bfv std.specdamper
TRANSCRIPT
-
7/30/2019 BFV Std.specdamper
1/39
T2.00 INTENT OF SPECIFICATION
This sub-chapter is intended to cover design,
materials
procurement,manufacture/fabrication,shop testing
and
supply of various types of valves the C.W.system
of
2 nos 210 MW units.
Scope of Work:
The contractor's scope of work shall include
Design,
engineering, Manufacture, Shop testing,
painting,
Packing, loading at works, Transportation to
site,
Unloading, Handling at site, Storage,
comprehensive
insurance, Preservation, Erection,Testing
commissioning of the required number of valves
as
listed below along with a pair of counter flanges
with
necessary nuts, bolts, washers and gaskets for each
of
the valves.
Scope of Supply
i) The scope of supply of the contractor
covered
under this specifications shall include the
valves
as specified in the following paragraphs; and
ii) Mandatory spare parts and special
maintenance
tools and tackles.
T2.01 Equipment Specifications
T2.01.01 The valves shall be designed, manufactured and
tested
as per relevant Indian Standards or as per
otherInternational standards acceptable to the Purchaser
and
will be suitable for the duty conditions
specified
below.
T2.01.02 Motor operated Butterfly Valves
i) No.of valves - 6 Nos.
-
7/30/2019 BFV Std.specdamper
2/39
ii) Nominal diameter - 1600 mm.
iii) Type of valve - Flanged Butterfly
valve
as per BS -
5155/AWWA
C - 504 with
electric
actuator.
iv) Location - Indoor in pump house.
T2.01.03 Motor operated butterfly valve
i) No.of valves - 2 Nos.
ii) Location - Makeup water pipe
to
forebay.
iii) Nominal diameter - 600 mm.
iv) Type of valve - Flanged Butterfly
valve
as Per BS -
5155/AWWA
C-504 with
electric
actuator for make-
up
water.
v) Location - Outdoor
T2.01.04 Gear operated butterfly valves
A. i) No.of valves - 8 Nos.
ii) Location - 4 nos. on tappings
forheat exchangers & 4
nos.
on makeup water
pipeline
as shown in the drawing.
iii) Nominal diameter - 600 mm
-
7/30/2019 BFV Std.specdamper
3/39
iv) Type6 of valve - Gear operated
Flanged
Butterfly valve as
Per
BS- 5155/AWWA.
B. i) No.of valves - 4 Nos.
ii) Location - Cooling Tower Hot
water
inlet (2 Nos. per
tower)
iii) Nominal diameter - 1600 mm
iv) Type of valve - Gear operated
Flanged
Butterfly valve as Per
BS
- 5155/AWWA.
T2.01.05 Manually operated butterfly valves
i) No.of valves - 2 Nos.
ii) Nominal diameter - 300 mm.
iii) Type of valve - Manually
operated
Flanged Butterfly
valve
as Per BS- 5155/AWWA
for
blow-down water.
T2.01.06 Miscellaneous valves
Gate/sluice valves shall conform to IS:780-1984
and
IS:2906-1984(R.A.1990)Class PN 1.0 as applicable.
Globe valves shall conform to IS:778-1984, Class
I.
Non-return valves shall conform to IS:5312-1986,Part
I.
Butterfly valves shall conform to AWWA C-504/BS 5155.
Flange drilling of all valves shall be as per table
11
-
7/30/2019 BFV Std.specdamper
4/39
of IS:6392-1971.
T2.01.07 All the Butterfly valves shall be of 6 Kg/cm2
rating
and conform to B.S -5155-1984 or ANSI/AWWA-C-504-
1987.
The valves shall be double flanged type and shall
be
supplied with matching flanges ,bolts,nuts
and
gaskets.
Drilling of flanges shall be as per table-11
of
IS-6392- 1971. The analysis of liquid to be handled
is
given in Annexures-D & E.
T2.01.08 All electric actuator driven valves shall be :
a) Complete with electric motor ,necessarygear
drive, position limit switches ,torque
switches
and terminal board.
b) Complete with Micro switch for disconnecting
power
supply when the valve is operated manually.
c) All limit and torque switches shall be dust
and
water proof.
d) The climate prevailing at site is tropical
and
humid with maximum temparature of 50 Deg.C
and
100% humidity but both not occuring
simulta-
neously. The equipment shall be designed to
suit
this condition.
T2.01.09 Direction of flow shall be clearly indicated on
the
valve by embossing an arrow on the valve body.
T2.01.10 All the valves shall have a permanent stainless
steel
-
7/30/2019 BFV Std.specdamper
5/39
name plate and stainless steel tag fixed on the
valve
body indicating the tag number,diameter,pressure
rating
and manufacturing standard code of the valve.
T2.01.11 The valves shall be designed for 100% water tight
shut
off.
T2.01.12 All the valves shall be provided with hand
wheel/
lever. The face of the wheel/lever shall be
clearly
marked with the words OPEN and CLOSE and an arrow
to
indicate the direction for opening/closing.
T2.01.13 All the valves shall be supplied with companion
flanges
made of Carbon Steel plates conforming to IS:2062-1992
Gr.2A and drilled to I.S.6392-1971 Table-11.
Materials of construction:
1. Body : C.I. IS-210 Grade FG260
2. Disc : C.I. IS-210 Grade FG260
3. Seat : Nitrite rubber/S.S (304)
4. Shaft : S.S. (304)
5. Seat retaining : S.S. (304)
rings/and screws
6. Shaft bearing : Self lubricated
T2.01.14 TECHNICAL SPECIFICATION FOR MOTOR ACTUATORS FOR VALVES
AC Motors
- Motor shall be totally enclosed, fan
cooled,
squirrel cage type.
