before the haryana electricity regulatory … · 2015-11-16 · respondent nigam to withdraw the...
TRANSCRIPT
1 | P a g e
BEFORE THE HARYANA ELECTRICITY REGULATORY COMMISSION AT PANCHKULA
Case No. HERC/PRO-17 of 2015
Date of Hearing: 10.08.2015 & 6.10.2015 Date of Order: 10.11.2015 In the Matter of Petition under Section 42(4) of the Electricity Act, 2003 read with Regulation 22 of the
Haryana Electricity Regulatory Commission (Terms and conditions for grant of
Connectivity and Open Access for Intra-State Transmission and Distribution System)
Regulations, 2012 seeking withdrawal of Sales Circular No. D-20/2015 dated
6.07.2015 issued by DHBVNL for levy of Additional Surcharge for the FY 2015-16.
And in the Matter of
Suo motu Order dated 26.04.2012 passed by the HERC in the matter of seeking
review / clarifications on various issues by the Power Utilities and other stakeholders
through ordinary letters / emails etc.
Petitioner
M/s Jindal Stainless Limited, Hisar.
Respondents
1. Dakshin Haryana Bijli Vitran Nigam Limited (DHBVNL), Hisar
2. Uttar Haryana Bijli Vitran Nigam (UHBVNL), Panchkula.
Present on behalf of the Petitioner
Shri R.K. Jain, Adviser, JSL Shri R.P. Jindal, ED, JSL, Hisar
Present on behalf of the Respondents
Shri Varun Pathak, Advocate Shri Raghujeet S. Madan & Sonia Madan, Advocates Shri Atul Pasrija, XEN, DHBVNL Shri R.K. Jain, GM/RA, UHBVNL
2 | P a g e
Shri Nirmal Singh, AE/RA, UHBVNL Shri Amit Singh, SDO, DHBVNL
Quorum
Shri Jagjeet Singh, Chairman
Shri M.S Puri, Member
ORDER
Brief Background of the Case
1. The Haryana Electricity Regulatory Commission had issued Order dated 29.05.2014
determining ARR / Tariffs for Distribution and Retail Supply for the FY 2014-15. In the
said Order Additional Surcharge to be paid by the Open Access Consumers in the FY
2014-15 was also determined. At Para 5.3 of the said Order the Commission had
observed as under:-
“The Commission observes that the distribution licensees, based on the
data provided by them for the period April 2013 to March 2014, have been
able to conclusively prove, backed with calculations, that their long term
power purchase commitments do get stranded most of the times when
power is drawn by embedded open access consumers from other sources
and the Discoms have to bear the fixed cost of such stranded power which
ultimately get passed on to other consumers. They have worked out the
cost of such stranded power and based on that has worked out the
additional surcharge as 97 paise / unit for FY 2013-14. The Commission
further observes that it would not be fair if the cost incurred by
distribution licensees for the power purchase commitments stranded on
account of power drawn by open access consumers from other sources is
passed on to other consumers as that would amount to cross-subsidising of
the open access consumers by other consumers. It would also be fair to
assume that, as the number of open access consumers and power drawn
through open access is increasing every year, the additional surcharge
worked on similar basis for FY2014-15 would not work out less than as has
been worked out by UHBVNL for FY 2013-14. The Commission, therefore,
after careful consideration of the submissions made in the petition by
UHBVNL, replies / comments furnished by various stakeholders in reply to
3 | P a g e
the petition, the comments / submissions by the petitioners and other
stakeholders made during the hearing held on 27.05.2014 and the relevant
statutory provisions is of the considered view that the additional
surcharge cannot be attributed to the entire energy drawn through Open
Access as the Discoms are expected to take into consideration some
quantum of power that would be drawn by the Open Access Consumers
based on the past trend while undertaking demand assessment and load
management. The Commission therefore considers it appropriate to pass
on 50% of the stranded cost worked out by the Discoms on account of
power drawn through Open Access. Such reduction is necessary in view of
the fact that the Discoms charges from most of the Open Access consumer
a part of the cost of distribution system and cost of 6% losses as wheeling
charges. Further the Discoms also collect, from most Open Access
consumers, demand charges on the basis of the connected load / contract
demand. Hence in the considered view of the Commission some adjustment
of the demand charges paid by the Open Access consumers in the stranded
fixed cost of the Discoms has to be made. HERC Order on ARR & Tariff of
UHBVNL & DHBVNL for D&RS business under MYT framework for the
control period FY2014-15 to the FY 2016-17.
