bep ppt
TRANSCRIPT
LOGO
BREAK-EVEN ANALYSIS
2
COST OF PROJECT
Cost of Project represents the total of all items of outlay associated with a project which are supported by long-term funds.
It is the sum of the outlays on: Land and site development Buildings and civil works Plant and machinery Technical know-how and engineering fees Expenses on foreign technicians and training of Indian
technicians abroad Miscellaneous fixed assets Preliminary and capital issue expenses Pre-operative expenses Margin money for working capital Initial cash losses
3
Land and Site Development
Cost of Land and site development includes: Basic cost of land including conveyance and
other allied charges Premium payable on leasehold and
conveyance charges Cost of laying approach roads and internal
roads Cost of tube wells
4
Buildings and Civil Works
It covers: Buildings for the main plant and equipment Buildings for auxiliary services like steam supply,
workshops, laboratory, water supply etc. Godowns, warehouses and open yard facilities Non-factory buildings like canteen, guest houses, time
office, excise house, etc. Quarters for essential staff Garages Sewers, drainage, etc. Other civil engineering works
5
Plant and Machinery
Cost of plant and machinery consists of: Cost of imported machinery
FOB (free on board) value Import duty Clearing, loading, unloading and transportation
charges Cost of indigenous machinery
FOR (free on rail) cost Sales tax, octroi and other taxes Railway freight and transport charges to the site
Cost of stores and spares Foundation and installation charges
6
Technical Know-How and Engineering Fees
Amount payable to technical consultants or collaborators from India and/or abroad for their advice and help in various technical matters.
7
Expenses on Foreign Technicians and Training of Indian Technicians Abroad
It includes: Salaries and allowances payable to foreign
technicians Expenses on their travel , boarding and lodging Expenses on Indian technicians who require
training abroad
8
Miscellaneous Fixed Assets
Fixed assets and machinery which are not part of the direct manufacturing process
It includes: Furniture Office machinery and equipment Tools Vehicles Transformers Laboratory equipment, etc.
9
Preliminary and Capital Issue Expenses
Preliminary expenses: Expenses incurred for identifying the project,
conducting the market survey, preparing the feasibility report, drafting the memorandum and articles of association and incorporating the company.
Capital issue expenses: Expenses incurred on raising of capital from
the public.
10
Pre-Operative Expenses
Establishment expenses Rent, rates and taxes Travelling expenses Interest and commitment charges on
borrowings Insurance charges
11
Margin Money for Working Capital
The principal support of working capital is provided by commercial banks and trade creditors.
A certain part of the working capital requirement has to come from long-term sources of finance.
It is referred to as the ‘margin money for working capital’.
12
Initial Cash Losses
Most of the projects incur cash losses in the initial years.
Promoters typically do not disclose the initial cash losses.
A provision should be made for the estimated initial cash losses in the project cost.
Failure to do so affects the liquidity position and impairs the operations.
13
COST OF PRODUCTION
Components of cost of production are:
1. Material cost
2. Utilities cost
3. Labour cost
4. Factory overhead cost
14
COST OF PRODUCTION
Material cost : It comprises of the cost of raw materials, chemicals,
components and consumable stores required for production.
It is a function of the quantities in which these materials are required and the prices payable for them.
Utilities cost : It consists of power, water and fuel
Labour cost : Cost of all the manpower employed in the factory. It is a function of the number of employees and the rate
of remuneration. Factory overhead cost :
Expenses on repairs and maintenance, rent, taxes, insurance on factory assets, etc.
15
BREAK-EVEN ANALYSIS
Break-even analysis determines how much should be sold to ensure that the project does not lose money
Sales revenues and total costs are analysed for each different level of production
16
BREAK-EVEN POINT
Minimum quantity at which loss is avoided
Point where total revenue equals to total costs
TR = TC
No profit, no loss situation
17
COSTS
Total cost includes fixed cost and variable cost Fixed costs- Costs that do not change in
response to changes in sales volume. executive salaries lease payments depreciation
Variable costs- Costs that change in response to changes in sales volume.
hourly wages raw material’s cost
18
COMPUTING BREAK-EVEN POINT
The break-even point can be calculated by using the following equation:
BEP = Fixed Costs __ Contribution Margin
= Fixed Costs______________________ Selling price per unit – Variable Cost per unit
19
CONTRIBUTION MARGIN
The contribution margin is the amount of money that is available from the sale of each unit to cover the fixed costs of the firm.
Once those fixed costs are covered, any further units that are sold will result in profit.
Contribution Margin=Selling Price-Variable Cost
20
CONTRIBUTION MARGIN
The following diagram illustrates the definition of contribution:
Contribution
Variable costs
Sales revenue
Profit
Fixed costs
21
EXAMPLE A teddy bear manufacturing company sells its bears to
retailers for an average price of Rs.180. The variable costs are Rs.30 per bear. The company’s fixed costs are Rs.1,50,000.
To calculate the break-even point, we first need to find the contribution margin:
Contribution Margin =Selling Price – Variable Costs=Rs.180 – Rs.30 =Rs.150
We can now calculate the break-even point:
BEP = Fixed Costs Contribution Margin= Rs.150,000 Rs.150= 1,000 bears
22
BREAK-EVEN CHART
23
TYPES OF BREAK-EVEN ANALYSIS
Break-even analysis can be explained in two ways:
Accounting Break-Even Analysis
Financial Break-Even Analysis