baseline risk assessment - national treasury wall...method statement: method statement to be...

29
BASELINE RISK ASSESSMENT TPL Bund Wall ad Bund Floor Upgrade – Cluster 7 Risk Assessment Template BRIEF DESCRIPTION OF WORK / ACTIVITY: Upgrading of bund walls and bund floors. CONTRACT NUMBER: PYP/ LOCATION : TPL Airport RISK ASSESSMENT TEAM TITLE / APPOINTMENT SIGNATURE COMMENTS Initials & Surname Contractor OSH 16.2 Appointee CR 8.1 Construction Manager CR 9.1 Risk Assessor CLIENT “B” Approval – CLIENT Dumisile Mthalane Project Manager Reg Motloung Client HSSE Manager EXISTING CONTROL MEASURES (SUBMIT & ATTACH TO THE RISK ASSESSMENT) Procedures : SWP’s, Permit to Work. Method statement: Method Statement to be supplied.

Upload: vuongngoc

Post on 06-Jul-2018

234 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: BASELINE RISK ASSESSMENT - National Treasury Wall...Method statement: Method Statement to be supplied. BASELINE RISK ASSESSMENT TPL Bund Wall ad Bund Floor Upgrade –Cluster 7 …

BASELINE RISK ASSESSMENT

TPL Bund Wall ad Bund Floor Upgrade – Cluster 7

Risk Assessment Template

BRIEF DESCRIPTION OF WORK / ACTIVITY: Upgrading of bund walls and bund floors.

CONTRACT NUMBER: PYP/ LOCATION : TPL Airport

RISK ASSESSMENT TEAM TITLE / APPOINTMENT SIGNATURE COMMENTS

Initials & Surname Contractor

OSH 16.2 Appointee

CR 8.1 Construction Manager

CR 9.1 Risk Assessor

CLIENT “B” Approval – CLIENT

Dumisile Mthalane Project Manager

Reg Motloung Client HSSE Manager

EXISTING CONTROL MEASURES (SUBMIT & ATTACH TO THE RISK ASSESSMENT)

Procedures : SWP’s, Permit to Work.

Method statement: Method Statement to be supplied.

Page 2: BASELINE RISK ASSESSMENT - National Treasury Wall...Method statement: Method Statement to be supplied. BASELINE RISK ASSESSMENT TPL Bund Wall ad Bund Floor Upgrade –Cluster 7 …

BASELINE RISK ASSESSMENT

TPL Bund Wall ad Bund Floor Upgrade – Cluster 7

Risk Assessment Template

Task Activity : Cluster 8 – Bund Wall and Bund Floor Upgrade.

Ite

m

Task or Activity Hazards (Potential danger) (Energy)

Risk/ Possible Consequence Likely to happen and impact.

Initial Risk Score

Existing & Proposed Control Measures

Revised Risk Score

Action assigned to

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

1.

SITE ESTABLISHMENT

a.

Access to be a main consideration when positioning offices,

stores and parking areas on site during planning

stage. Possible one way traffic to be introduced.

Restricted access to parking and delivery areas to

storage areas. Damage to transport and plant. 3 2 9

Proper layout of site by Construction Manager and Site Agent taking into consideration all

transport plant and material movements and storage on site. Site Agent to check layout

Drawings. To compare with OHS Act requirements and whether they are to SANS

standards.

2 2 5

Construction Vehicle and Mobile Plant Supervisor.

b. Storage of hazardous

chemicals and substances.

Fire may spread to adjacent buildings and plant if is too

close.

Burns on all parts of body. Damage to plant and property.

4 2 14

A slab with a bund wall capable of carrying 110% of the tank capacities must be constructed for the tanks to stand in.

MSDS to be available for the content stored in the bund.

The store should be fitted with a lock and controlled by a supervisor or controller. Signage to be posted to identify the fire

extinguisher and that no open flames are allowed in this area. Ensure that the fire

extinguisher is present at all times.

3 2 9 HCS Supervisor

Page 3: BASELINE RISK ASSESSMENT - National Treasury Wall...Method statement: Method Statement to be supplied. BASELINE RISK ASSESSMENT TPL Bund Wall ad Bund Floor Upgrade –Cluster 7 …

BASELINE RISK ASSESSMENT

TPL Bund Wall ad Bund Floor Upgrade – Cluster 7

Risk Assessment Template

Task Activity : Cluster 8 – Bund Wall and Bund Floor Upgrade.

Ite

m

Task or Activity Hazards (Potential danger) (Energy)

Risk/ Possible Consequence Likely to happen and impact.

Initial Risk Score

Existing & Proposed Control Measures

Revised Risk Score

Action assigned to

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

c.

All cables from distribution board to

offices, and to be under-ground. The

distribution board is to stand on a firm level base and should be locked at all times.

Damaged cables loose wires exposed.

Electrocution 4 3 18

Only a competent Electrician to do the Electrical connection. Electrician to ensure that

the cables are insulated and not exposed. Electrician to issue a Compliance Certificate to the contractor once a full inspection has been

done.

3 2 9

Temporary Electrical

Installations Supervisor

d.

Security fencing minimum height of 1

meter around site area together with double

access gates.

Access to unauthorised

persons. Injury to persons. 3 2 9

Construction Manager to put system of control in place. No unauthorised entry signs to be

posted and access to be controlled. 2 2 5

Construction Manager

e.

Services to be made available during site

establishment. Firefighting equipment.

First aid boxes. First aider.

Drinking water. Toilets.

Sanitation. Eating area with

sufficient seating.

Not having the essential services at hand.

Health/personal hygiene of employees.

Loss of property through fire. 2 3 8

Site Agent to see that these requirements are on site from start of site establishment.

Complying with the Facilities Regulation and Construction Regulation under Welfare

Facilities.

2 2 5 Safety Officer

f. Safety sign & notice

board to be placed close to entrance of main

Not informing employees and public what the site

rules are.

Injury to persons. Damage to property.

2 3 8 SABS standard notices/Posters to be displayed.

Site manager to check that board has been erected.

2 2 5 Safety Officer

Page 4: BASELINE RISK ASSESSMENT - National Treasury Wall...Method statement: Method Statement to be supplied. BASELINE RISK ASSESSMENT TPL Bund Wall ad Bund Floor Upgrade –Cluster 7 …

BASELINE RISK ASSESSMENT

TPL Bund Wall ad Bund Floor Upgrade – Cluster 7

Risk Assessment Template

Task Activity : Cluster 8 – Bund Wall and Bund Floor Upgrade.

Ite

m

Task or Activity Hazards (Potential danger) (Energy)

Risk/ Possible Consequence Likely to happen and impact.

Initial Risk Score

Existing & Proposed Control Measures

Revised Risk Score

Action assigned to

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

gate

g.

Lay down areas to be sufficient in size. Lay

down areas to be sufficiently barricaded

and signs posted.

With inadequate space various materials will be

stacked on top of each other causing unstable stacks.

Injury to persons loading, unloading materials.

2 3 8 Allow sufficient space for lay down area during

planning stage of site layout. Access to be considered important.

