bellefonte white paper

Upload: karthik-vijapurapu

Post on 05-Apr-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/2/2019 Bellefonte White Paper

    1/14

    BELLEFONTEUNIT1

    TennesseeValleyAuthority

    BellefonteUnit1OpportunityforanUnrealizedAsset

    August2011

  • 8/2/2019 Bellefonte White Paper

    2/14

    BellefonteUnit1Completion

    Introduction

    Witharenewedvisionofnationalleadershipinnuclearenergy,TVAislookingtotheunfinishedBellefonteproject.

    The1,600acresitewithtwopartiallycompleteBabcock&WilcoxpressurizedwaterreactorsnearHollywoodand

    Scottsboro,Alabama,remainsanunrealizedasset.

    TVAhaswrestledwithBellefontesfatesinceconstruction,whichbeganin1974,wassuspendedin1988because

    ofslowinggrowthinelectricitydemand.NowTVAsIntegratedResourcePlan,completedin2011,predictsmore

    energycapacitywillbeneededbytheendofthedecade.TheIRPidentifiesnuclearastherighttechnologytomeet

    thechallengewhilekeepingreliabilityhighandratescompetitive.Further,studiespointtothecompletionof

    BellefonteUnit1asthepreferred,leastcostoption.

    Withanoutputof1,260megawatts,BellefonteUnit1couldbethelargestreactorinTVAsnuclearfleet.Itwould

    beazero

    carbon

    powerhouse

    with

    the

    capacity

    to

    replace

    acoal

    fired

    power

    plant.

    That

    could

    be

    critically

    importantas TVAtransitionstolowercoalutilizationunderamajorcleanairagreementwiththeEnvironmental

    ProtectionAgencyandsetsitscoursetoleadthenationinlowcostandcleanerenergyby2020.

    InAugust2011,theTVABoardofDirectorsapprovedthe$4.9billioncompletionofBellefonteUnit1inthe2018

    2020timeframe.Thisdocumentreviewssomeoftheissuesconsideredbytheboardthatimpactedthatdecision.

    Issues

    PROS

    Currentfacilities

    already

    address

    aportion

    of

    the

    NuclearRegulatorCommission'ssafetyrequirementsfromFukushima

    Maintainsreliablepowertomeetincreaseddemands

    AllowsTVAtoretireagingcoalplants

    EnablesTVAtoachieveitsrenewedVision lowrates

    Providesanewsourceofclean,safe,reliable,affordableenergy

    Utilizesexistingassettodeliveranewnuclearplantata savingsofover$1.9billioncomparedtothenextbestnuclearalternative

    Leveragesexperiencecompleting,restartingidledprojects(WattsBarUnits12,BrownFerryUnit1)

    Createsjobs

    Fewerairemissions

    Hassupportfromlocal,regionalresidents

    CONS

    Publicconcerns

    over

    nuclear

    safety

    Regulatory/licensingissuesovercontructionpermit

    FirsttimeU.S.licensingofB&W205reactor

    PostJapanrequirements

    Statutorydebtlimitandcostofproject

    Ageofexistinginfrastructure

    Longtermmanagmentofnuclearwaste

  • 8/2/2019 Bellefonte White Paper

    3/14

    BellefonteUnit1 3

    TennesseeValleyAuthority Bellefonte Unit1Completion

    BackgroundInformation

    TheBellefonteProjectbeganinthe1970saspartofTVAsplantomeetfuturedemandwithnucleargeneration.At

    thetime,electricitydemandwasforecasttorise7percentayear.Butprojecteddemandfelldramaticallyasthe

    economyslowedinthe1980s,andTVAfounditselfwithmorebaseloadunderconstructionthanitcoulduse.

    Nuclearprojectsweredeferred,includingBellefonteUnit2in1985andBellefonteUnit1in1988.Whendemand

    revivedinthe1990s,TVAchosetofinishWattsBarUnit1ratherthanBellefonteUnit1largelybecauseofits

    similarityindesignandoperationtoSequoyah,thesisterplanttoWattsBar.

    In1994,TVAsaiditwouldnotcompleteBellefonteUnit1withoutafinancialpartner.Thisbeganadecadelong

    searchforanewoptionforBellefonteasacombinedcylenaturalgasplant,anationaldefensetritiumplantforthe

    DepartmentofEnergyoracoalgasificationplant.In2006,TVAaskedtheNuclearRegulatoryCommissionto

    withdrawitsconstructionpermitforBellefonte,transferredorsoldsome$60millioninpartsandequipmentover

    thenextfewyears,andofferedthesitetotheNuStartutilityconsortiumasthemodelorreferencesiteforanew

    combinedconstructionandoperatinglicenseforanewreactordesign,theWestinghouseAP(AdvancedPassive)

    1000. AlthoughSouthernCompanysPlantVogtlenuclearsiteinGeorgianowservesthisNuStartrole,TVAcould

    maintaintheoptionofeventuallybuildingoneortwoAP1000sattheBellefontesite,asBellefonteUnits3and4.

