bearing structure-fmea guideline - universität kassel ... · bearing structure-fmea ... for...

20
1 Bearing Structure-FMEA Guideline Bearing Structure-FMEA: Preventive Quality Control in Civil Engineering Werner Seim, Tobias Vogt Timber Engineering and Building Rehabilitation, 18.07.2011

Upload: hanga

Post on 13-May-2018

226 views

Category:

Documents


1 download

TRANSCRIPT

1

Bearing Structure-FMEA

Guideline

Bearing Structure-FMEA:

Preventive Quality Control in Civil Engineering

Werner Seim, Tobias Vogt

Timber Engineering and Building Rehabilitation, 18.07.2011

2

Table of contents

1. Introduction

1.1 Preliminary note

1.2 Terms and definitions

2. Proceedings Bearing-FMEA

2.1 Classification of the construction in the risk categories

2.2 Bearing structure design and preliminary measurement

2.3 Classification of the building in robustness categories

2.4 Classification of the building in FMEA-categories

2.5 Description of the global load bearing

2.6 Error analysis

2.7 Risk evaluation

2.8 Optimization

2.9 Documentation of the events

2.10 Monitoring of the further planning and execution

2.11 Error categories and error causes

2.12 Error types and discovery measures

List of references

3

1 Introduction

1.1 Preliminary Note

In civil engineering the proceedings to prepare static calculations is determined by standards and

regulations. In addition, it is stipulated in which way the impacts on a building are to be considered

by giving the appropriate load assumptions. The necessary guarantees are regulated by the semi-

probable safety concept. But these only relate to the uncertainty on the part of impacts and

resistance of the construction elements. To control the static calculations concerning the correct

application of the standards and regulations as well as the correctness of the bearing concept and

the calculations, one counts on the inspection of a qualified inspection engineer or, for smaller

construction projects, on a not specified, intern quality mechanism. However, this inspection takes

place without a generally accepted system and, thus, is not sufficiently traceable. Besides, mistakes

are so only found at a later date; consequently, the repair is often time-consuming and expensive.

The Failure Mode and Effects Analysis (FMEA) is used to secure the quality of products. Possible

mistakes are to be found in an early stage to prevent these from happening beforehand respectively

to minimize their consequences by taking the appropriate measures. FMEA is already used for

several decades in the field of mechanical engineering, especially in the area of aeronautics, as well

as in the automobile industry and there, it proved its worth in many ways. In the mean time, there, it

forms an important foundation for all projects especially in the development phase. For the

automobile companies, for example, the execution of a FMEA is required for a mutual cooperation

with their suppliers. Also insurance companies call increasingly for a FMEA respectively they contract

clearly better conditions to businesses that execute such ones.

The article “The role of the inspection engineer in the system of a preventive hazard control” by

Dressel [Dre09] gives further reasons for the necessity of an optimized quality control. A good survey

concerning the state of the art respectively the FMEA can be found in the booklet FMEA – Failure

Mode and Effect Analysis.

For the first time, the available guideline states the regulations to perform a FMEA in civil

engineering. In the process, the level of difficulty and the robustness of a building are defined as

parameter for the FMEA.

1.2 Terms and definitions

FMEA-types Mechanical Engineering / Aerospace industry

Framework-FMEA: It examines interaction between the frameworks and the framework

elements and provides the transparency of the whole system.

Construction FMEA: It steps further into the framework and analyses the framework in

detail. The error causes of the framework-FMEA are considered as error types and their

causes are traced.

4

Process-FMEA: It studies the errors that can develop during construction.

FMEA-types Civil Engineering

Bearing-FMEA: It is performed after planning and design (work phase 2 and 3) and is used to

prevent fundamental errors in an early stage.

Construction-FMEA: It follows the approval and the detailed planning and aims at securing

the correct the final static calculations and engineering drawings.

Fulfilment-FMEA: It should guarantee the correct performance and prevent errors in this

phase.