2 2 5 Stacking and

Storage Supervisor

h. Toilets are to be well

ventilated. No ventilation in toilets may cause germs to propagate.

Possible health problems due to germs.

3 2 9 Vent pipes to be fitted if required.

Supervisor to check if he is satisfied with ventilation.

3 1 6 SHE Rep

i. Lifting heavy items by

hand. Ergonomics.

Incorrect posture. Items to heavy to be

handled. Will lead to serious back strains. 2 3 8

Ensure that employees are trained in the correct lifting techniques. Ensure that there is sufficient amount of employees to carry heavy

items.

2 2 5 Safety Officer

j. Lifting and rigging of temporary offices.

Crane truck loaded unsafely. Property damage and possible

fatality. 4 2 14

Correct lifting techniques, lifting and rigging procedures, Lifting plan and competent employees to conduct lift. Loading to be

supervised by a competent supervisor, loading to be done by a competent and trained

operator.

2 2 5 Lift supervisor

Crane truck overturning

while offloading. Property damage and possible

fatality. 4 2 14

Loading to be supervised by a competent supervisor, operating of crane to be done by a

2 2 5 Lift Supervisor

Page 5: BASELINE RISK ASSESSMENT - National Treasury Wall...Method statement: Method Statement to be supplied. BASELINE RISK ASSESSMENT TPL Bund Wall ad Bund Floor Upgrade –Cluster 7 …

BASELINE RISK ASSESSMENT

TPL Bund Wall ad Bund Floor Upgrade – Cluster 7

Risk Assessment Template

Task Activity : Cluster 8 – Bund Wall and Bund Floor Upgrade.

Ite

m

Task or Activity Hazards (Potential danger) (Energy)

Risk/ Possible Consequence Likely to happen and impact.

Initial Risk Score

Existing & Proposed Control Measures

Revised Risk Score

Action assigned to

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

trained and competent operator, outriggers of crane truck to be fully extended, truck to stand on firm level ground and maximum mass load

not to be exceeded.

Sling failure while

offloading. Property damage and possible

fatality. 4 2 14

Sling to be load tested and certified safe for use, MML to be displayed on the sling, sling to

be inspected daily before use, slinging to be done by a trained and competent rigger and

task to be supervised by a competent supervisor.

2 2 5 Lift Supervisor

Incorrect slings being used. Property damage and possible

fatality. 4 2 14

Rigging to be done by a trained and competent rigger and task to be supervised by a competent supervisor. Slings to be checked by supervisor.

2 2 5 Lift Supervisor

Employee being struck by

load Possible fatality. 4 2 14

Load to be guided by means of guide ropes and all employees to stand well clear of the load

being lifted. Work area to be barricaded. Task to be supervised by a competent supervisor.

2 2 5

Lift Supervisor

Hydraulic pipe failure. Soil pollution, property damage and

serious injuries. 2 2 5

Daily checks to be done on all hydraulic pipes. Maintenance schedule to be followed. If any problems, it must be reported to your direct

supervisor.

2 1 3

Lift Supervisor

Hydraulic leaks. Soil pollution, property damage and

serious injuries. 2 2 5

Daily start up checks to be done by the operator, maintenance schedule to be followed. Leaks to be reported to the

supervisor of Construction Manager and to be

2 1 3

Lift Supervisor

Page 6: BASELINE RISK ASSESSMENT - National Treasury Wall...Method statement: Method Statement to be supplied. BASELINE RISK ASSESSMENT TPL Bund Wall ad Bund Floor Upgrade –Cluster 7 …

BASELINE RISK ASSESSMENT

TPL Bund Wall ad Bund Floor Upgrade – Cluster 7

Risk Assessment Template

Task Activity : Cluster 8 – Bund Wall and Bund Floor Upgrade.

Ite

m

Task or Activity Hazards (Potential danger) (Energy)

Risk/ Possible Consequence Likely to happen and impact.

Initial Risk Score

Existing & Proposed Control Measures

Revised Risk Score

Action assigned to

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

repaired by the workshop. Drip trays to be inserted underneath leak to prevent soil

contamination. Contaminated areas should be rehabilitated.

Fire or explosion. Property damage and possible

fatality. 4 2 14

Remove all flammable materials such as fuel, oil and debris from the engine. Do not flame cut

any pipe or tank that contains flammable fluids. Wiring must be kept in good order and no smoking or naked flames during refueling.

2 2 5 Lift Supervisor

2. USE OF CONSTRUCTION VEHICLES AND MOBILE

PLANT

a. Starting up of

construction vehicle or mobile plant.

Employee being injured by standing on, under or to

close to the engine or wheels.

Serious body injuries 3 2 9

All protective guards and cover must be in place before start of the engine. The Construction

Vehicle or Mobile Plant must be operated by a competent and trained operator.

2 2 5

Construction Vehicle and Mobile Plant Supervisor

Engine failure. Damage to equipment, loss of

production. 3 2 9

Engine to be started according to procedure and maintenance schedule to be followed.

2 2 5

Construction Vehicle and Mobile Plant Supervisor

b. Operating construction

vehicles and mobile plant.

Colliding into other plant. Damage to equipment and property. 3 2 9 Construction Vehicle or Mobile Plant to be

operated by a competent and trained operator. Operator to keep to the designated area of

2 2 5 Construction Vehicle and Mobile Plant

Page 7: BASELINE RISK ASSESSMENT - National Treasury Wall...Method statement: Method Statement to be supplied. BASELINE RISK ASSESSMENT TPL Bund Wall ad Bund Floor Upgrade –Cluster 7 …

BASELINE RISK ASSESSMENT

TPL Bund Wall ad Bund Floor Upgrade – Cluster 7

Risk Assessment Template

Task Activity : Cluster 8 – Bund Wall and Bund Floor Upgrade.

Ite

m

Task or Activity Hazards (Potential danger) (Energy)

Risk/ Possible Consequence Likely to happen and impact.

Initial Risk Score

Existing & Proposed Control Measures

Revised Risk Score

Action assigned to

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

work. Supervisor

Employee being run over by

Construction Vehicle or Mobile Plant.

Serious body injuries or fatality. 3 2 9

Construction Vehicle or Mobile Plant to be operated by a competent and trained operator. Employees to keep of the Construction Vehicle or Mobile Plant during operations. Ensure that the operator has seen you before approaching.

Construction Vehicle or Mobile Plant to be fitted with a reverse hooter.

2 2 5

Construction Vehicle and Mobile Plant Supervisor

Construction Vehicle or

Mobile Plant overturning. Damage to equipment and serious

body injury. 3 2 9

Construction Vehicle or Mobile Plant to be operated by a trained and competent operator,

Construction Vehicle or Mobile Plant to be operated at a safe angel, task to be supervised

by a competent supervisor.

2 2 5

Construction Vehicle and Mobile Plant Supervisor

Construction Vehicle or Mobile Plant working in

incorrect place can cause damage to other plant and

employees

Damage to equipment and serious body injury.

