barriere o, le roux p 26.02.2015

45
Barriere O, Le Roux P 26.02.2015 GIS PORTAL RACKS Integration of Equipment Racks in the Geographic Information Service (GS/ SE) https:// gis.cern.ch/gisportal/Racks.ht

Upload: ada-bradley

Post on 30-Dec-2015

216 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Barriere O, Le Roux P 26.02.2015

Barriere O, Le Roux P 26.02.2015

GIS PORTAL RACKS

Integration of Equipment Racks in the Geographic Information Service (GS/ SE)

https://gis.cern.ch/gisportal/Racks.htm

Page 2: Barriere O, Le Roux P 26.02.2015

2

Context Phase 1 data Integration Phase 2 update Proposals Summary

GIS Portal Racks Status Summary

Page 3: Barriere O, Le Roux P 26.02.2015

3

Context Phase 1 data Integration Phase 2 update Proposals Summary

GIS Portal Racks Status Summary

Page 4: Barriere O, Le Roux P 26.02.2015

4

GIS PORTAL Racks was born following an ACCOR study

To improve cabling, cabling documentation & data sharing

=> For BE/CO best effort service team.

To reduce accelerators downtime

Context

Page 6: Barriere O, Le Roux P 26.02.2015

6

Current System: Map CERN Lite

MAP CERN LITE

Page 7: Barriere O, Le Roux P 26.02.2015

7

Before System: GIS Portals

Page 8: Barriere O, Le Roux P 26.02.2015

8

Current system: GIS Portal

Page 9: Barriere O, Le Roux P 26.02.2015

9

Before system: GIS Portal

Before system limitations:We didn’t know the exact location of the rack

Page 10: Barriere O, Le Roux P 26.02.2015

10

Before system:Equipment Cabling Document

Page 11: Barriere O, Le Roux P 26.02.2015

11

Controls Configuration

DB

LayoutDB

Infor EAM DB IT NetOps DB

Before where to find information?

EDMS DB

DFS DB

GESMAR

Databases not linked

Page 12: Barriere O, Le Roux P 26.02.2015

12

We lack a global infrastructure to document our huge installations.

Each equipment group provides its own solution

1. Locating the equipment

2. Finding the corresponding documentation

Study conclusions

Page 13: Barriere O, Le Roux P 26.02.2015

13

GIS Portal Racks prototype

Integrate equipment racks in GIS Portal

Search by rack

Direct link to the technical documentation and databases

In databases, add links to GIS PORTAL RACKS

Page 14: Barriere O, Le Roux P 26.02.2015

14

ACCOR study in 2011

Prototype in 2012

Accelerator Sector management agreement to start the project (BE,EN,TE) June 2013

Started the project in September 2013

Context history

Page 15: Barriere O, Le Roux P 26.02.2015

15

Context Phase 1 data Integration Phase 2 update Proposals Summary

GIS Portal Racks Status Summary

Page 16: Barriere O, Le Roux P 26.02.2015

16

BPMN (Business Process Model Notification) data flow(Coralie Perollini from MFIO (Maintenance Framework Implementation Office),Pascal, Olivier) https://edms.cern.ch/document/1308160/1

Rack Inventory APEX interface & PL/SQL API to import/publish (Pascal) https://apex.cern.ch/pls/htmldb_accdb/f?p=rackinventory

Racks models inventory (Keith) Racks inventory (Keith) Check on site (Keith, Olivier,)(LHC U help of Didier & Pascal C) Arc GIS drawings (Keith) Coordination with EL-EN, EN-CV, GS-ASE, GS-SE, IT-CS, TE-EPC

(Olivier) Data update in CCDB (Alexander & Eve)

Phase 1 data integration

Page 17: Barriere O, Le Roux P 26.02.2015

17

InforEAMGS/ASE

EN/EL Cablothèque

Gesmar

"Demande d’installation de cables"

TE/CRGEN/CV

GS/ASE…

Layout DB

GIS DBGS/SE/DOP

RACK IMPORTSStaging table

Layout core tablesCombine with

already existing layout data

Import API running daily or on demand

Infrastructure and data flow

Page 18: Barriere O, Le Roux P 26.02.2015

18

InforEAMGS/ASE

EN/EL Cablothèque

Gesmar

"Demande d’installation de cables"

TE/CRGEN/CV

GS/ASE…

Layout DB

GIS DBGS/SE/DOP

RACK IMPORTSStaging table

Layout core tablesCombine with

already existing layout data

Import API running daily or on demand

Infrastructure and data flow

Inventory of the distinct rack models with photos

APEX Interface on RACK IMPORTS table

to manage the inventory by building

Page 19: Barriere O, Le Roux P 26.02.2015

19

InforEAMGS/ASE

EN/EL Cablothèque

Gesmar

"Demande d’installation de cables"

TE/CRGEN/CV

GS/ASE…

Layout DB

GIS DBGS/SE/DOP

RACK IMPORTSStaging table

Layout core tablesCombine with

already existing layout data

Import API running daily or on demand

Infrastructure and data flow

Sync to Layouton demand

Inventory status report by building, highlighting missing/incorrect data in layout, MTF or GIS