Utilisation-FMEA: Its goal is to observe the critical areas and the durability of buildings in the

utilisation phase.

Application Framework-FMEA

Structure analysis: All framework elements as well as their cutting points (connections,

correlations and dependencies) are recognised, analysed and documented. A description is

documented in an appropriate form.

Operational analysis: The respective functions of the framework elements are analysed and

assigned to the different points of the hierarchy.

Error analysis: An error is defined as “failure to perform an operation”. Hence, an error can

be defined for each operation. Additionally, its cause and consequences can be described in

this step. The analysis follows heuristic, i.e. intuitive and based on experience.

Risk evaluation: To estimate the actual risk, 3 criteria with numerical values between 1 and

10 each are reviewed in the most used form of risk evaluation. These are the importance (B)

of the error consequences, the occurrence probability (A) of the error cause as well as the

discovery probability (E) of the error respectively the error cause. The risk priority number

(RPZ) states the risk based on an error and is calculated by the multiplication of the

evaluation numbers:

RPZ = B*A*E.

The higher the RPZ the more important it is to perform an optimization for this error, i.e. the

higher the priority to examine this error. The possible results lie between 1 (no respectively

very low risk) and 1000 (very high risk).

Optimization: On this background it is possible to develop in teamwork appropriate

measures to detect respectively to prevent the errors for the identified risks. The defined

measures are considered at the evaluation of the criteria and lead to a reduction of the RPZ.

5

2 Proceedings Bearing-FMEA

The complete development of a Bearing–FMEA is shown in illustration 2.1 as a flow chart. Each

process step is shortly explained in illustration 2.2. Additionally, there is a hint to the appropriate

chapters, illustrations and charts.

2.1 Classification of the construction in the risk categories

The building is classified in the appropriate risk category (cf. illustration 2.4) due to the charge zone

(cf. chart 2.1) and the consequence class (cf. illustration 2.3).

charge zone planning requirements

HZ I very low HZ II low HZ III average HZ IV above average HZ V very high

chart 2.1 : charge zones according to HOAI

6

Proceeding Bearing-FMEA (complete development)

Planning / Design of the architect

1. Classification of the building in risk categories

2. Developing of an static concept (bearing concept and the pre-sizing

3. Classification of the building in robustness categories

Definition of the necessary extent of the FMEA and preparation of the session

4. Determination of the FMEA-Class

5. Presentation of the global load transfer

6. Error analysis

7. Risk evaluation

↓ Performance of the session for the

error analysis and optimisation

8. If necessary optimisation

9. Documentation of the results

10. Monitoring of the performance according to the assumption agreed on, otherwise adjustment of the FMEA and

if necessary performance of a new session

Control and adaptation during

planning and adaptations

Picture 2.1: Flow chart to demonstrate the total course of action of a bearing-FMEA

7

Line Process Step Intention Participants Respective Information

1

Classification of the building in risk categories

Determination of the necessary definition/correct observation at performing

the FMEA

Structural engineers, possibly definition by evaluation authorities

Chapter 2.1

Picture 2.3, 2.4

Chart 2.1

2

Static design and planning

Determination of an appropriate bearing concept

and the necessary dimensions of the

construction elements

Structural engineers

3

Classification of the building in

robustness classes

Determination of the necessary number of

elements to be detected for the performance of the FMEA

Structural engineers, possibly definition by evaluation authorities

Chapter 2.3

--

Chart 2.3, 2.4

4

Classification of the building in FMEA-classes

Determination of the

necessary extension of the FMEA performed

Structural engineers, possibly definition by evaluation authorities

Chapter 2.4

Picture 2.5, 2.6

Chart 2.6, 2.6

5

Presentation of the global load

transfer

Support for the determination of the error

consequences to continuative construction elements (error

propagation)