In view of the above disposition the Commission has now decided to levy
additional surcharge on the energy drawn by open access consumers
through open access @ 50 Paisa/kWh with effect from the date of this
Tariff Order. The additional surcharge shall be levied / recovered by the
distribution licensees from open access consumers as provided in
regulation 22 of the Haryana Electricity Regulatory Commission (Terms
and Conditions for grant of connectivity and open access for intra-State
transmission and distribution system) Regulations, 2012”.
2. The Petitioner M/s Jindal Stainless Limited (JSL) in the present Affidavit dated
18.07.2015 has submitted as under:-
That JSL is a large supply Industrial Consumers of the Respondent Nigam
(DHBVNL) having a sanctioned contract demand of 125 MVA and is getting power supply
4 | P a g e
on 220 kV through an independent feeder. Further, they avail Inter-State and Intra-State
Open Access to wheel its Captive Power from Odisha as well as power purchased from
Indian Energy Exchange (IEX) through collective transaction.
That, the Commission, in its Order dated 29th May, 2014 (the relevant paragraph
has been cited at Point No. 1 of this Order) has recorded that the data supplied by the
Discoms regarding stranded power related to the FY 2013-14 and the Additional
Surcharge determined is applicable for the FY 2014-15 so as to pass on 50% of the
stranded cost estimated by the Discoms on account of power drawn through Open Access
w.e.f. 29.05.2014. Further, it has been recorded that the Discoms are already charging a
part of the cost of distribution system and cost of 6% losses as wheeling from most of the
Open Access consumers.
That while considering the ARR / Tariff for the FY 2015-16, the Commission did
not determine the Additional Surcharge to be levied in the FY 2015-16 and observed as
under:-
“The Discoms have filed the petition along with the supporting details on
04.03.2015 vide memo no. Ch-12/GM/RA/N/F-15/Vol-III dated 04.03.2015
wherein the Discoms , based on the fixed cost paid by them for the stranded
capacity due to scheduling of Open Access power by the embedded Open
Access consumers, have proposed an additional surcharge of Rs. 0.80 per unit
to be paid by such consumers. As the proposed levy of additional surcharge
shall affect a large number of electricity consumers, the Commission has
considered it appropriate to hold a public hearing before finalising the same.
Accordingly, the Commission shall schedule a hearing of the stakeholders and
other interested persons and after hearing their objections / comments as
well as the reply of the Petitioners thereto, shall pass an appropriate Order in
the matter”.
That subsequent to the above, the Commission initiated the proceedings to
determine Additional Surcharge to be applicable for the FY 2015-16 and scheduled a
hearing on 9.07.2015. The hearing was deferred as the supporting data furnished by the
Discoms was found incomplete and not in the required format. Thus, for all intents and
5 | P a g e
purposes, the determinant of Additional Surcharge to be levied in the FY 2015-16 is still
undecided.
That on a clarification sought by the Faridabad Industries Association (FIA) vide
its letter dated 12.05.2015, the Commission, vide its Memo No. HERC/Tariff/Dir/719
dated 5/8.06.2015 addressed to the FIA, conveyed as under:-
“As the proposed levy of additional surcharge shall affect large number of
electricity consumers the Commission has considered it appropriate to hold a
public hearing before finalizing the same.
In view of the above, it is clarified that till the additional surcharge @ 50 Paise
/ Unit as decided by the Commission in its Order dated 29th May, 2014 is
revised or amended the same shall continue to be applicable”.
That in pursuance to the clarification (supra) the Respondent Nigam issued Sales
Circular No. 20/2015 dated 6.07.20915 (sic) conveying the clarification given by the
Commission.
