beach elementary school feasibility study ......feasibility study presentation to calvert county...
TRANSCRIPT
BEACH ELEMENTARY SCHOOLFEASIBILITY STUDY
Presentation toCalvert County Board of Education
February 7, 2019
FEASIBILITY STUDY Process
Step 1: Information Gathering & Evaluation• Compare Existing Building Program vs. Project Goals & Ed Spec
• Evaluate Existing Building Issues
• Code Analysis / Review
• Building Specific Diagrams
• Site Plan Analysis
Step 2: Concept Design• Proposed Concept Bubble Diagrams Depicting General Planning
Concepts
• Committee Input is Applied to Diagrams Combinations of Preferred Features
Incorporated of New Committee Input
Development of Refined Approaches
Step 3: Development of Plan Options• Concepts are refined into Formal Plan Approaches and Technically
Scrutinized
• Engineering Disciplines are Applied
• Code Compliance
• Cost Estimating
• Sustainability, Energy Conservation & Life Cycle Cost Analysis
• Construction Schedule, Duration, and Phasing Plan
Step 4: Technical Report Preparation• Prepare Board of Education Presentation and Brochures
• Prepare IAC Feasibility Study Submission
FEASIBILITY STUDY Stakeholder Advisory Group
• The study is the result of it’s collaborative process
• Thank you to the members of the Stakeholder Advisory Group for dedicating your time, knowledge, and efforts into this process
Dr. Michael Shisler, Principal, Beach Elementary School
Casey Grenier, Teacher, Beach Elementary School
Gwen Redden Henderson, Parent, Beach Elementary School
Mary Sterling, Parent, Beach Elementary School
Shuchita Warner LEED AP, Director of School Construction, CCPS
Darrell Barricklow AIA, LEED AP, Supervisor of School Construction, CCPS
Gregg Gott, Supervisor of Operations, CCPS
Ed Cassidy, Director of Transportation, CCPS
FEASIBILITY STUDY Program Goals
• Existing Building
Area: 54,893 GSF
SRC: 514 students
9 Portables
• Proposed Building
Ed Spec NSF: 50,115
Ed Spec GSF: 67,860
Ed Spec SRC: 600
Admin
Instructional
Media Center
Special Ed
Gym/ Cafe
Music/ Arts
Building Services
FEASIBILITY STUDY Exist ing Condit ions Evaluation
• Architectural Smolen Emr Ilkovitch Architects
• Civil Collinson Oliff & Associates
• Structural ADTEK Engineers
• Mechanical James Posey Associates
• Electrical James Posey Associates
• Plumbing James Posey Associates
• Data / IT James Posey Associates
• Life Safety Smolen Emr Ilkovitch Architects
James Posey Associates
• Cost Estimating MK Consulting Engineers
FEASIBILITY STUDYApproach Comparison
APPROACH 1Phased While Occupied
Minimize Demolition
Maximize Adaptive-Reuse
Minimize Sitework
Satisfactory Program &
Adjacencies
APPROACH 2Phased While Occupied
Increase Demolition
Increase New Construction
Improve Sitework
Good Program & Adjacencies
APPROACH 3A*Phased While Occupied
APPROACH 3BPhased While Occupied
APPROACH 3C
REVITALIZATION MODERNIZATION REPLACEMENT
Complete Demolition
All New Construction
Site Redevelopment
Ideal Program & Adjacencies
*Retains 2006 Addition
The purpose of a feasibility study is to determine the project approach, not to design the building
APPROACH 1: REVITALIZATIONSite & Floor Plan
APPROACH 1: REVITALIZATIONPhasing Plan
existing building
addition
demolition
renovation
new building
PHASING KEY
SY 1
