    BASIC CONCEPT OF Q.S.

    BASIC CONCEPT

    OF

    QUANTITY SURVEYING (Q.S.)

    -PREPARED BY MANIRUL ISLAM

    Quantity Surveyor (Civil), Teejan, Oman1. UNITS OF MEASUREMENTS

    SL.NO ITEMS

    UNITFOR LABOUR

    WORK

    UNITFOR COMPLETED ITEM(MATERIAL+LABOUR)

    01 Excavation cum / cft cum / cft

    02 Back filling /

    soling

    cum / cft cum / cft

    03 Footing

    (Concreting)

    No. cum / cft

    04 P.C.C sqm / sft cum / cft

    05 Column / Beam

    / Lintel

    Concreting

    rm / rft cum / cft

    06 Slab

    concreting

    sqm / sft cum / cft

    07 Pardi / Chajja /

    Loft

    Concreting

    sqm / sft cum / cft

    08 Staircase

    Concreting

    No. (per step) cum / cft

    09 Brick masonry

    10cm to 15cm

    thick

    sqm / sft sqm / sft

    10 Brick masonry

    23cm thick

    sqm / sft cum / cft

    11 Brick masonry

    35cm thick

    cum / cft cum / cft

    12 U.C.R.

    masonry

    cum / cft cum / cft

    13 Plastering /

    Pointing

    sqm / sft sqm / sft

    14 Flooring /

    Tiling

    sqm / sft sqm / sft

    15 Skirting / Steps rm / rft rm / rft

    16 Sill Patti rm / rft rm / rft

    17 Kitchen otta No. or rm / rft rm / rft

    18 Painting sqm / sft sqm / sft

    19 Doors /

    Windows

    No. or sqm / sft sqm / sft

    20 Plumbing rm / rft rm / rft

    http://manirengineerdiary.blogspot.com/2012/04/useful-data-for-estimation-of.htmlhttp://manirengineerdiary.blogspot.com/2012/04/useful-data-for-estimation-of.htmlhttp://manirengineerdiary.blogspot.com/2012/04/useful-data-for-estimation-of.html
  • 7/30/2019 Basic Concept of q

    2/13

    pipes

    21 Plumbing

    fitting /

    sanitary ware

    No. No.

    22 Water tanks ltr. ltr.

    23 Septic tanks ltr. No. of users

    24 Road work

    (asphalting)

    sqm / sft sqm / sft

    25 Electrical

    cabling /

    Wiring

    rm / rft rm / rft

    26 Electrical

    points

    No. No.

    27 Water-proofing

    to terrace

    sqm / sft sqm / sft

    28 Water-proofing

    of W.C

    No. sqm / sft

    29 Gardening

    (lawn)

    sqm / sft sqm / sft

    30 Gardening

    (trees /

    bushes)

    No. No.

    2. CONVERSION TABLE

    SR.NO UNIT EQUIVALENT UNITS

    01 1 meter 100 centimeter

    02 1 meter 3.28 feet

    04 1 centimeter 0.393 inch

    05 1 foot 0.305 meter

    07 1 inch 2.54 centimeter/ 25.4 mm

    08 1 tone 1000 kg

    09 1 kg 1000 grams

    10 1 kg 0.001 tone

    11 1 gram 0.001 kg

    13 1 sq meter 10.76 sq feet

    14 1 brass 100 sq feet

    15 1 brass 9.29 sq meter

    16 1 cu meter 35.28 cu feet

    17 1 cu meter 1000 liters

    18 1 cu feet 28.315 liters

    19 1 brass 100 cu feet

    20 1 cu feet 0.0283 cu meter

    21 1 liter 0.001 cu meter

  • 7/30/2019 Basic Concept of q

    3/13

    22 1 liter 0.0353 cu feet

    23 1 cu feet 0.01 brass

    24 1 cu meter 0.35 brass

    3. WEIGHTS OF BUILDING MATERIAL

    SR.NO MATERIAL THEORETICAL WEIGHT IN Kg/cum

    01 Cement 1440

    02 Steel 7850

    03 Dry sand 1600

    04 River sand 1840

    05 Stone 2850 to 2960

    06 Water 1000

    07 P.C.C 2240

    08 R.C.C. (2% steel) 2420

    09 Bricks 1600 to 1920

    10 Brick masonry 192011 Soil 1760

    12 Cement concrete block (solid) 1800

    13 Cement mortar 2080

    14 Lime mortar 1760

    15 Lime 640

    16 Glass 2530

    17 Teak wood 670 to 830

    18 Sal wood 990

    19 Marble stone 2620

    20 Granite stone 2460 to2800

    21 Cuddappa 2720

    22 Bitumen 1040

    RATE

    ANALYSIS

    1. P.C.C. FOOTING (1:3:6)

    Consider 10 cum volume.