Structural engineers

Chapter 2.5

Picture 2.7, 2.8

--

6

Error analysis

Detection of possible mistakes as well as the

corresponding causes and consequences

Participants of the meeting according to

chapter 2.4 respectively 2.6

Chapter 2.6

--

Chart 2.6, 2.9, 2.10

7

Risk evaluation

Determination if the existing

risk observes the defined boundaries

Participants of the meeting according to

chapter 2.4 respectively 2.6

Chapter 2.7

Picture 2.9, 2.10, 2.11

Chart 2.8

8

Optimisation

Reduction of the risk when the defined boundaries are

not observed

Participants of the meeting according to

chapter 2.4 respectively 2.6

Chapter 2.8

--

Chart 2.9, 2.11

9

Documentation of the incidents

Documentation of the

important information and using these in further phases

Recording participant of the meeting

according to chapter 2.4 respectively 2.6,

confirmation by participants

Chapter 2.9

Picture 2.12

--

10

Monitoring of

the further planning and performing

Monitoring, if criteria determined are respected

and if necessary adjustment of the FMEA to new

conditions

Determing a

responsible person, e.g. inspection engineer

Chapter 2.10

--

--

Picture 2.2: Explanations and cross references with regards to the flow chart

8

2.2 Bearing structure design and preliminary measurement

Corresponding to the requirements of the risk category (see chart 2.2) a bearing structure design is

developed and the preliminary measurements are performed.

Risk category Necessary complexity of the preliminary measurement

GK 1 / 2 Developing the static design and the preliminary measurements in the usual way

GK 3 Developing the static design and performing an accurate preliminary measurement, preliminary

dimensioning of the attachments and connections. Defining the critical elements by comparative calculation (measurement for a

deficiency of the construction elements).

Chart 2.2: Complexity of the preliminary measurement in dependence to the risk category

2.3 Classification of the building in robustness categories

The classification of the building in robustness categories results on the basis of chart 2.3. The

robustness number is defined by chart 2.4.

Robustness category Robustness number

1 < 10 2 -10 to +10 3 > 10

Chart 2.3: Proposal for the classification in robustness categories

9

characteristics statement applies to

not at all

little average a lot absolutely

Redundancy Bearing

structure

Alternative load path exist

-4 -2 0 +2 +4

There is a static uncertain bearing

structure

-2 -1 0 +1 +2

Local deficiencies do not have huge

effects

-4 -2 0 +2 +4

Redundancy connections

The connections bear even if single

fastener fail

-4 -2 0 +2 +4

The connections can also adjust loads that

are caused by the start-ups of

alternative load paths

-4 -2 0 +2 +4

Construction material / behaviour

The construction elements have a

sufficient ductility to exclude a failure

without an advance notice

-8 -4 0 +4 +8

Security of the construction

elements

There are no construction

elements that are increasingly possible

to fail

-8 -4 0 +4 +8

Easiness to maintain

Construction elements and

connections relevant for maintenance are easy accessible and

monitorable

-6 -3 0 +3 +6

Robustness number RZ = ∑

Chart 2.4: proposal of an evaluation method to define the robustness of bearing structures

10

2.4 Classification of the building in FMEA-categories

The classification of the building in FMEA-categories is dependent on the risk and the robustness

category (see picture 2.5). These define in what extend the FMEA has to be carried out (see chart 2.6

and 2.7). A schematic illustration of defining the category of a building is shown in picture 2.6:

Robustness category

Ris

k C

ateg

ory

RK 3 RK 2 RK 1

GK 1

1

2

3r

GK 2

2 2 3r

GK 3

3g 3g 4

Picture 2.5: Defining the FMEA-categories in dependence to risk and robustness categories