- Degree of protection for motors, bearings
and
terminal boxes shall be IP-55.
- Shaft extension as per requirement.
- Bearing suitable for running of motors in
either
direction.
Terminal box
- Terminal box of all motors shall be
liberally
-
7/30/2019 BFV Std.specdamper
6/39
sized to accomodate termination of
Aluminium
Conductor PVC armoured cables as per
enclosed
table.
- Terminal box shall be provided normally on
the
right side when viewed from the driving end or
on
the top.
Cooling
- Motors shall be TEFC design
- Ventilation system shall be effective
irrespective
of direction of rotation.
Quality of operation
- Rotor shall be dynamically balanced.
- Vibration and noise level shall be as
per
IS-12O75- 1991 & IS-12O65-1987 respectively.
Electrical Design
- Motors shall be suitable for DOL starting
- Shall be suitable for 415V + 6% , 50HZ + 3%
- Motors shall have class B insulation
with
temperature rise limited to 65 deg.C over
an
ambient of 55 deg.C.
- All motors shall be provided with 2 nos.earthing
bolts.
- All motors shall be designed conforming to IS-
325-
1978.
Limit switches
-
7/30/2019 BFV Std.specdamper
7/39
- All limit switches shall be of
robust
construction, capable of withstanding
repetitive
operations.
- Shall be lever or rotating cam type
depending
upon requirement.
- Shall be provided with 10 A, 2 NO + 2 NC
contacts.
- Shall be housed in robust metalic, dust
and
weather proof, enclosure conforming to IP-
65
enclosure, suitable for outdoor installation.
- Earthing studs (2 nos) shall be provided
- Shall be provided with suitable cable gland
plates
with knockout holes of required size
T2.02 INSPECTION, TESTING & SHOP PAINTING
T2.02.01 Inspection & Testing
The tests to be conducted at shop for various
sub-
assemblies/assemblies of equipment shall include,
but
not limited to the following:
- Material test
- Testing during manufacture/fabrication
- Dimensional checking
- Hydrostatic testing of body and seat.
- Demonstration of guaranteed opening &
closing
time.
Any other test, as required to prove the
functional
requirement of various parts of equipment/system.
-
7/30/2019 BFV Std.specdamper
8/39
T2.02.02 The final tests shall be conducted in the presence
of
the Purchaser's representative. Test certificates
for
different tests shall be made available to
the
Purchaser. Material test certificates for bought
out
items shall be obtained from original
manufac-
turer/reputed test house. For all bought out
items,
test certificates as relevant to the items shall
be
furnished by the contractor.
T2.02.03 All the equipments shall be subject to stage
inspection
by the contractor's own inspecting
authority.
However, Purchaser's Inspector may visit theworks
from time to time who should have free access to
all
the places of the manufacturing premises where
any
part/parts are under manufacture.
T2.03 Shop Painting
a) Surface preparation shall be as per St-2 and/
or
St-3 of Swedish standard SIS 055900 or
GERMAN
STANDARD DIN 55928 Part 4
b After surface preparation, two coats of
single
pack air drying phenolic modified
alkydcomposition primer with Zn phosphate as
per
IS:2074-1992 shall be applied. Dry Film
Thickness
of each coat should be 40 microns(minimum).
c) Two coats of single pack air drying high
gloss
-
7/30/2019 BFV Std.specdamper
9/39
phenolic alkyd modified synthetic enamel
paint,
suitably pigmented shall be given as
Final
paint.Dry film thickness of each coat shall
be
25 microns.
T2.04 Performance Guarantee and Warranty
- The valves supplied shall be guaranteed
for
satisfactory performance as per
General
Conditions Of Contract.
LIST OF MANDATORY SPARES FOR VALVES
The following mandatory spares shall be included in
the
contract for Butterfly valves of each size.I) For DN 1600 motor operated butterfly valves.
1. Valve disc. - 1 Set
2. Shaft - 1 set
3. Shaft key - 1 set
4. Bearings - 1 set
5. Allen screw - 1 set
6. 'O' rings - 1 set
7. Gland packing - 2 sets
8. Seal clamping units and bolts - 1 set
9. Position indicator - 1 set
10. Actuators (as applicable) - 1 set
11. Torque/limit switches - 1 set
12. Handle - 1 set
II) For DN 1600 gear operated butterfly valves.
1. Valve disc. - 1 Set
2. Shaft - 1 set
3. Shaft key - 1 set
4. Bearings - 1 set
5. Allen screw - 1 set
6. 'O' rings - 1 set
7. Gland packing - 2 sets
8. Seal clamping units and bolts - 1 set
9. Position indicator - 1 set
10. Actuators (as applicable) - NA11. Torque/limit switches - NA
12. Handle - 1 set
-
7/30/2019 BFV Std.specdamper
10/39
iii) For DN 600 motor / gear operated butterfly
valves.
1. Valve disc. - 2 Set
2. Shaft - 2 set
3. Shaft key - 2 set
4. Bearings - 2 set
5. Allen screw - 2 set
6. 'O' rings - 2 set
7. Gland packing - 4 sets
8. Seal clamping units and bolts - 2 set
9. Position indicator - 2 set
10. Actuators (as applicable) - 2 set
11. Torque/limit switches - 2 set
12. Handle - 2 set
Iv) For DN 300 manually operated butterfly valves.
