best practices award submission
TRANSCRIPT
Construction IndustryBEST PRACTICES 2013 Awards Application
Saint Louis University School of Law in Scott Hall ST. LOUIS, MO
TEAM INFORMATION:Owner: David Florek Project Manager, Saint Louis UniversityPh: 314-977-2916 // E: [email protected] Builder:Clayco Inc.Tom Sieckhaus, Senior VP/PartnerPh: 314-429-5100 // E: [email protected]
Jared Hegeman, Project ExecutivePh: 314-429-5100 // E: [email protected]
Matt Reiter, Project ManagerPh: 314-429-5100 // E: [email protected]
Perry Esslinger, Project Director-StructuralPh: 314-592-2220 // E: [email protected]
Electrical: Bob Kaemmerlen, Kaemmerlen ElectricPh: 314-535-2266 // E: [email protected]
Fire Protection:Matt Coleman, Engineered Fire ProtectionPh: 314-771-0033 // E: [email protected]
Plumbing:Peter DeLuca, DeLuca PlumbingPh: 314-427-5551 // E: [email protected]
Fountains:Chuck Schmitz, Commercial Aquatic EngineeringPh: 952-345-6444 // E: [email protected]
Flooring:Shelly Bourque, Flooring Systems, Inc.Ph: 314-329-9300 // E: [email protected]
Structural Steel:Guy DonCarlos, Atlas Iron WorksPh: 314-383-7200 // E: [email protected]
Weaver Steel:Mike Deane, Weaver Steel Construction LLCPh: 636-397-5076 // E: [email protected]
Roofing:David Steinkuhler, Bi-State RoofingPh: 636-225-3050 // E: [email protected]
HVAC:Tom Murawski, Icon MechanicalPh: 618-452-0035 // E: [email protected]
Sheet Metal:Russ Obergfell, Kuenz Heating & Sheet MetalPh: 636-936-1555 // E: [email protected]
Painting:Chri LonessO-Neill Painting IIPh: 636-398-3003 // E: [email protected]
Glass and Glazing:Jeff Hartnett, St. Charles Glass & GlazingPh: 636-887-2315 // E: [email protected]
Fred Foan, MEP/FP Project ManagerPh: 314-595-6378 // E: [email protected] Tony Williams, Project EngineerPh: 314-592-2269 // [email protected]
Al Morton, General SuperintendentPh: 314-429-5100 // E: [email protected]
Architect:The Lawrence GroupMichael SchnaarePh: 314-231-5700 // E: michael.schnaare@thelawrence group.comGary ConradPh: 314-231-5700 // E: [email protected]
ADDITIONAL KEY TEAM MEMBERS:
Construction IndustryBEST PRACTICES 2013 Awards Application
PROJECT OVERVIEWThe new Saint Louis University (SLU) School of Law in Scott
Hall welcomes the future generations of professionals that will
receive an excellent education at the university and prepare
themselves for a rewarding legal career. Clayco, in collabora-
tion with SLU and an entire team of professionals, helps the
students by improving the way they receive their education,
with the addition of a centralized library and a full size mock
courtroom. The program, which was once spread out across
several buildings on SLU’s mid-town campus, is now self-
contained in the heart of downtown St. Louis, adjacent to the
Custom and Civil Courts Building.
Roof Patio
Construction IndustryBEST PRACTICES 2013 Awards Application
In the face of many challenges related to an older building, a
restrictive schedule and tenant occupation, the 276,000 sq. ft.
building expansion and renovation project was completed on
schedule in 10 months and just under the $32 million budget.
Mobilization on to the site began on Oct. 1, 2012 and substan-
tial completion was achieved on July 25, 2013. As this was an
expansion to an existing facility, one of the many challenges
was performing all of the necessary structural modifications
to the existing building that was originally constructed in the
mid 1960’s and had sat partially vacant and neglected for many
years. This challenge was met and safely overcome, and we are
proud of the fact that even with all of the high-risk modifica-
tions, we repurposed and expanded a 47-year-old office build-
ing to accommodate SLU Law School’s programming needs,
while fitting within SLU’s high standards for overall campus
design and appeal.
Continuous collaboration with our collective team eliminated
delays and setbacks, and allowed SLU to incorporate additional
space and amenities within the project budget. By conducting
extensive programming and constructability reviews with a
diverse group of owners, building users, design professionals,
and construction professionals, complex problems were identi-
fied, analyzed, and solved prior to the start of construction min-
imizing potentially significant budget and schedule impacts.