That the Petitioner is aggrieved on the following grounds:-
The levy of Additional Surcharge is decided on the basis of data regarding
‘stranded power’ due to purchase of power from outside by the open access consumers
and is to be levied in the subsequent year. As the same is not a perpetual levy, its
applicability in the next year is purely an ad-hoc action and against the relevant laws and
Regulations. Hence, there cannot be an ad-hoc levy of Additional Surcharge before the
conclusion of the public hearing in the matter. Further, the Proviso to Regulation 22(3) of
the HERC Open Access Regulations, 2012 stipulates that any additional surcharge so
determined shall be applicable to all the Open Access consumers availing Open Access
from the date of determination of the same by the Commission. Therefore, till such time
the Commission determines the additional surcharge to be levied in the FY 2015-16, no
ad-hoc levy could be made effective.
That the issue of such clarification without holding public hearing is contrary to
the Hon’ble APTEL’s judgment dated 14.11.2013 in the Appeal No. 231 of 2012
6 | P a g e
(JSL Vs DHBVN) wherein the Hon’ble APTEL had considered issuance of a similar
clarification by the HERC vide Memo No. HERC/Dir (Tariff) / ARR -11-12/1325-26 dated
28.07.2011 and held that the same was against the principles of natural justice and
accordingly the Commission’s Order to that extent was set aside.
That even this Commission had taken note of the matter of issuance of
clarifications on simple letters from Utility / Stakeholders and passed an Order dated
26.04.2012 that the Commission shall not respond to any such application / pleading
from the power utilities / stakeholders which are not filed in accordance with the laid
down procedure. Hence, the issuance of the impugned clarification vide letter dated
5/8.06.2015 is not only violation of the Hon’ble APTEL’s judgment in Appeal No. 231 of
2012 dated 14.11.2012 but also in violation of the Commission’s own Order dated
26.04.2012.
In view of the above the Petitioner has prayed as under:-
1. The clarification given by the office of the Commission vide letter dated 5/8.06.2015 may kindly be held in abeyance / withdrawn till such time a final Order is passed by the Commission on the determination of Additional Surcharge for the year 2015-16.
2. The impugned Sales Circular No. 20/2015 dated 6.07.2015 issued by the Respondent Nigam may kindly be quashed and necessary directions given to the Respondent Nigam to withdraw the above Circular from the date of issue.
3. The Respondent Nigam may kindly be directed to immediately refund the amount charged by way of additional surcharge w.e.f. 1.04.2015 till the order is passed by the Commission on determination of additional surcharge for the year 2015-16.
4. May kindly grant any other relief admissible to the Petitioner Company.
3. Reply filed by the Discoms (DHBVNL & UHBVNL)
DHBVNL
The Respondent DHBVNL, through Shri Varun Pathak / Raheel Kohli, Advocates,
filed a detailed written reply to the issues raised and relief sought by the Petitioner in the
present case. The said reply, in brief, is as under:-
The Respondent herein dwelt at length on the MYT Regulations, 2012 to establish
that the tariff determined under the MYT framework which includes ‘truing up’, shall
7 | P a g e
continue till it is modified or revised by the Commission. It has been further submitted
that Additional Surcharge is one of the element (under income / receipt head) for
determination of tariff. Regulation 63 of the ibid Regulations provides that the Additional
Surcharge is to be determined as per HERC Open Access Regulations, 2012. Further,
Regulation 63(3) provides that the Discoms shall submit along with ARR, requisite
calculation for determination of cross subsidy surcharge and additional surcharge and
these charges as determined by the Commission shall be payable as determined by the
Commission “from time to time”.
DHBVNL has submitted that the tariff Order dated 29.05.2014 passed by the
Commission allowed Additional Surcharge @ 50 Paise / unit. Further, it was held that the
same shall be applicable w.e.f the date of the Tariff Order i.e. 29.05.2014 and shall remain
effective till it is revised by the Commission. Hence, in the light of the legal framework,
MYT Regulations, 2012, Open Access Regulations, 2012 and the Tariff Order dated
29.05.2014; the additional surcharge at the rate of 50 Paise/unit shall remain effective till
the time it is revised by the Commission.