1. Valve disc. - 1 Set
2. Shaft - 1 set
3. Shaft key - 1 set4. Bearings - 1 set
5. Allen screw - 1 set
6. 'O' rings - 1 set
7. Gland packing - 2 sets
8. Seal clamping units and bolts - 1 set
9. Position indicator - 1 set
10. Actuators (as applicable) - NA
11. Torque/limit switches - NA
12. Handle - 1 set
Notes:
1. One set shall be applicable for one valve of
each
size.
DATA SHEET FOR VALVES
I) MOTOR OPERATED BUTTERFLY VALVE AT PUMP DISCHARGE
1) Name of manufacturer : Fouress
2) Nominal diameter of valve
in mm. : 1600
3) Test Pressure -
a) Body -Kg/Cm2 : 9
b) Seat -Kg/Cm2 : 6
-
7/30/2019 BFV Std.specdamper
11/39
4) Quantity - Nos. : 6
5) Manufacturing Standard : BS 5155
6) Drilling Standard for flanges : As per BS 4504 PN-10
7) Length over flanges - mm : 440
8) Thickness of valve disc - mm : 190
9) Details of motor actuator.
a) Make : Auma
b) Model : SA30E90
c) Type of motor : 3 Phase AC motor, sq.
cage
d) K.W. : 2.5
e) motor speed : 2800
f) Output RPM : 90
g) Class of Insulation/
degree of protection : CL B / IP68
h) Voltage : 415 V
i) Frequency : 50 Hz
j) Duty : S2-15
10) Valve opening/ closing time
in seconds : 75 + 5
11) Materials of construction
a) Body : IS 210 Gr. FG 260
b) Disc : IS 210 Gr. FG 260
c) Drive Shaft : AISI 431
d) Stub Shaft : AISI 431
e) Seat Ring : Stainless Steel
f) Clamping Ring : S.G.Iron
-
7/30/2019 BFV Std.specdamper
12/39
g) Bearing : Teflon
h) End Cover Plate : IS 210 Gr.FG 260
i) Shaft Pin : AISI 431
j) Seal : Nitrile rubber
k) Gears : S.G.Iron
l) Hand Wheel : Fabricated steel
m) Eye Bolt : Steel
n) Integral Flanges : IS 210 Gr. FG 260
o) Matching Flanges : Carbonsteel.IS2062,Gr-2A
p) Bolts : Iinternal SS304/External
HTS/CS
q) Nuts : HTS/CS
r) Gaskets : Nitrile Rubber
12) Weight of Valve Assembly Kg. : 5650 (approx)
II. MOTOR OPERATED BUTTERFLY VALVE ON MAKE-UP WATER PIPELINE
1) Name of manufacturer : Fouress
2) Nominal diameter of valve
in mm. : 600
3) Test Pressure -
a) Body -Kg/Cm2 : 9
b) Seat -Kg/Cm2 : 6
4) Quantity - Nos. : 2
5) Manufacturing Standard : BS 5155
6) Drilling Standard for flanges : IS 6392-1971 Table-11 /
7) Length over flanges - mm : 267
8) Thickness of valve disc - mm : 80
9) Details of motor actuator.
-
7/30/2019 BFV Std.specdamper
13/39
a) Make : Auma
b) Model : SA12E63
c) Type of motor : 3 Phase AC motor, sq.
cage
d) K.W. : 1.1
e) Motor speed : 2800
f) Output RPM : 63
g) Class of Insulation/
degree of protection : CL B / IP68
h) Voltage : 415 V
i) Frequency : 50 Hz
j) Duty : S2-15
10) Valve opening/ closing time
in seconds : 42 + 5
11) Materials of construction
a) Body : IS 210 Gr. FG 260
b) Disc : IS 210 Gr. FG 260
c) Drive Shaft : AISI 431
d) Stub Shaft : AISI 431
e) Seat Ring : Stainless Steel
f) Clamping Ring : S.G.Iron
g) Bearing : Teflon
h) End Cover Plate : IS 210 Gr.FG 260
i) Shaft Pin : AISI 431
j) Seal : Nitrile rubber
k) Gears : S.G.Iron
l) Hand Wheel : Fabricated steel
-
7/30/2019 BFV Std.specdamper
14/39
m) Eye Bolt : Steel
n) Integral Flanges : IS 210 Gr. FG 260
o) Matching Flanges : Carbonsteel.IS2062,Gr-
2A
p) Bolts : Iinternal
SS304/External
HTS/CS
q) Nuts : HTS/CS
r) Gaskets : Nitrile Rubber
12) Weight of Valve Assembly Kg. : 600 (approx)
III) GEAR OPERATED BUTTERFLY VALVE
1) Name of manufacturer : Fouress
2) Nominal diameter of valve
in mm. : 600 1600
3) Test Pressure -
a) Body -Kg/Cm2 : 9
b) Seat -Kg/Cm2 : 6
4) Quantity -Nos. : 8 4
5) Manufacturing Standard : BS5155
6) Drilling Standard for flanges: IS 6392-1971 Table-11/
BS4504 PN10
7) Length over flanges -mm : 267 440
8) Details of gears :
9) Materials of construction
a) Body : IS 210 Gr. FG 260
b) Disc : IS 210 Gr. FG 260
c) Drive Shaft : AISI 431
d) Stub Shaft : AISI 431
e) Seat Ring : Stainless Steel
-
7/30/2019 BFV Std.specdamper
15/39
f) Clamping Ring : S.G.Iron
g) Bearing : Teflon
h) End Cover Plate : IS 210 Gr. FG260
i) Shaft Pin : AISI 431
j) Seal : Nitrile rubber
k) Gears : SG iron
l) Hand Wheel : Fabricated steel
m) Eye Bolt : Steel
n) Integral Flanges : IS 210 Gr. FG 260
o) Matching Flanges : Carbonsteel.IS2062,Gr-
2A
p) Bolts : Iinternal
SS304/External
HTS/CS
q) Nuts : HTS/CS
r) Gaskets : Nitrile Rubber
10) Weight of Valve Assembly : 530 kg 5650 Kg
(appx)
IV) MANUALLY OPERATED BUTTERFLY VALVES
1) Name of manufacturer : Fouress
2) Nominal diameter of valve
in mm. : 300
3) Test Pressure -
a) Body -Kg/Cm2 : 9b) Seat -Kg/Cm2 : 6
4) Quantity -Nos : 2
5) Manufacturing Standard : IS 5155
6) Drilling Standard for flanges: IS 6392-1971 Table-11
7) Length over flanges - mm : 114