1
2a
SY 2 SY 3
2b
3
site
PHASING SCHEDULE 39 Months
phas
e 0
phas
e 2
site
phas
e 3
phas
e 1
ab
APPROACH 1: REVITALIZATIONAdvantages
• New addition and renovation allows for 21st century learning environments
• Front entry faces Bayside Road
• Separated Bus & Student Drop-Off
• Achieves Site Program
• All Teaching Spaces receive Natural Light and Views
• Defined Pod Structure for Each Grade
APPROACH 1: REVITALIZATIONDisadvantages
• Keeps most of building’s existing infrastructure
• Choke point from main entry to instructional core of the building
• Does not meet all ed spec adjacencies Cafetorium to Gym
Instrumental Music to 4th & 5th
Grades
• Media, Art & Music have to traverse through the open Cafeteria
• No Natural Light in Cafeteria
• Gym SF remains the same
• 1971 addition revitalization is costly
• Admin and Public Program is distant from Instruction (long travel distance)
• Gym is remote from Play Fields
• Differing Floor Elevations
• Nose to Tail Bus Parking
• Longer Construction Duration due to Phasing
APPROACH 2: MODERNIZATIONSite & Floor Plan
2nd floor
APPROACH 2: MODERNIZATIONPhasing Plan
existing building
addition
demolition
renovation
new building
PHASING KEY
phas
e 0
phas
e 2
phas
e 4
phas
e 1
phas
e 3
site
a
b
SY 1
1
2
SY 2 SY 3
3
site
PHASING SCHEDULE 30 Months
4a
4b
APPROACH 2: MODERNIZATIONAdvantages
2nd floor
• New addition and renovation allows for 21st century learning environments
• A clear front entry faces Bayside Road
• Separated Bus & Student Drop-Off
• Achieves Site Program with exception of Outdoor Dining
• Media Center is Prominent on Front of Building
• All Teaching Spaces receive Natural Light and Views
• 2nd Floor allows views toward the Water
• Clear separation of Public vs. Private Secure evening use
APPROACH 2: MODERNIZATIONDisadvantages
2nd floor
• Choke point from main entry to instructional core of the building
• Does not meet ed spec adjacencies for some programs General Music to Stage
Art to Music Suite
Instrumental Music to 4th & 5th Grade
• Gym is remote from Play Fields
• Outdoor Play Areas are remote from Cafeteria
• Differing Floor Elevations
• Media Center is not Centralized
• Must cross Bus Loop from Parking Lot
• Drop-off Loop creates a push condition
• Longer Construction Duration due to Phasing
APPROACH 3A: REPLACE. PWOSite & Floor Plan
2nd floor
APPROACH 3A: REPLACE. PWOPhasing Plan
phas
e 0
phas
e 2
phas
e 4
phas
e 1
phas
e 3
phas
e 5
site
SY 1
1
2
SY 2 SY 3
3
site
PHASING SCHEDULE 30 Months
4
5
existing building
addition
demolition
renovation
new building
PHASING KEY
APPROACH 3A: REPLACE. PWOAdvantages
2nd floor
• New addition and renovation allows for 21st century learning environments
• Separated Bus & Student Drop-Off
• Achieves Site Program
• When students enter they split into two directions eliminating pinch point
• Media Center is Centralized
• All Teaching Spaces receive Natural Light and Views
• Achieves all Adjacencies
• Large Courtyard can serve Controlled Outdoor Learning Environments
• Clear separation of Public vs. Private Secure evening use
• Ideal Building Location Phased While Occupied Replacement
APPROACH 3A: REPLACE. PWODisadvantages
2nd floor
• Gym does not directly open to Play Fields
• May have Differing Floor Elevations
