www.energy.gov/EM 1
Idaho Cleanup Project (ICP) Solid Waste Management
December 4, 2013
Ben Roberts Federal Project Director for Solid Waste Disposition
Nolan Jensen Federal Project Director for Soil and Water Remediation
![Page 2: Ben Roberts Nolan Jensen](https://reader035.vdocuments.site/reader035/viewer/2022062906/586a16351a28abe7148bb3dd/html5/thumbnails/2.jpg)
www.energy.gov/EM 2
Agenda
• Background/Requirements Drivers
• Overview of Scope Elements
![Page 3: Ben Roberts Nolan Jensen](https://reader035.vdocuments.site/reader035/viewer/2022062906/586a16351a28abe7148bb3dd/html5/thumbnails/3.jpg)
www.energy.gov/EM 3
3
Site Map
![Page 4: Ben Roberts Nolan Jensen](https://reader035.vdocuments.site/reader035/viewer/2022062906/586a16351a28abe7148bb3dd/html5/thumbnails/4.jpg)
www.energy.gov/EM 4
Regulatory Drivers
4
Idaho Settlement Agreement • All Legacy TRU waste subject to Idaho Settlement Agreement removed from
Idaho by 12/31/2018 RCRA Site Treatment Plan • Provides framework for mixed waste management at INL Site including
Calcine
CERCLA Federal Facility Agreement/Consent Order • Governs environmental restoration activities • Sub-surface Disposal Area (SDA) • Idaho CERCLA Disposal Facility
General Compliance Drivers
• Laws, Regulations, DOE Orders
• Permits
• Records of Decision
![Page 5: Ben Roberts Nolan Jensen](https://reader035.vdocuments.site/reader035/viewer/2022062906/586a16351a28abe7148bb3dd/html5/thumbnails/5.jpg)
www.energy.gov/EM 5
Idaho CERCLA Disposal Facility
LLW/MLLW & TRU storage
RH-TRU Processing
RH-TRU processing, Characterization, & shipping
![Page 6: Ben Roberts Nolan Jensen](https://reader035.vdocuments.site/reader035/viewer/2022062906/586a16351a28abe7148bb3dd/html5/thumbnails/6.jpg)
www.energy.gov/EM 6
Subsurface Disposal Area Accelerated Retrieval Project (ARP)
AMWTP
Sludge Repackaging Project
CERCLA
RCRA
RH-LLW disposal
![Page 7: Ben Roberts Nolan Jensen](https://reader035.vdocuments.site/reader035/viewer/2022062906/586a16351a28abe7148bb3dd/html5/thumbnails/7.jpg)
www.energy.gov/EM 7
Elements of Scope
2. Solid Waste Management
• CH-TRU • Complete shipment of AMWTP (above ground TRU & primary MLLW) by 12/31/18
(1st qtr. 2019)
• Market AMWTP capabilities for use on off-site waste
• RCRA Closure of AMWTP facilities by 2024
• Accelerated Retrieval Project (ARP) • Construct ARP IX Exhumation Enclosure
• Design and Construction (2016 – 2018)
• Complete exhumation (ARP VIII and IX by 2023) – Ship by 2024
• RH-TRU • Continue to operate RH-TRU program through 2024 (CPP-659 & CPP-666)
• Ship remaining Settlement Agreement waste by 12/31/2018
• Coordinate RH-TRU processing among EM, NE, NR
• May require identification of new waste streams to support ongoing mission
![Page 8: Ben Roberts Nolan Jensen](https://reader035.vdocuments.site/reader035/viewer/2022062906/586a16351a28abe7148bb3dd/html5/thumbnails/8.jpg)
www.energy.gov/EM 8
Elements of Scope
2. Solid Waste Management (continued)
• LLW/MLLW • Process waste as generated from EM operations
• Operate Idaho CERCLA Disposal Facility (ICDF)
• Close RH-LLW Disposal Facility at RWMC • Cease disposal of NRF RH-LLW Waste by 2020 (Operations at full cost recovery from NR)
• Complete DOE Order 435 closure process by 2023
• Disposition IWTU and PEW secondary system rinse and decontamination liquids after SBW processing complete
• Disposition U-233 waste to Waste Control Specialists
• Waste Characterization (Exhumed Buried Waste) • CH-TRU
• MLLW
![Page 9: Ben Roberts Nolan Jensen](https://reader035.vdocuments.site/reader035/viewer/2022062906/586a16351a28abe7148bb3dd/html5/thumbnails/9.jpg)
www.energy.gov/EM 9
• Interdependencies and Interfaces
• ARP (exhumed buried waste), and RH-TRU utilize the CCP Contractor for TRU waste characterization and certification.