    Inearly2008,withcommoditypricesrising,includingthecostofconstructionmaterials,TVArevivedinterestin

    completingBellefontesunfinishedoriginalreactors. AtTVAsrequest,theNuclearRegulatoryCommission

    reinstatedBellefontesconstructionpermit.SeveralindepthstudieslaterconfirmedBellefontescontinuing

    viabilityandpotentialasamodernnuclearfacility.BellefonteUnit1wasabout88percentfinishedwhentheunit

    wasplacedindeferredstatusin1988.Thoughequipmentupgrades,updatesandreplacementsareneeded,

    Bellefonte

    Unit

    1s

    infrastructure

    is

    sound

    and

    the

    facility

    is

    considered

    about

    55

    percent

    complete

    today.

    1974....ConstructionStarted Nuclearexpansionprogram

    1985....ConstructionSlowed Slowereconomy/projectedloadgrowthdropped

    1988....PlantDeferred Longonbaseloadpower

    1992....CompletionEngineeringRestarted Maintainedunderassetpreservationprogram

    1993....NRCConstructionLicenseReactivated Maintainedunderassetpreservationprogram

    1994....CompletionEngineeringCeased BothWattsBarandBellefonteweregoodoptions didnotneedboth

    2005....Layup&PreservationCeased Collapseofpowermarketscontinuedtoevaluateoptions

    2006....ConstructionPermitsWithdrawn Duetopromiseofalower costoptionwithAP1000 *in2007,TVAdecidedtofinishWattsBar

    2009....ConstructionPermitsReinstated FivekeystudiesdeterminedthatBellefontewasthebetteroptionthantheAP1000

    BellefonteTimeline

    TVAhada10yearperiodofnorate

    increasesbetweenOct1987andOct1997

  • 8/2/2019 Bellefonte White Paper

    4/14

    TheNeedforNewEnergy

    TVAsIntegratedResourcePlan(IRP)identifiedaneedfor7,500megawattsofadditionalcapacityby20182020to

    maintainsystemreliability.NuclearexpansionispresentinamajorityoftheIRPssuggestedpoweroptions.

    AlthoughtherecessionhasreducedelectricitygrowthintheTennesseeValleytoabout1percentannually,TVAhas

    aneedfornewbaseloadgenerationwiththeretirementof18agingcoalfiredunitsbytheendof2017underthe

    EPAagreement,andtwoadditionalunitssubsequentlyidentifiedforidlingatJohnSevierFossilPlantbytheendof

    2012. ThiswouldmarkTVAsfirstcoalplantretirementsincetheWattsBarSteamPlantleftservicein1982.

    BellefonteUnit1couldreplacetheequivalentoffiveto10coalunits,therebyreducingTVAssmog,hazeandacid

    raincontributingemissionsbynearly11milliontonsofcarbondioxide,34,000tonsofsulfurdioxide,900tonsof

    nitrogenoxideand300poundsofmercuryannually.

    CapacityShortfall2010 2020

    Overitsfull20yearhorizon,theIRPidentifiesupto5,900megawattsofnewnucleargenerationby2029.That

    meansevenwithadditionalenergyefficiency,naturalgas,renewablesandhydropumpedstorage,TVAcouldstill

    needuptothreenewreactors,includingtheWattsBarUnit2reactornowexpectedtocomeonlinein2013.

    FinishingBellefonteUnit1wouldmeetasubstantialportionofTVAsfuturegeneratingneedsatalowercostper

    installedkilowatt.ADetailedScoping,EstimatingandPlanningstudyontheBellefontesitecompletedin2010

    estimatedconstruction

    costs

    of

    $3,120

    to

    $3,360

    per

    kilowatt

    to

    complete

    the

    Bellefonte

    Unit

    1reactor,

    compared

    with$3,300to$4,900perkilowatttobuildanewAP1000,asBellefonteUnit3,expressedin2010dollars.TVA

    expectstosavemorethan$1.5billionbycompletingBellefonteUnit1ratherthanbuildinganAP1000,asomewhat

    smallerreactorwhosefinaldesignrequirementsarestillunderNRCreview.

    Asshowninthechartsbelow,Bellefonte(oneortwounits)wasselectedin33of48(69percent)IRPcasestudies.

    In82percentofthosecases,thebestinservicedatefellbetween2018and2020. Theassumptionsunderwhich

    1,000

    2,000

    3,000

    4,000

    5,000

    6,000

    7,000

    8,000

    9,000

    2012 2013 2014 2015 2016 2017 2018 2019 2020

    PlannedEEDR Bellefonte1 CapacityGap CapacityNeedMW

  • 8/2/2019 Bellefonte White Paper

    5/14

    BellefonteUnit1 5

    TennesseeValleyAuthority Bellefonte Unit1Completion

    Bellefontewasapreferredassetsupportstherobustnessofthepotentialvalueoflowcostnuclearpowerina

    numberofpossiblefutures.