The team used all of the best practices on this project in some
form but excelled at Front End Planning, Constructability and
Team Building. These best practice processes were employed
by the entire team (Owner, Builder, Architect, Engineers and
Subcontractors) from the beginning of the design process to
project completion.
PROJECT OVERVIEW
Library
Construction IndustryBEST PRACTICES 2013 Awards Application
BEST PRACTICES IMPLEMENTED FRONT END PLANNING, CONSTRUCTABILITY, TEAM BUILDING
Front End Planning
Which members of the project team were involved in the front end planning process? Key team members from Clayco,
SLU, the architectural firm Lawrence Group and key engineers
met after the contract award date to begin establishing a plan.
From Clayco, Matt Reiter, project manager, was responsible for
all day to day activity from beginning to end. He also served as
the liaison between Clayco, the architect and ownership group,
planning and organizing all meetings and design processes.
Jared Hegeman, project executive, was crucial in the early
stages of design helping with overall scheduling and critical
planning activities. Clayco’s in-house mechanical, electric, fire
protection, plumbing and exterior envelope team helped in the
early stages of planning and design to determine which propos-
als would be best within our time and budget constraints and
also through construction to implement the final design.
What were the identified project risks? What courses of action were taken to mitigate or eliminate these risks? First and foremost we were given a fairly aggressive schedule
with a set deadline to open the building for fall semester 2013.
This strict schedule, tenants occupying the building for over
four months during construction and an unknown tenant for
the restaurant space demonstrated unique risk factors in the
renovation.
Through the front end planning stage we had to determine what
was usable in a 47-year-old building, identifying our scope of
work for renovation and maximizing what could be repurposed
and reused. Based on extensive investigation and multiple pay-
back analysis calculations it was determined that a significant
portion of the existing HVAC systems and the majority of the
electrical systems should either be replaced or enhanced. Also,
because of the building’s age and the plan to expose the build-
ing interiors to the elements during winter to add the new 12th
level, exceeding the budget was a constant risk.
Once construction began, portions of the exterior façade were
removed for either the new level or façade improvements.
Adhering to our strict schedule left no options for exposure to
the elements during the winter months or work stoppage due
to high winds. Aside from the weather we had to ensure the
safety of pedestrians, traffic and our team during the exterior
work and installation of the cornice. The cornice was pre-
fabricated offsite, delivered in 20-30 foot sections and installed
12 stories above the ground. Our limited space also presented
complicated logistics related to the insertion of substantial
structural members through small window openings. This pro-
cess involved hoisting huge steel members through the side of
the building with a crane over busy streets below to allow for
the reinforcement of existing floors to accommodate the new
library and classroom areas.
In order to mitigate all of these potential risks, we held mul-
tiple meetings and conducted several pre-planning exercises.
Clayco became involved in the project in January 2012, with the
construction start date set for Oct. 1, 2012, so the team went
through multiple different options and approaches. We had to
decide whether to add one floor, two floors or no floors or raise
the ceilings on the 11th floor instead. We then had to determine
where the library should go and develop a plan for reinforcing
those floors in order to properly support the books and micro-
films. Our team ran through a multitude of possible scenarios
with budget and schedule in mind.
Equally as challenging was the unknown tenant for the res-
taurant space on street level. An operator for the space was
secured five months into the 10 month project creating a
Construction IndustryBEST PRACTICES 2013 Awards Application
condensed schedule for build out of the 1st floor space. No
advance planning, material ordering or construction could
take place until the type of restaurant was established and the
space design completed.
In order to make sure we were adhering to our budget, we did a
budget update for every major decision in the design process.
There was never a point during the planning phases that we
didn’t know what the cost would be. During these meetings, we
worked closely with our subcontractors so they would have the
opportunity to provide input for the budget and schedule, and
ultimately to be committed to both. We investigated the build-
ing before construction began to identify all potential risks.
During the design phase, we conducted small-scale strategic
demolition to the building to allow structural investigation. We
also thoroughly investigated all HVAC, electric and plumbing
systems to identify the condition of every piece of equipment,
piping, etc. to define potential budget and schedule impacts.
We worked closely with the structural engineer (KPFF) to prop-
erly design extremely large structural steel beams that could
be fabricated, delivered from offsite facilities, staged on a very
small project site, hoisted through a small window opening and
spliced back together once inside the building.
All of this coordination prior to construction was vital for the
project’s successful completion. The most unique features for
the building were going to be the highest risk elements, so
doing all of the necessary field investigation and pre-planning
was crucial to the overall project.
