beam load estimates for the ps2 beam dump systems t. kramer, m. benedikt, b. goddard
TRANSCRIPT
Beam load estimates for the PS2 Beam Dump Systems T. Kramer, M. Benedikt, B. Goddard
24.10.2007 T. Kramer AB-BT-TL 2
Main PS2 design parameters and key assumptions for the dump load calculations
Assumed 200 days of operation
Maximum of 1.08 x 1021 protons /y
All calculations are done in a rather conservative way
Injection energy (T) GeV 4
Extraction energy (T) GeV 50
Maximum beam intensity p+ 1.51014
Minimum cycle period to 50 GeV s 2.4
Maximum norm.emittance (H-V) .mm.mrad 15.0-8.0
Cycles per year 7.200,000
Protons accelerated per year p+ 1.081021
24.10.2007 T. Kramer AB-BT-TL 3
Dump functionalities
Injection line setting up Fast injection setting up H- Injection Emergency abort Machine development Machine setting up Extraction line setting up Slow extraction ‘remaining beam’
24.10.2007 T. Kramer AB-BT-TL 4
H- Injection 6.4x1019 p.a. (5.92%) @ 4 GeV details later….
Emergency beam abort assumed 0.5% of cycles dumped 5.4x1018 (0.5%) particles p.a. (50% @ 4-20 GeV)
Machine setting up 6 days (2 per beam); 20% of full intensity 6.5x1018 p.a. (0.6%) (50% @ 4-20GeV)
Machine development 100h p.a. 20% of full intensity 4.3x1018 p.a. (0.4%) (50% @ 4-20 GeV)
Particles remaining after slow extraction Max. 1 % remaining particles; 50 GeV; operational 50% p.a.; 3.6s cycle 3.6x1018 p.a. (0.33%)
Fast injection setting up and failures 1 day p.a.; 20% dumped; 100 failures p.a. 1.08x1018 p.a. (0.1%) @ 4 GeV
Setting up of injection transfer line 4 days p.a.; 10% intensity; 20 foil exchange interventions; 3.06x1018 p.a. (0.28%) @ 4 GeV
Setting up of extraction transfer line 2 days p.a.; 30% intensity; 3.25x1018 p.a. (0.3%) @ 50 GeV
24.10.2007 T. Kramer AB-BT-TL 5
Summary of beam loads
Function E [GeV] Load [p+]% oftotal
Possible beam destinations
Injection transfer
line dump
Internal fast injection
dump
Internal or external H- dump
Internal or external
emergency dump
Injection line setting up 4 3.1x1018 0.28 X
Fast injection setting up 4 1.1x1018 0.10 X
H- injection losses 4 6.4x1019 5.92 X
Emergency abort 4-20 2.7x1018 0.25 X
Machine development 4-20 2.2x1018 0.20 X
Machine setting up 4-20 3.3x1018 0.30 X
Function E [GeV] Load [p+] % of total
Possible beam destinations
Internal or external emergency dump
External beamline or transfer line dump
Emergency abort 20-50 2.7x1018 0.25 X
Machine development 20-50 2.2x1018 0.20 X X
Machine setting up 20-50 3.3x1018 0.30 X X
Extraction line setting up 50 3.3x1018 0.30 X
Slow extraction beam 50 3.6x1018 0.33 X X
Table 1: Beam loads @ “high Energy”
Table 2: Beam loads @ “low Energy”
24.10.2007 T. Kramer AB-BT-TL 6
External beam line
dump
PS2 extraction line dump TED
External H- injection
dump
PS2 injection transfer line
dump TED(s)
Internal fast injection
dump
Internal emergency
dump
? ?
SPS
TT12
EAs
PS2
TT10
from SPL
Schematic overview
24.10.2007 T. Kramer AB-BT-TL 7
Unstripped beam 2 kW unstripped H-,H0 (5% efficiency) 5.4x1019 p.a. (5%)
Yearly startup 8x1018 p.a. (0.75%)
Setting up Injection systems / foil exchange 1.8x1018 p.a. (0.16%)
H- Injection - Beam Loads
24.10.2007 T. Kramer AB-BT-TL 8
H- Injection - extract beam back to TT10
Overview of PS2 H-Injection; B. Goddard; PS2 meeting; 05/2007
24.10.2007 T. Kramer AB-BT-TL 9
H- Injection - Factors of Influence
Stripping efficiency Emittance dilution Foil heating
To be considered:
Lorentz Stripping H0 excited states
Stripping efficiency Beam blow up
Lifetime
Temperature
Foil thickness
Beam loadH0/H-
Foil material
Size, activation, positionof the beam dump
5%
<0,1 pi mm mrad
Losses!
Some optimization should be possible - studies
24.10.2007 T. Kramer AB-BT-TL 10
Internal emergency dump
Possible solution (as proposed):
Internal dump only takes the beam which really has to go there (8x1018 4-20 GeV + 2.7x1018 p@50 GeV p.a.)
Whenever there is time to extract the beam safely a beam line dump is used (slow extraction, machine development. 5.5x1018 @ 20-50 GeV + 6.9x1018 @ 50GeV p.a. )
External dump at end of beamline in well-shielded EA zone?
Advantages System is easier to build, cheaper, desirable from point of
operations, “some internal dump” to set up the extraction is anyway needed
Disadvantage For operations like in the SPS a very high beam load is expected -
Radiation source within the machine
24.10.2007 T. Kramer AB-BT-TL 11
Summary of loads and issues
PS2 dumpBeam loads [p+ /y]
4 GeV 4-20 GeV 20-50 GeV 50 GeV
1. PS2 injection transfer line dump 3.1x1018 - - -
2. Internal fast injection dump 1.1x1018 - - -
3. External H- injection dump 6.4x1019 - - -
4. Internal emergency dump - 8.2x1018 2.7x1018 -
5. External beamline dump - - 5.5x1018 6.9x1018
Issues Need for TEDs/beam stoppers at the end of transfer lines…including for ions and p+ from
PSB before SPL comes on line. Configuration for injection and extraction region….becoming congested. Extraction and dumping of unstripped H- beam (acceptance, losses, …) Optimization of losses for H- injection? Studies need to be done… Conservative calculation to keep the highest degree of freedom; If we have serious
problems concerning feasibility (costs) we have to define more accurate operations and design parameters and look into detail again.