  • Barrow Offshore WindfarmDesign & Build of UKs First OWF Sub-

    station

    October 2005

    Phillip CartwrightCommercial/Engineering Director

    AREVA T&D Technology Centre

    Rupert BerrymanEngineering Manager - Barrow Offshore Wind Farm

    VKBR

  • 2Agenda

    1. Introduction to design & build team members

    2. Overall Project Scope & Context

    3. Lessons Learnt

    4. Summary

  • 31. Introduction to design & build team members

  • 4The Team

    XClientsCentrica - Major UK energy generation & supply

    company

    DONG - Major Danish Oil, Gas and energy generation & supply company

    XPrime ContractorVestas - Major Danish wind turbine manufacturerKBR International engineering and programme

    management company

  • 5The Team

    DONG CENTRICA

    Barrow Offshore Wind Ltd

    MPIOffshore

    Installation

    SIF/SMULDERSSubstructure fabrication

    VESTAS

    WTG

    AREVAElectricalPackage

    PIRELLI/NEXANSMarine Cable

    Supply

    VKBRConsortium

    50% 50%

    VKBRStructural

    Design

  • 62. Overall Project Scope and Context

  • 7The Challenge

    XConnect 30, 3MW Wind Turbines to the GridSystem via an offshore sub-station

    XEnsure the connection meets the requirementsof the connection agreement

  • 8The Key Connection Requirements

    XThe steady state reactive power flow at the Heysham substation connection point shall be unity power factor +/- 5MVAr for active power flow in the range 0 and 90MW into the NGT system

    XThe system shall remain stable and connected to the system without tripping for a solid three phase fault or any unbalanced short circuit for a total fault clearance time of up to 140ms

  • 9The 90MW Barrow Offshore Wind Farm Project

  • 10

    The 90MW Barrow Offshore Wind Farm Project

    VKBR copyright

  • 11

    Headline Project Scope1) Design

    Conceptual and structural design VKBR System studies, detailed electrical design and equipment supply - AREVA

    2) Connection at Heysham The wind farm connects into the Grid via an existing United Utilities circuit within

    Heysham switchyard

    3) Transmission Cable System 27km of offshore, single 3-core cable 132kV 2.8 km of single circuit, 3 off single-core cable 132kV system

    4) Module supply and fitout - Module Builders, Aberdeen Cabins:- Protection and control, 33kV, 132kV, Capacitors, Diesel Generator, HVAC,

    Mess/Refuge 132/32kV main and auxiliary transformers

    5) Modules and other plant fitted onto Platform Fitted at Barrow, site and main deck supplied by VKBR. Module fixing and inter-

    module cabling works performed by installation contractor, Test and Dry Commissioning by AREVA

    6) Electrical System commissioning Includes commissioning work on offshore platform

  • 12

    Site Locations

    Leatherhead VKBR Offices

    Barrow, Platform kitout

    Aberdeen, Modules

    Heysham connection point

  • 13

    Connection at Heysham - Onshore

    XHeysham Grid connection pointNew sub-station adjacent to Heysham switchyard

    z All civil works

    z 132kV open terminal bay (Extended creep)

    z Solidly connected 24MVAr shunt reactor

    z Incoming cable from beach cable vault

    z Outgoing cable from new compound to existing Heysham switchyard circuit breaker

    z Protection System, SCADA RTU,Batteries and LVAC auxiliaries

  • 14

    Offshore Sub-station

    X OverviewLength - 23mWidth - 15mHeight - 10mWeight - 440 tonnes

  • 15

    Offshore Substation

    XModularised quipment33kV Board 14 panel including protection33/132kV 120MVA Transformer with OLTC132kV GISRelay and control panel suite roomLVAC and DC plant room (incs UPS for navigation lights)225kVA standby diesel generatorRefuge, mess and workshop modules5MVAr shunt capacitor bank modulesHVAC systems INERGEN/water mist fire suppression system

  • 16

    Power Transformer

    AuxiliaryTransform

    er

    Module BModule A Module C

    Module E

    Module D

    Heli-Lift

    AuxiliaryTransformer

    Module B

    Module A

    Module C

    Platform Deck

    Cable Deck132kV Cable Transition

    33kV Cable Transition

    P+132+M+1-W-*

    Offshore Substation

  • 17

    Module C

    Module A Module B

    StandbyDiesel

    33kV

    LV Room

    Control

    132kV

    Fire

    StoreAuxiliary

    Transformer

    Power Transformer

    Offshore Substation

  • 18

    During Construction at end of June 05

  • 19

    Loading Out 12th August 05

  • 20

    Offshore Sub-station

  • 21

    Installed on Monopile 16th August 05

  • 22

    Project Programme

    Order Placement 02/09/04 9

    Modules ready for fitting to platform 10/05/05 9

    Offshore Substation complete 02/08/05 9

    Platform shipout (by VKBR) 16/08/05 9

    Heysham available 24/08/05 9

    Electrical System commissioned 01/11/05

    Windfarm commissioned including10 day reliability run 10/05/06

  • 23

    3. Lessons Learnt

  • 24

    Lessons Learnt

    X System Modelling Inter party confidentiality agreements need to be resolved pre-

    contract commencement

    XWay-leaves & Land LeasesAll way-leaves and land leases need to be finalised and secured

    before construction contract is let

    X Design Design Freezes are required after equipment interface reviews

    z Hazop reviews

    z Windfarm SCADA design that meets substation P&C design cycle

    Clarity of Design & Supply responsibilitiesz Use of Division of Responsibility Matrix at contract development

    stage - requires sufficient contract lead in time

  • 25

    4. Summary

  • 26

    Summary

    XFirst high voltage offshore substation in the UKA modularised solution - rapid assembly time at load-

    out point

    Sub-structure (mono-piles) is common with wind turbines (mono-piles) - economy of design

    Rapid design, build and install programme