before the maharashtra electricity …mercindia.org.in/pdf/order 58 42/order-03 of 2015...connection...
TRANSCRIPT
MERC Order in Case No. 3 of 2015 1 of 13
Before the
MAHARASHTRA ELECTRICITY REGULATORY COMMISSION
World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005
Tel. 022 22163964/65/69 Fax 22163976
Email: [email protected] Website: www.mercindia.org.in / www. merc.gov.in
CASE NO. 3 of 2015
In the matter of
Petition of Reliance Infrastructure Ltd. (Distribution) for directions to State Transmission
Utility to release Outlets from Reliance Infrastructure Ltd. (Transmission) and Tata
Power Co. Ltd. (Transmission)
Coram
Shri Azeez M. Khan, Member
Shri Deepak Lad, Member
Reliance Infrastructure Limited (Distribution) ……. Petitioner
V/S
1) State Transmission Utility
2) The Tata Power Company Limited (Transmission)
3) Reliance Infrastructure Limited (Transmission) ......Respondents
Appearance
For the Petitioner : Shri Abhaji Naralkar (RInfra-D)
For the Respondents : 1) Shri R.N.Farkade (STU)
2) Smt. Swati Mehendale (TPC-T)
3) Shri Rakesh Raj (RInfra-T)
Authorized Consumer Representative : Dr. Ashok Pendse, TBIA
ORDER
Dated: 21 December, 2016
M/s Reliance Infrastructure Ltd. (Distribution) (RInfra-D), H Block, 1st Floor, Dhirubhai
Ambani Knowledge City, Navi Mumbai, has filed a Petition on 29 December, 2014 for
directing the State Transmission Utility (STU) to approve and release Outlets from Reliance
Infrastructure Ltd. (Transmission) (RInfra–T) and Tata Power Co. Ltd. (TPC-T), under
MERC Order in Case No. 3 of 2015 2 of 13
Sections 39 (2) (b & c) and 86(1) (c) of the Electricity Act (EA), 2003 and Regulation 36.3
of the MERC (State Grid Code) Regulations, 2006 (‘State Grid Code’).
2. In its Petition, RInfra-D has prayed as follows:
“a) To direct Committee appointed under Chairmanship of STU in Case No. 110 of 2014
to look into outlet requirement of RInfra-D.
b) In the interim to prayer (a) above, direct STU to approve and release 4 nos. of outlets
from TPC-T’s proposed BKC EHV Station (expected to be commissioned shortly) and 2
nos. of outlets from TPC-T’s Hiranandani EHV Station, which are very critical for
release of new loads and reliving of existing network.
c) Direct STU to initiate planning towards one breaker one cable (feeder) concept and
direct Transmission Licensee to implement the same.
d) To pass any other order(s), as the Hon’ble Commission may deem fit and appropriate
under the circumstances of the present case and in the interest of justice;
e) Allow additions / alterations / changes / modifications to the petition if required;
f) Condone any inadvertent omissions / errors / rounding off / differences /
shortcomings.”
3. The Petition states that:
(1) RInfra-D is a Distribution Licensee in the suburbs of Mumbai catering to around 2.8
million consumers. Over the last few years, demand on RInfra-D’s network has
increased substantially. RInfra-D’s network is also used by the Tata Power Company
Ltd. (Distribution) (TPC-D) to supply to change-over consumers. The Non-Coincident
System Peak Demand (NCPD) on RInfra-D’s network from FY 2009-10 to FY 2013-
14 as well as the estimated demand upto FY 2017-18 considering growth of 4 % is as
given below:
S. No. Year NCPD (MVA)
1 2009-10 1648
2 2010-11 1822
3 2011-12 1806
4 2012-13 1908
5 2013-14 1887
6 2014-15 1974
7 2015-16* 2053
8 2016-17* 2135
9 2017-18* 2220
*Considering 4% CAGR for future demand
(2) RInfra-D has registered applications for new connections (including residential and
commercial projects) of more than 1600 MW load across its supply area. These new
loads would slowly realize on the network over the next 5-10 years.