Additionally, DHBVNL, in its reply, dwelt at length on the interpretation of “from
time to time” as per Section 14 of the General Clauses Act, 1897 as well as the following
judgments:-
a) State of Rajasthan Vs. Basant Agrotech (India) Ltd (2003) 15 SCC 1.
b) Vasantlal Maganbhai Sanjanwala Vs. State of Bombay and Others – AIR 1961 SC4.
c) Kashmir Singh Vs. Union of India and Others.-MANU/PH/1170/2002.
The sum and substances of the aforesaid judgments cited by the Respondent is that
the phrase “from time to time” “connotes “as occasion may arise, at intervals, now and
then occasionally” and not from “term to term”.
In conclusion DHBVNL has submitted that this Commission is empowered to
determine the Additional Surcharge as and when occasion requires and till then the rate
of additional surcharge i.e. 50 Paise / unit determined as per the Tariff Order dated
29.05.2014 shall prevail.
8 | P a g e
UHBVNL
UHBVNL, in its written reply dated 29.09.2015 filed through Shri Raghujeet
Singh Madan & Sonia Madan, Advocates, has submitted that the Commission’s Order
dated 29th May, 2014 explicitly states that the levy of tariff shall remain ‘as it is’ till the
same is revised or amended by the Commission. Further, since the computation of
additional surcharge has been made a part of the ibid Order the same is also covered in
the expression ‘revised tariff’, the levy of entire tariff including additional surcharge. It has
also been pointed out that as the number of Open Access consumers and power drawn
thereto is increasing every year, the additional surcharge estimated on similar basis for
the FY 2014-15 would not work out less than as has been estimated by the UHBVNL for
the FY 2013-14. Hence, the continuation of levy of additional surcharge at the rates
assessed in the previous financial year is rational and just.
Additionally, it has been submitted that the Petitioner has wrongly set up its
present case on the Judgment of the Hon’ble APTEL in Appeal No. 231 of 2012 as well as
the Judgment in Appeal No. 204 of 2010. These judgments, relied upon by the Petitioner,
are in no manner applicable in the present case. The Respondent herein, in support of its
contention that the clarification issued by the Commission vide its Memo No. 5.06.2015 is
in fact a reiteration of its previous Order and the same contains no illegality or even
irregularity, cited APTEL’s judgment in Appeal No. 243 of 2012. The said judgment relied
on the settled law by the Hon’ble Supreme Court in Ram Chandra Singh Vs. Savitri Devi
and Others (2004) 12 SCC 713 upholding that an application for clarification or
modification touching the merits of the matter would not be maintainable but the
application for clarification may be entertained when it is shown that such a clarification
is necessary to the interest of justice and does not touch the merits of the matter. The
operative part of the ibid judgment cited by the Respondent herein is as under:-
“36. In the light of the above, we deem it appropriate to give a clarification with
reference to the above aspect to the effect that Interim Order passed by this
Tribunal got merged with the final judgment dated 28.11.2013. We feel that this
clarification has to be issued necessarily in the interest of justice as held by the
Hon’ble Supreme Court in (2004) 12 SCC 713 in the case of Ram Chandra Singh Vs
Savitri Devi and Others. Accordingly ordered”.
9 | P a g e
The Respondent (DHBVNL) further cited Regulation 85 of the HERC (Conduct of
Business Regulations), 2004 which confers exemplary powers on the Commission to issue
such clarificatory Orders in the interest of justice. The relevant Regulation is reproduced
below:-
“86. Nothing in these Regulations shall be deemed to limit or otherwise affect the
inherent powers of the Commission to make such orders as may be necessary for
ends of justice or to prevent the abuse of the process of the Commission”.
In conclusion, the Respondent herein, submitted that viewed from any angle, the
impugned clarification issued by the Commission is valid and just. Hence, the prayer of
the Petitioner to defer the levy of additional surcharge is in violation of the objective of
introduction of additional surcharge. The deferment, if considered, will result in
additional burden to the Respondent as it will have to bear the fixed cost of power
purchase by taking additional loans.