What procurement method was selected (Design/Bid/Build, Construction Management, Design-Build, Collaborative)? Why was this method selected? Clayco
was selected by SLU, based largely on our successful comple-
tion of previous SLU projects, our reputation for working col-
laboratively with all team members, our respect for the budget,
timely project completion and an organized safety and risk
management approach. Ultimately a GMP was reached when
all major design decisions were made. This method was
selected because it allowed for the design and construction
team to begin working together immediately so that a col-
laborative approach is taken, real time budgeting can occur,
educated decisions can be made and constructability can be
incorporated into the design.
What project constraints (resource availability, budget, etc.) were identified during the pre-planning process and what measures were taken in the pre-project planning process to overcome these constraints? We encountered
several constraints that we were able to identify in the early
stages of development and planning. Existing tenants occu-
pying the building for the first several months added to the
complexity of the job. Their locations on the 1st and 11th floors
presented obstacles to our logistics and challenged the critical
path of our schedule for adding the 12th floor. Extensive pre-
planning was required to work around these tenants.
We also had to consider that our team would be working out-
side during the winter months without the ability to postpone
work that would risk missing our deadline. Weather was a
huge project constraint as we removed portions of the façade
on the west and south elevations, and as we removed the roof
to add the 12th floor. We were able to successfully navigate
around work stoppages due to inclement weather during the
winter months.
In addition to weather, aggressive schedules and the afore-
mentioned complex additions to an existing structure, the loca-
tion of the building itself presented obstacles of its own. The
building is in the downtown St. Louis business district, located
across the street from the Civil and Custom Courts Building. In
addition to the challenges of the geographic location, the small
Construction IndustryBEST PRACTICES 2013 Awards Application
size of the site meant we had to closely coordinate deliveries
and deal with very little site storage and laydown areas.
Because this is a high-traffic area public safety was a major
concern. We had to work with the city to shut down sidewalks
and drive lanes, and make sure pedestrians and passing vehi-
cles were kept safe from cranes in the roadways and personnel
hoists on the sidewalks.
What project controls were selected for use during construction of the project? Clayco has dramatically set
new standards for design, quality and craftsmanship, efficient
project management, cost containment and worker safety.
We’ve integrated the building process from head to tail and
adopted new technologies that bring state of the art design-
build opportunities to clients and the communities they serve.
In order to properly manage the project, we used a program
that allowed us to track costs, changes and change orders. This
allowed us to continually update our budget to make sure we
were always on point, or to reassess if necessary. We used
standard Clayco practices by implementing schedule programs,
detailed sequence schedules, cost reporting programs, change
management programs, manpower and production docu-
mentation, safety audits and material delivery logs. We held
regular subcontractor coordination meetings, design meetings,
owner meetings and maintained documented meeting min-
utes, commissioning and start-up checklists, field reports and
punchlists. We focused on communications with critical safety
meetings for risky activities, world tour executive walk thrus,
All Hands On Deck safety walk-thru’s and emergency evacua-
tion drills. Working as a team, and using these programs and
Pavillion
Construction IndustryBEST PRACTICES 2013 Awards Application
procedures, we were able to provide the owners all the tools to
make informed decisions to help guide the project and ensure
they were happy with the outcome.
Constructability
At what stages of the project were constructability reviews conducted? Because of the complex scope of this project, the
constraints with adding a level, the challenges of crafting and
installing the SLU identifying cornice and the significant repur-
posing of an existing building, constructability reviews were
performed repeatedly from the beginning of the design process
through completion of the construction. Constructability was
continuously analyzed for every major design decision so the
ownership and design team had a clear understanding of the
impact of any changes to both project cost and schedule.
What processes and tools did you use during these reviews? Our constructability review is something that is a
cultural standard for Clayco and is regularly completed with the
assistance of our in-house Technical Assurance Group (TAG).
This group of construction experts, engineers and technical
assistants apply their skill sets and technical knowledge to
support delivery of the best possible product, with the best
possible value and in a safe manner. Throughout the project we
used the collective information gathered from the constructabil-
ity review process to maximize efficiency in the field, minimize
the impact of having to re-design during the construction pro-
cess, and complete the desired scope within the construction
schedule, all while safely completing the high-risk activities.
What benefit did these reviews yield? As a result of regular
constructability reviews, the ownership and design team was
able to modify certain aspects of the project during the design
process to capitalize on constructability efficiencies. We were
also able to implement design criteria that would not only meet
the owner’s list of needs but also provide the most valuable
results. For instance, the existing building had been designed
with future vertical expansion capabilities, which made the
idea of adding a 12th floor exciting. The constructability analy-
sis performed on the existing structure resulted in savings and
efficiencies by using as much of the original design as possible,
with only minor modification, to accommodate the addition of
the 12th floor.
