environment-themed Training Sessions at BBMB: Environment-themed training sessions /

    seminars which have taken place at BBMB from 2003 - 2009 include:

    • Seminar on Environmental Management System

    • Training on handling of solid waste and drinking water issues.

    • Seminar on polythene bags and their environmental effects.

    • Seminar on T-(B) operation and maintenance of DG set and LT system.

    • Seminar on T-A(1) maintenance of static excitation equipment of Dehar units and environmental

    aspects.

    • Seminar on T-(1) maintenance of unit transformers and environmental aspects.

    • Seminar on Quality and environmental management of Slapper Division, and operation and

    maintenance of BCW silt ejector and gates.

    • Seminar on divisional profile and works and quality of environmental management of Slapper

    Division.

    • All India Seminar on environmental considerations in planning and design of power projects.

    • Short-term course on Environmental Management for River Valley Projects.

    • Training programme on Environmental Law - policy and practice.

    • Training on Environmental System (ISO-14001).

    • Training on Environmental Aspects.

    • Environment Protection Act 1986 and Motor Vehicle Act 1986.

    • Interactive session for engineers/workers, environmental aspects-issues and challenges and fire

    safety at working places.

    • Programme on Environmental Protection Act 1986 and Motor Vehicle Act 1986, Hazardous

    Waste Management and Handling Rules 1989, and Batteries Management and Handling Rules

    2001.

    44

  • Environmental Audit Report – BBMB

    • Training programme on effective assessment, management and monitoring of environmental

    safeguards in river valley and hydel projects.

    • Seminar on quality and environmental management of township divisions.

    • Seminar on operation and maintenance of hydel channels: quality and environmental management.

    • Interactive programme regarding general awareness of environmental pollution and child welfare.

    • Seminar on quality and environmental management of BRSC and PD Divisions.

    • Seminar on quality and environmental management of Electrical and Workshop Divisions

    • Seminar on quality and environmental management of dredging operations and disposal of silt.

    • Interaction sessions for awareness training programme for EMS/QMS

    • Lead assessors training programmes

    Since 2006, training specific to EMS/QMS has been imparted to 210 persons (as on 11th March

    2010)

    While the topics above are comprehensive, it may be useful if BBMB considers training sessions

    specifically on

    • Environmental Data Management

    • Geographical Information Systems

    • Integrated Management Systems (especially QMS and EMS integration)

    • Corporate Social Responsibility

    • Clean Development Mechanism (under this theme series of programmes may be considered such

    as how to prepare a Project Idea Note, Project Design Document etc)

    4.14 Internal and External Audits: BBMB has implemented a common system of internal audit for

    EMS and QMS through a well documented procedure for Internal Audit of QMS and EMS (MR/

    AUD/P/07). Audits are carried out at planned intervals. The interval period depends up on many factors

    such as significant environmental impacts, results of previous audit, impending visits of statutory

    authorities, changes affecting operations such as monsoon conditions etc.

    Audits are conducted with objective of:

    • Determination of conformity with environmental criteria and status of maintenance and

    implementation of EMS.

    • Reporting performance of EMS to management.

    • Identification of improvement opportunities.

    Annual Audit Plans are prepared by concerned MRs as well as the Central Management Representative

    (CMR). Frequency of audit shall at the minimum be six monthly at both CE level and at Head Office level.

    However, this frequency can be modified depending upon factors such as:

    45

  • Environmental Audit Report – BBMB

    • Audit results.

    • Changes in environmental impacts.

    • Non – compliance to legal or other applicable environmental requirement

    • Changes in process parameters, machinery, technology.

    • Occurrence of emergency / near emergency situations.

    • Results of air/ water / soil testing as applicable.

    • Operational controls and results of monitoring.

    • Accidents / incidents.

    • Public complaints.

    The Procedure for Internal Audit of QMS and EMS (MR/ AUD/P/07) addresses the responsibilities and

    requirements for :

    • Planning the audits.

    • Conducting the audit.

    • Reporting the audit results.

    • Follow-up actions as a result of audit (mitigation, rectification, corrective or preventive).

    • Closing of audit non-conformities.