-
7/30/2019 BFV Std.specdamper
16/39
8) Materials of construction :
a) Body : IS 210 Gr. FG 260
b) Disc : IS 210 Gr. FG 260
c) Drive Shaft : AISI 431
d) Stub Shaft : AISI 431
e) Seat Ring : Stainless Steel
f) Clamping Ring : SG Iron
g) Bearing : Teflon
h) End Cover Plate : IS210 Gr.FG 260
i) Shaft Pin : AISI 431
j) Seal : Nitrile rubber
k) Hand Wheel : Fabricated steel
l) Eye Bolt : Steel
m) Integral Flanges : IS 210 Gr. FG 260
n) Matching Flanges : Carbonsteel.IS2062,Gr-
2A
o) Bolts : Iinternal
SS304/External
HTS/CS
p) Nuts : HTS/CS
q) Gaskets : Nitrile Rubber
9) Weight of Valve : 120 kg(approx)
10) Any other information
GUARNTEED DATA FOR B.F.VALVES
-
7/30/2019 BFV Std.specdamper
17/39
The contractor guarantees that each Butterfly valve
for
cooling water system shall meet the following
performance
requirement :
1.00.00 Design working pressure of
Butterfly Valve (Kg/cm2(g)) : 6
2.00.00 When valve fully closed : 6
2.01.00 Rate of leakage : Nil
2.02.00 Maximum shut-off pressure,
(Kg/cm2(g)) : 6
3.00.00 Valve operating time in secs. : For 1600mm dia
from open to close and vice- : 75 +15 sec.
versa (only for electrically : For 600mm diaoperated valves) : 42 +5 sec.
4.00.00 Guarantee Characteristic curves: Not Applicable
for regulating valves submitted
Note : This Guaranteed Performance Data is applicable
for each size of the valve.
SIGNATURE OF THE
contractor ............
NAME ...................................
DESIGNATION ............................
NAME AND ADDRESS OF COMPANY
......................................
..
DATE ...................................
COMPANY SEAL:
T3.00 INTENT OF SPECIFICATION
- This sub-chapter is intended to cover
design,
materials procurement,
manufacture/fabrication,
-
7/30/2019 BFV Std.specdamper
18/39
testing and supply of various types of
fabricated
and boughtout pipes,fittings,expansion
joints,
gates, screens and other miscellanious
items
connected with the circulating water system
of
2 x 210 MW units.
C.W.PIPING
Scope of Work
The contractor's scope of work shall include
design,
engineering, supply of steel plates,
accessories,
loading, unloading at site, comprehensive
insurance,
fabrication of required circulating water pipingat
site, outside surface coating and wrapping of
pipes,
inside painting for pipes above 1600mm dia.,
painting,
handling of fabricated pipes at site, erection,
testing
and commissioning of circulating water piping
system.
The scope of work also includes Civil works
like
excavation, and back filling, construction of anchor
/
thrust blocks chamber of man holes / air valves
and
other miscellaneous civil works that would be
required
for installation of piping.
Scope of Services
All piping systems as shown in enclosed
drawings
No.MEC/S/P123/A04/S4/01 and 02 complete with all
final
joint welding at Battery limits viz., piping from
inletand outlet of condensers, cooling water pipe for
heat
exchangers (inlet and outlet), connection of C.W
piping
at cooling tower inlet, make up water pipes
and
blowdown pipes.
-
7/30/2019 BFV Std.specdamper
19/39
All bends , reducers, tees distance pieces, dished
ends
etc. of all sizes and shape required for complete
the
system.
All piping and fittings for vents, drains,
instruments
tapping points with stubs and root valves and
stubs
for the thermowell connections etc.
All counter flanges, blank flanges, caps etc.
necessary
for the piping. All necessary bolts, nuts, and
gaskets
required for installation of the system.
All flanges, manhole and manhole covers, flanged
tees
with blank flanges, automatic air-vent
valves
required on above piping are included in
the
contractor's scope of supply.A minimum number of 6
nos.
automatic air release cum vacuum break valves
(Double
air vent) for each unit (total 12 nos.) shall
be
provided on CW piping.The air release valves shall
be
of 200 mm dia with separate 200mm dia isolation
gate
valves.
Manhole shall be provided on either side of
the
Butterfly valves for maintenance purpose (except
for
300mm dia.).
- The pipework covered under this section shall
also
include internal pipework for the pumphouse
and
piping between pump house and main plant and
other
units as indicated in the drawings enclosed
with
-
7/30/2019 BFV Std.specdamper
20/39
the specification and described in
various
paragraphs of the specification. G.I. pipe
work
for drinking water, service air and instrument
air
piping etc., pipe work for service water air
is
also included in the scope of the contractor.