3 2 9 Task to be supervised by a competent

supervisor at all times. 2 2 5

Construction Vehicle and Mobile Plant Supervisor

Operator exposed to noise. NIHL 4 2 14 Operator to make use of ear protection and

take frequent brakes. 2 2 5

Construction Vehicle and Mobile Plant Supervisor

Operator exposed to dust. Asphyxiation. 4 2 14 Operator to make use of Dust masks. 3 2 9 Construction Vehicle and

Page 8: BASELINE RISK ASSESSMENT - National Treasury Wall...Method statement: Method Statement to be supplied. BASELINE RISK ASSESSMENT TPL Bund Wall ad Bund Floor Upgrade –Cluster 7 …

BASELINE RISK ASSESSMENT

TPL Bund Wall ad Bund Floor Upgrade – Cluster 7

Risk Assessment Template

Task Activity : Cluster 8 – Bund Wall and Bund Floor Upgrade.

Ite

m

Task or Activity Hazards (Potential danger) (Energy)

Risk/ Possible Consequence Likely to happen and impact.

Initial Risk Score

Existing & Proposed Control Measures

Revised Risk Score

Action assigned to

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

Mobile Plant Supervisor

Driving into trench or

excavations. Damage to equipment. 3 2 9

Construction Vehicle or Mobile Plant to be operated by a competent and trained operator.

Task to be supervised by a competent supervisor.

2 2 5

Construction Vehicle and Mobile Plant Supervisor

c. Maintenance. Hydraulic pipe bursting

during operation. Hydraulic oil spills causing soil

pollution. Damage to equipment. 2 2 5

Burst pipe to be replaced by workshop and maintenance schedule to be followed.

2 1 3

Construction Vehicle and Mobile Plant Supervisor

Employee being injured while working on

Construction Vehicle or Mobile Plant.

Serious body injuries. 3 2 9 Maintenance and repair work to be done by a

competent person and machine must be locked out at all times.

2 1 3

Construction Vehicle and Mobile Plant Supervisor

Hydraulic oil being injected into employee while

working on Construction Vehicle or Mobile Plant.

Serious body injuries and health impact.

2 2 5 Make use of a board or cardboard when checking for leaks in the hydraulic pipes.

2 1 3

Construction Vehicle and Mobile Plant Supervisor

Hydraulic oil leaking. Soil pollution. 2 2 5

Leaks to be reported to the Construction Manager and to be repaired by the workshop.

Drip trays to be installed under the Construction Vehicle.

2 1 3

Construction Vehicle and Mobile Plant Supervisor

Employee injured while

changing the wheels on the Construction Vehicle or

Back, arm, foot, leg and hand injury. 3 2 9 Changing of the wheels to be performed by a

competent person, and tyres must be taken off site to be repaired.

2 2 5 Construction Vehicle and Mobile Plant

Page 9: BASELINE RISK ASSESSMENT - National Treasury Wall...Method statement: Method Statement to be supplied. BASELINE RISK ASSESSMENT TPL Bund Wall ad Bund Floor Upgrade –Cluster 7 …

BASELINE RISK ASSESSMENT

TPL Bund Wall ad Bund Floor Upgrade – Cluster 7

Risk Assessment Template

Task Activity : Cluster 8 – Bund Wall and Bund Floor Upgrade.

Ite

m

Task or Activity Hazards (Potential danger) (Energy)

Risk/ Possible Consequence Likely to happen and impact.

Initial Risk Score

Existing & Proposed Control Measures

Revised Risk Score

Action assigned to

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

Mobile Plant. Supervisor

Oil and filters disposal. Environmental impact and pollution. 2 2 5 Make use of local waste collectors to collect the

used oil and filters. 2 1 3

Construction Vehicle and Mobile Plant Supervisor

Employee sustaining burns while working on the

Construction Vehicle or Mobile Plant.

Skin burns. 3 2 9

Allow the engine to cool down before maintenance work is carried out.

Maintenance to be done by a competent person.

2 2 5

Construction Vehicle and Mobile Plant Supervisor

Employee caught by rotating

part of engine. Lose of limbs. 3 2 9

No work to be done on the Construction Vehicle or Mobile Plant while the engine is still running. Only trained and competent mechanic

will work on any machine not an operator.

2 2 5

Construction Vehicle and Mobile Plant Supervisor

Employee coming in contact

with battery acid Skin irritation and skin burns. 3 2 9

Do not allow electrolyte to come in contact with the skin or eyes.

Make use of the correct P.P.E when working with batteries.

2 2 5

Construction Vehicle and Mobile Plant Supervisor

Fire or explosion occurring. Damage to property and fatality. 4 2 14

Remove all flammable materials such as fuel, oil and debris from the engine. Do not weld or

flame cute any pipe or tank that contains any flammable fluids. Wiring must be kept in good order and no smoking or naked flames during

refueling.

3 2 9

Construction Vehicle and Mobile Plant Supervisor

Page 10: BASELINE RISK ASSESSMENT - National Treasury Wall...Method statement: Method Statement to be supplied. BASELINE RISK ASSESSMENT TPL Bund Wall ad Bund Floor Upgrade –Cluster 7 …

BASELINE RISK ASSESSMENT

TPL Bund Wall ad Bund Floor Upgrade – Cluster 7

Risk Assessment Template

Task Activity : Cluster 8 – Bund Wall and Bund Floor Upgrade.

Ite

m

Task or Activity Hazards (Potential danger) (Energy)

Risk/ Possible Consequence Likely to happen and impact.

Initial Risk Score

Existing & Proposed Control Measures

Revised Risk Score

Action assigned to

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

3.

LOADING AND OFFLOADING OF

TRUCKS AND TRAILERS BY HAND

a. Not using PPE Injury to hands, legs and feet 2 2 5 All workers to be trained are to be trained in

the use of PPE and its maintenance, Supervisor and safety officer to monitor the use of PPE

2 1 3 Safety Officer

b. Obstacles on ground may

cause worker to trip and fall with the load on top of him

Body injuries, possibly fatal 4 2 14 Employees to be inducted in the importance of good housekeeping, supervisor to determine if

lay down area is large enough and safe. 2 2 5

Housekeeping Supervisor

c. Material may dislodge

causing employee to fall Injuries to all parts of the body. 2 2 5

Employees must be instructed not to climb on top of stacks, supervisor to monitor that this

does not happen. 2 1 3

Construction Supervisor

d. Having no control Injury to employees 3 2 9 Supervisor to plan procedure to be followed

and instruct employee accordingly. 3 1 6

Construction Supervisor

e. Workers may injure their

backs if loads are to heavy Injury to backs, dropping load on

fingers, legs or feet. 2 2 5

Employees to made aware of all ergonomic hazards, trained in correct lifting.

2 1 3 Safety Officer

Page 11: BASELINE RISK ASSESSMENT - National Treasury Wall...Method statement: Method Statement to be supplied. BASELINE RISK ASSESSMENT TPL Bund Wall ad Bund Floor Upgrade –Cluster 7 …

BASELINE RISK ASSESSMENT

TPL Bund Wall ad Bund Floor Upgrade – Cluster 7

Risk Assessment Template

Task Activity : Cluster 8 – Bund Wall and Bund Floor Upgrade.