    Volume of dry concrete = 15.2 cum. (Adding 50 to 52% for compaction, wastages etc)

    Proportion (1:3:6) = 1+3+6 = 10

  • 7/30/2019 Basic Concept of q

    4/13

    Volume of cement = 15.2/10 = 1.52 cum.

    = 1.52/0.035 = 43.4 bags ~ 44 bags.

    Volume of sand = 1.52 X 3 = 4.56 cum.

    Volume of metal = 1.52 X 6 = 9.12 cum.

    MATERIAL QTY RATE PER AMOUNT

    CEMENT 44 265 Rs. Bag 11660.00

    SAND 4.56 1270 Rs. Cum 5791.20

    METAL 9.12 900 Rs. Cum 8208.00

    LABOURS NO. RATE PER AMOUNT

    HEAD MASON 02 400 Rs. Day 800.00

    MASON 04 250 Rs. Day 1000.00

    MALE COOLIE 16 200 Rs. Day 3200.00

    FEMALE COOLIE 07 150Rs. Day 1050.00

    TOTAL = 31709.2

    TOOLS & PLANTS L.S. 1% = 317.092

    TOTAL=31709.2+317.092 = 32026.292

    WATER & ELECTRIC CHARGES 2% = 640.52

    TOTAL=32026.292+640.52 = 32666.818

    CONTRACTORS PROFIT 25% = 8166 .705

    GRANT TOTAL= 3266.818+8166.705 = 40833.505

    RATE FOR 10 CU.M = 40833.505 Rs.

    RATE FOR PER CU.M = 4083.350 Rs.

    2. BRICK WORK

  • 7/30/2019 Basic Concept of q

    5/13

    Considering 1:4 ratios for cement mortar in 150mm thick brickwork.

    Calculation of quantity for 5 cu.m volume in brickwork as follows:

    Size of brick = 19 cm x9 cm x9 cm.

    Vol. of brick = (0.19 x 0.09 x 0.09) cu.m

    = 0.00154cu.m.

    Vol. of brick with cement mortar

    = (0.2 x 0.1 x 0.1) cu.m

    = 0.002 cu.m.

    No. of bricks in 5 cu.m

    = 5 (vol. of one brick with mortar).

    = 5 0.002

    = 2500

    Vol. of 2500 bricks = 2500 x vol. of one brick without mortar.

    =2500 x 0.00154

    = 3.85cu.m.

    Vol. of mortar = 5 3.85 = 1.15 cu.m.

    Add 15% (Bulkage + wastage)

    \ Vol. of wet mortar = 1.15 + {1.15 x (15 100)}

    = 1.323cu.m

    Vol. of dry mortar = 1.323 + 33% in wet mortars for interlocking =1.759cu.m

    Vol. of cement = 1.759 (1+4) =0.352cu.m

    \ No. of cement bags = 0.352 0.035

    =10.057bags.

  • 7/30/2019 Basic Concept of q

    6/13

    10.00bags

    Vol. of sand = 0.352 x 4

    = 1.408cu.m.

    ITEM DESCRIPTION QUANTITY RATE RS. AMOUNT RS.

    a. Material

    Cement

    Sand

    Bricks

    10 bags

    1.408 cu.m

    2500 Nos.

    250/bag

    1270/cu.m

    4/no.

    2500.00

    1788.16

    10000.00

    Mason

    Head Mason

    Male coolie

    4

    1

    10

    250/day

    400/day

    200/day

    1000.00

    400.00

    2000.00

    Total 17688.16

    c. Tools & Plants 1% 0f total 176.88

    Total 17865.04

    d. Water charges 2% Of total 357.30

    Total 18222.34

    e. Supervisor, Overhead & Profit 25% Of the total 4555.58

  • 7/30/2019 Basic Concept of q

    7/13

    Total 22777.92

    RATE FOR 5 CU.M = 22777.92 Rs.