- The term 'pipework' referred herein
generally
covers pipes, fittings (such as bends,
tees,
reducers, plugs, nipples, sockets,
unions,
flanges, crosses, etc) valves, throttling
pieces,
stubs for primary sensing instruments etc.
T3.01 The pipes shall be manufactured/supplied asspecified
below:
i) Upto 150 mm nominal size - M.S ERW Black
pipes
conforming to
IS-
1239-1984
Part-I
(Medium Duty)
With
Plain ends.
ii) 200 mm to 350 mm size - M.S. ERW
Pipes
conforming to
IS-
3589-1973 but
thick-
ness as
specified
below :
Nominal Dia O.D X Thickness in mm
DN 200 mm : 219.1 x 6.35
DN 250 mm : 273.0 x 7.14DN 300 mm : 323.9 x 7.14
DN 350 mm : 355.6 x 7.14
-
7/30/2019 BFV Std.specdamper
21/39
iii) 400 mm to 600 mm size - Spirally Welded
M.S.
Pipes( Manufactured
at Rourkela
Steel
Plant) of
commercial
quality.
Nominal Dia O.D X Thickness in mm
DN 400 mm : 406.4 x 7.14
DN 450 mm : 457.0 x 7.14
DN 500 mm : 508.0 x 7.90
DN 600 mm : 610 x 9.50
iv) 1600 mm and above - Fabricated from
M.S.
plates as
specifiedin para T3.02
a) For Service Air : IS:1239 - 1984 (Part-I)
Heavy duty/IS:1978 -
1984
St.25 seamless
b) For Instrument Air : IS:1239 - 1984 (Part-I)
Heavy duty/IS:1978 -
1984
St.25 seamless (Hot dip
galvanised)
c) Drinking water : IS:1239 - 1984 (Part-I)
Heavy G.I.
d) Service water : IS:1239 - 1984 (Part-I)
Heavy / IS:3589.
T3.02 Fabricated Steel Pipe lines
T3.02.01 All fabricated pipelines specified below shall
be
fabricated from tested quality M.S. plates
conforming
to IS-2O62-1992 Grade -A by submerged arc
weldingprocess as per IS-10234 or equivalent having
thickness
indicated against the pipe dia:
-------------------------------------------------------
Nominal dia Outside dia Plate thickness
of pipe mm of pipe mm mm
-
7/30/2019 BFV Std.specdamper
22/39
-------------------------------------------------------
16OO mm 1632 16
24OO mm 2432 16
-------------------------------------------------------
T3.02.02 All fabricated pipes shall be manufactured by
cold
bending using a plate bending machine. The
plates
shall be gradually bent to true cylindrical shape
sothat no undue stress develops in the
plate.The
tolerances on dimensions of pipe fabricated from
plate
shall be as follows:
i) On outer diameter
as calculated from
circumference : + 1/4 of plate
thickness.
ii) Out of roundness : + 3 mm & -1.5 mm
iii) Out of straightness : 1 mm per metre length
(Max.)
T3.02.03 The pipe circumferential weld shall be done in such
a
way that the longitudinal welds become staggered in
any
two consecutive sections.
T3.02.04 Pipe sections in straight lengths delivered at
erection
site shall be of suitable length to minimise
field
joints as far as possible. End preparation shallbe
done at the fabrication yard to facilitate
site
welding.Straps shall be provided at field joints.
T3.02.05 The contractor shall submit detailed working
drawings
of pipelines and fittings including
fabrication
-
7/30/2019 BFV Std.specdamper
23/39
drawings for approval by Purchaser/ Consultants.
These
drawings shall indicate design parameters,
complete
bill of materials, welding and all other
fabrication
details. Details of hydrostatic and ND tests
proposed
to be done shall also be specified.
T3.03 Pipe fittings
Fittings shall be supplied as per IS:1239-1992 Part
II
for pipes upto 150 mm dia and shall be fabricated
from
pipes for dia 200 mm and above.
All root joint welding from headers for service
air,
instrument air, service water and drinking wateretc.,
shall be carried out by the contractor.
Gate valves, Drain valves, Root valves, Blind
flanges,
pipe flanges, Gaskets, Bolts, nuts and washers
etc
shall be supplied in quantities and sizes as
required
during detailed engineering with price included in
the
lumpsum quoted.
T3.04 Fabrication of pipelines and welding of pipe joints
T3.04.01 The contractor shall arrange at his cost all
tools,
plant, welding transformers, instruments
and
consumables including any acytelene and oxygen
gascylinders, welding electrodes for electric arc
welding
and filler rods, fluxes etc. for gas welding
for
carrying out the welding at site. Submerged orc
welding
as per IS 10234-1982 shall be carried out as
per
relevant International code.
-
7/30/2019 BFV Std.specdamper
24/39
The contractor shall indicate the procedure he is
going
to follow for fabrication/erection/hydraulic testing
of
M.S.Pipes.
T3.04.02 The contractor shall arrange at his own cost for
all
tests outlined in this section.
T3.04.03 Requirement of welded joints
The contractor shall ensure the following
requirements
while welding the plates/ pipejoints etc.
i) Strength-equality with parent metal
ii) Absence of defects
iii) Corrosion resistance of the weld shall not be
less
than that of the parent metal in
agressive
environment.
T3.04.04 Method of Quality Control in Welded Joints
Following steps shall be taken by the
contractor,
besides controlling quality in general, to
make
effective control in carrying out welded joints.
a) Welding procedures shall be prepared in line
with
IS:7307(Part-I)-1974, reaffirmed in 1991 and
tests
shall be carried out to quality procedures.