Ite

m

Task or Activity Hazards (Potential danger) (Energy)

Risk/ Possible Consequence Likely to happen and impact.

Initial Risk Score

Existing & Proposed Control Measures

Revised Risk Score

Action assigned to

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

4. USE OF HAND TOOLS

a. Flying foreign objects,

employee unprotected. Injury to employee 2 2 5

Use the prescribed PPE for the tool or job- goggles, gloves, dust mask etc. supervisor and

safety officer to enforce. 2 1 3

Construction Manager

b. Incorrect use of tool. Poor

quality of work Injury to employee, Re-do-work 2 2 5

Workers to be trained in use of the correct tool for the job, supervisor to enforce

2 1 3 Construction

Manager

c. Mushroom heads on chisels,

Broken handles, and blunt ends

Injury to workers, 2 2 5 Tools to be maintained regularly and tools to be

checked and recorded on a checklist 2 1 3

Hand tool Inspector

d. Tools lying around causing

trip hazards. Injury to workers 2 2 5 Good housekeeping practices to be enforced. 2 1 3

Housekeeping Supervisor

5. WORKING WITHIN THE

SPILL BASIN

a. Access in and out of spill

basins. Equipment and employees falling

into the spill basin. 3 2 9

Access in and out of the spill basin needs to be provided by means of a access platform fitted

with hand railings. 3 1 6

Construction Manager

b. Slippery surfaces. Slip and fall. 2 2 5 Non slip safety foot wear are to be worn when

working inside of the spill basin. The construction manager is required to inspect the

2 1 3 Construction

Manager.

Page 12: BASELINE RISK ASSESSMENT - National Treasury Wall...Method statement: Method Statement to be supplied. BASELINE RISK ASSESSMENT TPL Bund Wall ad Bund Floor Upgrade –Cluster 7 …

BASELINE RISK ASSESSMENT

TPL Bund Wall ad Bund Floor Upgrade – Cluster 7

Risk Assessment Template

Task Activity : Cluster 8 – Bund Wall and Bund Floor Upgrade.

Ite

m

Task or Activity Hazards (Potential danger) (Energy)

Risk/ Possible Consequence Likely to happen and impact.

Initial Risk Score

Existing & Proposed Control Measures

Revised Risk Score

Action assigned to

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

spill basin before work to ensure that the condition of the spill basin floor is stable.

When the spill basin is

out of service. Contamination Soil pollution. 3 3 13

Ensure that the inlet and outlet to the spill basin is blanked off to prevent any spillages

from spreading towards the spill basin. 3 1 6

6. LAYER WORK/BACK

FILLING

a.

Traffic accidents on site when transporting materials

and reversing of trucks or mobile plant

Property damage, injury to workers possible fatality.

4 2 14 Speed limit and traffic signs must be posted and

enforced reverse alarms to be fitted. 2 2 5

Construction Vehicle and Mobile Plant Supervisor.

b. Wet:: affecting ability to

work safely Injury to workers 2 2 5 Provide rain wear/gum boots where necessary 2 1 3 Safety Officer.

c. Cold:: affecting ability to

work safely Injury to workers. 2 2 5 Provide protection against cold 2 1 3 Safety officer.

d. Heat exhaustion/

dehydration/collapse Health consequences to workers 2 2 5 Provide drinking water and rest periods. 2 1 3 Safety Rep.

Tools and equipment Hand injury 2 2 5 Correct tools to be used for the task at hand.

Employees to wear leather gloves. 2 1 3

SHE Rep and or safety Officer.

Page 13: BASELINE RISK ASSESSMENT - National Treasury Wall...Method statement: Method Statement to be supplied. BASELINE RISK ASSESSMENT TPL Bund Wall ad Bund Floor Upgrade –Cluster 7 …

BASELINE RISK ASSESSMENT

TPL Bund Wall ad Bund Floor Upgrade – Cluster 7

Risk Assessment Template

Task Activity : Cluster 8 – Bund Wall and Bund Floor Upgrade.

Ite

m

Task or Activity Hazards (Potential danger) (Energy)

Risk/ Possible Consequence Likely to happen and impact.

Initial Risk Score

Existing & Proposed Control Measures

Revised Risk Score

Action assigned to

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

Dust Inhalation Respiratory failure 3 2 9 Application of dust masks. 3 1 6 SHE Rep and or safety Officer.

Manual handling Back strains 3 2 9 Workers should take regular breaks and when lifting heavy materials they should use correct

lifting techniques. 3 1 6

Construction Manager/Supervis

or.

7. USE OF HAZARDOUS

CHEMICAL SUBSTANCES

a. Making contact with skin or

eyes. Skin irritation, burns or infections,

could cause loss in eyesight. 3 2 9

Product MSDS’s to be available at all times, workers to be trained in the understanding of

MSDS and to utilize correctly, PPE to be provided for the use of different HCS’s and

workers are to be trained in the correct use of PPE and the maintenance thereof.

3 1 6 HCS Supervisor

b. Inhalation or indigestion Lung infections and could be fatal 4 2 14

Product MSDS’s to be available at all times, workers to be trained in the understanding of

MSDS and to utilize correctly, PPE to be provided for the use of different HCS’s and

workers are to be trained in the correct use of PPE and the maintenance thereof.

2 2 5 HCS Supervisor

Open flames, smoking to be

prohibited within the storage area.

Fire or explosion leading to property damage and possible fatality

4 2 14 Ensure that the storage area is well ventilated. Signs to be posted such as no smoking and no open flames. Ensuring that the storage area is

2 2 5 HCS Supervisor

Page 14: BASELINE RISK ASSESSMENT - National Treasury Wall...Method statement: Method Statement to be supplied. BASELINE RISK ASSESSMENT TPL Bund Wall ad Bund Floor Upgrade –Cluster 7 …

BASELINE RISK ASSESSMENT

TPL Bund Wall ad Bund Floor Upgrade – Cluster 7

Risk Assessment Template

Task Activity : Cluster 8 – Bund Wall and Bund Floor Upgrade.

Ite

m

Task or Activity Hazards (Potential danger) (Energy)

Risk/ Possible Consequence Likely to happen and impact.

Initial Risk Score

Existing & Proposed Control Measures

Revised Risk Score

Action assigned to

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

equipped with the appropriate fire extinguishers.

8. MANUAL EXCAVATIONS

a.

All excavated materials must

be discharged not closer than 1m

from the edge of the excavation.

When excavating manually,

observe the following:

Materials can fall in excavation and may need

extra work

Injuries to employees and the excavation may need extra work

2 2 5 Supervisor must instruct operator where to

place discharged soil and gravel. 2 1 3

Excavation Supervisor.

b. Using a pick and

shovel. Unsafe use of a pick or

shovel Serious body injuries.

3 2 9 Induct employees on safe working procedures. 3 1 6 Excavation Supervisor.

c. Check sides of

excavation. Unstable / loose material causes unsafe conditions

Injuries to employees and damage to excavation 3 2 9 Supervisor to inspect sides on a regular basis. 3 1 6

Excavation Supervisor.

d.