    BellefontesSupplementalEnvironmentalImpactStatement(SEIS)consideredstudiesthatsuggestedenergy

    efficiencycouldplayabiggerroleinTVAspowerportfolio.However,thereportssaidmajortechnicalandpolicy

    changesmaybeneccesary.InTVAsservicearea,thelevelofparticipationandinvestmentbydistributorcustomers

    wouldalsobeanuncertainty.TheSEISconcludedthatsubstantialpolicy,legislativeandbehavioralchangesmust

    occurbeforeTVAcanrelyextensivelyondependablecapacityfromconservationmeasuresasasubstituteresource

    forbalancinggenerationandload.

    Inaddition,theIRPsfinalplanningdirectionmovesTVAtowardsaportfoliocomprisedofbothEnergy

    Efficiency/DemandResponseandnuclear.TVAismovingforwardwithanexpandeduseofEnergy

    Efficiency/DemandResponse

    within

    its

    capacity

    plan.

    Over

    the

    next

    decade,

    TVAs

    generating

    portfolio

    will

    be

    a

    morediverseandbalancedmixwithnuclear,coal,gasandrenewableresourceseachaccountingforabouta

    quarterofTVAstotalgeneratingassets,consistentwithTVAsvisionofcleanerairandmissiontostablerates.

    Renewables

    1880%

    Hydro

    6,19515%

    Nuclear

    10,71926%

    Coal

    9,24423%

    Gas

    8,60821%

    Purchases

    2,1025%

    EE/DR

    3,96310%

    GenerationMixby2022

    61%

    3%

    18%

    18%

    BLN1InServiceYearWhenSelected

    2 01 8 2 0 19 2 02 0 2 02 2

    2018- 2020

    2022

    18%

    82%

    Bellefonte Unit 1 In-Service Year Was Between

    2018-2020 82 Percent of Time When Selected

    33

    15

    0

    5

    10

    15

    20

    25

    30

    35

    Bellefonte1or2Units NoNuclearUnits

    Frequencyof

    Nuclear

    Unit

    Selection

    (outof48IRPcasesrun)

  • 8/2/2019 Bellefonte White Paper

    6/14

    TheSEISindicatedthatcountingtooheavilyonsomerenewableenergysources,suchaswindandsolar,wouldbe

    impracticalbecauseof intermittentreliabilityandlimitedenergystorage.InstallationsequaltoaBellefonteUnit1

    reactoralsowouldrequireahugefootprint.ThereportestimatedaBellefontesizedsolarpowersystemwould

    require193solararraysof50megawattseachcovering89squaremiles.Forwind,some2,783turbineswouldbe

    requiredspreadoutover436squaremiles,morethanhalfthesizeoftheGreatSmokyMountainsNationalPark.

    TVAhasrecentlycontractedforupwardsof1350MWsofwindenergyfromtheMidwestandGreatPlainsinan

    efforttohaveabalancedportfolio.

    EngineeringIntegrity

    TheDesign,Scoping,EstimatingandPlanning(DSEP)studyontheBellefontesite,completedin2010aftersome

    150,000laborhoursandhavinggeneratedsome8,500pagesofdetailedreports,foundthematerialconditionof

    theplantsystem,structuresandcomponentsareconsistentwiththatexpectedforaplantthathasbeendeferred

    forover20years.Manycomponentswillneedtobereplacedorrefurbishedtomeetdesignorperformance

    standards.Usingallknownavailabletechnologiesvisualinspection,coredrilling,ultrasoundandacoustic

    soundingTVAinvestigatedgroundwaterintrusionatBellefonteUnit1,andfoundnoindicationofcompromiseor

    degradationto

    the

    foundation.

    The

    containment

    building

    had

    no

    water

    intrusion

    at

    all.

    Theposttensioningstructuralsupportforthecontainmentbuildingwasevaluatedafteroneofthe185vertical

    steelcabletendonsthatanchorthecontainmentinbedrookcameloosein2009. Arootcauseanalysisfound

    stresscorrosioncrackinginthetendoncouplingcausedbymechanicalgreasethathadbeencontaminatedwith

    sulfites,whichintroducedmoisture.Inspectionsindicatedthisproblemwasisolatedtotheonecoupling.Overall,

    theDSEPreportconcluded:Theplantisstructurallysound;andfoundnoengineeringconcernsthatwould

    preventtheBellefonteprojectfromproceedingforwardtocompletion.

    TVAalsoevaluateddesignandstructuralissuesthatledtocontainmentwallgappingordelaminating atthe

    Crystal

    River

    Nuclear

    Plant

    in

    Florida.

    TVA

    determined

    Bellefonte

    Unit

    1s

    containment,

    strength

    of

    concrete

    and

    greaterdensityofrebarminimizesthepossibilityofsimilarproblemsatBellefonte.Additionally,unlikeatCrystal

    RiverUnit3,steamgeneratorscanberemovedandreplacedatBellefonteUnit1throughahatch,eliminatingthe

    needtocutaholeinthecontainment.