• Single loaded Corridor is Inefficient
• Service is visible from Bayside Road Will require screening
• Longer Construction Duration due to Phasing
APPROACH 3B: REPLACE. PWOSite & Floor Plan
2nd floor
APPROACH 3B: REPLACE. PWOPhasing Plan
existing building
addition
demolition
renovation
new building
PHASING KEY
phas
e 0
phas
e 2
phas
e 4
phas
e 1
phas
e 3
site
SY 1
1
2
SY 2 SY 3
3
site
PHASING SCHEDULE 30 Months
4
site
APPROACH 3B: REPLACE. PWOAdvantages
2nd floor
• Achieves 21st century learning environments
• Separated Bus & Student Drop-Off
• Achieves Site Program
• Media Center is Centralized & Prominent on face of Building
• All Teaching Spaces receive Natural Light and Views
• Achieves all Adjacencies
• Large Plaza focuses the design on Outdoor Learning Environments The shape provides features of a
courtyard without being a courtyard
• All play areas are remote from street
• 2nd Floor allows views toward the Water
• Clear separation of Public vs. Private with secure evening use
• Gym and Cafeteria are tucked away
• Portables do not have to be moved
• Ideal Building Location
APPROACH 3B: REPLACE. PWODisadvantages
2nd floor
• Parking is Remote from Entry Service area is visible from parking
and possible secondary entrance
• Longer Construction Duration due to Phasing
APPROACH 3C: REPLACEMENTSite & Floor Plan
2nd floor
3rd floor
APPROACH 3C: REPLACEMENTViews
APPROACH 3C: REPLACEMENTPhasing Plan
existing building
addition
demolition
renovation
new building
PHASING KEY
SY 1
1
2
SY 2 SY 3
PHASING SCHEDULE 27 Months
site
phas
e 0
phas
e 2
phas
e 1
site
APPROACH 3C: REPLACEMENTAdvantages
2nd floor
3rd floor
• Lighthouse concept acknowledges Nautical identity of Community
• Fronts both roads
• Achieves 21st century learning environments Large, Controlled Collaboration
Spaces
• Separated Bus & Student Drop-Off Very long Drop-off Loop
Preferred Bus Loop Stacking
• Achieves Site Program
• Media Center is Centralized
• All Teaching Spaces receive Natural Light and Views
• Achieves all Adjacencies
• 2nd & 3rd Floors Views of Water
• Clear separation of Public vs. Private with secure evening use
• Ideal Building Location Takes advantage of learning
opportunities from the creek
• Shorter Construction Duration
APPROACH 3C: REPLACEMENTDisadvantages
2nd floor
3rd floor
• Vertical Circulation
• Highest Gross Area Greatest collaboration opportunities
• Parking is remote from entry
SUMMARYArea Comparison
APPROACH 1Phased While Occupied
ExistingDemo.Reno.NewTotalEfficiency
54,893 18,237 36,693 31,666 68,359
73%
APPROACH 2Phased While Occupied
ExistingDemo.Reno.NewTotalEfficiency
54,893 39,466 15,320 52,321 67,641
74%
APPROACH 3APhased While Occupied
ExistingDemo.Reno.NewTotalEfficiency
54,893 51,985
2,912 64,570 67,482
73%
APPROACH 3BPhased While Occupied
ExistingDemo.Reno.NewTotalEfficiency
54,893 54,893
0 67,135 67,135
75%
APPROACH 3C
ExistingDemo.Reno.NewTotalEfficiency
54,893 54,893
0 69,692 69,692
72%
REVITALIZATION MODERNIZATION REPLACEMENT
SUMMARYProgram Comparison
APPROACH 1Phased While Occupied
AdminGuidanceItinerantGrades 1-5Pre-K & KSpecial EdMusicVisual ArtsMedia CtrPEFacilitiesCafetorium
NETGROSS
97%101%
85%100%100%
96%134%
93%98%78%99%
111%
100%101%
APPROACH 2Phased While Occupied