FMEA-category

accuracy / depth of consideration

number of elements covered

1 -- -- 2 low low

3g high low 3r low high 4 high high

Chart 2.5: Description of the FMEA-classes

accuracy / depth of consideration

low: In-house error analysis and optimisation meeting, other project participants can be included. Normal preparation of the meeting: establishing the static design and the preliminary measurements. Describing of the global load bearing under consideration of the essential bearing elements. Medium limit for risk priority number (RPZ)

high: Error analysis and optimisation meeting in extended group of people, preferably with the architect, the test engineer, the construction supervisor of the performing company and, if possible, the building owner. Extensive preparation of the meeting: establishing the static design and performing of an accurate preliminary measurement, pre-dimensioning of the connections and contacts. Already before the meeting, description of the critical elements by comparative calculations (measuring for failure of construction elements). Description of the global load bearing under consideration of all bearing elements. Low limit for risk priority number RPZ.

number of elements covered

low: restriction to critical construction elements high: taking all construction elements involved in the load bearing into consideration

Chart 2.6: definition of the terms “low” and “high”

11

Consequence Classes according to VDI-RL 6200

(picture 2.3)

Charge Zones according to HOAI

(chart 2.1)

Risk Category (picture 2.4)

Robustness Category (picture 2.3 + 2.4)

FMEA-Categories (picture 2.5)

Picture 2.6: Schematic illustration to define the categories of a building

2.5 Description of the global load bearing

According to the requirements of the FMEA-category, either all or only the essential elements of the

bearing structure are described in a “description of the global load bearing”. In that, the load flow

within the bearing structure is visualized from element to element. On this basis the error

consequences to continuative elements and, thus, the significance of errors within the bearing

structure are illustrated. An example is given in the pictures 2.7 and 2.8.

12

2.6 Error analysis

In the context of an error analysis and optimisation meeting, the structural bearing and the individual

construction elements and connections are checked for possible errors that can occur.

The meeting takes place either in-house or with an extended group of people (compare chart 2.6),

according to the requirements of the FMEA-category. In chart 2.7, both group of people mentioned

are defined in a more accurate way.

Possible error causes as well as error consequences are looked for and documented for the found

possible errors (error types). To support this process, support in form of error categories, examples

for error causes and an error catalogue are presented in the next chapters.

In-house group of people

- structural engineer, who prepared a static design and performed preliminary measurements

- responsible of the project (supervisor of the structural engineer) - construction engineer - other in-house participants

Additionally in an extended group of people

- test engineer - architect - supervisor of the performing company - other participants at the construction site (e.g. geotechnical expert) - possibly owner of the building

Chart 2.7: definition of the in-house and the extended group of people for an error analysis and

optimization meeting

2.7 Risk evaluation

The risk evaluation caused by possible errors is performed on consensus by the participants of the

error analysis and optimization meeting. The existing risk is described by the risk priority number

(RPZ) that consists of the following three evaluation criteria:

Importance of the error consequence according to chart 2.8

Occurrence probability of the error cause

According to picture 2.9a, a category for the construction element is defined with the help of

the existing experiences of the participants with a certain construction element and the

expected element quality in dependence to the producing place. Together with the

utilization factor calculated of the construction element, there is an evaluation number for

the occurrence probability according to picture 2.9b. This determined number is consistent

with a “tendency number”, an accurate definition is made by the participants of the meeting.

Occurrence probability of the error respectively the error cause

Determination of a bearing structural evaluation number for the discovery probability in

13

dependence to the honorary zone and the determined FMEA-category (cf. picture 2.10). This

number is equal to a “tendency number”, an accurate definition is made by the participants

of the meeting.

The evaluation is made with numbers between 1 (“low risk” respectively “good”) and 5 (“high risk”

respectively “poor”). The RPZ is calculated by the multiplication of these evaluation numbers, thus

RPZ = B A E. Hence, it lies in the area between 1 and 125. A schematic illustration of the evaluation

system can be seen in picture 2.11.

description of the error consequences evaluation number

­ failure of the bearing structure or of a part system 5

­ huge damages at the bearing structure or at a part system, ­ bearing capacity is not guaranteed anymore, ­ no (economic) restoration possible