    TVAdeterminedtheexistingvalueofBellefonteUnit1versusnewnuclearconstructionforthesamecapacityis

    $1.9billion.Thisincludeselectrical,piping,valves,rebarandsteel,concreteandsiteinfrastructure. AfterTVA

    terminatedtheBellefonteconstructionpermitsin2006,someequipmentwassoldortransferredtootherTVA

    facilitiesaspartofanassetrecoveryeffort.Thisincludedsteamgenerators,severalfeedwaterheaters,large

    pumpsandmotors,demineralizedwaterandcondensatestoragetanks,maincondensertubesandsomepiping

    andvalves

    in

    the

    turbine

    building.

    In

    2008,

    TVA

    contracted

    astudy

    that

    determined

    what

    was

    removed

    and

    where

    ithadbeenlocated.TVAhasmaintainedallqualityassurancerecordsfortheentirelifeoftheplantinanonsite,

    climatecontrolledvaultforuseinfuturelicensing.

  • 8/2/2019 Bellefonte White Paper

    7/14

    BellefonteUnit1 7

    TennesseeValleyAuthority Bellefonte Unit1Completion

    BellefonteExistingFacilities

    Essentially,alloftheexistingpowerplantbuildingscanbeused,includingacoolingtower,alongwiththereactor

    vesselandinternals,piping,cabletrays,instrumenttubingandmuchoftheinstalledelectricalcable.Everyplant

    systemwouldbeevaluatedandequipmentreplacedorrefurbishedtolikenewcondition.Theageofthebase

    facilitiesisnotexpectedtolimitthe40yearoperatinglicensingperiodforthereactor.Itisfurtheranticipatedthat

    theunitcouldoperateforupto60yearsfollowingfutureevaluationsinaccordancewithNRCslicenserenewal

    program.

    Componentsremoved

    or

    sold

    during

    the

    asset

    recovery

    project

    would

    be

    replaced

    at

    acost

    of

    about

    $390

    million.

    Overhalfofthisamountwouldbefornewstreamgenerators.Thesereplacementsarepartofsome$2.1billionin

    newequipmenttomeetcontemporarysafetymarginsandindustryrequirements.Majorareasforinvestment

    wouldincludeamoderncontrolroom,newsteamgenerators,aredesignedmainturbine,digitalinstrumentation

    andcontrols,maintransformersandswitchyard,andenergyefficientlighting,plumbingandinsulation.

    RespondingtoFukushima

    AnNRCtaskforcehasrecommendedsafetyimprovementsforU.S.nuclearplantsinresponsetotheearthquake

    andtsunamithatcrippledtheFukushimanuclearplantinJapaninMarch2011.Therecommendationsinclude

    requiringplants

    to

    have

    the

    capability

    to

    cope

    with

    blackouts

    of

    up

    to

    72

    hours,

    backup

    systems

    to

    assure

    cooling

    ofspentfuelrodsandsufficientmarginsforbeyonddesigneventsinvolvingearthquakesandflooding.

    TheBellefonteplantalreadyisarobustlydesignedandconstructedfacilitywithmanyadvanceddesignfeatures

    installedorplannedtobeinstalledtocopewithnaturaldisasters,includingFukushimatypeevents,maximum

    floodsanddamfailures.

  • 8/2/2019 Bellefonte White Paper

    8/14

    NuclearGenerationDevelopmentandConstruction9

    ContainmentDesign

    TheBellefonteUnit1reactorbuildingconsistsofaposttensionedconcreteprimarycontanmentstructureanda

    freestandingreinforcedconcretesecondarycontainmentstructureorshieldbuilding.Theprimarycontainment,

    whichhousesthereactorpowerconversionandcoolantsystems,hasaleaktightsteelliner.Thisissurroundedby

    afreestandingsecondarycontainmentcomposedofareinforcedconcreteshell.Theprimarycontainmentcan

    withstandpressuresof50poundspersquareinchassociatedwithalossofcoolantaccident.Thesecondary

    containmentisdesignedtoresistvariouscombinationsofsevereseismicactivity,highesttornadowindvelocities,

    externalmissilesandwaterpressurefromnormalandaccidentconditions.

    AdditionalFukushimarelatedmodifications,whichcouldbeaddedtoBellefonteUnit1asitiscompletedrather

    thanretrofitted

    later

    as

    with

    existing

    nuclear

    plants,

    would

    address

    the

    loss

    of

    AC

    power

    by

    installing

    backup

    air

    cooledandwatercooleddieselgenerators,enhancementstomaintainDCpowertosafelyshutdownequipment

    andinstrumentation, anadditionalDCpowerpumptomaintainsealcooling,andanadditionalpumpwith

    independentwatersupplyandheatexchangertoaddwatertospentthefuelpoolandmaintaincooling.