AdminGuidanceItinerantGrades 1-5Pre-K & KSpecial EdMusicVisual ArtsMedia CtrPEFacilitiesCafetorium
NETGROSS
100%106%104%
98%96%
101%98%97%
101%101%
97%103%
99%98%
APPROACH 3APhased While Occupied
AdminGuidanceItinerantGrades 1-5Pre-K & KSpecial EdMusicVisual ArtsMedia CtrPEFacilitiesCafetorium
NETGROSS
100%100%105%
99%99%
100%91%85%
100%100%
96%101%
99%100%
APPROACH 3BPhased While Occupied
AdminGuidanceItinerantGrades 1-5Pre-K & KSpecial EdMusicVisual ArtsMedia CtrPEFacilitiesCafetorium
NETGROSS
102%97%89%
100%98%
100%98%
101%100%100%
95%106%
100%99%
APPROACH 3C
AdminGuidanceItinerantGrades 1-5Pre-K & KSpecial EdMusicVisual ArtsMedia CtrPEFacilitiesCafetorium
NETGROSS
108%134%101%
99%100%101%
99%95%98%
101%105%100%
100%103%
REVITALIZATION MODERNIZATION REPLACEMENT
SUMMARYCost Comparison
APPROACH 1Phased While Occupied
Duration39 months
Construction Cost$22,850,970
Contingency (13%)$2,970,626
Escalation (15.6%)$4,034,624.35
Constr. Budget$29,856,220
Life Cycle
O&M Expense: $8,425,508
40 Year Cost:$38,281,729
APPROACH 2Phased While Occupied
Duration30 months
Construction Cost$22,762,190
Contingency (12%)$2,731,463
Escalation (13.8%)$3,505,377
Constr. Budget$28,999,029
Life CycleO&M Expense: $8,337,011
40 Year Cost:$37,336,040
APPROACH 3APhased While Occupied
Duration30 months
Construction Cost$23,527,973
Contingency (10%)$2,352,797
Escalation (13.8%)$3,558,605
Constr. Budget$29,439,375
Life CycleO&M Expense: $7,908,665
40 Year Cost:$37,348,040
APPROACH 3BPhased While Occupied
Duration30 months
Construction Cost$22,849,118
Contingency (10%)$2,284,912
Escalation (13.8%)$3,455,929
Constr. Budget$28,589,959
Life CycleO&M Expense: $7,867,997
40 Year Cost:$36,457,955
APPROACH 3C
Duration27 months
Construction Cost$23,222,447
Contingency (10%)$2,322,245
Escalation (12.8%)$3,256,948
Constr. Budget$28,801,640
Life CycleO&M Expense: $8,089,939
40 Year Cost:$36,891,578
REVITALIZATION MODERNIZATION REPLACEMENT
SUMMARYOveral l Results
APPROACH 1Phased While Occupied
ExistingDemo.Reno.NewTotalEfficiencyDuration
Const. Budget
Life Cycle
54,893 18,237 36,693 31,666 68,35973.2%
39months
$29,856,220
$38,281,729
APPROACH 2Phased While Occupied
ExistingDemo.Reno.NewTotalEfficiencyDuration
Const. Budget
Life Cycle
54,893 39,466 15,320 52,321 67,64174.8%
30months
$29,999,029
$37,336,040
APPROACH 3APhased While Occupied
ExistingDemo.Reno.NewTotalEfficiencyDuration
Const. Budget
Life Cycle
54,893 51,985
2,912 64,570 67,48273.5%
30months
$29,439,375
$37,348,040
APPROACH 3BPhased While Occupied
ExistingDemo.Reno.NewTotalEfficiencyDuration
Const. Budget
Life Cycle
54,893 54,893
0 67,135 67,135
75% 30
months
$28,589,959
$36,457,955
APPROACH 3C
ExistingDemo.Reno.NewTotalEfficiencyDuration
Const. Budget
Life Cycle
54,893 54,893
0 69,692 69,692
72% 27
months
$28,801,639
$36,891,578
REVITALIZATION MODERNIZATION REPLACEMENT
RECOMMENDED APPROACHBy Stakeholder Advisory Group
Stakeholder Advisory Group Unanimously Recommends the Replacement Approach
• Offers ideal building and site learning environments and adjacencies
• Eliminates failing existing building conditions
• All options were relatively equal in construction budget
• Reduces complexity and duration of construction limiting interference to instruction
• Offers best life cycle cost analysis