4

­ average damages at the bearing structure or at a part system, ­ bearing capacity is limited, ­ restoration to guarantee the bearing capacity is possible with

medium effort

3

­ small damages at the bearing structure or at a part system, ­ bearing capacity little effected, ­ small restoration steps are necessary

2

no damage of the bearing structure or a part system 1

Chart 2.8: Evaluation of the meaning of an error respectively the error consequence

quality of fabrication category of construction element

fre

qu

en

cy o

f u

se

prefabricated construction

element

partly prefabricated construction

element

fabrication

on-site

uti

lisat

ion

rat

io

I

II

III

often

I

I

II

1

2

3

barely

I

II

III

60-85 %

2

3

4

for the first time

II

III

III

3

4

5

Picture 2.9: (a) Determination of the category of the construction element; (b) Determination of the

evaluation number for the occurrence probability (“tendency value”)

14

FMEA-category

ho

no

rary

zo

ne

4

3g/r

2/1

HZ I/II

1

2

3

HZ III

2

3

4

HZ IV/V

3

4

5

Picture 2.10: Determination of the evaluation number for the discovery probability (“tendency

value”)

meaning of the error consequence

(chart 2.8)

occurrence probability (A) of the error cause

(picture 2.9)

discovery probability (E) of the error respectively of

the FU (picture 2.10)

Risk priority number RPZ = B*A*E

Picture 2.11: Defining of the risk priority number in dependence to the evaluation numbers

2.8 Optimization

When a defined RPZ exceeds a specified risk barrier, an optimization by taking the appropriate steps

is necessary. On the one hand, these can be steps to prevent the error cause and, on the other hand,

steps to detect the errors respectively the error causes. By taking these steps the related evaluation

number is reduced depending on the area improved. If no appropriate measures can be found or the

defined measures are not sufficient, it is also possible to reduce the RPZ with a modified bearing

structural concept. An assortment of possible discovery measures in dependence on the error

categories is shown in chart 2.11.

2.9 Documentation of the events

The results of the analysis, evaluation and optimization are documented in form sheets (cf. picture

2.12). For each step defined, a responsible person is appointed to be in charge of the realization. A

date for the performance has to be stipulated.

15

When important points are determined in a meeting that have to be taken into consideration for the

following project phases, it is necessary to document these as directions for the following project

phases. These directions as well as the information about the critical parts will be handed out to the

engineers responsible for the licence and the detailed planning as well as for the building

construction to be pursuit.

16

construction element / connection

evaluation of the errors:

- occurrence probability (A) - importance of the error consequence (B)

- discovery probability of the error / the error cause (E) function

possible error consequences

B possible error (error type)

possible error causes

preventive measures

A discovery measures

E RPZ responsible / date

Picture 2.12: Form sheet for the error evaluation in the error analysis and optimization meeting

according to [DIN06]

17

2.10 Monitoring of the further planning and execution

During the planning and execution process many modifications occur, be it by planning modifications

by the architect or the realization of alternative proposals by the performing company. When such

modifications occur, they have to be included afterwards into the FMEA. At a certain amount, an

error analysis and optimization meeting is again necessary. Additionally, it has to be monitored if the

assumptions and requirements are observed in the appropriate manner.

2.11 Error categories and error causes

To support the determination of errors and their cause, the possible error causes are classified into

categories. At the moment, these are limited to the areas calculation, measurement and design (see

chart 2.9)

2.12 Error types and discovery measures

For an assortment of typical construction elements in the common surface construction, a failure

catalogue with possible error types is presented in chart 2.10. It can be used a basis for the definition

of an in-house or also for a public failure catalogue.