Page 20: Barriere O, Le Roux P 26.02.2015

20

InforEAMGS/ASE

EN/EL Cablothèque

Gesmar

"Demande d’installation de cables"

TE/CRGEN/CV

GS/ASE…

Layout DB

GIS DBGS/SE/DOP

RACK IMPORTSStaging table

Layout core tables

GIS info PanelView

Combine with already existing

layout dataSync to Layout

on demand

Update LAYOUT_ID

or create new rack

Import API running daily or on demand

Creation not fullyautomated yet

Infrastructure and data flow

Page 21: Barriere O, Le Roux P 26.02.2015

21

InforEAMGS/ASE

EN/EL Cablothèque

Gesmar

"Demande d’installation de cables"

TE/CRGEN/CV

GS/ASE…

Layout DB

GIS DBGS/SE/DOP

RACK IMPORTSStaging table

Layout core tables

GIS info PanelView

Combine with already existing

layout dataSync to Layout

on demand

Update LAYOUT_ID

or create new rack

Import API running daily or on demand

ESRI ArcGIS Interface to draw the rack shapes on top of the building/floor

schematics

Infrastructure and data flow

Page 22: Barriere O, Le Roux P 26.02.2015

22

InforEAMGS/ASE

EN/EL Cablothèque

Gesmar

"Demande d’installation de cables"

TE/CRGEN/CV

GS/ASE…

Layout DB

GIS DBGS/SE/DOP

RACK IMPORTSStaging table

Layout core tables

GIS info PanelView

Combine with already existing

layout dataSync to Layout

on demand

Update LAYOUT_ID

or create new rack

Import API running daily or on demand

Match GIS Shapes with Layout data

using Labels &

LAYOUT_IDAutomatic since April

2014

Provide rack data to GIS

Infrastructure and data flow

Page 23: Barriere O, Le Roux P 26.02.2015

23

Rack in the building hierarchy

GIS integration

Link to MTF

Link to GIS

45U Empty rack to be

filled in

Results in Layout web interface

Page 24: Barriere O, Le Roux P 26.02.2015

24

Results in MTF / INFOR. EAM

Slot available for documentation

Page 25: Barriere O, Le Roux P 26.02.2015

25

Process done & to be done

InforEAMGS/ASE

EN/EL Cablothèque

Gesmar

"Demande d’installation de cables"

TE/CRGEN/CV

GS/ASE…

Layout DB

GIS DBGS/SE/DOP

RACK IMPORTSStaging table

Layout core tables

GIS info PanelView

Combine with already existing

layout dataSync to Layout

on demand

Update LAYOUT_ID

or create new rack

Import API running daily or on demand

Match GIS Shapes with Layout data

using Labels &

LAYOUT_IDAutomatic since April

2014

Provide rack data to GIS

NETWORK DBIT-CS

IT sockets in racks

Page 26: Barriere O, Le Roux P 26.02.2015

26

Results in GIS Portal Racks

Zoom 1:10

IT Socket list by rack done

by IT First Line

IT Socket Status:

FreeAssignedPortable

….

Page 27: Barriere O, Le Roux P 26.02.2015

27

Process done & to be done

InforEAMGS/ASE

EN/EL Cablothèque

Gesmar

"Demande d’installation de cables"

TE/CRGEN/CV

GS/ASE…

Layout DB

GIS DBGS/SE/DOP

RACK IMPORTSStaging table

Layout core tables

GIS info PanelView

Combine with already existing

layout dataSync to Layout

on demand

Update LAYOUT_ID

or create new rack

Import API running daily or on demand

Match GIS Shapes with Layout data

using Labels &

LAYOUT_IDAutomatic since April

2014

Provide rack data to GIS

CCDB

NETWORK DBIT-CS

BE-CO

IT sockets in racks

Diamon

BE-CO

Page 28: Barriere O, Le Roux P 26.02.2015

28

Results in CCDB & Diamon

GIS Portal Racks linksBuildingRoom Rack

Page 29: Barriere O, Le Roux P 26.02.2015

29

Process done & to be done

InforEAMGS/ASE

EN/EL Cablothèque

Gesmar

"Demande d’installation de cables"

TE/CRGEN/CV

GS/ASE…

Layout DB

GIS DBGS/SE/DOP

RACK IMPORTSStaging table

Layout core tables

GIS info PanelView

Combine with already existing

layout dataSync to Layout

on demand

Update LAYOUT_ID

or create new rack

Import API running daily or on demand

Match GIS Shapes with Layout data

using Labels &

LAYOUT_IDAutomatic since April

2014

Provide rack data to GIS

CCDB

NETWORK DBIT-CS

BE-CO

IT sockets in racks

TO BE DONE

Diamon

BE-CO

Page 30: Barriere O, Le Roux P 26.02.2015

30

Process to be done

Link FEC’sto racks

Page 31: Barriere O, Le Roux P 26.02.2015

31

Process done & to be done

InforEAMGS/ASE

EN/EL Cablothèque

Gesmar

"Demande d’installation de cables"