    UsedFuelManagement

    Bellefonteisdesignedtostoredischargedusednuclearfuelonsiteinspentfuelpoolsforaminimumoffiveyears

    (theaveragetimeforspentfueltocoolbeforeitcanbeplacedindrycaskstorage)anduptoapproximately15

    yearsdependingonhowquicklythepoolsarefilled.TheBellefontefuelpoolstoragedesignisperhapsthesafestin

    thenation

    as

    the

    independent

    pools

    for

    each

    unit

    are

    protected

    within

    separate

    reinforced

    concrete

    structures

    capableofwithstandingearthquakes,tornadoesandexplosions. Bellefontesusedfuelisexpectedtobestored

    eitheronsiteoroffsiteusingdrycaskstoragetechnologyafteritisremovedfromthespentfuelpool. Drycask

    storageisanestablishedtechnologyinwhichusedfuelisstoredinsteelcanisters.Thismethod,whichreliesonair

    tocooltheusedfuel,canstoreusedfuelformanydecadesifneeded.

    Finaldispositionofusedfuelremainsanunresolvednationalpolicyissue.Thereareseveralsolutionsavailable

    todaybutsustainedpoliticalandpolicysupportforanyofthemhasprovenelusive.Ultimatedisposalforatleasta

    ContainmentDesign

  • 8/2/2019 Bellefonte White Paper

    9/14

    BellefonteUnit1 9

    TennesseeValleyAuthority Bellefonte Unit1Completion

    portionofthespentfuelwillrequireageologicalrepository.Afteryearsofresearchandlicensingpreparation,

    CongresseliminatedfundingforageologicrepositoryatYuccaMountaininNevada.Intheinterim,theNRCand

    others,suchastheMassachusettsInstituteofTechnologyandmostrecentlytheBlueRibbonCommission,which

    wasappointed

    by

    the

    administration

    to

    review

    the

    national

    policy

    on

    used

    fuel,

    have

    concluded

    that

    fuel

    can

    be

    safelystoredindrycasksfor100ormoreyears,thatthereistimetodevelopabettersolutionandthatasolution

    canbeavailablebythetimeneeded.

    TVAandotherscontinuetosupportthereprocessingofspentnuclearfuel,whichallowsmuchoftheremaining

    energyvalueinthefueltobeusedagainandatthesametimereducethevolumeofremainingwasterequiring

    disposal.Manycountries,includingFrance,Russia,Britain,Japan,ChinaandIndia,arealreadyreprocessingspent

    fuelorareinthefinalprocessofitsimplementation.

    Thevolumeofusednuclearfuelthatmustbemanagedisactuallyrelativelysmall.TheNuclearEnergyInstitute

    (NEI)estimates

    the

    total

    volume

    of

    spent

    nuclear

    fuel

    from

    all

    of

    the

    commercial

    reactors

    in

    the

    United

    States

    since

    theindustrybeganinthe1950s(about66,000metrictons)wouldfillonefootballfieldaboutsevenyardsdeep.

    InJuly2011,theBlueRibbonCommissionissueddraftrecommendations,including:

    Aconsentbasedapproachtositinganddevelopingnuclearwastemanagementanddisposalfacilities.

    Aneworganizationtodevelopandimplementaprogramforthetransportation,storageanddisposalofnuclearwaste.ThishasbeenlooselycallFedCorpinsomepreviousdraftlegislationand

    hasbeenmodeledonastructuresimilarinconcepttoTVA.

    AssuredaccesstotheNuclearWasteFundandtoannualnuclearwastefeepayments. Utilitiespay0.1

    cents/kwh

    for

    every

    kwh

    generated

    from

    nuclear

    plants

    into

    this

    fund

    each

    year.

    Promptdevelopmentofoneormorepermanentdeepgeologicalfacilities. Prompteffortstodeveloponeormorecentralinterimstoragefacilities.

    LicensingandLegalIssues

    BellefontesBabcock&Wilcox205pressurizedwaterreactorshaveneverbeenlicensedintheUnitedStates.The

    205referstothe205fuelassembliesinthereactorcore. Four205plantswereordered:BellefonteUnits12,

    WashingtonNuclearUnit1andtheMulheimKarlichplantinGermany.OnlytheGermanplantwasfinished.It

    operatedatahighcapacity(88percent)for13months,19871988,butclosedattheendofitsfirstfuelcycleover

    politicaland

    administrative

    issues.

    TheB&W205isanextgenerationdesignbasedonthesmallerBabcock&Wilcox177designnowusedatseven

    licensednuclearunitsintheUnitedStates.TVAcancitetheexperiencesofthosesimilarplants,whichoperatedat

    over92percentcapacitybetween20042009,andtheGermanplantinitslicenseapplication.

  • 8/2/2019 Bellefonte White Paper

    10/14

    TheageofBellefontesbasefacilitiesisnotexpectedtolimitthe40yearNRClicensingperiod.Bellefonteisthe

    sameageasWattsBarandyoungerthanBrownsFerry,Sequoyahandmostotherreactorsnowoperatingsafely

    andreliablyintheUnitesStates.OfalltheU.S.operatingreactorsthathaveappliedfora20yearextensiontotheir

    original40yearlicense,norequestshavebeendenied.Seventyoneofthecountrys104reactorshavebeen

    grantedanextension,indicatingthatfacilityagewouldnotsignificantlyinfluencethereasonablelifeexpectancyfo

    Bellefonte.