(3) In anticipation of the increasing demand and its obligation to meet the increase in
load, RInfra-D has requested additional Outlets by making applications to the STU as
MERC Order in Case No. 3 of 2015 3 of 13
per the State Grid Code from EHV Stations of the Transmission Licensees, viz.
RInfra-T and TPC-T. Even after several reminders, RInfra-D has not received any
response from either the STU or the Transmission Licensees regarding itst Outlet
requirement.
(4) On 16 May, 2011, RInfra-D made a Connection Application to the STU as per
Regulation 13 of the State Grid Code for release of 35 Outlets from TPC-T.
(5) Pursuant to a meeting with STU on 10 October, 2011, RInfra-D reviewed its
requirement of Outlets from TPC-T to 33, and a letter to that effect was sent to STU
on 13 October, 2011. Vide letter dated 15 December, 2011, the STU forwarded the
Connection Application made by RInfra-D vide letters dated 16 May and 13 October,
2011 to TPC-T for its suggestions/comments and necessary action. RInfra-D has not
received any response from the STU or TPC-T even after almost 3 years.
(6) RInfra-D again made an application on 1 June, 2012 to the STU to release 99 Outlets
(which included 9 Outlets from the list of 33 Outlets requisitioned in October, 2011 as
the area was overlapping) from RInfra-T’s EHV Stations. Vide letter dated 16 June,
2012, the forwarded the Connection Application made by RInfra-D to RInfra-T for its
suggestions/comments and necessary action. RInfra-T released only 14 Outlets and
communicated it to the STU on 10 July, 2012, and forwarded a copy of its letter to
RInfra-D on 11 July, 2012.
(7) The 14 Outlets released by RInfra-T were only sufficient to meet the old pending
requirement of RInfra-D. Based on the STU’s Five Year Transmission Plan for FY
2010-11 to 2014-15, under which TPC-T has planned many EHV Stations in and
around the Mumbai Suburbs, RInfra-D submitted a Connection Application vide its
letter dated 28 November, 2012 for release of 85 Outlets from TPC-T. On 6 March,
2013, a reminder was sent to STU.
(8) In view of the urgency in order to meet its demand, RInfra-D requested STU on 22
November, 2013 to release 21 Outlets, out of 85 Outlets requested, on priority so as to
initiate the work to cater to the applied load of developers. Further reminder was sent
to STU on 19 September, 2014.
No. of
Outlets Saki Borivali BKC Hiranandani Mira
21 3 2 9 4 3
(9) On 17 February, 2014, RInfra-D requested STU to allocate 28 Outlets from the 220
kV Nagri Niwara/Film City EHV Station. RInfra-D also reminded the STU to release
85 Outlets as per its application dated 21 December, 2013. As against the Outlet
requirement requests of RInfra-D, only 14 outlets have been released so far from
RInfra-T.
MERC Order in Case No. 3 of 2015 4 of 13
(10) Out of the all the requisitioned Outlets, 4 Outlets from TPC-T’s proposed Bandra-
Kurla Complex (BKC) EHV Station (expected to be commissioned shortly) and 2
Outlets from its Hiranandani EHV Station have become extremely critical, not only
for releasing new loads but also for relieving the existing stressed network which is
likely to impact reliability in the concerned areas.
(11) The Committee under the Chairmanship of STU appointed in Case No. 110 of 2014
may be asked to look into the requirement of Outlets of R-Infra-D. The Commission
may also direct the STU to approve and release 4 Outlets from TPC-T’s proposed
BKC EHV Station (expected to be commissioned shortly) and 2 Outlets from its
Hiranandani EHV Station.
(12) There are many breakers of TPC-T or RInfra-T where more than one cable/feeder of
RInfra-D is connected, and a fault on any one of these cable/feeders interrupts the area
fed by both the cables/feeders. This can be avoided if the STU follows the principle of
one breaker-one Outlet/cable/feeder, as suggested by Dr Khaparde of IIT-Bombay in
his Report of July, 2006.