    RATE FOR PER CU.M = 4555.58 Rs.

    3. R.C.C. COLUMN

    Consider 10 cum volume.

    Grade of concrete M 40

    Proportion (1: 1.808:1.616) 1+1.808+1.616= 4.424 {as per mix design}

    Volume of dry concrete = 15.2 cum. (52% for compaction & wastages)

    Volume of Cement = 15.2/4.424 = 3.435 cum.

    Cement bags = 3.435/0.035 = 98.12 ~ 99 Bags.

    Sand = 3.435 X 1.808 = 6.21 cum.

    Metal = 3.435 X 1.616= 5.55 cum.

    MATERIAL QTY RATE PER AMOUNT

    CEMENT 99 265 Rs. Bag 26235.00

    SAND 6.21 1270 Rs. Cum 7886.70

    METAL 5.55 900 Rs. Cum 4995.00

    LABOURS NO. RATE PER AMOUNT

    HEAD MASON 1 400 Rs. Day 400.00

  • 7/30/2019 Basic Concept of q

    8/13

    MASON 3 250 Rs. Day 750.00

    MALE COOLIE 16 200 Rs. Day 3200.00

    BHISTI 7 150 Rs. Day 1050.00

    CARPENTER 4 200 Rs. Day 800.00

    HELPER 8 125 Rs. Day 1000.00

    TOTAL = 46316.7

    Tools & Plants charges 1% = 463.167

    TOTAL=46316.7+463.167 = 46779.86

    Water charges 2% = 935.59

    TOTAL=46779.86+935.59 = 47715.45

    Contractors profit 25% = 11928.8

    TOTAL = 47715.45+11928.8 = 59644.31

    RATE FOR 10 CUM = RS. 59644.31/-

    RATE FOR PER CU.M = RS. 5964.43/-

    4. INTERNAL PLASTER

    12mm thick internal plaster

    Considering 100sqm area

    Proportion of C:M = 1:4

    Summation of proportion =5

  • 7/30/2019 Basic Concept of q

    9/13

    Quantity of one cement bag = 0.035cum

    Quantity of wet mortar = 0.012 x 100 = 1.2cum

    Adding 15% wastage = 1.2 + (1.2 x 0.15) =1.38cum

    Volume of dry mix = 1.38 + (1.38 x 1/3) =1.84cum

    Volume of cement = (dry volume / 5) x 1

    = (1.84 /5) x 1

    = 0.368cum

    = 0.368 / 0.035

    =10.5 bags

    Volume of sand = (dry volume / 5) x 4

    = (1.84 /5) x 4

    = 1.472 cum

    MATERIALS QUANTITY RATE (RS) AMOUNT (RS)

    Sand 1.472cum 1300 /cum 1913

    Cement 10.5bags 250 / bag 2625

    Scaffolding L.S 550 550

    LABOURS QUANTITY RATE (RS) AMOUNT (RS)Mason 8nos 200 1600

    Helper 12nos 90 1080

    Total 7768

    Tools & Plants 1% 0f total 77.68

    Total 7845.68

    Water charges 2% Of total 156.91

    Total 8002.59

  • 7/30/2019 Basic Concept of q

    10/13

    Supervisor, Overhead & Profit 25% Of the total 2000.65

    Total 10003.23

    RATE FOR 100m = 10003.23Rs.

    RATE FOR 1m = 100.03Rs.

    5. EXTERNAL PLASTER

    20mm thick external plaster

    Considering 100sqm area.

    Proportion for mix C:M = 1:4.

    Summation of proportion = 5.

    Quantity of one cement bag = 0.035cum.

    Quantity of wet mortar = 0.02 x 100 = 2cum.

    Adding 20% wastage = 2 +( 2 x 0.2 ) = 2.4cum.

    Volume of dry mix = 2.4 + (2.4 x 1/3) = 3.2cum.