• AMWTP, ARP, and RH-TRU utilize WIPP shipping assets.
![Page 10: Ben Roberts Nolan Jensen](https://reader035.vdocuments.site/reader035/viewer/2022062906/586a16351a28abe7148bb3dd/html5/thumbnails/10.jpg)
www.energy.gov/EM 10
2
1
4
3 3 3 3
4
4
5
4
6
•Treatment - 1
• Retrieval - 2
• Storage - 3
• Characterization - 4
• Payload - 5
• Shipping - 6
3
3
Advanced Mixed Waste Treatment Project (AMWTP)
1
1
3
![Page 11: Ben Roberts Nolan Jensen](https://reader035.vdocuments.site/reader035/viewer/2022062906/586a16351a28abe7148bb3dd/html5/thumbnails/11.jpg)
www.energy.gov/EM 11
AMWTP Waste Retrieval
Degraded Box.
![Page 12: Ben Roberts Nolan Jensen](https://reader035.vdocuments.site/reader035/viewer/2022062906/586a16351a28abe7148bb3dd/html5/thumbnails/12.jpg)
www.energy.gov/EM 12
AMWTP Waste Retrieval
Degraded Drums.
![Page 13: Ben Roberts Nolan Jensen](https://reader035.vdocuments.site/reader035/viewer/2022062906/586a16351a28abe7148bb3dd/html5/thumbnails/13.jpg)
www.energy.gov/EM 13
AMWTP Treatment Facility
13
Top Left: AMWTP Treatment Facility.
Bottom Left: Boxline waste processing
trough and Brokk
Bottom Right: A Brokk manipulator
processing boxed waste
![Page 14: Ben Roberts Nolan Jensen](https://reader035.vdocuments.site/reader035/viewer/2022062906/586a16351a28abe7148bb3dd/html5/thumbnails/14.jpg)
www.energy.gov/EM 14
AMWTP Characterization and Supercompactor
The real-time radiography x-ray of a drum. Supercompactor Glovebox.
Supercompactor
![Page 15: Ben Roberts Nolan Jensen](https://reader035.vdocuments.site/reader035/viewer/2022062906/586a16351a28abe7148bb3dd/html5/thumbnails/15.jpg)
www.energy.gov/EM 15
AMWTP Waste Storage
100 Gallon Product Drums
55-Gallon Drums Ten Drum Overpacks
Standard Waste Boxes
Waste Boxes and MacroPacks
![Page 16: Ben Roberts Nolan Jensen](https://reader035.vdocuments.site/reader035/viewer/2022062906/586a16351a28abe7148bb3dd/html5/thumbnails/16.jpg)
www.energy.gov/EM 16
AMWTP Loading and Shipping
Top Left: Workers load a TRUPACT II
container.
Bottom Left: Loaded TRUPACTs ready for
shipment to WIPP
Top Right: Loaded Macropacks ready for
shipment to NNSS
![Page 17: Ben Roberts Nolan Jensen](https://reader035.vdocuments.site/reader035/viewer/2022062906/586a16351a28abe7148bb3dd/html5/thumbnails/17.jpg)
www.energy.gov/EM 17
LLW/MLLW & RH-TRU Storage
RH-TRU Processing
RH-TRU Processing, Characterization, & Shipping
Remote Handled Transuranic Waste Project (RH-TRU)
![Page 18: Ben Roberts Nolan Jensen](https://reader035.vdocuments.site/reader035/viewer/2022062906/586a16351a28abe7148bb3dd/html5/thumbnails/18.jpg)
www.energy.gov/EM 18
RH-TRU Waste Retrieval/Transport
Truck Loaded with Facility Transfer Container
![Page 19: Ben Roberts Nolan Jensen](https://reader035.vdocuments.site/reader035/viewer/2022062906/586a16351a28abe7148bb3dd/html5/thumbnails/19.jpg)
www.energy.gov/EM 19
RH-TRU Waste Repackaging
Prohibited Item Removal from Waste
Container Cutting Product Drum Removal
Waste Removal from Container
![Page 20: Ben Roberts Nolan Jensen](https://reader035.vdocuments.site/reader035/viewer/2022062906/586a16351a28abe7148bb3dd/html5/thumbnails/20.jpg)
www.energy.gov/EM 20
RH-TRU Characterization and Shipping 20
RH-72B Loading
Impact Limiter Installation Loaded RH-72B
Characterization
