BCPC LOADING JETTY AND STOCK PILE Perbedaan ketinggian elevasi air dengan daratan ± 5 meter dari level
muka air Survey 27 July 2011
Kondisi Lahan untuk Stock Pile Survey Tgl 27 July 2011
Orientation of Location from mine pit to loading jetty
Hauling Road 40 KM
Loading Jetty
Schematic Flow Diagram Stock Pile and Loading Jetty
MINING AREA ROM STOCKPILE AT MINESITE
MINE - HAUL ROAD LONG DISTANCEHAUL ROAD
COAL TERMINAL
DUMP STATION
EMERGENCY STOCKPILE
CRUSHINGSTATION
BARGE LOADING CONVEYOR
BARGE
Loading Conveyor
Stock pile and Loading conveyor conceptual
Conveyor Lay Out
Conveyor Configuration
Propose Coal Handling and stock pile, for reference only
Loading conveyor 1500 ton/hour capacity
Other Optional Propose Plot Plan Gadur Jetty and Mess,Housing and other facility
Proposed for mess
and housing facility
Extend Stock Pile
Stock pile and reclaim feeder
Contoh Pondasi Jetty
Dolphin to Accommodate 8000 DWT Barge
Loading jetty for 8000 DWT Barge
Coal pile configuration on 8000 DWT barge
Loading conveyor 1500 ton/hours
Long Profile Of Loading JETTY Accommodate 8000 DWT Barge
Walkways on the trestle
Typical Tower Loading Conveyor ke Barge
CPT Location and land boundary yang dilakukan oleh GRM
Stock Pile,Loading Conveyor dan Loading Jetty untuk 8000 DWT
Survey tanggal 29 July 2011
CONE PENETRATION TEST CPT-10 DENGAN KEDALAMAN 27,4 M
Hasil Cone Penetration Test CPT-10
Contoh Laporan hasil Sondir sebagai referensi
Contoh Laporan Sondir untuk design pondasi dan tiang pancang
Contoh laporan Deep bore hole untuk piling dan pondasi
Kondisi Banjir 10 tahunan menurut data penduduk lokal elevasi tinggi kurang lebih 2 meter dari muka tanah
Ketinggian elevasi air pada saat banjir 10 tahunan,pada posisi 1,2 km dari bibir sungai
Kondisi Tanah di Jetty
Tanah keras 350 mDari bibir sungai
Tanah lembekberlumpur 1,2 km dari bibir sungai
Contoh test beban untuk mendapatkan consolidated settlement dengan menggunakan model PLAXIS 2 D
Indikasi tanah Lembek/Rawa-2 dari hauling road sepanjang 10,5 KM
Tanah lembek dan berawa
Project Plan Chart
Jetty &Stock Pile Milestone
• Construction of Loading and Stock Pile / Jetty Milestone• • Item Job description PIC Est Completion• • AMDAL Yuanito October 2011• • Land Identification/Additional Sukadi August 2011• • Land Acquisition Sukadi End Of Sept • • Boundary identification Construction team Early Oct 2011• • BED/DED Of loading jetty Paul/Ardyan/Adi End Oct 2011• Stock pile, coal handling• Bathymetry,Geotech, Topo• Hydrology, estimate CBM fill• • Set up Temporary facility Adi Sumanto Nov 2011• • Stacking out area for land clearing Adi Sumanto Nov 2011• And checking final elevation• Conveyor center line, jetty position• Stock pile and chain feeder position• Coal Crushing Plant,Site Facility• • Selected Land clearing Contractor Adi Sumanto Oct 2011• • Mobilization land clearing sub con Adi Sumanto Nov 2011• • Land Clearing Activities Adi Sumanto March 2012•