CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS) 12-Nov-15
Excavation
A M2 110 3.00 330.00
B Pit for pad footing not exceeding 1.50m deep M3 8 15.00 120.00
C 50mm thick under pad footing M2 8 11.50 92.00
D Ditto under ground slab M2 110 11.50 1,265.00
E Pad footing M3 4 310.00 1,240.00
F Column stump M3 1 310.00 310.00
G 150mm Thick ground slab M2 110 46.50 5,115.00
H Pad footing Kg 400 3.20 1,280.00
J Column stump Kg 300 3.20 960.00
K Layer of B.R.C. Ref. No A8 and embedded in apron m2 69 16.00 1,104.00
Sawn formwork as described to:-
L Sides of pad footing M2 24 38.00 912.00
M Sides of column stump M2 15 38.00 570.00
N 150mm thick to sides of concrete slab M 50 4.75 237.50
13,535.50
Excavate oversite average 200mm deep commencing
from formation level, get out, part return, fill in and
ram, deposit and spread in making up levels where
directed within the site and remainder load and cart
away to Contractor's own dump
Description
Lean concrete grade 15 as described spread and
levelled :-
Excavate commencing from formation level, get
out, part return, fill in and ram, deposit and
spread in making up levels where directed within
the site and remainder load and cart away to
Contractor's own dump :-
Unit
ELEMENT NO. 1 - WORK BELOW LOWEST FLOOR FINISH
Amount (RM)
Vibrated reinforced concrete Grade 30 as
described in :-
Rate (RM)
Mild steel & High tensile reinforcement bar to B.S.
4449 as described in :-
To Collection
QuantityItem
= RM16.00
= RM16.00 = RM16.00
C10/E1/1
CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS) 12-Nov-15
Description Unit
ELEMENT NO. 1 - WORK BELOW LOWEST FLOOR FINISH
Amount (RM)Rate (RM)QuantityItem
Damp Proof Membrane
A M2 110 3.00 330.00
B M2 0 30.00 0.00
Anti-Termite
C M2 110 5.00 550.00
880.00To Collection
Prepare and apply an approved waterproofing
compound as described to wet area in floor slab and
wall, all strictly in accordance with the manufacturer's
instructions
Single layer of 0.25mm thick (heavy-duty) polythene
sheet laid under floor bed on top of blinding screed
(measured separately) well lapped of joints and seal
with approved pressure-adhesive tapes (measured nett -
no allowance for laps)
An approved anti-termite treatment to be executed
strictly in accordance with the manufacturer's
instructions complete with five (5) years warranty
C10/E1/2
CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS) 12-Nov-15
Description Unit
ELEMENT NO. 1 - WORK BELOW LOWEST FLOOR FINISH
Amount (RM)Rate (RM)QuantityItem
ELEMENT NO. 1 - WORK BELOW LOWEST
Collection
Page C10/E1/1 13,535.50
Page C10/E1/2 880.00
14,415.50To Summary
= RM16.00
C10/E1/3
CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS) 12-Nov-15
A M2 50 3.00 150.00
B Trench for perimeter drain not exceeding 1.50m deep. M3 8 15.00 120.00
C 50mm thick blinding screed and levelled under apron M2 50 11.50 575.00
D Ditto under ramp M2 0 11.50 0.00
E 150mm thick hardore under apron M2 50 11.25 562.50
F Ditto under ramp M2 0 11.25 0.00
G 100mm Thick apron M2 50 31.00 1,550.00
H 175mm Thick ramp M2 0 54.25 0.00
……………………………
J Kg 125 3.20 400.00
K Layer of B.R.C. Ref. No A8 and embedded in apron. M2 50 16.00 800.00
L Ditto, in ramp M2 0 18.00 0.00
4,157.50
ELEMENT NO.2 : APRON, PERIMETER DRAIN & RAMP
Lean concrete grade 15 as described spread and
levelled :-
Item Description
Excavate oversite average 200mm deep commencing
from formation level, get out, part return, fill in and
ram, deposit and spread in making up levels where
directed within the site and remainder load and cart
away to Contractor's own dump
Excavate commencing from formation level, get
out, part return, fill in and ram, deposit and
spread in making up levels where directed within
the site and remainder load and cart away to
Contractor's own dump :-
Rate (RM)Unit Quantity Amount (RM)
To Collection
Hardcore consisting of hard, dry broken bricks or
stones, spread and levelled, well consolidated,
watered and blinded with sand.