![Page 21: Ben Roberts Nolan Jensen](https://reader035.vdocuments.site/reader035/viewer/2022062906/586a16351a28abe7148bb3dd/html5/thumbnails/21.jpg)
www.energy.gov/EM 21
ARP VIII
ARP Steel Frame being Erected
Buried Waste Accelerated Retrieval Project
![Page 22: Ben Roberts Nolan Jensen](https://reader035.vdocuments.site/reader035/viewer/2022062906/586a16351a28abe7148bb3dd/html5/thumbnails/22.jpg)
www.energy.gov/EM 22
Maintenance in Air Lock
![Page 23: Ben Roberts Nolan Jensen](https://reader035.vdocuments.site/reader035/viewer/2022062906/586a16351a28abe7148bb3dd/html5/thumbnails/23.jpg)
www.energy.gov/EM 23
Exhumation in ARP VII
Drum Packaging Station
Close Circuit TV Room
![Page 24: Ben Roberts Nolan Jensen](https://reader035.vdocuments.site/reader035/viewer/2022062906/586a16351a28abe7148bb3dd/html5/thumbnails/24.jpg)
www.energy.gov/EM 24
Waste Sorting in Drum Packaging Station Glove Box
Drum Packaging
![Page 25: Ben Roberts Nolan Jensen](https://reader035.vdocuments.site/reader035/viewer/2022062906/586a16351a28abe7148bb3dd/html5/thumbnails/25.jpg)
www.energy.gov/EM 25
ARP Area
(acres)
Acres Complete 9/23/2013
Acres Remaining 9/23/2013
Anticipated by
10/1/2015 Status
ARP I 0.5 0.5 0 0 Waste exhumation complete and retrieval enclosure demolished
ARP II 0.34 0.34 0 0 Waste exhumation complete and retrieval enclosure in standby awaiting retrieval from ARP III waste transfer vestibule
ARP III 0.43 0.38 .05 0 Retrieval enclosure in standby awaiting retrieval of 0.05 acres from area obstructed by a waste transfer vestibule
ARP IV 0.79 0.79 0 0 Waste exhumation complete and retrieval enclosure in standby
awaiting demolition
ARP V 0.55 0.55 0 0 Waste exhumation complete and retrieval enclosure in use for
repackaging sludge waste from the Advanced Mixed Waste
Treatment Project
ARP VI 0.4 0.4 0 0 Waste exhumation complete and retrieval enclosure demolished
ARP VII 0.27 0.15 .12 0 Retrieval enclosure in standby awaiting retrieval of remaining 0.12 acres by September 2015
ARP VIII 1.72 0 1.72 <1.38 Retrieval enclosure construction complete March 2013
ARP IX 0.69 0 .69 .69 Retrieval enclosure design and construction in the future
Total 5.69 3.11 2.58 <2.07
Status of Accelerated Retrieval Project (ARP)
![Page 26: Ben Roberts Nolan Jensen](https://reader035.vdocuments.site/reader035/viewer/2022062906/586a16351a28abe7148bb3dd/html5/thumbnails/26.jpg)
www.energy.gov/EM 26
Sludge Repackaging Project in ARP V
Sludge drum handling
Excavator emptying a drum
![Page 27: Ben Roberts Nolan Jensen](https://reader035.vdocuments.site/reader035/viewer/2022062906/586a16351a28abe7148bb3dd/html5/thumbnails/27.jpg)
www.energy.gov/EM 27
Organic Contamination in the Vadose Zone (OCVZ)
One of three functioning vapor extraction units
Inside Vapor Extraction Unit
Vapor Sampling
![Page 28: Ben Roberts Nolan Jensen](https://reader035.vdocuments.site/reader035/viewer/2022062906/586a16351a28abe7148bb3dd/html5/thumbnails/28.jpg)
www.energy.gov/EM 28
Idaho CERCLA Disposal Facility (ICDF)
![Page 29: Ben Roberts Nolan Jensen](https://reader035.vdocuments.site/reader035/viewer/2022062906/586a16351a28abe7148bb3dd/html5/thumbnails/29.jpg)
www.energy.gov/EM 29
Grouting Waste
Hot Cell Disposal
ICDF continued
![Page 30: Ben Roberts Nolan Jensen](https://reader035.vdocuments.site/reader035/viewer/2022062906/586a16351a28abe7148bb3dd/html5/thumbnails/30.jpg)
www.energy.gov/EM 30
RH-LLW Disposal