All excavations deeper than 1.5m

must have an access ladder

Employees not able to enter or exit the excavation safely

In case of emergency too many employees may be buried as a result

of inadequate access. Employees may also strain muscles to get in or

2 2 5

Providing a ladder makes access into and out of excavation areas easy and safe. Excavation Supervisor to ensure that there is always a

ladder available for access.

2 1 3

Excavation Supervisor.

Page 15: BASELINE RISK ASSESSMENT - National Treasury Wall...Method statement: Method Statement to be supplied. BASELINE RISK ASSESSMENT TPL Bund Wall ad Bund Floor Upgrade –Cluster 7 …

BASELINE RISK ASSESSMENT

TPL Bund Wall ad Bund Floor Upgrade – Cluster 7

Risk Assessment Template

Task Activity : Cluster 8 – Bund Wall and Bund Floor Upgrade.

Ite

m

Task or Activity Hazards (Potential danger) (Energy)

Risk/ Possible Consequence Likely to happen and impact.

Initial Risk Score

Existing & Proposed Control Measures

Revised Risk Score

Action assigned to

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

available every 6M for workers to get into and

out of excavation safely.

out of an excavation without safe and convenient access.

e.

Sides of excavation to be shored (if necessary)

and barricaded immediately.

Sides may collapse. Employees may not be

aware of the excavation and fall into it.

Damage to the excavation. Injury to employees.

2 2 5 Put adequate shoring and strong physical

barricades in place immediately. 2 1 3

Excavation Supervisor.

f.

Excavations must be backfilled as soon as

possible after excavation.

Excavations could collapse. Employees could trip and

fall in. Vehicles and machinery could damage

excavations.

Damage to excavations. Injuries to employees. Damage to plant and

machinery. 2 2 5 Keep area barricaded with strong physical barricade and backfill as soon as possible.

2 1 3

Excavation Supervisor.

g. Supporting pipe work during excavations.

Uncontrolled collapse of pipe work.

Damage to pipes and serious body injury to employees.

3 3 13 Pipe work to be supported with pipe trestles

fitted with a base plate and timber soleplate for stability in the case of unstable soil.

3 2 9

Construction Manager & Excavation Supervisor.

Damaged pipe trestles. Trestles collapsing causing pipe damage and/or serious injury to

employees. 3 3 13

Pipe trestles to be inspected on a daily basis. Trestles to undergo load testing and certificates

to be present on site at all times. 3 2 9

Construction Manager & Excavation Supervisor.

Trestles collapsing. Damage to pipe work and serious

body injuries to employees. 3 3 13

Pipe trestles to be inspected on a daily basis. Trestles to undergo load testing and certificates

to be present on site at all times. 3 2 9

Construction Manager & Excavation

Page 16: BASELINE RISK ASSESSMENT - National Treasury Wall...Method statement: Method Statement to be supplied. BASELINE RISK ASSESSMENT TPL Bund Wall ad Bund Floor Upgrade –Cluster 7 …

BASELINE RISK ASSESSMENT

TPL Bund Wall ad Bund Floor Upgrade – Cluster 7

Risk Assessment Template

Task Activity : Cluster 8 – Bund Wall and Bund Floor Upgrade.

Ite

m

Task or Activity Hazards (Potential danger) (Energy)

Risk/ Possible Consequence Likely to happen and impact.

Initial Risk Score

Existing & Proposed Control Measures

Revised Risk Score

Action assigned to

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

Supervisor.

h.

The plate compactor will be utilized, to

finally compact the area.

Operator working with plate compactor not trained ,

running over workers feet Foot injuries, and bruises 2 2 5

Supervisor to ensure workers standing clear of plate compactor, and workers wearing correct

PPE 2 1 3

Construction Manager.

Dust, particles, accumulated

gasses, body strain, vibration

Chemical inhalation, skin irritation, eye damage, vibration causing blood

cloths and limb stress, 2 2 5

Rotate the operators of the compactor after every 60 minutes.

2 1 3

Construction manager.

i. Casting ready mix concrete by hand.

Ready mix truck not using stop blocks during pour

operations, truck may move forward or backwards

May cause injuries to workers and property damage

1 2 2

Supervisor to make sure Ready mix truck, complies with stop blocks, and that truck is

secured before pouring concrete. into concrete pump loading bin

1 1 1

Supervisor

Employees coming in contact with concrete

Skin Irritation 2 3 8 Supervisor to make sure that employees are wearing the correct PPE prescribed by the MSDS from the ready mix service provider.

2 2 5 Supervisor

9. STEEL FIXING

Page 17: BASELINE RISK ASSESSMENT - National Treasury Wall...Method statement: Method Statement to be supplied. BASELINE RISK ASSESSMENT TPL Bund Wall ad Bund Floor Upgrade –Cluster 7 …

BASELINE RISK ASSESSMENT

TPL Bund Wall ad Bund Floor Upgrade – Cluster 7

Risk Assessment Template

Task Activity : Cluster 8 – Bund Wall and Bund Floor Upgrade.

Ite

m

Task or Activity Hazards (Potential danger) (Energy)

Risk/ Possible Consequence Likely to happen and impact.

Initial Risk Score

Existing & Proposed Control Measures

Revised Risk Score

Action assigned to

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

a. Personal Protective

Equipment. Workers not complying to

safety Serious hand injuries

2 2 5 Supervisor to ensure that all workers being issued with the required PPE Overall, Safety

boots, safety gloves, reflective vest. 2 1 3

Supervisor / Foreman / Safety

officer

b.

Offloading of rebar from truck Loading and Offloading with (Crane

Truck).

Load of reinforcing can fall onto workers whilst been off

loaded Employees may sustain hand and finger injuries

whilst securing the chain or nylon sling to the load of

rebar Reinforcing may not be

neatly stacked and workers to watch out for protruding

steel

Serious injuries and disability Pinch point and hand injuries

2 3 8

All employees must ensure they do not stand below an overhead load, the banksman are to

ensure the load is properly balanced and secure Supervisor to ensure all workers involved in the

offloading are wearing safety gloves. Supervisor to ensure that offloaded steel is

properly stacked and no protruding steel cause tripping hazards

2 2 5

Supervisor / foreman / Operator /

Banksman / Safety Officer

c.

Handling of Rebar Employees may lift too heavy a load, which can cause back injuries and

disability.

Serious injuries / disability

2 3 8

Foreman to conduct regular toolbox talks to communicate to employees that they should not lift heavy loads and that they must seek

assistance to help lift the load.

2 2 5

Supervisor / foreman / Safety

Officer

Employees may not wear safety gloves, which can lead to hand injuries and

disability.