4. In its Reply dated 20 May, 2015, the STU stated that:
(1) RInfra-D has submitted its requirement of Outlets from RInfra-T and TPC-T as
follows:-
a) 35 Outlets from TPC-T on 16 May, 2011
b) Revised 33 Outlets from TPC-T on 13 October, 2011
c) 99 Outlets from RInfra–T (including 9 Outlets from the above requirement) on 1
June, 2012, considering load demand up to FY 2017-18
d) Fresh requirement of 85 Outlets from TPC-T on 22 November, 2012
e) Urgent requirement of 21 Outlets from TPC-T on 22 November, 2013
f) Reminder to STU for the above 21 Outlets from TPC-T on 19 September, 2014
g) 28 Outlets from 220 kV Nagri Niwara/ Film City sub-Station
(2) After receipt of the requirements, a meeting was held with RInfra-D and the
requirement of Outlets was forwarded to RInfra-T and TPC-T. In response, RInfra-T
has released 14 Outlets from its existing sub-Stations and committed to release the
remaining 85 Outlets from its proposed sub-Stations likely to be commissioned during
FY 2015-16 to FY 2017-18.
(3) The requirement of various Outlets by RInfra-D spanned over a period of 9 years, i.e
from 2009-10 to 2017-18. Some of its requirements were from existing sub-Stations
and others from proposed EHV sub Stations of both RInfra-T and TPC-T.
(4) TPC-T has released 2 Outlets from its Hiranandani sub-Station and approved 4
Outlets from its BKC sub Station which is to be commissioned in near future.
(5) As per the STU Plan, the following two EHV sub-Stations of TPC-T are planned in
FY 2014-15 :-
MERC Order in Case No. 3 of 2015 5 of 13
S.No. Sub-Station Status
1 110 kV HDIL Kurla The tendering of civil works is in progress.
The delay is due to various NOCs required
from different departments
2 110 kV BKC 90 % works are completed and sub-Station
can be commissioned within few months
(6) The comments of TPC-T regarding release of Outlets from its sub-Stations are set out
below:-
Sr.No. TPC Sub-
Station
DSS No of
Outlets
required
Remarks
1 Borivali Gokuldam 2 Bays are not available
2 BKC Godrej/
Tulsiani/Makers/
Chandivali
SRA/Motilal
Nagar/MMRDA/Godr
ej/ Shivalik
9 Presently
commissioning of
BKC R/S is delayed
and Outlets will be
allotted after shifting
of existing TPC-D
feeders from old DSS
3 Mira Saduru/Kalpataru/Rav
i Mhada/Vinamara
3 220 kv Mira Road R/s
not yet commissioned
4 Saki ESIS hospital 3 RInfra-D may explore
taking load from
220kV/ 33kV Saki R/s
of R-Infra-D
5 Vikroli Mhada Kannamwar/
Kalpataru/Aura
2 Bays not available
(7) As per the STU Plan, the 220 kV Nagri Niwara sub-Station was to be constructed and
commissioned by RInfra-T but, due to non-availability of land, the work is not taken
up by RInfra-T.
(8) Looking to the requirement of 28 Outlets by R-Infra-D, STU has made efforts and
identified the land in coordination with Maharashtra State Electricity Distribution Co.
Ltd (MSEDCL) to establish an EHV sub-Station in Goregaon Film City area as an
alternative solution for the 220 kV Nagri–Niwara sub-Station. The proposal is also
included in the STU Plan and is under consideration of Maharashtra State Electricity
Transmission Co. Ltd. (MSETCL).
(9) The following EHV Sub-Stations of RInfra-T and TPC-T are planned, as per the STU
Plan:-
RINFRA-T PROJECTS
Sr.No. Projects Year Outlets
MERC Order in Case No. 3 of 2015 6 of 13
TPC-T PROJECTS
AugmentationProjects
From the above sub-Stations, the requirement of RInfra-D can be met in the
future.
(10) As regards the request of RInfra-D of one breaker - one cable arrangement for all
feeders in the Mumbai distribution system, a study has been carried out by the Prof.
S.A. Khaparde (IIT Bombay) Committee. Its final Report of July, 2006, on
developing criteria for allotting additional distribution Outlets stated that all the
Receiving sub-Stations (RSS) of TPC-T are space-constrained and it is difficult to
arrange for a new circuit breaker for every Outlet. Hence, it is not possible to arrange
a separate breaker for each Outlet.