4. On the aforesaid reply filed by the Discoms, the Petitioner vide filing dated
5.10.2015 raised the issue of incorrect affidavit attached with the reply and further
submitted that since the hearing in the matter was concluded on 10.08.2015, the reply
filed by the Discoms is totally uncalled for. Additionally, it has been submitted that the
Respondents have attempted to mix-up two entirely separate issues i.e. normal
distribution tariff determined under section 62 of the Electricity Act, 2003 and Additional
Surcharge determined under Section 42(4) of the said Act. Further, the additional
surcharge is determined (not revised or revisited) based on the six monthly details
regarding the quantum of such stranded cost and the period over which these remain
stranded and hence the same cannot be perceived as a general levy.
That in the hearing held on 10.08.2015 no one was present on behalf of UHBVNL
and no request was ever made to implead UHBVNL as a party in the present case. Further,
the Respondent present in the said hearing merely stated that the action taken by them
was simply in compliance of clarification dated 5/8.06.2015 issued by the Commission.
Further, the Commission vide its interim Order dated 11.08.2015, had directed UHBVNL
to submit its reply to the Petition under consideration by 7th September, 2015 with a copy
to the Petitioner, but till date no such reply has been received by the Petitioner.
10 | P a g e
In conclusion it has been submitted by the Petitioner that this Commission has
to consider its own decision to issue letter of 8.06.2015 and no argument from the
Respondent Nigam is going to change the colour or substance of the case.
The Commission held a hearing in the matter on 10.08.2015 as the parties
mostly relied on their written submissions as reproduced in the present Order, the same,
for the sake of brevity, is not being reproduced here.
5. Commission’s Analysis & Order
At the outset, the Commission would like to deal with the preliminary objections
raised by the Petitioner i.e. defective Affidavit under which replies were filed by the
Respondent and impleading UHBVNL as a party in the present case. The Commission has
examined the Affidavits dated 29th September, 2015 (UHBVNL) as well as the Affidavit
dated 4th October, 2015 (DHBVNL) filed in the Commission and observes that both are in
order. However, the Commission hastens to add that the Discoms ought to exercise
caution while filing an Affidavit and any copy of the same that may be provided to the
other party should be complete in all respects and ought not to be different than what has
been filed in the Commission. In case such incidence happens, the officer/person
concerned shall be personally liable for the consequences that may follow for filing
defective/inconsistent Affidavits.
Regarding the second preliminary objection i.e. impleading UHBVNL without
any request from any party and filing reply after conclusion of the hearing, the Petitioner
needs to note that any tariff and charges including Additional Surcharge that is
determined by the Commission are equally applicable to both the Distribution Licensees
in Haryana i.e. UHBVNL and DHBVNL. Hence, before deciding any such issue it is
appropriate that both the Discoms are given an opportunity to present their views on any
Petition under the consideration of the Commission despite the fact that the Petitioner
may not have made one or the other Discom a party in the case preferred by them.
As far as the reply filed after conclusion of the hearing is concerned, the
Commission is of the view that till the time an Order disposing off the case is passed the
11 | P a g e
Commission has the inherent powers to seek additional data / information or assistance
of any party. However, it is up to the Commission’s discretion whether to consider such
submissions including any reply filed or not. At times, when substantive additional data /
information is filed by any party on the directions of the Commission or even otherwise
the Commission endeavors to make the same available to all the parties concerned. In the
present case the Commission observes that the Petitioner on the one hand has questioned
the legality of the reply filed by the Discoms including alleged non – receipt of the reply
filed by UHBVNL while on the other hand it has been submitted that “…no arguments from
the Respondent Nigam is going to change the colour or substance of the case”. Hence, the
Commission finds no merit in the preliminary objections raised by the Petitioner and shall
now proceed to examine the case on merits.
On perusal of the Petition filed by M/s JSL including their arguments in the
public hearing as well as the replies filed by the Discoms, the Commission observes
that the short point for the consideration is whether the impugned clarification
issued (by the Commission) is ultra virus and the Discoms Sales Circulars that
flowed from it are null and void and liable to be withdrawn or not.