Hand injuries

2 3 8

Supervisors to conduct regular toolbox talks and spot checks to ensure employees are

wearing safety gloves when handling rebar. 2 2 5

Supervisor / foreman / Safety

Officer

d. Fixing steel. Employees may fix steel

above their heads and not wear eye protection and

eye injuries 2 3 8

Steel fixers must wear eye protection when fixing steel above their heads to prevent eye

injuries. 2 2 5

Supervisor / foreman / Safety

Officer

Page 18: BASELINE RISK ASSESSMENT - National Treasury Wall...Method statement: Method Statement to be supplied. BASELINE RISK ASSESSMENT TPL Bund Wall ad Bund Floor Upgrade –Cluster 7 …

BASELINE RISK ASSESSMENT

TPL Bund Wall ad Bund Floor Upgrade – Cluster 7

Risk Assessment Template

Task Activity : Cluster 8 – Bund Wall and Bund Floor Upgrade.

Ite

m

Task or Activity Hazards (Potential danger) (Energy)

Risk/ Possible Consequence Likely to happen and impact.

Initial Risk Score

Existing & Proposed Control Measures

Revised Risk Score

Action assigned to

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

may cause eye injuries and disability.

e.

Workers may use worn and unsafe tools when fixing

steel and may cause injury and disability.

Injuries

2 3 8

Supervisors to conduct regular tool inspections to ensure tools are correct, safe and in good

order for the job. 2 2 5

Supervisor / foreman / Safety

Officer

F

Steel fixers may try to bend steel by hand, which can

result in hand injuries and disability.

Hand injuries

2 3 8

Supervisors need to be informed of any steel that needs to be bent and proper tools must be

used to bend the steel. 2 2 5

Supervisor / foreman / Safety

Officer

g.

Rebar may be brought into contact with electrical

cables that can lead to an electric shock and disability.

Serious injuries / Electrocution

3 3 13

Steel fixers must be alert at all times not to bring steel in contact with electrical power lines

and DB boards. Supervisors must ensure that the area is free from any electrical supply prior

to steel fixing.

2 2 5

Supervisor / foreman / Safety

Officer

h. Housekeeping & environmental

procedure.

Off cuts of rebar and steel may cause an environmental

incident by corroding.

Environmental damage 2 2 5

Housekeeping is a daily activity and all off cuts of rebar must be placed into a skip or

designated grey drum for disposal 2 1 3

Supervisor / foreman / Safety

Officer

10. ERRECTING FORM AND

SUPPORT WORK

Page 19: BASELINE RISK ASSESSMENT - National Treasury Wall...Method statement: Method Statement to be supplied. BASELINE RISK ASSESSMENT TPL Bund Wall ad Bund Floor Upgrade –Cluster 7 …

BASELINE RISK ASSESSMENT

TPL Bund Wall ad Bund Floor Upgrade – Cluster 7

Risk Assessment Template

Task Activity : Cluster 8 – Bund Wall and Bund Floor Upgrade.

Ite

m

Task or Activity Hazards (Potential danger) (Energy)

Risk/ Possible Consequence Likely to happen and impact.

Initial Risk Score

Existing & Proposed Control Measures

Revised Risk Score

Action assigned to

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

a. Person not competent and

appointed.

The collapse of structure can cause injuries and damage to properties.

2 3 3

Formwork and support work must be erected, inspected by competent persons in accordance

with construction regulation 12.

2 2 5 Support work

Supervisor.

b. Manual handling. Hand injuries & back injuries. 2 3 8 Wear safety gloves, non slip. Correct lifting

techniques for example, do not bend back. Lift equipment by means of bending knees.

2 2 5 Formwork erectors.

11.

BREAKING CONCRETE BY MEANS OF USING A

JACK HAMMER (DEMOLITION WORK)

a.

Noise NIHL

4 2 14

Employee to make use of SABS approved hearing protection, supervisor to ensure that

the correct P.P.E is used. Task to be supervised by a competent supervisor.

2 2 5 Safety

Officer/Mobile Plant Supervisor

b.

Breaking concrete next to existing services.

Fire or explosion. Collapse of structures, pipe lines or other

services. 3 3 13

Contractor to arrange with Project Manager for fire standby. Fire standby person to ensure that

all valves and drains are covered and continuous gas testing is conducted. Sufficient amount of fire-fighting equipment to be placed at the work area. Ensure that all services such

as pipes, support and structures are temporarily secured and supported.

2 2 5 Construction

manager

Page 20: BASELINE RISK ASSESSMENT - National Treasury Wall...Method statement: Method Statement to be supplied. BASELINE RISK ASSESSMENT TPL Bund Wall ad Bund Floor Upgrade –Cluster 7 …

BASELINE RISK ASSESSMENT

TPL Bund Wall ad Bund Floor Upgrade – Cluster 7

Risk Assessment Template

Task Activity : Cluster 8 – Bund Wall and Bund Floor Upgrade.

Ite

m

Task or Activity Hazards (Potential danger) (Energy)

Risk/ Possible Consequence Likely to happen and impact.

Initial Risk Score

Existing & Proposed Control Measures

Revised Risk Score

Action assigned to

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

c.

Flying foreign objects, employee unprotected.

Injury to employee 2 2 5 Use the prescribed PPE for the tool or job-

goggles, gloves, dust mask etc. supervisor and safety officer to enforce.

2 1 3 Construction

Manager

d.

Faulty Equipment & incorrect use.

Multiple injuries to a person.

3 3 13

Ensure all components, attachments and guards are secure before starting.

Know the best way to do the job. Review any operational procedures.

Be aware that this power tool is designed to create severe vibration. The hands, arms and

legs will quickly tire. Take regular breaks.

Always use two hands. Ensure you have a firm footing and are always ready to handle any

reaction the tool may make.

Operators should be prepared to brace themselves against the high level of torque

exerted by the tool.

Apply slight pressure on the tool. Pressing very hard will not increase efficiency. Stop operation if the tool bounces around

uncontrollably.

Do not touch the bit immediately after operation. It may be extremely hot.

Do not operate this power tool at no-load unnecessarily.

To Stop, release the handle grip switch. Turn

2 2 5

Construction manager.

Construction Supervisor &

Operator.

Page 21: BASELINE RISK ASSESSMENT - National Treasury Wall...Method statement: Method Statement to be supplied. BASELINE RISK ASSESSMENT TPL Bund Wall ad Bund Floor Upgrade –Cluster 7 …

BASELINE RISK ASSESSMENT

TPL Bund Wall ad Bund Floor Upgrade – Cluster 7

Risk Assessment Template

Task Activity : Cluster 8 – Bund Wall and Bund Floor Upgrade.

Ite

m

Task or Activity Hazards (Potential danger) (Energy)

Risk/ Possible Consequence Likely to happen and impact.

Initial Risk Score

Existing & Proposed Control Measures

Revised Risk Score

Action assigned to

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

off and disconnect after use. Never leave this power tool unattended.

12. CHEMICAL JOINT

SEALING

Raking out of joints. Hand and eye injury.

2 3 8 Use the correct tool for the correct task. Ensure

the employee uses safety gloves and safety glasses for this task.

2 2 5 Construction

Manager

Sealing of joints. Skin irritation.

2 3 8 Refer to MSDS. Construction manager to ensure all the employees are wearing the correct PPE

as prescribed by the MSDS. 2 2 5

Construction manager.