5. In its Reply dated 28 October, 2015, TPC-T has stated that:
(1) TPC-T has no objection to the request of RInfra-D that the Committee under the
Chairmanship of the Chief Engineer (STU) in Case No. 110 of 2014 be asked to look
into the Outlets requirement of RInfra-D.
(2) Since 2011-12, 56 Outlets have been provided to cater to around 880 MVA load of
RInfra-D, which is 45% of the total load catered to by it. 5 Outlets have been provided
to RInfra-D as recently as FY 2014-15 and FY 2015-16.
(3) On the request of RInfra-D for 21 Outlets, a meeting between RInfra-D and TPC-T
was held on 2 February, 2015, and TPC-T provided its response to STU and RInfra-D
on 11 March, 2015.
1 220kV BKC Golibar 2016-17 39 Outlets
2 220kV Airport 2018-19 26 Outlets
3 220kv dahisar housing 2018-19 39 Outlets
Sr.No. Projects Year Outlets
1 110kV HDIL-Kurla 2014-15 23 Outlets
2 110 kv BKC 2014-15 25 Outlets
3 400 kV Vikroli 2015-16 23 Outlets
4 110 kv Chembur tapping 2016-17 24 Outlets
5 400 kV Marvey ( Malad) 2018-19 23 Outlets
6 220 kV DahisaR (East) 2018-19 23 Outlets
7 220 kV Vikroli (West) 2018-19 23 Outlets
8 220 kv Mira Road (West) 2018-19 23 Outlets
Sr.No. Sub-Stations Capacity Year Outlets
1 110kV BKC 1X125 MVA 2016-17 13 Outlets
2 110 kV Powai 2X90 MVA 2017-18 11 Outlets
3 220 kV Saki 1X125 MVA 2018-19 12 Outlets
MERC Order in Case No. 3 of 2015 7 of 13
(4) As an interim arrangement, RInfra-D requested 4 Outlets from the BKC RSS of
TPC–T and 2 Outlets from Hiranandani Powai of TPC-T as they are critical for
release of new loads and relieving of the existing distribution network.
(5) TPC-T has released 2 Outlets from Hiranandani Powai to RInfra-D in March, 2015.
However, in spite of the criticality cited by RInfra-D, there seems to be no action at
the ground level for connecting cables and initiating power supply from these Outlets.
TPC-T will be in position to provide Outlets from BKC after June, 2016.
(6) There is severe space constraint at various Receiving Stations of TPC-T. Hence, it
may not be practically possible to implement the one Outlet - one cable connection
concept in its area of operation unless significant capital expenditure is incurred,
which will require the approval of the Commission.
(7) With respect to discrimination between Distribution Utilities with TPC-D on
provisions of back-to-back feeders, TPC-T has also provided back-to-back feeders to
Brihanmumbai Electric Supply and Transport Undertaking (BEST) and TPC-D. Back-
to-back feeders for TPC-D may be less as compared to R-Infra-D.
6. At the hearing held on 29 October, 2015, the parties were informed of the Commission’s
decision to constitute a two-Member Bench to hear and decide this Case. RInfra-D set
out its request for Outlets from RInfra-T and TPC-T as follows:-
Sr.No
.
Transmission
Licensee
Total Outlets
requested
Outlets
released
Balance required
Outlets
1 R-Infra-T 99 14 85
2 TPC-T 33 2 31
In view of the urgency for meeting its demand, RInfra-D had requested STU to release
21 Outlets (out of the total sought) on priority, and this was followed by a reminder.
TPC-T stated that it has already released 2 Outlets from its Hiranandani sub-Station in
March, 2015 and would provide 4 more Outlets from its BKC sub-Station as soon as it is
ready. The Commission directed RInfra-D to submit the status and break-up of all
required Outlets from existing and upcoming sub-Stations from RInfra-T and TPC-T
along with the priority and the quantum of load expected in the near future. The
Commission asked all the concerned Utilities to meet with the STU within a week, sort
out their Outlets requirements for the immediate future and jointly finalise the issues
through discussion. The parties should file their submissions within two weeks from the
meeting.