Number
of procedures will depend on variables
like
positions of welding, thickness range etc. Once
a
welding procedure is qualified, strict
adherence
to it shall be made during actual welding.
b) Welders employed shall be qualified as per
IS:7310
(Part-I)-1974, reaffirmed in 1987 after
passing
necessary tests.
-
7/30/2019 BFV Std.specdamper
25/39
c) Welding consumables shall be of approved
type.
Such consumables are, however, subject
to
qualifying initial check tests as per IS:814-
1991.
d) The contractor shall strictly follow
approved
welding procedures during actual welding.
Besides,
the following stages of inspection shall also
be
carried out :
i) Weld edge preparation before welding,proper
fit up, position of welding, cleaning of
slag
between the passes, proper weld profile
etc.,
shall be checked visually, amongst others.
ii) Non-destructive tests of weld of
welded
joints shall be carried out as per
approved
procedures/ drawings.
T3.04.05 Preparation of joints
The contractor shall prepare the edge correctly to
the
shape, size and dimensions of the vee-grooves as
per
ANSI B-16.25 unless otherwise specified
in
drawings/documents.
The welding surfaces shall be smooth, uniform and
free
from fins, teers, notches or any other defect which
mayadversely afect welding and shall be free from
loose
scale, slag, rust, grease, paint, moisture or any
other
foreign material. The clean surface shall extend
to
about 10 mm beyond the welding faces to
avoid
-
7/30/2019 BFV Std.specdamper
26/39
contamination of the weld metal with foreign
material
and to avoid unsound weld deposit.
T3.04.06 Assembly, Alignment & Welding
The sequence of welding shall be so planned
and
followed that there shall be a balance of welding
about
the neutral axis of the fabrication. The
contractor
shall employ sufficient number of welders working
at
the same time in diagonal quadrants of the shell
using
back-step method of welding. The rate of progress
of
each welder shall be more or less equal and
quality
uniform.
The general direction of welding shall be towards
the
free end of the joint, but in a long joint as in
shell
fabrication, back-step technique shall be used
to
reduce distortion.
To minimise internal locked up stresses due to
welding,
the vertical joints for the shell shall be welded
and
completed to a circular course and then the
horizontal
circumferential seam welded. However, before
the
welding of horizontal seam started, the
complete
circular course shall be aligned and adjusted for
theircorrect axes.
Alternatively, the contractor shall complete
each
course in all respects on ground and then the
pre-
assembled course shall be lifted and placed
in
-
7/30/2019 BFV Std.specdamper
27/39
position. In such a sequence and planning, the
same
principle of balancing of weld about the neutral
axis
shall be followed and the method of fabrication of
each
course shall be similar to fabrication of
penstock
pipes or transmission/industrial pipelines of
bigger
diameter.
Pipe and attachment shall be aligned properly
by
accurate and permanent methods prior to welding.
If
tack welds are used, the tack shall be either
fused
into the first layer of weld or else chipped out.
T3.04.07 Tests on welded joints
(a) Visual examination
The contractor shall conduct visual examination
and
measurement of external dimensions of the weld for
all
joints. Before examining the welded joints, areas
close
to it on both sides of the weld for a width not
less
than 20 mm shall be cleared of slag and
other
impurities. Examination shall be done by a
magnifying
glass which has a magnification power of ten (10)
and
measuring instrument which has an accuracy of + 0.1
mm
or by weld gauges. Welded joints shall be examined
from
both sides. The contractor shall examine the
following
during the visual examination :-
i) Check the correctness of shape and size of
thewelded joints
ii) Incomplete penetration of weld metal
iii) Influx
iv) Burns
v) Under cuts
-
7/30/2019 BFV Std.specdamper
28/39
vi) Unwelded crates
vii) Cracks in welded spots and heat affected zones
viii)Porosity in welds and spot welds
ix) Compression in welded joints as a result
of
electrode impact while carrying out
contact
welding
x) Displacement of welded element.
The contractor shall carryout any or all tests
as
specified hereinafter to satisfy the Purchaser
about
the acceptability of the welded joints, as directed
by
the Purchaser. However minimum 10% DPT or MP
test
shall be carried out in the fabricated pipes.
(b) Liquid Dye-penetrant Test
Liquid dye-penetrant tests shall be carried out
in
accordance with IS:3658-1981, reaffirmed in 1991
for
surface/sub-surface defects.
(c) Test by Blowing
The surface of the weld shall be covered with
soap
solution consisting of one (1) litre of water
and
hundred (100) grammes of soap. Compressed air shall
be
blown from the opposite side at pressure of 4to
5 kg/cm. sq. The distance between the tip of base
and
the weld shall not be more than 50 mm. Any formation
of
soap buble will indicate welding defects.
Portable
compressor shall be arranged by the contractor,
if
-
7/30/2019 BFV Std.specdamper
29/39
necessary, for this purpose.
Tolerance
Deviations for assembly of welded joints may
be
permitted to the following extent :
Tolerance
-------------------------
Manual arc
Automatic
a) Source butt-joints
i) Gap between the + 2.00 mm + 1.00 mm
ends of plates - 1.00 mm
Tolerance
-------------------------
Manual arc
Automatic
ii) Stepping of one
plate over the
other 1.00 mm 2.00 mm
b) Single Vee-groove Joints
i) Bevol angle + 5 deg. + 5 deg.