Saw cutting by means of

using a grinder.

Inspection not done. Injuries, equipment damage, electrocution and disability effect.

2 3 8

Inspection to be done by a competent person. User of the grinder to be trained on how to do the pre use inspection. Inspection registers to

be signed off by a competent supervisor.

2 2 5 Tool and

equipment inspector.

Changing of cutting or grinding disk.

Grinder not made safe – not plugged out may lead to injuries, equipment

damage and disability 2 3 8

Only a trained person is allowed to change the disk on a grinder. Disks that get wet or lay in

water may not be used. User to ensure that the grinder is plugged out.

2 2 5 Construction Supervisor.

Incorrect tools used to

change the disk. Lead to injuries and minor

equipment damage. 3 2 9 Only trained, appointed and competent person

to change the disc on the grinder. 2 2 5 Tool and

equipment operator. Safety

Page 22: BASELINE RISK ASSESSMENT - National Treasury Wall...Method statement: Method Statement to be supplied. BASELINE RISK ASSESSMENT TPL Bund Wall ad Bund Floor Upgrade –Cluster 7 …

BASELINE RISK ASSESSMENT

TPL Bund Wall ad Bund Floor Upgrade – Cluster 7

Risk Assessment Template

Task Activity : Cluster 8 – Bund Wall and Bund Floor Upgrade.

Ite

m

Task or Activity Hazards (Potential danger) (Energy)

Risk/ Possible Consequence Likely to happen and impact.

Initial Risk Score

Existing & Proposed Control Measures

Revised Risk Score

Action assigned to

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

officer.

Safety guard not in place may cause.

Deep cuts or lacerations.

3 2 9

Grinder to be inspected before use by a trained and competent person. The procedure to be

communicated and signed for by all operators. Safety gloves to be used when cutting.

2 2 5 Tool inspector.

Dust inhalation. Serious lung disease and permanent

disability. 4 1 10 User of grinder to make use of a dust mask.

Task to be supervised by a competent supervisor.

2 1 3 Safety Officer

Noise. NIHL

4 2 14

Operator to be trained in use of ear protection. Supervisor to supervise the task and to ensure

that all employees working in close proximity to the grinding operations are wearing ear

protection.

2 2 5 Safety Officer

13. PPE.

Incorrect PPE. Skin burns, cuts, pinches, being struck by tools and equipment.

3 2 9

When entering the site employees should wear safety glasses, hard hats, FLAME RETARDANT

OVERALS “long sleeve” ( SABS APPROVED ), face shields when cutting, safety gloves, safety

shoes, dust masks when working in dusty areas or cutting concrete, Knee pads when working

3 1 6 Safety Officer.

Page 23: BASELINE RISK ASSESSMENT - National Treasury Wall...Method statement: Method Statement to be supplied. BASELINE RISK ASSESSMENT TPL Bund Wall ad Bund Floor Upgrade –Cluster 7 …

BASELINE RISK ASSESSMENT

TPL Bund Wall ad Bund Floor Upgrade – Cluster 7

Risk Assessment Template

Task Activity : Cluster 8 – Bund Wall and Bund Floor Upgrade.

Ite

m

Task or Activity Hazards (Potential danger) (Energy)

Risk/ Possible Consequence Likely to happen and impact.

Initial Risk Score

Existing & Proposed Control Measures

Revised Risk Score

Action assigned to

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

on knees.

Fire or explosion Skin burns and possible fatalities.

4 1 10 The contractor is required to issue all his employees with flame retardant clothing. 2 1 3

Construction manager/16.2

14. WASTE MANAGEMENT

& SAFE DISPOSAL

a.

Contaminated materials. Pollution to the environment.

2 3 8

Work to be done in bunded areas if hazardous chemicals are being used. Drip trays to be

placed underneath construction vehicles and mobile plant. If the contractor comes across a area where there is contamination, this should

be reported to the Project Manager, treated and removed by Spill Tech.

2 2 5

Housekeeping Supervisor,

Construction Manager.

b.

Mixed material such as concrete and steel.

Pollution to the environment.

2 3 8

Waste must be separated. Steel must be separated from concrete once concrete is being

removed. Each should be placed in separate bins or skips.

2 2 5

Housekeeping Supervisor,

Construction Manager.

c.

Environmental impact. Soil pollution and unsafe disposal of hazardous waste may cause damage

to the environment. 2 3 8

A designate waste management area needs to be identified. Waste should be sorted and separated. Waste must be disposed of at a certified waste site and waste disposable

certificates needs to be obtained and kept in

2 2 5

Housekeeping Supervisor,

Construction Manager.

Page 24: BASELINE RISK ASSESSMENT - National Treasury Wall...Method statement: Method Statement to be supplied. BASELINE RISK ASSESSMENT TPL Bund Wall ad Bund Floor Upgrade –Cluster 7 …

BASELINE RISK ASSESSMENT

TPL Bund Wall ad Bund Floor Upgrade – Cluster 7

Risk Assessment Template

Task Activity : Cluster 8 – Bund Wall and Bund Floor Upgrade.

Ite

m

Task or Activity Hazards (Potential danger) (Energy)

Risk/ Possible Consequence Likely to happen and impact.

Initial Risk Score

Existing & Proposed Control Measures

Revised Risk Score

Action assigned to

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

the safety file.

15. HOT WORK ACTIVITIES

ON BULK STORAGE FACILITIES

All types of hot work such as: grinding,

cutting, breaking of concrete, drilling.

Fire or explosion Skin burns, possible fatality, property damage.

4 1 10

Fire stand by will be required when a contractor needs to do hot work within a classified

hazardous area. Hot work is not allowed within 15 meters from a tank farm, spill basin or

manifold area unless arrangements have been made for fire standby. Continuous gas testing

will then be required.

2 2 5 Construction

Manager/Project Manager

16. PUBLIC SAFETY

a.

Neighboring businesses and public exposed due

to the nature of the construction activities.

Emissions of HCS, dust and noise.

Health impact

3 3 13

Communication with neighboring companies is critical. Health risks must be communicated to all the employees regarding the environments

that they are working in. Dust and noise generated due to the nature of construction work must be managed to ensure it does not

2 2 5 Construction

Manager

Page 25: BASELINE RISK ASSESSMENT - National Treasury Wall...Method statement: Method Statement to be supplied. BASELINE RISK ASSESSMENT TPL Bund Wall ad Bund Floor Upgrade –Cluster 7 …

BASELINE RISK ASSESSMENT

TPL Bund Wall ad Bund Floor Upgrade – Cluster 7

Risk Assessment Template

Task Activity : Cluster 8 – Bund Wall and Bund Floor Upgrade.

Ite

m

Task or Activity Hazards (Potential danger) (Energy)

Risk/ Possible Consequence Likely to happen and impact.

Initial Risk Score

Existing & Proposed Control Measures

Revised Risk Score

Action assigned to

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

influence the public.

17. PAINTING.

a. Prepare surfaces using scrappers and copper

wire brushes.