7. In its additional submission dated 10 March, 2016, the STU stated that:
(1) As per the directives of the Commission vide Daily Order dated 29 October, 2015,
STU has submitted its Report to the Commission. The summary is as below:-
(i) CE (STU) conducted five meetings with TPC-D, R-Infra-D, TPC-T and BEST
from 16 November, 2015 to 16 February, 2016 for joint discussion with all
MERC Order in Case No. 3 of 2015 8 of 13
concerned to arrive at amicable solutions.
(ii) After detailed deliberations with all Distribution and Transmission Licensees,
the feeder Outlets are allocated as per the requirement of the Distribution
Utilities i) for immediate need, i.e. up to 2017-18 and ii) for future need, i.e.
from 2017-18 onwards.
(2) The 21 priority Outlets requested by RInfra-D till 2017-18 are as below:-
Sr.
No.
Outlet requested
(EHV Sub-Station)
No. of
Outlets
Outlet Allotted
(EHV Sub-
Station)
Final allocation
1 TPC BKC 10 TPC BKC
TPC HDIL
Kurla
6 - TPC BKC
4 - TPC HDIL Kurla
2 TPC Borivali 02 RInfra-T
Borivali
2 - RInfra-T Borivali
3 TPC
Hiranandani
02 TPC
Hiranandani
2 - TPC Hiranandani
4 TPC Mira
(Prop)
03 RInfra-T
Ghodbundar
3 - RInfra-T
Ghodbundar 5 TPC Saki 02 TPC Saki 2 - TPC Saki
6 TPC Vikhroli 02 TPC Vikhroli
1 Outlet allotted. 1Outlet
after
commissioning of
400 kV TPC
Vikhroli sub-
Station
Total 21 21
(3) The priority Outlets requested by TPC-D till FY 2017-18 are set out below:-
Sr.
No.
Outlet requested
(EHV Sub-
Station) n)
No. of
Outlets
Outlet Allotted
(EHV Sub-Station
)
Final allocation
1 RInfra-T Aarey 4 RInfra-T Aarey 4 – RInfra-T Aarey
2 RInfra-T Saki 2 RInfra-T Saki 2 - RInfra-T Saki 3 TPC Saki 5 TPC Saki 5 – TPC Saki 4 RInfra-T
Goregaon
2 RInfra-T
Goregaon
2 - RInfra-T
Goregaon 5 RInfra-T
Chembur
4 RInfra-T
Chembur
4 - RInfra-T Chembur
6 RInfra-T
Versova
2 RInfra-T Versova 2 – RInfra-T Versova
7 TPC Powai 9 TPC Powai 9 – TPC Powai 8 TPC Carnac 6 TPC Carnac 6 – TPC Carnac 9 TPC Mahalaxmi 6 TPC Mahalaxmi 6 - TPC Mahalaxmi 10 TPC Parel 6 TPC Mahalaxmi 6 – TPC Parel 11 TPC Chembur 4 TPC Chembur 4 – TPC Chembur 12 TPC HDIL
Kurla
4 TPC HDIL Kurla 4 – TPC HDIL Kurla
13 TPC Antop Hill 2 TPC Antop Hill 2 – TPC Antop Hill 14 TPC BKC 8 TPC BKC 8 – TPC BKC
Total 64 64
MERC Order in Case No. 3 of 2015 9 of 13
(4) The Outlets requested by RInfra-D for future needs, i.e from 2017-18 onwards, are
as as tabulated below:
(5) The Outlets requested by TPC-D for future needs from 2017-18 onwards is as
tabulated below
Sr.
No.
EHV Sub-Station Commissioning
Schedule
Outlets
allotted
Remark
1 RInfra-T
Golibar/TPC
HDIL Kurla
2018-19 10 To be reviewed in STU
rolling plan
2 RInfra-T Malad 2020-21 04 To be reviewed in STU
rolling plan
3 TPC Antop Hill 2018-19 08 To be reviewed in STU
rolling plan
4 TPC Chunabhatti 2018-19 05 To be reviewed in STU
rolling plan
5 RInfra-T
Saki/TPC Sahar
Commissioned 04 To be reviewed in STU
rolling plan
Total 31
(6) The priority Outlets requirement of BEST till 2017-18 is as below:-
Sr.