    Volume of cement = (dry volume / 5) x 1

    = (3.2 /5) x 1

    = 0.64cum

    = 0.64 / 0.035

    = 18.3 bags

    = 19 bags

    Volume of sand = (dry mix / 5) x 4

    = (3.2 /5) x 4

    = 2.56cum.

    PARTICULAR QUANTITY RATE(RS) AMOUNT(RS)

    Materials

  • 7/30/2019 Basic Concept of q

    11/13

    Sand 2.56cum 1300 3328

    Cement 19bags 250 4750

    Scaffolding L.S. 550 550

    Labors

    Mason 8nos 200 1600

    Helper 12nos 90 1080

    Total 11708.5

    Tools & Plants 1% 0f total 117.08

    Total 11825.60

    Water charges 2% Of total 236.512

    Total 12062.112

    Supervisor, Overhead & Profit 25% Of the total 3015.53

    Grand Total 15077.64

    RATE FOR 100m = 15077.64Rs.

    RATE FOR 1m =150.77Rs.

    USEFULL DATA FOR ESTIMATION

    Mixer Machine Capacity:

    Sr. No: Capacity Dry volume in cumWet volume incum

    Output per hourPetrol consumption per hourin litre

    Remarks

    1 6' / '4' 0.170 0.113 2.266 1.000

    Each batch of concrete requireabout 3 minutes of mixing

    2 7' / '5' 0.198 0.142 2.832 1.400

    3 10' / '7' 0.283 0.198 3.965 1.700

    Cement Mortar:

    Sr. No: Ratio Cement in Kg Cement in bag Sand in 'cum'. Remarks

    http://www.blogger.com/blogger.g?blogID=1059917570796814997http://www.blogger.com/blogger.g?blogID=1059917570796814997http://www.blogger.com/blogger.g?blogID=1059917570796814997
  • 7/30/2019 Basic Concept of q

    12/13

    1 1 : 1' 1054 21.08 0.73

    Water may be generallytaken as 140 litres per 'cum'.

    50 kg. cement bag size is (400350mm x 250mm internally. Vper is = 0.035 'cum'.

    2 1 : 2' 686 13.72 0.96

    3 1 : 3' 491 9.82 1.02

    1 1 : 4' 380 7.60 1.05

    5 1 : 6' 253 5.06 1.05

    6 1 : 8' 192 3.84 1.06

    Cement Concrete:

    Sr. No: Ratio Cement in Kg Cement in bag Sand in 'cum'. Aggregate in 'cum'. Remarks

    11 : 4 : 8' NominalMix

    161 3.22 0.45 0.89

    21 : 3 : 6' NominalMix 212 4.24 0.44 0.88

    3 1 : 2 : 4' M15 317 6.34 0.44 0.88

    4 1 : 1.5 : 3' M20 403 8.06 0.42 0.84

    5 1 : 1 : 2' M25 555 11.10 0.385 0.77

    Remarks

    Considering dry density of concrete is 1.54 'cum'.

    Aggregate may be used 60% : 40% ratio of 20mm and 10mm down respectively.

    Water required for concrete varies from 28 to 35 litres per bag of (50kg) cement depending on the mix and proportion.

    Reinforcement (Steel) works:

    Reinforcement usually required in various situation is as follows:

    Culvert and foundaion = 0.5% to 1%

    Slab and landing = 0.5% to 1.5%

    Arch, wal, floor and flate roof = 1% to 2%

    Column and brace = 2 % to 3%

    Column and brace = 2 % to 3%

    Pile = 2% to 5%

    Remarks

  • 7/30/2019 Basic Concept of q

    13/13

    Binding or tying wire for reinforcement may be taken as 0.9 to 1.3 kg per quintal of reinforcement.

    One 50 kg. bag of cement will make approximately following volume of concrete:

    The equivalent size of a box for 50 kg. cement bag is 400mmx350mmx250mm internally.

    0.133 'cum' of 1 : 1.5 : 3 concrete.

    0.166 'cum' of 1 : 2 : 4 concrete.

    0.140 'cum' of 1: 1 : 2 concrete.

    0.250 'cum' of 1: 3 : 6 concrete.

    0.333 'cum' of 1: 4 : 8 concrete.

    0.400 'cum' of 1: 5 : 10 concrete.

    0.500 'cum' of 1: 6 : 12 concrete.