- -
ii) Gap between two + 2.00 mm + 1.00 mm
- 1.00 mm
iii) Stepping of one
plate over other 2.00 mm 2.00 mm
c) Lap Joint
i) Overlap 5.00 mm 5.00 mm
ii) Gap between the
surface 2.00 mm 1.00 mm
d) Tee-filler joints
i) Gap between the 2.00 mm 2.00 mm
-
7/30/2019 BFV Std.specdamper
30/39
edge of the web
and the surface
of the flange
T3.05 Rubber Expansion Joints
T3.05.01 Design and Construction
Design of the expansion joint shall take care of
the
axial, angular or rotational movement of the bellow
and
/ or the equipment vibration, as stipulated in the
data
specification sheets enclosed. The expansion
joint
shall be designed such that no periodic adjustment
is
required.
T3.05.02 Body
Expansion bellow shall be of heavy duty
construction
manufactured from high grade abrasion resistant
natural
or synthetic rubber, as specified in data sheets,
with
integral flanges at both ends. Split retaining rings
of
adequate design shall be supplied for securely
holding
the expansion joint with connecting pipe flanges.
T3.05.03 Carcass
Fabrics of high strength synthetic fibres shall be
used
in suitable number of plies to hold the shape of
the
bellow at the working condition. All fabric plies
shall
be impregnated with rubber or synthetic componentsto
permit flexibility between them.
Copper coated steel wire or solid endless rings
embedded
in the carcass shall be used for reinforcement of
the
expansion bellow.
-
7/30/2019 BFV Std.specdamper
31/39
T3.05.04 Cover
The exterior and interior surfaces of the bellow
shall
be coated with suitable material to protect the
carcass
from outside damage and fluid corrosion.
Protective hypalon coatings may be applied at
the
exterior.
T3.05.05 Control Rod Assembly
Each expansion joint shall be supplied with control
rod
assembly to prevent excessive elongation or
contraction
of the bellow. Control rod assembly will consist
of
long bolt, nuts & lock nuts, sphericalwashers,
connecting plates (gusset plate) for fixing the
assembly
with mating flanges.
Control rod assembly shall allow transverse
and
rotational movements under limiting axial conditions
of
the expansion joints.
Design of the control rod assembly shall take care
of
the maximum axial thrust across the bellow calculated
on
the basis of maximum fluid internal pressure and
the
internal diameter of the arch.
T3.05.06 End Flanges
The expansion joint shall have integral
fabric
reinforced full face rubber flanges. The bolt hole
on
the flange shall have no eccentricity in relation to
the
-
7/30/2019 BFV Std.specdamper
32/39
corresponding bolt hole of the flange on the other
face.
The end rubber flange shall be drilled to suit
the
companion pipe flanges. The companion flanges shall
be
suitably match marked for easy identification
during
erection by others.
T3.05.07 Counter Flanges
Counter flanges shall be as per AWWA C-207.
Required numbers of carbon steel nuts, bolts,
washers
and rubber gaskets shall be furnished.
7.05.08 Hydrostatic Pressure Test and Vacuum Test
a) Pressure Test
All expansion bellows shall be subjected to
internal
hydrostatic pressure test at a value of one and a
half
(1.5) times the maximum working pressure under
the
following conditions for thirty (30) minutes:
i) Free position of the bellow
ii) With permitted (design) elongation and
lateral
deflections
iii) With design contraction and lateral deflection
Inspection for leakage from the bellow shall be
carried
out during pressure test.
Before the hydro test and after the hydro test is
over,
the bellow shall be dimensionally inspected to
check
deformation, if any.
During the test, the control assembly shall be
suitablyadjusted to obtain the test conditions of the bellow.
b) Vacuum Test
All expansion joint shall be subjected to a vacuum
test
at 700 mm of Hg vacuum. The test shall be conducted
in
-
7/30/2019 BFV Std.specdamper
33/39
three different positions for a minimum period of
thirty
(30) minutes duration in each position. These
positions
are as described above for pressure test.
c) Additional Tests
Purchaser shall have the right to demand
additional
tests as may be found necessary for quality
assurance.
All the above tests shall be carried out without
extra
cost to Purchaser.
T3.05.09 The Rubber Expanson Joints shall conform to
the
following standards/codes:
i) Expansion joints manufacturers' Association,
USA
standards
ii) Fluid sealing Association, USA
Design of Expansion joint shall take care of the
axial,
angular or rotational movements of the bellow and/
or
the equipment vibration.
The body of expansion joint shall be made from
abrasion
resistant rubber.
The expansion joints shall have integral flanges
at
both ends complete with split retaining rings.
The external and internal surfaces of the
expansionjoint shall be of Neoprene of 3 mm thickness with
a
shore hardness of 65 + 5 deg.
Steel wire/synthetic fabric shall be used
for
reinforcement of the expansion bellows.
Tie rods shall be provided in the expansion joints.
-
7/30/2019 BFV Std.specdamper
34/39
T3.05.10 Design Requirement
i) Qty. - 5 Nos.
ii) Nominal diameter - 1600 mm.
iii) Type - Single arch type.
iv) Design pressure - 6 Kg/cm2
v) Liquid to be handled- Circulating water
(for analysis see
Annexure-D & E).
vi) Working temperature
(oC) (Max./Min.) - 44/30
vii) Maximum flow
(M3/hr) - 16500
viii)Location - Indoor
ix) Test pressure
(kg/cm2g) - 7.5
x) Vacuum design - 750mm of Hg vacuum
xi) Vacuum test - 700mm of Hg vacuum
xii) Freelength (mm) - Manufacturers std.