No.
Outlet requested
(EHV Substn)
No. of
Outlets
Outlet Allotted
(EHV Substn)
Final allocation
1 TPC Mahalaxmi 05 TPC Mahalaxmi 5 – TPC Mahalaxmi
2 TPC Parel 02 TPC Parel 2 – TPC Parel 3 TPC Carnac 02 TPC Carnac 2 – TPC Carnac
Tota
l
09 09
Sr.
No.
EHV Sub-
Station
Commissionin
g
Schedule
Outlets
allotted
Remark
1 RInfra Golibar 2018-19 04 To be reviewed in STU
rolling plan 2 RInfra Borivali Commissioned 06 Additional bus section to be
added - To be reviewed in
STU rolling plan 3 Goregaon Film
city
2019-20 10 To be reviewed in STU
rolling plan 4 TPC Chunabhatti 2018-19 05 To be reviewed in STU
rolling plan 5 TPC
Malad/RInfra
Goregaon
Commissioned 09 AIS to GIS conversion - To
be reviewed in STU
rolling plan 6 400kV TPC
Vikhroli
2019-20 05 To be reviewed in STU
rolling plan 7 RInfra Dahisar 2019-20 10 To be reviewed in STU
rolling plan 8 TPC Sahar Commissioned 05 Additional bus section to be
added - To be reviewed in
STU rolling plan 9 220kV TPC
Versova
2018-19 10 To be reviewed in STU
rolling plan Total 64
MERC Order in Case No. 3 of 2015 10 of 13
TPC-T has agreed to the above Outlets requirement of BEST.
8. In its additional submission dated 24 September, 2016, RInfra-D stated that:
(1) As directed by the Commission, CE (STU) discussed with all the Mumbai
Distribution Utilities for a holistic view and clarity on Outlets allocation and to devise
the process for future allocation of Outlets.
(2) After detailed consultations with all the parties, the STU bifurcated the Outlet
requirement into two phases, i.e. priority requirement till FY2017-18, and balance
requirement to be addressed in FY 2017-18 as per the requirements stated by the
Distribution Licensees.
(3) As per the STU Report, RInfra-D was allotted 21 Outlets on priority, i.e. 16 from
TPC-T and 5 from RInfra-T, upto FY2017-18. Further, STU has in principle allotted
64 Outlets required post FY 2017-18 and stated that this would be reviewed in the
STU Annual Plan.
9. In its additional submission dated 26 September 2016, TPC-T stated that:
(1) On 16 May, 2011, RInfra-D made a request for 35 Outlets from TPC-T, which was
revised on 23 October, 2011 to 33 Outlets. Vide letter dated 15 December, 2011, the
STU forwarded the connection application made by RInfra-D to TPC-T. TPC-T has
not responded to the STU letter by oversight, and there were no reminders from STU.
(2) RInfra-D applied for 99 Outlets to RInfra-T, in which it indicated a requirement of 9
out of the 33 Outlets applied for from TPC-T. Subsequently, RInfra-D also made an
application for 85 Outlets from TPC-T on 28 November, 2012. This was reduced to
21 Outlets by a revised application to STU dated 22 November, 2013.
(3) TPC-T has not received any communication from STU either for the requirement of
85 Outlets or for the revised requirement of 21 Outlets. TPC-T received a
communication from STU for 21 Outlets only on 2 December, 2014. Subsequently, a
meeting was held between RInfra-D and TPC-T on 2 February, 2015 regarding the
requirement of Outlets. TPC-T has provided 8 Outlets to RInfra-D during the period
from FY 2010-11 to FY 2014-15.
(4) CE (STU) conducted meetings from November, 2015 to February, 2016 with
Distribution and Transmission Licensees in the Mumbai area to understand the
requirements of 22/33 kV Outlets from RInfra-D and TPC-D and to finalize the
allocation of required 22/33 kV Outlets.