    ApetitionispendingbeforetheU.S.CourtofAppealsinWashington,D.C.,that,ifsuccessful,couldrequireTVAto

    obtainnewconstructionpermitsforBellefonte.TheconstructionpermitforBellefonteUnit1wasissuedin1974

    andhasbeenextendedseveraltimes.AtTVAsrequest,theNRCwithdrewthepermitin2006andthenreinstated

    itatTVAsrequestin2009.PetitionersclaimTVAmustnowapplyforanewconstructionpermit. NRC

    commissionersfoundbya21votepreviouslythattheNRChadauthorityundertheAtomicEnergyActtoreinstate

    Bellefontesoriginalpermits.

    TheexistingconstructionpermitforBellefonteUnit1expiresonOctober1,2011.TVAhasappliedforanextension

    of

    the

    permit

    until

    2020.

    Under

    NRC

    regulations,

    TVAs

    timely

    request

    for

    an

    extension

    allows

    the

    permit

    to

    remainineffectuntiltheNRCcanactontheextension.

    ExperienceatOtherSites

    TVAhasshownwithWattsBarUnit1andBrownsFerryUnit1thatitcansuccessfullycompleteandoperatea

    nuclearreactorafteranextendedidlingordeferral.Lessonslearnedfromtheseexperienceswouldbeappliedto

    BellefonteUnit1.Broadly,theyincludedevelopingtheregulatoryframeworkforlicensing,integratedscheduling,

    projectcontrols, completedengineeringpriortobeginningconstruction,hiringandacultureofcollaboration

    amonganexpectedconstructionworkforceofupto2,800employees.

    Thevalue

    of

    those

    projects

    is

    clear.

    Browns

    Ferry

    Unit

    1,

    which

    returned

    to

    service

    in

    2007

    after

    a$1.9

    billion

    investment,isexpectedtoachievepaybackby2017,evenwhencomparedwithrecentlyreducednaturalgas

    prices.Oncetheprojecthitsitspaybackperiod,BrownsFerryUnit1isexpectedtosavecustomersabout$22

    millionpermonthinavoidednaturalgaspowerpurchases.Overitslifetime(assuminganother30yearsof

    operation)thesavingsfromBrownsFerryUnit1couldamountto$660million.

    Since1997,ayearafterbecomingthelastnewnuclearplanttocomeonlineintheUnitedStates,WattsBarUnit1

    hasoperatedatanaveragecapacityof89percent.TheBrownsFerrystationhasaveraged90percentoverthe

    sameperiod.AndtheSequoyahplanthasoperatedat91percent.TheaveragefortheentireU.S.nuclearindustry

    was87percentduring19972010.

    Currently,TVAsnuclearreactorsrepresentafifthofTVAsgeneratingcapacityyetproduceathirdofTVAs

    electricity.Thisindicatesthevalueofnuclearscontinuous,24/7baseloadcontributiontoTVA.

    ComparingAlternatives

    VariousalternativestoBellefonteUnit1wereconsideredindetailintheBellefonteSupplementalEnvironmental

    ImpactStatementandtheIntegratedResourcePlan.Insummary,forlargebaseloadpowerneedstherearethree

    alternatives:nuclear,naturalgascombinedcycleandcoal.Sometypesofenergyefficiencyimprovementscan

  • 8/2/2019 Bellefonte White Paper

    11/14

    BellefonteUnit1 11

    TennesseeValleyAuthority Bellefonte Unit1Completion

    reducepowerinawaythatoffsetsbaseloadneeds,butEnergyEfficiency/DemandResponseisbetterappliedto

    mediumandpeakingenergyreductions.

    Nucleargenerally

    costs

    more

    to

    build

    but

    less

    to

    operate

    than

    the

    other

    baseload

    energy

    sources

    coal

    and

    naturalgas.Nuclearalsoproducesnocarbonemissions,whichcarryuncertainregulatorycostsinthefuture.A

    combinedcyclegasplantwouldbethenextbestalternativetoBellefonteUnit1.Butcombinedcyclegasplants

    aresubjecttogreaterfuelpricevolatilityand,thoughcleanerthancoal,stillreleasesignificantlymoregreenhouse

    gasemissionsthananuclearplant.Reliabilityofcombinedcyclegasisgood,butnuclearhasproventobebetter.A

    combinedcyclegasplantwouldonlydispatchabout60percentofthetimebasedonforecastedmarketpricesover

    thenext10to15years.TVAsnuclearreactorshavedemonstratedcapacitycloseto90percent.Acombinedcycle

    gasplantmayneedtobereplacedin30years.BellefonteUnit1isexpectedtobeabletooperateforatleast60

    years.