xiii)Counter flange - AWWA-C 207, 1-50 lb
class
slip on type
xiv) Axial elongation(mm)- 15
xv) Axial contraction
(mm) - 15
xvi) Lateral deflection
(mm) - 15
xvii)Angular deflection
(deg.) - 0.5
xviii) Torsional movement
(deg.) - 0.5
xix) Pump speed (rpm) - 497
-
7/30/2019 BFV Std.specdamper
35/39
T3.05.11 Materials of Construction
Bellow - Synthetic Rubber
Carcass - Synthetic fibre
Stiffening ring - Manufacturers standard
External cover - Hypalon or approved
equivalent
Internal cover - Manufacturer's standard
Control assembly - Manufacturer's standard
Retaining ring - Galvanised Steel
Flanges/Counter flanges - Carbon Steel IS:2062
Gasket - 3 mm thick reinforced
rubber
Nuts, bolts and washers - Carbon Steel - ASTM A
307
Grade A
Pipe thickness - 16 mm
DATA SHEET FOR RUBBER EXPANSION JOINT
1.00.00 GENERAL
1.01.00 Service : C.W.System
1.02.00 Nominal size (NB)/Qty. : 1600mm - 5 Nos.
1.03.00 Duty : Continuous
1.04.00 Type : Spool type
1.05.00 Overall dimensions (mm) : 750
1.06.00 Gross weight of the complete
assembly (kg) : 1750 kgs (appx)
-
7/30/2019 BFV Std.specdamper
36/39
1.07.00 Model No. : During Detail engg.
2.00.00 PERFORMANCE CAPABILITY
2.01.00 Axial elongation / contraction
(mm) : 15/15
2.02.00 Lateral deflection (mm) : 15
2.03.00 Angular movement : 0.5o
2.04.00 Torsional movement (degrees) : 0.5
2.05.00 Axial spring rate (N/mm) : 1925 (Appx)
2.06.00 Torsional spring rate
(kg/mm/deg) : 180
2.07.00t Frequency of vibration (Hz) : During detail Engg.
2.08.00 Maximum pressure drop throughthe expansion joint at design
flow rate, Kg/cm2g : < 0.01
3.00.00 DESIGN AND CONSTRUCTION
3.01.00 Design standard : As per spec.
3.02.00 Design pressure (kg/cm2g) : 6
3.03.00 Design vacuum in mm of mercury: 750
3.04.00 Design Temperature (oC) : 60
3.05.00 No. of arch / corrugation : Single
3.06.00 Flange pressure rating and
drilling standard : BS 4504 PN-10
3.07.00 No. of limit / control rods : 6Nos./Per Joint
3.08.00 Bursting pressure of bellow : Twice the design(kg/cm2g) pressure
4.00.00 MATERIAL OF CONSTRUCTION
4.01.00 Bellow : Synthetic Rubber
4.02.00 Carcass : Synthetic fibre
4.03.00 Bellow exterior : Neoprene Rubber
-
7/30/2019 BFV Std.specdamper
37/39
4.04.00 Bellow interior : Neoprene Rubber
4.05.00 Metal reinforcement : IS 2062 Gr. A Sq. Annular
Ring
4.06.00 Control rod assembly: IS1367 Gr.63.8/6.0, stretcher
plate IS-2062 Gr.A.
4.07.00 Retaining ring segments: IS:2062 Gr.A Galvanised
4.08.00 Flanges/counter flanges: IS:2062 Gr.A
4.09.00 Fasteners : IS:2062 Gr.4.6/4.0
4.10.00 Gaskets : Not recommended as Internal
Rubber flange shall act as
self gasket
5.00.00 INSPECTION AND TESTING INCLUDED
5.01.00 Materials Test Certificates : Yes
5.02.00 Certificates for bought out items : Yes
5.03.00 Dimensional tolerance as per specification : Yes
5.04.00 Hydrotest as per specification : Yes
6.00.00 ACCESSORIES INCLUDED
6.01.00 Control rod assembly with gusset plate, nuts
spherical washers etc. : Yes
6.02.00 Counter flanges with nuts, bolts etc. : Yes
7.00.00 LIST OF TECHNICAL DOCUMENTS ENCLOSED WITH THE CONTRACT
7.01.00 Dimensional General Arrangement drawing
as specified : Yes
7.02.00 A cross-sectional drawing of the
expansion bellow : Yes
7.03.00 Manufacturers standard catalogues and
Literature : No
7.04.00 A write-up on the manufacturing inspection
and testing facilities available at the
manufacturer's works :
7.05.00 Any other information :
-
7/30/2019 BFV Std.specdamper
38/39
LIST OF MANDATORY SPARES FOR R.E. JOINTS
1. Rubber Expansion Joint : 1 set
Complete assembly of 1600 mm dia.
2. Slip-on type matching flange : 1 set
with bolts, nuts and gaskets
3. Reinforced Rubber Gasket for above : N.A.
R.E. Joints
4. Control rod assembly complete with : 2 sets
nuts etc.
Note: One set corresponds to the quantity of
particular
part used in one R.E. Joint.
GUARANTEED DATA FOR R.E.JOINTS.
The contractor guarantees that each rubber expansion
joint
for CW system shall meet the following minimum
performance
data.
1.00.00 Design working pressure of
bellow (kg/cm2 g) : 6 Kg/cm2
2.00.00 Minimum bursting pressure of
bellow (kg/cm2 g) : 12 kg/Cm2
3.00.00 Axial elongation/contraction
(mm) : 15/15
4.00.00 Lateral deflection (mm) : 15
5.00.00 Angular movement (degrees) : 0.5
6.00.00 Torsional movement (degrees) : 0.5
7.00.00 Flange standard : BS 4504 PN-10
SIGNATURE .........................
-
7/30/2019 BFV Std.specdamper
39/39
NAME ..............................
DESIGNATION .......................
NAME AND ADDRESS OF COMPANY
.................................
..
DATE ..............................