Vibrated reinforced concrete Grade 30 as
described in :
10mm Diameter high tensile rod reinforcement as
starter bar
Steel fabric reinforcement as described well lapped
at joints including notching around all obstructions
(measured nett - no allowance for laps) :-
C10/E2/4
CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS) 12-Nov-15
ELEMENT NO.2 : APRON, PERIMETER DRAIN & RAMP
Item Description Rate (RM)Unit Quantity Amount (RM)
Sawn formwork as described to:
A M 50 3.80 190.00
B To edges of ramp slab, ditto M 0 3.80 0.00
Damp Proof Membrane
C Single layer of 0.25mm thick (heavy-duty) polythene
sheet laid under floor bed on top of blinding screed
(measured separately) well lapped of joints and seal
with approved pressure-adhesive tapes (measured nett -
no allowance for laps)
M2 0 4.00 0.00
Perimeter Drain
D M 50 65.00 3,250.00
Precast Concrete Cover
E 600mm x 250mm wide precast concrete cover slab M 7 40.00 280.00
Mild Steel Grating
F Heavy duty mild steel grating overall size 800mm x
600mm consisting of 75mm x 50mm x 6mm thick
angle framing all around with 50mm x 6mm thick
mild steel flat bar in fill at 40mm centres all welded to
12mm x 50mm mild steel framing including priming
and hoisting to position
No 1 120.00 120.00
Anti-Termite
G M2 50 4.00 200.00
4,040.00
225mm (internal) Wide half-round precast concrete as
described surface water drain channel including
hoisting, jointing and pointing in cement and sand
(1:3) and laid to falls including all necessary
excavation, 100mm concrete (Grade 15 - 40mm
aggregate) as described base and half brickwall sides
with and including all necessary cement and sand
(1:3) plastering to wall complete, all as per drawing.
To edges of apron slab exceeding 200mm but not
exceeding 300mm high
To Collection
An approved anti-termite treatment to be executed
strictly in accordance with the manufacturer's
instructions complete with five (5) years warranty
= RM16.00 = RM16.00 = RM16.00
C10/E2/5
CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS) 12-Nov-15
ELEMENT NO.2 : APRON, PERIMETER DRAIN & RAMP
Item Description Rate (RM)Unit Quantity Amount (RM)
Collection
Page C10/E2/1 4,157.50
Page C10/E2/2 4,040.00
8,197.50To Summary
ELEMENT NO.2 : APRON AND PERIMETER
DRAIN
= RM16.00
C10/E2/6
CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS) 12-Nov-15
A Column M3 5 310.00 1,550.00
Mild steel reinforcement bar to BS 4449 as
described :-
In column
B 10mm diameter as stirrups. Kg 225 3.20 720.00
C Column Kg 938 3.20 3,001.60
Sawn formwork as described to:
D Sides of column M2 56 38.00 2,128.00
7,399.60
ELEMENT NO.3 : FRAME
Rate (RM) Amount
(RM)
To Summary
High tensile reinforcement bar to B.S. 4449 as
described in :-
Vibrated reinforced concrete Grade 30 as
described in :-
Item Description Unit Quantity
= RM16.00 = RM16.00
C10/E3/1
CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS) 12-Nov-15
Vibrated reinforced concrete Grade 30 as
described in :-
A 150mm thick ditto M2 8 46.50 372.00
Sawn formwork as described to:
B To soffit of suspended floor slab including strutting. M2 8 38.00 304.00
High tensile reinforcement bar to B.S. 4449 as
described in :-
C 10mm Diameter in suspended floor slab. Kg 132 3.20 422.40
………………………..
Waterproofing
D Prepare and apply an approved waterproofing
compound as described to wet area in upper floor slab
and wall, all strictly in accordance with the
manufacturer's instructions.