    TVAremains

    interested

    in

    other

    nuclear

    generation

    designs.

    But

    TVA

    determined

    that

    completing

    Bellefonte

    Unit

    1

    offersacostandschedulingadvantageoveranAP1000.TVAestimatesBellefonteUnit1couldbecompletedfor

    about$4.9billionin96to108months.BuildinganAP1000wouldcostabout$6.3billionandrequire110to122

    months.TheAP1000wouldalsobeabout140megawattssmallerthantheuprateddesignplannedforBellefonte

    Unit1.

    SouthernCompanyanditspartnershavesaidthetwoAP1000reactorstheyarebuildingatSouthernsVogtlesite

    nearAugusta,Ga.,willcost$14billion,includinginterest. (Theconsortiumhasreceived$8.3billioninnuclearloan

    guaranteesfromtheU.S.DepartmentofEnergy. TVAisnoteligibleforguaranteesduetoitsstatusasafederal

    agency.)Althoughconstructionhasntbegun,thereareconcernsaboutpotentialscheduledelaysandcost

    increases.In

    aJune

    2011

    report,

    William

    Jacobs,

    anuclear

    engineer

    appointed

    by

    the

    Georgia

    Public

    Service

    CommissiontomonitortheVogtleproject,saidunresolveddesigncertificationissueswiththeAP1000reactorsare

    amongseveralfactorsthatcouldinflatecostsandcreateconstructiondelays.

    MitigationofKeyMarketandRegulatoryRisks

    AsignificantbenefittoBellefonteUnit1isitsabilitytomitigatecertainkeymarketandregulatoryrisks.Risk

    reductionforapowerportfoliothatincludesBellefonteUnit1isprimarilyafunctionof(1)lessexposuretomore

    volatilefossilfuelcosts,aswellas(2)potentialcarbonemissionscoststhatwouldnegativelyimpactpredominantly

    fossilbasedpowerportfolioswithbasicallynomarketinstrumentsforhedging.Asapartofitsintensiveand

    detailedIRP

    process,

    and

    as

    part

    of

    specific

    business

    case

    assessments,

    TVA

    analyzed

    numerous

    risks,

    including:

    LoadgrowthTVAanalyzedtherelativevalueofexpansionatBellefonteevenwhenloadsaredramaticallylowerthanplanned.IntheIRP,nuclearexpansionwasindicatedinmostportfoliosexceptthose

    characterizedbyflattonegativeloadgrowthrates,oftenwithnoCO2regulation.

    NaturalgaspricesNuclearexpansionatBellefonteislowercosteveninscenarioswherenaturalgaspricesarelowerthanTVAsforecast.

  • 8/2/2019 Bellefonte White Paper

    12/14

    CO2regulationIfacostforemittingcarbonisincluded,productioncostsforfossilpowerwillrise,makingnuclearpoweranevenmoreattractivesourceofelectricity.

    ConstructioncostsUndercurrentforecasts,constructioncostswouldneedtoincreasebyapproximately30percentbeforecompletingtheBellefonteunitwouldhavenegativerateimplicationscomparedwiththe

    nextbestalternative.

    Financials

    DeliveringreliableelectricityatthelowestratesfeasibleispartofTVAsstatutoryimperativeundertheTVAAct.

    ThefinancialchallengeforTVAwouldbetocompleteBellefonteUnit1withoutasubstantialrateimpactand

    withoutexceedingTVAs$30billionstatutorydebtlimitsetbyCongress.TVAsfinancialguidingprinciplesassume

    thatcapitalinvestmentswillberecoveredoverthelifetimeoftheassetsandfinancedwithnewdebtratherthan

    revenues,orthroughalternativefinancingthatdoesnotcountagainstthestatutorydebtlimit.Alternative

    financinghasincludedtheuseofsaleleasebacks,prepaymentsofenergybycustomersandotherarrangements.

    TVAcurrentlyhasabout$24billioninbondsoutstanding.

    RateImpact

    AnanalysisperformedaspartofTVAsroutineplanningprocessessupportscompletionofBellefonteUnit1

    overagasalternative(thenextleastcostoption)basedontheimpactonrevenuerequirementsexpressedin

    termsofrates,includingcostrecoveryofcapital,financing,andoperatingandmaintenancecosts.TheTVA

    staffestablishedthathavingBellefonteintheportfolioprovidesforloweraveragerates.Theanalysisalso

    showsthatforthefirstfewyearsoftheBellefonteproject,debt,interestandO&Mcostsaregreaterthanfuel

    andCO2savings.Butby2023,thistrendreversesandratepressuresdecline.