Chart 2.11 includes possible discovery measures that are based on the defined error categories, as

well.

error category possible error causes

conceptual error (global level) ­ hidden kinematics at bearing concept ­ insufficient reinforcement of the building ­ deficient robustness, i.e. insufficient reserves for

smaller failure of construction elements and sensitivity to unplanned disturbances, such as not scheduled impact load or explosions

errors in determing the impacts ­ wrong defined loads ­ non-consideration of a decisive impact ­ non-consideration of the decisive load case combination

error in modelling ­ error at entering the model ­ The model does not correspond with reality (e.g. joint

moment instead of rotating clip,…)

error in calculation and measurement

­ The cross section determination is wrong. ­ The bearing resistance was calculated wrongly.

error at connections and details ­ The dimensioning of the connections was calculated wrongly.

­ The details are not realizable.

chart 2.9: possible error causes (exemplary)

18

1. bearing structure 2. shear wall

- stability failure (crippling) [s] - compressive failure [d/s] - tension failure (tension support) [d] - bending failure [d/s] - too strong deformation [d] - becomes relocatable (unusual) [d] - shear failure (e.g. short bearings at earth

quakes) [s]

- compressive failure (strut) [s] - tension failure (at the support) [d/s] - too strong deformation [d] - failure at openings [d/s]

3. binding girder 4. top panel

- bending failure [d/s] - shear failure [d/s] - too strong deformation [d] - failure at openings [d/s]

- too strong deformation [d] - bending failure [d/s] - shear failure [d/s] - failure at openings [d/s] - punching shear [d at ductility

reinforcement]

5. wall-like bearing 6. floor panel

- compressive failure (of the strut) [s] - tension failure (in tension zone) [d] - failure at openings [d/s]

- too strong deformation [d] - shear failure [d/s] - failure at openings [d/s] - punching shear [d at ductility

reinforcement]

7. foundation

- bending failure [d/s] - shear failure [d/s] - failure of a tensile bracing (launching of the forces) [d/s] - too little position stability [d/s] - for individual foundation: punching shear [d at ductility reinforcement] (not included are failures concerning the floor like e.g. base failure)

d = ductile material behaviour s = brittle material behaviour

chart 2.10: failure catalogue for possible error types of different construction elements of reinforced

concrete (exemplary)

19

error category possible discovery measures

conceptual error (global level) verifying the static design on global level of bearing capacity (1st step of the error analysing and optimization meeting)

error in determing the impacts

verifying the determination of loads and load case combinations by:

- check list with all impacts - inspection of all the relevant load case combinations,

especially on critical places

error in modelling verifying the model after entry by: - anew entry (comparison) - inspection of every joint and element - 2nd engineer (in-house)

error in calculation and measurement

verifying of the assessment of the state of strain and dimensioning by:

- 2nd program or basic hand calculation - 2nd engineer (in-house) - Check list with all necessary documentation

Chart 2.11: Possible discovery measures to reduce the risk (exemplary)

20

List of references

[DIN06] DIN EN 60812:2006; Analysetechniken für die Funktionsfähigkeit von Systemen - Verfahren für die Fehlzustandsart- und –auswirkungsanalyse (FMEA). 2006

[Dre09] DRESSEL, B.: Die Rolle des Prüfingenieurs im System der vorbeugenden Gefahrenabwehr. Stahlbau 78, Heft 3, Ernst & Sohn Verlag: 214-220, 2009

[e.V08] e.V., VEREIN DEUTSCHER INGENIEURE (Herausgeber): Entwurf der VDI-Richtlinie 6200: Standsicherheit von Bauwerken – regelmäßige Überprüfung. VDI-Gesellschaft Bautechnik, 2008.

[Var04] VARWIG, J.: FMEA – Fehlermöglichkeits- und Einflussanalyse. Hrsg.: Deutsche Gesellschaft für Qualität e.V. (DGQ), Frankfurt; Beuth Verlag GmbH, 2004

[Vog09] VOGT, T.: Durchführung einer Tragwerk-FMEA für ein Bürogebäude und Erarbeitung von Fehlerkategorien. Projektarbeit. Universität Kassel, Fachgebiet Bauwerkserhaltung und Holzbau (als Download unter www.tragwerk-fmea.de), 2009