The Commission observes that the Petitioner, while seeking relief in the present
case, has mostly relied on the Hon’ble APTEL’s judgment dated 14.11.2013 in the Appeal
No. 231 of 2012 (JSL Vs DHBVN) as well as this Commission’s Order dated 26.04.2012.
The relevant part of these Orders, as cited by the Petitioner, have already been
reproduced in the present Order, hence the same are not being repeated here. The
Commission has perused the Judgment (supra) relied upon by both the parties i.e. the
Petitioner as well as the Respondents and observes that the Petitioner has culled out a
paragraph from the APTEL’s judgment dated 14.11.2013 and has not placed the entire
judgment including the prayer of the party before it and issues framed by the Hon’ble
APTEL on which the judgment was rendered. Per Contra the Respondents, while alleging
that the present Petition is misleading to that extent, has attempted to put the said
judgment in a proper perspective. Nonetheless, the Commission has carefully perused the
Hon’ble APTEL’ judgment in the Appeal No. 231 of 2012 and observes as under:-
12 | P a g e
The issue, as framed by the Hon’ble APTEL, and the findings thereto are
reproduced below:-
“v) Has the State Commission violated the principles of natural justice in
amending the tariff of LT consumers (emphasis added) by way of suo motu
clarification by a subsequent communication dated 4.10.2010 imposing monthly
minimum charges?”
Further, the Hon’ble APTEL while deciding the matter as set out above, had
relied on their judgment dated 11.8.2011 in Appeal No. 204 of 2010 in Faridabad
Industrial Association Vs Haryana State Commission. The said judgment was also perused
by the Commission. The relevant part of the judgment is as under:-
“10.5. According to learned counsel for the respondents 2 & 3, the
clarificatory order was a correction of an error apparent on the face of
records. We do not agree with the contention of Respondent no. 2 & 3. The
State Commission has also contended that monthly minimum charges were
inadvertently left out in the impugned order. Admittedly, the monthly
minimum charges for LT industry prior to the impugned order were
Rs. 120/- per kW. However, in the clarification issued on 4.10.2010,
the same has been enhanced to Rs. 240/- per kW (emphasis added).
Thus, the State Commission without providing an opportunity to hear the
concerned parties has amended the tariff for LT consumers. This is against
the principles of natural justice and provisions of Sections 64(3) and 86(3)
of the Electricity Act, 2003. The Judgment of Hon’ble Supreme Court
referred to by the learned counsel for the Respondents 2 and 3 is not
relevant to the present case. The State Commission may hear the concerned
parties and pass a reasoned order in this matter which shall be applicable
prospectively. Till then, the Monthly Minimum charges as applicable to LT
consumers’ up to 20 kW load prior to the date of the impugned order shall
continue”.
A plain reading of the ibid judgment makes it clear that the said clarification
given by the Commission was set aside due to the fact that MMC for LT industry was
13 | P a g e
Rs. 120/- per kW and the same vide clarification issued on 4.10.2010 was enhanced to
Rs. 240/- per kW. However, in the present case no such change/enhancement was made
by the Commission in the impugned clarification.
As distinguishable from the above, in the present case the impugned
clarification issued by this Commission did not touch upon the merit of the case and the
same was issued in the interest of justice as held by the Hon’ble Supreme Court in
Ramchandra Singh Vs. Savitri Devi and Others (2004) 12 SCC 713. Thus, the ratio of the
Judgments of the Hon’ble APTEL in Appeal No. 231 of 2012 and Appeal No. 204 of 2010
are not applicable in the present case as the same are clearly distinguishable on facts.
Further, while seeking relief in the present case, the Petitioner has relied upon the
Commission’s Order dated 26.04.2012 i.e. that the Commission shall not respond to any
such application / pleading from the power utilities / stakeholders which are not filed in
accordance with the laid down procedure. Hence, the Petitioner has contended that the
clarification dated 5/8.06.2015 is in violation of the Commission’s own Order dated
26.04.2012.