    LongtermtermcostsareimprovedwithBellefontecomparedtootherbaseloadoptionswhenthetotalcosts

    arecompared.ThechartbelowcomparesBellefonteUnit1costsagainstother nuclearalternativesthestillunlicensedAP1000reactorandthemPowerSmallModularReactor(SMR)concept aswellascoaland

    naturalgascombinedcycleastheywouldbeforecastin2020.Thenaturalgascombinedcycleisshownwith

    botha50percentand90percentcapacityfactortoshowthedifferenceincostdependingontheamountof

    productionachieved.Overthenextdecade,TVAmodelsshowthistypeofgenerationmightonlybecalledon

    toproducepower60to70percentofthetimebasedontheincrementalcostofthefuel.Boththecoaland

    thenaturalgascostareshownwiththepotentialimpactofCO2costs.In2020,theCO2costisforecasttobe

    $16/tonrisingto$27/tonlaterthatdecade.Also,shownonthischartisthepotentialrangeforfurthercost

    escalationswiththeAP1000newreactor,basedonreportsfromtheVogtleprojectinGeorgia.

  • 8/2/2019 Bellefonte White Paper

    13/14

    BellefonteUnit1 13

    TennesseeValleyAuthority Bellefonte Unit1Completion

    TotalCost FY2020/kWh

    0

    2

    4

    6

    8

    10

    12

    Bellefonte1&2

    Average2520MWe

    Bellefonte1

    1260MWe

    AP1000

    Single1120MWe

    mPowerSMR

    TwoTwinpacks

    576MWe

    Supercritical

    CoalNoCCS

    NaturalGas

    Comb.Cycle

    $6.50/mmbtu

    cents/kWh

    6.9cents/kWh

    AccountingConsiderations

    InJuly2005,theTVABoardapprovedtheamortizationandinclusionintoratesofTVAs$3.9billioninvestmentin

    thedeferrednucleargenerationunitsatBellefonteNuclearPlantovera10yearrecoveryperiodbeginningin2006.

    Theamountisincludedasacurrentregulatoryassetonthebalancesheet.

    AsoftheendofFY2011,TVAwillhaveamortized$2.3billionoftheregulatoryassetforBellefonte,leaving$1.6

    billiononthebalancesheet.Onebilliondollarsoftheremainingregulatoryassetbalancewillcontinuetobe

    amortizedwhiletheremaining$600millionwillbetransferredtocompletedplantwhentheconstructionis

    finished.Uponcommercialoperation,Bellefontewillbedepreciatedoveritsusefullife.

  • 8/2/2019 Bellefonte White Paper

    14/14

    SupportforNuclearPower

    TVAandnuclearpowerisviewedfavorablybythecommunitiessurroundingitsnuclearplantsaccordingtorecent

    publicopinionsurveys.AlthoughtheBellefontecommunityhasbeensubjecttoarollercoasterrideduetothe

    numerousstartsandstopsofworktocompletetheplantsincethemid1980s,electedofficialsandbusiness

    leadershavesupportedTVAanditseffortstomakeuseoftheexistingfacilities.

    Asurveyofresidentswithinthe10mileradiusofBellefontefindsalargemajoritysupportscompletingtheplant.

    Thesurveyalsofindsfavorableattitudestowardnuclearenergyandthenearestoperatingnuclearpowerplant.

    Thesurveyof300fulltimeresidentslivinginthevicinityoftheBellefontesitewasconductedJune1618,2011.It

    waspartofanationwidepublicopinionsurveythatexcludedresponsesfromhouseholdsinwhichsomeone

    workedatanuclearplant.

    ConcerningBellefonteUnit1completion,86percentfavoritand13percentareopposed.Ofthese,66percent

    stronglyfavorcompletionand8percentstronglyopposeit.Themainreasonsinfavor:jobsandtheeconomy,the

    needforpowerandtoplanforthefuture,andaffordableelectricity.Themainreasonagainst:concernabout

    safety.

    J.D.Powers2011ElectricUtilityResidentialCustomerSatisfactionStudyalsofoundmajoritysupportfornuclear

    energy.Thesurvey,basedonresponsesfrommorethan98,000onlineinterviewsconductedfromJuly2010

    throughMay2011,found57percentofcustomerssupportbuildingnuclearpowerplantsintheUnitedStates.

    AmongthoseawareoftherecentnuclearcrisisinJapan,supportwasevenhigherat60percent.Threeoutoffour

    supportersofnuclearcitedthebenefitofreducingdependenceonforeignoil.Thesurveyfound70percentof

    customerslivingwithin50milesofanuclearplantsupportnuclearenergy.

    Conclusion

    TheBellefonte

    Unit

    1project

    has

    been

    thoroughly

    evaluated

    for

    over

    two

    years

    with

    every

    evaluation,

    including

    theIRP,concludingBellefonteUnit1wouldbethebetterchoiceforcapacitybetween20182020.Thisisanoption

    thatwouldofferfewerairemissions,couldreplaceretiringcoalfiredbaseloadgenerationandwouldhaveminimal

    newenvironmentalimpactsonanexistingsite.Itcouldtakeadvantageofnearly$2billioninunrealizedassetvalue

    atthesite,helptheregionaleconomybycreating2,800constructionjobsand650permanentjobs,andprovidea

    newsourceofreliable,lowcostpowerfortheTennesseeValley.