Ultimately, the amount of time devoted to conducting the
reviews allowed the project to be completed on time and within
budget with minimal changes during construction resulting from
unforeseen conditions. The collective team was able to imple-
ment a significant scope change into the building’s designed
space. During the initial stages of planning, several ideas were
explored to find the best option for meeting SLU’s program-
ming needs, including adding one or two additional floors in
conjunction with repurposing the existing space. After the team
worked through each idea considering several factors related
to feasibility, budget and scheduling, the team determined the
best option was to add one floor and repurpose the existing
remaining floors. This was a critical decision as it allowed for a
large mock courtroom and multi-use event space to be added
without reducing the space allocated for other programming
requirements. The final design also incorporated the addition
of a full-service restaurant on the first floor, a two-story open
concept library on the 5th and 6th floors and glass curtain wall
exposing communicating stairways.
Did you have a formal constructability program used on the project and a method to review and adjust for the future? Yes, as mentioned above, TAG assisted in conduct-
ing the formal constructability review and then presented
their findings to the team. We met as an entire group (builder,
designer, owner) to review, discuss and decide what would
be implemented for this unique project. This group was also
involved throughout the construction phase and assisted with
essential pre commissioning activities.
Construction IndustryBEST PRACTICES 2013 Awards Application
We also performed an extensive existing building survey. We
evaluated all aspects of the building from structure, to mechan-
ical, electrical, plumbing and fire protection systems to assess
the conditions, determine requirements for needed repairs,
incorporate these repairs into the subcontractor procurement
process and uncover any potential issues prior to the design
completion. This was a huge factor in avoiding additional costs
and schedule delays during construction.
Real-time meetings were held as needed to allow for immediate
revisions to the scope of work, allowing decisions to be made
quickly and efficiently. Our process was flexible and conformed
to the needs of the project, allowing us to revisit our payback
analysis. The need for quick, educated decisions helped define
and drive our constructability process.
What lessons were learned? Collectively, the team learned
that extensive early investigations of existing structure and
building systems during design and before construction can
prevent many problems and issues that can hit at inopportune
times and negatively affect the schedule and budget. For the
architectural cornice feature, we determined it was safer, faster
and less expensive to build it in an offsite facility. Other SLU
buildings have similar architectural pieces but the idea of
prefabricating the cornice for this building was unique to the
project. Our collaborative team effort and attention to detail
allowed Clayco to work with clear direction and purpose toward
a common goal and objective.
Team Building
What was the team building process that you employed? We applied the culture of our company to this project from
beginning to the end. Clayco strives to see “Beyond These
Walls” and seeks to be a part of the solution to improve the
built world with the understanding that it’s about the people
using these buildings, more than it is about the building itself.
It’s about the students of SLU that will gain an outstanding edu-
cation in this building and gain real world experience because
of its proximity to the Civil and Custom Courts Buildings and
downtown law district, where many of them will eventually work
as professionals. We stayed focused on turning SLU’s vision
for a world class law school into reality.
We gave full disclosure, working with ownership and third
party groups at every step of the way, and undergoing pric-
ing exercises and schedule reviews for each new idea. It was
a collaborative effort between Clacyo, the architect, owners,
subcontractors and third party consultants. We involved SLU’s
facilities department on the front end to garner their input in
design decisions to help them better operate and maintain the
building after it was completed.
In addition to focusing on the team aspect within the core
owner, builder, designer dynamic, we took this philosophy to
the subcontractors and workers on the job site. We wanted to
ignite a greater sense of passion, accomplishment and own-
ership in each person that played a part in the completion of
this project by communicating the reason behind the building
in our weekly and monthly meetings. This created a sense of
pride for the subcontractors and workers, which helped to bring
them on board as key players in the success of the project.
We went beyond our contractual obligations to bring more to
the table than required. We made an intentional effort to come
together with SLU ownership, designers and technical group to
round out the team with the project’s best interests in mind.
We capped off these 10 months of hard work with a subcon-
tractor appreciation event that allowed each subcontractor the
opportunity to bring their families and children to the job site
to better understand the soaring achievement the building rep-
resented in the community. We were successful in becoming a
team with all of the players that worked together for a common
mission of project success.