Per Contra the Respondents have argued that Additional Surcharge is one of the
elements (under income / receipt head) for determination of tariff. Further, Regulation 63
of the ibid Regulations provides that the Additional Surcharge is to be determined as per
HERC Open Access Regulations, 2012. Regulation 63(3) further provides that the Discoms
shall submit along with ARR, requisite calculation for determination of cross subsidy
surcharge and additional surcharge and these charges as determined by the Commission
shall be payable as determined by the Commission “from time to time”.
Additionally, the Respondent herein cited several judgments interpreting the
phrase “from time to time” as enshrined in the Commission’s MYT Regulations, 2012.
Accordingly, the Respondents argued that the Commission is empowered to determine
Additional Surcharge as and when occasion arises and not necessarily on six monthly
basis.
14 | P a g e
The Commission observes that as far as interpretation of the phrase “from time to
time” is concerned the matter stands settled by the judgments cited by the Respondents.
However, the same is not germane to the present case before this Commission. It is an
admitted fact that as on the date of issuing the impugned clarification the process of
determining Additional Surcharge applicable for the FY 2015-16 was under consideration.
Hence, given the fact that till the time the Commission, based on voluminous data
involved, determined the Additional Surcharge applicable for the FY 2015-16 and the fact
that the PPAs continued to remain stranded for one reason or the other including due to
the Open Access Consumers there would have been a vacuum leading to lower revenue
realizations for the Discoms. This, at some stage would have been passed on (partly or
wholly) to all the electricity consumers of the State. Thus, the Commission in the interest
of justice and on the letter written by the FIA, issued the impugned clarification.
While issuing the impugned clarification the Commission was convinced that the
Additional Surcharge also flew from the Order of the Commission determining the ARR /
Tariffs of the Discoms including source wise power to be purchased by the Discoms;
consumer category-wise sales including inter-State sales etc. Hence, the Commission
considered it appropriate to issue the said clarification levying the Additional Surcharge
as determined by its Order dated 29th May, 2014 till the time the same was revised /
amended.
In the considered view of the Commission the said Additional Surcharge @ 50
Paise / Unit, as also recorded in the ibid Order, was only about 50% of the Additional
Surcharge proposed by the Discoms based on data filed by them. Further, given the clearly
discernible trend in power being drawn by the Open Access Consumers and the power
being surrendered by the Discoms, the ibid additional surcharge @ 50 Paisa/Unit was the
minimum acceptable levy due to data limitations at that point.
The same erred more in the favour of the Open Access Consumers rather than the
Discoms. Thus, there was no occasion or legal requirement for the Commission to direct
FIA to file a Petition for seeking clarification on the levy of Additional Surcharge.
15 | P a g e
Such a Petition would have become essential in view of the Commission’s Order
dated 26.04.2012 in case there existed any doubt in its mind regarding continuation of the
Additional Surcharge as determined vide its Order dated 29th May, 2014 till the time the
same is revised / amended or discontinued.
Additionally, the Commission observes that a major portion of the proceeds of the
Additional Surcharge from the short – term Open Access Consumers is utilized towards
reducing the ARR of the Discoms and tariff(s) payable by the electricity consumers in
Haryana thereto. Hence, any vacuum left in the interim period from 1st April, 2015 till the
time Additional Surcharge for the FY 2015-16 is determined de -novo, would tantamount
to avoidable burden on the electricity consumers in the State in general and an unjust
gains to a few Open Access Consumers who are using the Open Access mechanism by
striking a trade-off between “Discoms power” and “power brought from outside for
commercial gains”.
Thus, given the iniquitous situation between the large number of electricity
consumers in general and a few Open Access Consumers, the Commission issued the
impugned clarification which was in the interest of justice and in the nature of a
reiteration of the obvious facts flowing from the relevant statutes / Regulations as well as
the Commission’s Order dated 29th May, 2014.
In view of the above discussions the Commission holds that the impugned
clarification issued by the Commission and the subsequent Sales Circular issued by the
Respondents suffers from no legal infirmity.
The Petition is accordingly disposed off.
This order is signed, dated and issued by the Haryana Electricity Regulatory
Commission on 10th November, 2015.
Date: 10.11.2015 (M.S. Puri) (Jagjeet Singh) Place: Panchkula Member Chairman