M2 11 65.00 715.00
E Allow for performing ponding test if required by the
S.O. over areas of waterproofed to ensure
watertightness and effectiveness of waterproofing
system used including providing water, pumps,
temporary walling, etc. and making good all defects
and leave the whole in perfect working order .
Item 100.00 100.00
1,913.40To Summary
Item Description Unit Amount (RM)
ELEMENT NO.4 : UPPER FLOOR
Rate (RM)Quantity
= RM16.00
= RM16.00
= RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00
C10/E4/2
CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS) 12-Nov-15
Roof Covering
A M2 183 60.00 10,980.00
B M 0 15.00 -
C Ditto, 3-way apex tile No 0 25.00 -
D Ditto, end cap No 0 20.00 -
Roof Trusses
E M2 183 35.00 6,405.00
Roof Insulation Work
F M2 183 8.00 1,464.00
G M2 183 12.00 2,196.00
Wrot pressure treated timber Grade 'B' as
specified :
H 200mm x 25mm thick fascia board M 83 18.00 1,494.00
Prepare and apply one under coat and two
finishing coats of gloss enamel paint as described
on the followings woodworks :
J M 83 7.00 581.00
23,120.00
ELEMENT NO. 5 : ROOF
Item Quantity
Metal decking roof covering of approved brand as
selected by the S.O. with and including all accessories
on a layer of double sided sisalation sheet on chicken
wire mesh (both measured separately) and laid on
purlins to Engineer's detail
To Collection
An approved ridge/hip capping tiles to match roofing
tiles bedded in jointed in coloured cement and sand
(1:3) mortar as described including cutting and
splayed ends, mitres and intersection
50mm Rockwool insulation (60kg/m3) as described to
laid on rafter well lapped at joints (measured nett - no
allowance for laps)
'Ajiya' light weight roof trusses or approved equivalent
as selected by S.O. including strut, rods, purlins, bolt,
nut with washer, gusset plate, painting and all
accessories and fittings.
Layer of approved sisalation (non-tear) double-sided
aluminium foil sisalation fixed to top of steel purlins
with 150mm (minimum) lapped at joints, including
layer of chicken wire mesh all laid strictly in
accordance with manufacturer's instructions
(measured nett - no allowance for laps)
To surface of fascia board exceeding 200mm and not
exceeding 300mm high
Description Rate
(RM)
Amount
(RM)
Unit
= RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00
= RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00
= RM16.00
= RM16.00
C10/E5/3
CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS) 12-Nov-15
ELEMENT NO. 5 : ROOF
Item QuantityDescription Rate
(RM)
Amount
(RM)
Unit
No. 22 gauge galvanised iron sheeting as described:-
A Flashing; 570mm girth, three times bend, one end
chased into concrete work or brickwall and other end
dressed over roofing including metal paint on all
exposed surfaces
M 23 38.00 874.00
B Valley gutter 900mm girth, 5 times bend, bolt and
fixed under roof tiles
M 0 25.00 -
Flat Roof
Vibrated reinforced concrete Grade 30 as
described in :-
C 100mm thick roof slab M2 0 25.00 0.00
D 450mm high 100 thick R.C wall for roof slab M 0 150.00 0.00
Sawn formwork as described to:
E To soffit of suspended roof slab including strutting. M2 0 30.00 0.00
F To side of flat roof M 0 3.00 0.00
High tensile reinforcement bar to B.S. 4449 as
described in :-
G 10mm Diameter in suspended floor slab. Kg 0 2.60 0.00
………………………..
Waterproofing
H Prepare and apply an approved waterproofing
compound as described to wet area in upper floor slab
and wall, all strictly in accordance with the
manufacturer's instructions.