(5) On 23 February, 2016, the STU shared its draft Report on the Outlets allocation as per
the requirements of all Distribution Utilities with TPC-D. Thereafter, vide letters
dated 23 June and 3 August, 2016 to TPC-D and RInfra-D, the STU provided the final
allocation of Outlets to these Distribution Utilities from TPC-T and RInfra-T.
MERC Order in Case No. 3 of 2015 11 of 13
(6) TPC-T is in agreement with the allocation of Outlets to RInfra-D, TPC-D and BEST
as agreed upon during the meetings with STU along with the concerned Utilities, and
that allocation has been reflected in the draft Report.
(7) Since the final Report has not been provided to TPC-T, it is in agreement with the
same presuming that the final Report reflects the same allocation as agreed upon in
the meetings held by the STU with the Utilities.
(8) Nothing survives in the present Petition as the Outlets allocation has been finalized by
the STU and the parties have mutually agreed to comply with it. The Commission
may dispose of the Petition accordingly.
10. At the hearing held on 27 September, 2016, RInfra-D stated that, as per its Report, the
STU has allotted 21 Outlets to RInfra-D on priority, i.e. 16 from TPC-T and 5 from
RInfra-T. 5 Outlets were released by RInfra-T, and these have been charged by RInfra-D.
Out of 16 Outlets required from TPC-T, 3 Outlets were released and have been charged
by RInfra-D. 5 Outlets from Vikhroli and HDIL sub-Stations of TPC-T are pending as
the sub-Stations are yet to be commissioned. Out of the remaining 8 Outlets, RInfra-D
has forwarded the Connection Agreement to TPC-T on 3 September, 2016 for 6 Outlets
from BKC sub-Station. For 2 Outlets from Saki sub-Station, TPC-T has not provided
switch/feeder numbers. After receipt of the switch/feeder numbers, RInfra-D would
forward the Connection Agreement to TPC-T for these 2 Outlets within a week. TPC-T
stated that it has received the Connection Agreement from RInfra-T for 6 Outlets from
BKC sub-Station in September, 2016 and will sign it within two weeks and communicate
it to R-Infra-D. It will provide switch/feeder numbers for 2 Outlets from Saki sub-Station
to RInfra-D within 10 days and sign the Connection Agreement for these Outlets within a
week of its receipt. The Commission enquired about the installation and commissioning
status of HDIL and Vikhroli sub-Stations. TPC-T replied that it will commission the
HDIL sub-Station by March, 2018 and the Vikhroli sub-Station by FY 2019-20. The
STU stated that, as per directives of the Commission vide Daily Order dated 29 October,
2015, it has submitted its Report for allocation of Outlets. STU will review the Outlets
requirements for FY 2017-18 onwards yearly. The Commission expressed that the STU
should play a more pro-active role with regard to the allocation of Outlets by Distribution
Licensee and monitor the status, instead of such matters having to be brought before the
Commission.
11. In its further submission dated 13 October, 2016, TPC-T stated that:
(1) In compliance to the Daily Order dated 27 September, 2016, TPC-T has signed the
Connection Agreement on 12 October, 2016 for RInfra-T’s 6 Outlets from BKC sub-
Station.
(2) TPC-T has also provided the switch numbers for 2 Outlets from TPC-T’s Saki
Receiving Station to RInfra-T vide e-mail dated 12 October, 2016.
MERC Order in Case No. 3 of 2015 12 of 13
Commission’s Analysis and Ruling
12. RInfra-D has filed the present Petition as it did not receive any response from the
STU to its applications for Distribution Outlets from the EHV sub-Stations of TPC-
T and RInfra-T. The initial applications were followed by several reminders.
RInfra-D has submitted the details of Outlets required by it from 2011 onwards, as
summarized in the following Table:
S.No. Transmission
Licensee
Outlets
requested
Outlets
released
Balance required
Outlets
1 RInfra-T 99 14 85
2 TPC-T 33 2 31
Out of the above remaining 116 Outlets required, RInfra-D has sought release of 21
Outlets on priority for meeting its immediate demand requirements.