What characteristics of this project made team building a critical element of success? The SLU building was
Construction IndustryBEST PRACTICES 2013 Awards Application
an important and complex project that involved several major
points of modifications to the existing building, which required
clear communication and proper planning. The project sched-
ule had to be maintained, the budget had to be met and the
potential risks had to be established on the front end, all while
incorporating a complete law school program. The element of
trust between every level of contractor and employee on the
site created a winning situation for the SLU. Egos were checked
at the door and we encouraged the mindset that it is not who is
right, but what is right for the project that allowed everyone to
come together for a common goal. Without a successful team
approach and a mutual trust in all of the team members, the
opportunity for failure and major schedule impacts could have
been devastating.
What barriers or obstacles were encountered in imple-menting the team building concept and how they were addressed? We approached this project with the goal of find-
ing the best possible outcome for each individual challenge.
Once the team understood that our only motive was to deliver
the best project possible, it was a natural progression of work-
ing together to achieve a common goal. Even as scope changes
occurred, our team worked to provide viable alternative solu-
tions and ultimately served to give SLU the best possible value
on time and within budget.
Because of our front end planning many of the obstacles were
faced before the project began. Maintaining open communica-
tion, reviewing all decisions with payback analysis and keeping
team members focused on doing what is right for the project,
not what is right for the individual.
Certainly the schedule was the greatest obstacle. We had less
than a year between our start date, when the building would
be vacant, and when classes would begin, to complete the
project. This meant working through the winter exposed to
the elements, in order to add the additional 12th floor (which
includes an outdoor patio space) and to replace large portions
of the existing brick façade with a glass curtain wall system. In
order to meet our strict deadline, delaying the project for any
reason was not an option. This required an extraordinary team
effort to make sure each element and step was in the proper
place so that once construction began work stoppages were
minimal.
What benefits did the project achieve as a result of the team effort and what experience was gained that will be implemented on future projects? The project benefitted
from the collective efforts of the entire team working together
that was energized by our drive and motivation. This approach
is exemplified and recognizable through the project from the
schedule delivery, previous work with SLU and experience
with their unique needs, attention to detail and quality to the
efficiency in the turnover process, punch list completion and
owner closeout. While there were few mishaps once construc-
tion began, this was an important lesson in the value of exten-
sive pre planning. All of the front end meetings kept change
orders down which ultimately allowed the project to finish
slightly under budget while meeting all of the owner’s criteria.
What benefits did the project achieve as a result of the team effort and what experience was gained that will be implemented on future projects? The project benefitted from
the collective efforts of the entire team working together, ener-
gized by our drive and motivation. This approach is exemplified
and recognizable through the project from the schedule deliv-
ery, previous work with SLU and experience with their unique
needs, attention to detail and quality, to the efficiency in the
turnover process, punch list completion and owner closeout.
While there were few mishaps once construction began, this
was an important lesson in the value of extensive pre-planning.
Construction IndustryBEST PRACTICES 2013 Awards Application
All of the front end meetings kept change orders down which
ultimately allowed the project to finish slightly under budget
while meeting all of the owner’s criteria.
Conclusion
From the first stages of planning, to completion, Clayco is
extremely proud of everyone who worked on this ambitious
project. Our final hurdle was completely unplanned and unpre-
dicted, when one month before completion the front door
canopy collapsed and had to be completely redesigned and
built within days of the scheduled opening. Every aspect of our
front end planning, constructability and team building were put
to the test to manage this final challenge.
The end result was not only aesthetically pleasing, blending
aspects of other SLU buildings with a sleek design befitting a
downtown building, it serves new functions to meet the needs
of the students and faculty of SLU’s law program. Students are
able to better envision their future as a law professional in the
mock courtroom, or in the outdoor space that faces the Custom
and Civil Courts Building. Our dedicated team of professionals
remained focused on our mission to create the best possible
outcome, with the best possible valuable that would meet and
exceed the owner’s expectations.
With several high-risk factors including structural assessment
to an aging building, logistical issues such as moving large
sections of the pre-fabricated cornice into place in a crowded
downtown area, and large-scale removal of the façade and roof,
our team came together to create a plan that would allow our
workers to be safe, and the outcome to be within budget and
open in time for student orientation. This was a task we did not
take lightly at any stage of the process, and was particularly
emphasized in the pre-planning process, and exemplified
through our constructability reviews and collaborative team
“The Docket” - Restaurant
Construction IndustryBEST PRACTICES 2013 Awards Application
ADDITIONAL SUPPORTING INFORMATIONCornice Installation
Exterior Facade Enhancements
Court Room
Construction IndustryBEST PRACTICES 2013 Awards Application
“Commons”
Court Room