M2 0 35.00 0.00
874.00 To Collection
= RM16.00
= RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00
= RM16.00
= RM16.00
C10/E5/4
CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS) 12-Nov-15
ELEMENT NO. 5 : ROOF
Item QuantityDescription Rate
(RM)
Amount
(RM)
Unit
ELEMENT NO.5 : ROOF
Collection
Page C10/E5/1 23,120.00
Page C10/E5/2 874.00
23,994.00 To Summary
= RM16.00 = RM16.00
= RM16.00
C10/E5/5
CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS) 12-Nov-15
Staircase
Vibrated reinforced concrete Grade 30 as
described in :-
A In Staircase M3 2 200.00 400.00
B 125mm Thick suspended landing slab. M2 1 25.00 25.00
High tensile reinforcement bar to B.S. 4449 as
described in :-
In staircase
C 12mm Diameter bar Kg 125 2.60 325.00
D 10mm Diameter bar Kg 37 2.60 96.20
Landing slab
E 12mm Diameter bar Kg 53 2.60 137.80
F 10mm Diameter bar Kg 22 2.60 57.20
Sawn formwork as described to:
G Sloping soffit of staircase M2 6 30.00 180.00
H Soffit of landing slab M2 1 30.00 30.00
J M 4 9.00 36.00
K M 15 6.00 90.00
L Edge of landing slab ditto M 1 6.00 6.00
1,383.20
ELEMENT NO.6 : STAIRCASE
Sides of raking open string of staircase 300mm
(extreme) width including cutting to profiles of tread
and riser.
Undercut riser exceeding 100mm but not exceeding
200mm high.
Rate (RM) Amount (RM)
To Collection
Item Description Unit Quantity
= RM16.00
C10/E6/6
CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS) 12-Nov-15
ELEMENT NO.6 : STAIRCASE
Rate (RM) Amount (RM)Item Description Unit Quantity
Staircase Finishes
Cement and sand (1:6) with and approved
plasticiser as specified.
A 19mm Thick, to sloping soffit of staircase. M2 6 12.00 72.00
B 19mm Thick to soffit of landing slab. M2 1 12.00 12.00
C M 4 3.60 14.40
D M 1 3.60 3.60
Cement and sand (1:3) backing screed as specified
:-
E To receive tiles at riser, 250mm high. M 15 12.00 180.00
F To receive tiles at tread, 164mm width. M 13 2.00 26.00
G To receive tiles at landing slab. M2 3 3.00 9.00
H To receive nosing tiles. M 15 14.00 210.00
100mm x 100mm homogeneous tiles or approved
equivalent as described bedded and jointed in
cement and sand (1:3) mortar as described and
pointed in matching coloured cemnet and laid on
screeded bed (measured separately) to required
pattern.
J To landing slab. M2 3 40.00 120.00
K To undercut riser, 250mm high. M 15 8.00 120.00
L To tread, 164mm width. M 13 7.00 91.00
M Nosing tile 75mm wide x 200mm x 8mm thick. M 15 6.00 90.00
Prepare and apply one undercoat and two coat
emulsion paint as specified.
N On plastered sloping soffit of staircase M2 6 7.00 42.00
P On plastered soffit of landing slab. M2 1 7.00 7.00
Q M 4 7.00 28.00
R M 1 2.00 2.00
1,027.00
On plastered sides of raking open string of staircase
300mm (extreme) wide.
On plastered to edge of landing slab exceeding
100mm but not exceeding 200mm high
To Collection
19mm Thick to edge of landing slab exceeding
200mm but not exceeding 300mm high.
19mm Thick to sides of raking open string of staircase
300mm (extreme) wide.
C10/E6/7
CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS) 12-Nov-15
ELEMENT NO.6 : STAIRCASE
Rate (RM) Amount (RM)Item Description Unit Quantity
Stainless Steel Handrail
A M 5 285.00 1,425.00
A M 5 380.00 1,900.00
3,325.00
Supply and fix 1000mm high stainless steel
handrailing, consist of balustrading, top rail,
intermediate rail, bottom rail and complete with
accessories and finishes, all accordance to S.O's
instruction and Architect's drawings.
To Collection
Supply and fix 1000mm high stainless steel
handrailing with glass, consist of balustrading, top
rail, intermediate rail, bottom rail and complete with
accessories and finishes, all accordance to S.O's
instruction and Architect's drawings.