13. As directed by the Commission during these proceedings, the STU held meetings
with the Distribution and Transmission Utilities and submitted its Report on the
Outlets requirements of RInfra-D as well as the other Mumbai Distribution
Licensees, BEST and TPC-D. The Report separately identifies the immediate
requirements and allocations upto FY 2017-18, and the future dispensation beyond
FY 2017-18 which it would review annually. The details are set out at para. 7 of this
Order, and are also summarized below.
14. As per the Report, the STU has allocated 21 Outlets to R-Infra-D on priority till
FY2017-18 as follows:-
- 5 Outlets from RInfra-T
- 16 Outlets from TPC-T
The 5 Outlets released to RInfra-D from RInfra-T as above have been charged. Out
of 16 Outlets from TPC-T,
- 3 Outlets have been charged by RInfra-D.
- 5 Outlets from the HDIL and Vikhroli sub-Stations of TPC-T are pending as
these sub-Stations will be commissioned by March, 2018 and FY 2019-20,
respectively.
- As regards the remaining 8 Outlets (6 from BKC and 2 from Saki),
Connection Agreements for 6 Outlets have been signed and switch numbers
for 2 Outlets have been provided. This has been confirmed by TPC-T vide
letter dated 13 October, 2016.
The STU has also allotted, in principle, 64 Outlets sought by RInfra-D to cater to
future demand from FY 2017-18 onwards from various ongoing EHV sub-Stations
of TPC-T and RInfra-T. These Outlets allocations will be subject to review in the
STU Annual Plans.
15. For TPC-D, the STU has allocated 64 Outlets on priority till FY 2017-18, and 31
Outlets for future needs from FY 2017-18 onwards from various ongoing EHV sub-
MERC Order in Case No. 3 of 2015 13 of 13
Stations of TPC-T and RInfra-T. These future Outlets allocations will also be
subject to review in the STU Annual Plans.
16. As sought by BEST, the STU has allocated 9 Outlets to it from TPC-T till FY 2017-
18. The Report states that BEST’s requirements for FY 2017-18 onwards will be
considered while preparing the STU Rolling Plan.
17. While the Outlets requirements raised by RInfra-D in this Petition have been
resolved by the STU as set out above, along with the immediate and near-future
requirements of the other Mumbai Distribution Licensees, the Commission’s
intervention would not have been necessary had the STU properly discharged its
functions under the State Grid Code. Regulation 13.5 of the State Grid Code
expects the STU to decide on connection applications within a month of their
receipt, during which time the STU would consider the responses of the other
concerned Utilities. Under Regulation 36.1, the STU has to monitor the compliance
of the provisions relating to connections. Thus, it is also incumbent on the STU to
follow up the timely finalization of Connection Agreements. The Commission
expects that the STU will discharge its functions in this regard diligently henceforth,
so that it needs to be approached only as a last resort.
18. Regulation 8.2 of the State Grid Code requires the 5-year Transmission System
Plan to be updated and published by the STU by the 30th
of September each year.
The Commission notes that this is also delayed, and directs the STU to finalise the
updated Plan expeditiously so that the road-map is clear to all the concerned
Utilities and uncertainties and disputes are minimized.
19. As regards RInfra-D’s plea for one breaker - one cable arrangements for all feeders
in the Mumbai Distribution System, the Commission notes that the earlier Report
of the Committee chaired by Prof. S.A. Khaparde (IIT-Bombay) on developing
criteria for allotting additional distribution Outlets concluded that the existing
Receiving sub-Stations of TPC-T are space-constrained and that it would be
difficult to provide for a new circuit breaker for every Outlet. However, the Utilities
may explore the feasibility of any technological alternatives that may become
available. Moreover, the Commission expects the STU and the Utilities to
coordinate the planning and execution of future sub-Stations such that the one
breaker - one Outlet concept becomes the norm.
The Petition of M/s Reliance Infrastructure Ltd. (Distribution) in Case No. 3 of 2015
stands disposed of accordingly.
Sd/- Sd/-
(Deepak Lad) (Azeez M. Khan)
Member Member