TE/CRGEN/CV

GS/ASE…

Layout DB

GIS DBGS/SE/DOP

RACK IMPORTSStaging table

Layout core tables

GIS info PanelView

Combine with already existing

layout dataSync to Layout

on demand

Update LAYOUT_ID

or create new rack

Import API running daily or on demand

Match GIS Shapes with Layout data

using Labels &

LAYOUT_IDAutomatic since April

2014

Provide rack data to GIS

CCDB

NETWORK DBIT-CS

BE-CO

IT sockets in racks

TO BE DONE

Equipment groups DB

TO BE DONE

TO BE DONE

Diamon

BE-CO

Page 32: Barriere O, Le Roux P 26.02.2015

32

Service Number of buildings Number of racks

Total (manpower/month)Database Work

Total (manpower/month)Installations Teams

Only BE/CO racks 301 4’811

All the racks in the buildings For

BE, EN, TE301 16’888

12 m.m(temp. Resource, PJAS)

14 m.m(temp. Resource, FSU)

All CERN racks for BE, EN, TE + GS, IT, PH, 496 25’174

19 m.m(temp. resource)

22 m.m(temp. resource)

N e c e s s a r y R e s o u r c e s E s t i m a t i o n ( 1 s t P h a s e B a s e d o n P r o t o t y p e )

Planning

Page 33: Barriere O, Le Roux P 26.02.2015

Started September 2013 (but only 14 months of work done) PS Complex & LHC Underground done To finish LHC Surface -> 1month SPS -> 3 months Finally we are on time

Planning

33

Page 34: Barriere O, Le Roux P 26.02.2015

34

Context Phase 1 data Integration Phase 2 update Proposals Summary

GIS Portal Racks Status Summary

Page 35: Barriere O, Le Roux P 26.02.2015

35

Validate data imported

Maintain data up to date

Phase 2 Update

Page 36: Barriere O, Le Roux P 26.02.2015

36

Validate data: LIU PSB Pilot( L H C I n j e c t o r U p g r a d e )

Check of equipment responsible done by

BE-OP Machine Coordinator(K.Hanke & F.Chapuis)

Names of racks to be changedIn Infor EAM, Gesmar, MTF…

Page 37: Barriere O, Le Roux P 26.02.2015

37

Use BE-OP Machines coordinators to validate imported data

EN-EL is creating a DIR (Demande d’Installation de Rack) form

EN-EL is creating a DDR (Demande de Désafectation de Rack) form

Include GIS Portal Racks in the ECR (Equipment Change Request) workflow

Develop a GIS Portal application to report errors, to GIS Portal Rack support

One person for all equipment groups to make changes in GIS Portal Racks

Each equipment groups will be able to make updates

Strategy to be defined

Data Maintenance Proposal

Page 38: Barriere O, Le Roux P 26.02.2015

38

Context Phase 1 data Integration Phase 2 update Proposals Summary

GIS Portal Racks Status Summary

Page 39: Barriere O, Le Roux P 26.02.2015

39

Proposals to extend GIS Portal Racks

Automatically draw racks & electrical panels in LHC Tunnel

Automatically draw FIP Bus in LHC Tunnel

Display 1553 bus & Timing distribution in ‘GIS Portal Racks’

Search and display cables in ‘GIS Portal Racks’

Display Racks power distribution

Page 40: Barriere O, Le Roux P 26.02.2015

40

Display Racks Power distributionLinks between:

Racks & power distribution

Page 41: Barriere O, Le Roux P 26.02.2015

41

GIS Portal Racks is the first step

Page 42: Barriere O, Le Roux P 26.02.2015

42

Racks Layout automatic

Application for Racks Layout:Link to CCDB to import data &Draw equipment not in CCDB

Page 43: Barriere O, Le Roux P 26.02.2015

43

Cabling Layout automatic

Application for cabling Layout:Link to CCDB &

Draw equipment not in CCDB

Page 44: Barriere O, Le Roux P 26.02.2015

44

summaryContext Situation before & now

Before it took time to locate a rack & find cabling documentation Before databases were not linked together Now, thank to GIS Portal Racks & geolocalisation Rapidly locate equipment racks Provide a standardized solution and easy access to cabling documentation & databases => To reduce accelerators downtime

1st Phase Data integration Data flow & Infrastructure are in place but there are still some links to be done Collecting data:

PS Complex, LHC underground & LHC surface in 15 months

SPS 3 months to do it

2nd Phase Data maintenance Validate imported data in collaboration with BE-OP Machines Coordinators Maintain data up to date:

Discussion on going with EN/EL (DIR, DDR)

Strategy to be discussed

Tools & procedures to be developed

Proposals: To extend ‘GIS PORTAL Racks’ in LHC tunnel, FIP bus, 1553 bus, cables…

○ Put them in place GIS Portal Racks is only the first step Next steps:

○ Develop tools to display rack & cabling Layout, synchronised with DB

Page 45: Barriere O, Le Roux P 26.02.2015

45

Demonstration

https://gis.cern.ch/gisportal/Racks.htm