Working with hand tools and dust from old paint.

Hand cutting, bruises and breathing dust from old paint which impacts a

person’s health. 2 2 5

Correct use of gloves and safety glasses. Inspect tools before use. Wearing of dust mask. 2 1 3 Supervisor

b. Paint equipment Fumes from paint and

thinners. Health hazard from inhaling fumes

from both product. 2 2 5 Use protective mask and follow MSDS

instruction for safety reason. Put on your PPE 2 1 3 Supervisor

18. SECURITY CONCERNS. NATIONAL KEY POINT

ACT.

Unauthorised access to site. Not complying with the National Key Point Act.

Injury to trespassers, possibility of theft

4 2 14

Access control to be used at the site gate, warning signs must be displayed, Security

Vetting (as per minimum requirements - SAPS, Police clearance), registers, alcohol testing,

name tags. Foreign Nationals Required security clearance and current work permit copy of passport. Compliance with regards to the

2 2 5 Access Controller

Page 26: BASELINE RISK ASSESSMENT - National Treasury Wall...Method statement: Method Statement to be supplied. BASELINE RISK ASSESSMENT TPL Bund Wall ad Bund Floor Upgrade –Cluster 7 …

BASELINE RISK ASSESSMENT

TPL Bund Wall ad Bund Floor Upgrade – Cluster 7

Risk Assessment Template

Task Activity : Cluster 8 – Bund Wall and Bund Floor Upgrade.

Ite

m

Task or Activity Hazards (Potential danger) (Energy)

Risk/ Possible Consequence Likely to happen and impact.

Initial Risk Score

Existing & Proposed Control Measures

Revised Risk Score

Action assigned to

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

Co

nse

qu

ence

Like

liho

od

Ris

k R

atin

g

National Key Point act.

19. TRANSPORTING

EMPLOYEES

Vehicle Accidents Serious injury or possible fatality

5 2 19

The driver or user of a vehicle shall not transport employees with any tools or

equipment. Employees shall be transported in vehicles with a closed cabin supplied with

sufficient seating and safety belts.

5 1 16 Licensed

driver/16.2 Appointee

Page 27: BASELINE RISK ASSESSMENT - National Treasury Wall...Method statement: Method Statement to be supplied. BASELINE RISK ASSESSMENT TPL Bund Wall ad Bund Floor Upgrade –Cluster 7 …

BASELINE RISK ASSESSMENT

TPL Bund Wall ad Bund Floor Upgrade – Cluster 7

Risk Assessment Template

RISK & ASSURANCE STANDARD RISK MATRIX Hazard Effect / Consequence

RISK MATRIX PROCEDURE:

1. Select the impact that the task or activity will have. 2. Follow in line with the hazard effect/consequence. Numbered 1-5. 3. Draw a straight line to the bottom and indicate what the likelihood might be of the identified hazard. 4. The risk rating will indicate whether the hazard associated is high, significant, medium or low. 5. If the risk is in RED or Orange, work are not allowed to continue until the risk rating has been lowered to medium or low. 6. The risk must be as low as reasonable practicable at all times.

IMPACT:

Loss Type 1

Insignificant 2

Minor 3

Moderate 4

Major

5 Catastrophic

Timeline

No impact on overall project timeline

May result in overall project timeline overrun of less than 5%

May result in overall project timeline overrun of between 5% and less than 20%

May result in overall project timeline overrun of between 20% and less than 50%

May result in overall project timeline overrun of 50% or more

Budget

No impact on the budget of the project

May result in overall project budget overrun of less than 5%

May result in overall project budget overrun of between 5% and less than 20%

May result in overall project budget overrun of between 20% and less than 50%

May result in overall project budget overrun of 50% or more

Investment Return – NPV loss Less than R5m R5m to less than R50m R50M to less than R500m

R500m to R5b R5b or more

Quality

No impact on quality Minimal quality issues that can be addressed in a short timeframe with minimal interactions

Some quality issues that requires immediate management action

Significant quality issues that requires senior project management interaction

Significant quality issues that requires sponsorship intervention with significant resource and cost implications for rework

Safety / Health First aid case / Exposure to minor health risk

Medical treatment case / Exposure to major health risk

Lost time injury / Reversible impact on health

Single fatality or loss of quality of life / Irreversible impact on health

Multiple fatalities / Impact on health ultimately fatal

Environment Minimal environmental harm – L1 incident

Material environmental harm – L2 incident remediable short term

Serious environmental harm – L2 incident remediable within LOM

Major environmental harm – L2 incident remediable post LOM

Extreme environmental harm – L3 incident irreversible

Legal & Regulatory No legal impact Minor legal concerns with minor

impact Some legal concerns with manageable level of impact

Serious legal concerns and significant impact on operations

Legal non compliance with risk of shutdown of operations with significant cost impacts

Reputation / Social / Community Slight impact - public awareness may exist but no public concern

Limited impact - local public concern Considerable impact - regional public concern

National impact - national public concern

International impact - international public attention

Page 28: BASELINE RISK ASSESSMENT - National Treasury Wall...Method statement: Method Statement to be supplied. BASELINE RISK ASSESSMENT TPL Bund Wall ad Bund Floor Upgrade –Cluster 7 …

BASELINE RISK ASSESSMENT

TPL Bund Wall ad Bund Floor Upgrade – Cluster 7

Risk Assessment Template

Likelihood Risk Rating

5 Almost Certain

The unwanted event has occurred frequently; has a 90% and higher probability of reoccurring

11 Medium 16 Significant 20 Significant 23 High 25 High

4 Likely

The unwanted event has a probability of between 60% and less than 90% of occurring

7 Medium 12 Medium 17 Significant 21 High 24 High

3 Possible

The unwanted event has a probability of between 30% and less than 60% of occurring

4 Low 8 Medium 13 Significant 18 Significant 22 High

2 Unlikely

The unwanted event has a probability of between 1% and less than 30% of occurring

2 Low 5 Low 9 Medium 14 Significant 19 Significant

1 Rare

The unwanted event has never occurred, has a probability of less than 1% of occurring

1 Low 3 Low 6 Medium 10 Medium 15 Significant

Page 29: BASELINE RISK ASSESSMENT - National Treasury Wall...Method statement: Method Statement to be supplied. BASELINE RISK ASSESSMENT TPL Bund Wall ad Bund Floor Upgrade –Cluster 7 …

BASELINE RISK ASSESSMENT

TPL Bund Wall ad Bund Floor Upgrade – Cluster 7

Risk Assessment Template

RISK ASSESSMENT ACKOWLEDGEMENT I, the undersigned, hereby acknowledge that the relevant hazards as identified on the Risk Assessment, was communicated to me and I understand and acknowledge the safety instructions and control measures relevant to my activities. I further more undertake to ensure compliance with the safety regulations and instructions noted. I hereby commit myself to create and maintain a safe work environment.

Date

RA Number Facilitator

No Name ID Number Signature No Name ID Number Signature

1 13

2 14

3 15

4 16

5 17

6 18

7 19

8 20

9 21

10 22

11 23

12 24