C10/E6/8
CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS) 12-Nov-15
ELEMENT NO.6 : STAIRCASE
Rate (RM) Amount (RM)Item Description Unit Quantity
Collection
Page C10/E6/1 1,383.20
Page C10/E6/2 1,027.00
Page C10/E6/3 3,325.00
5,735.20To Summary
= RM16.00 = RM16.00 = RM16.00
= RM16.00
C10/E6/9
CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS) 12-Nov-15
BRICKWALL
Brickwork in Special Interlocking Clay Brick all
as per architect's drawings and the manufacturer's
detail
A
No. 9,600 1.80 17,280.00
SUNDRIES
Bituminous sheet damp proof course as specified
(measured nett - no allowance made for laps)
B 115mm wide to half brickwall M 42 2.50 105.00
RC Coping
C 100mm x 75mm Thick cast in-situ concrete or precast,
grade 25 as described concrete coping including
reinforcement and formwork setting in position,
jointed and pointed in cement mortar (1:3) all as per
detail drawing. M 133 38.00 5,054.00
22,439.00
ELEMENT NO.7 : EXTERNAL WALL & INTERNAL WALL
Rate (RM) Amount (RM)
To Summary
Item Description Unit Quantity
115mm Thick brickwall, reinforced with and
including brick reinforcement at every fourth course.
= RM16.00
C10/E7/1
CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS) 12-Nov-15
EXTERNAL DOOR
Lintol
A
M 6 30.00 180.00
Supply and fix the following timber door complete
with metal frames, painting, ironmongery and other
accessories for the proper installation of the works
all as per architect's drawings and the
manufacturer's detail :-
B Single leaves timber flush door overall size 900 mm x
2400 mm high with external waterproof as per
architect's drawing
No 1 380.00 380.00
Supply and fix the following solid timber door
complete with metal frames, painting, ironmongery
and other accessories for the proper installation of
the works all as per architect's drawings and the
manufacturer's detail :-
C Double leaf solid decorative timber door overall size
1100mm x 2400mm high with external waterproof as
per architect's drawing No 1 1,350.00 1,350.00
D Single leaf solid decorative timber door overall size
900mm x 2400mm high with external waterproof as
per architect's drawing No 2 1,200.00 2,400.00
Supply and fix the following powder coated
aluminium sliding door complete with aluminium
frames, painting, ironmongery and other
accessories for the proper installation of the works
all as per architect's drawings and the
manufacturer's detail :-
E A set of aluminium sliding door overall size 1500mm x
2400mm high with 6mm thick clear glass panel (SD1)
No 0 2,000.00 0.00
F A set of aluminium sliding door overall size 3000mm x
2400mm high with 6mm thick clear glass panel (SD2)
No 0 4,000.00 0.00
4,310.00
Amount (RM)Rate (RM)
ELEMENT NO.8 : WINDOW AND EXTERNAL DOORS
125mm wide x 200mm high cast in-situ concrete or
precast, grade 25 as described lintol including
reinforcement and formwork setting in position, jointed
and pointed in cement mortar (1:3) all as per detail
drawing.
Item Description Unit
To Collection
Quantity
C10/E8/1
CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS) 12-Nov-15
Amount (RM)Rate (RM)
ELEMENT NO.8 : WINDOW AND EXTERNAL DOORS
Item Description Unit Quantity
WINDOWS
Lintol
A
M 24 30.00 720.00
Supply, deliver and install the following in powder
coated aluminium frame window glass panel or
approved equivalent with 5mm thick light grey
tinted glass including all frames, transomes,
mullions, fittings, locks, fasteners, stays,
ironmongery and other accessories for the proper
installation of the works all as per architect's
drawings and manufacturer's detail:-
B Casement window of various sizes and panels complete
with light grey tinted glass M2 17 380.00 6,460.00
7,180.00
125mm wide x 200mm high cast in-situ concrete or
precast, grade 25 as described lintol including
reinforcement and formwork setting in position, jointed
and pointed in cement mortar (1:3) all as per detail
drawing.
To Collection
C10/E8/2
CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS) 12-Nov-15
Amount (RM)Rate (RM)
ELEMENT NO.8 : WINDOW AND EXTERNAL DOORS
Item Description Unit Quantity
ELEMENT NO.8 : WINDOW AND EXTERNAL
DOORS
Collection
Page C10/E8/1 4,310.00
Page C10/E8/2 7,180.00
11,490.00To Summary
= RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00
= RM16.00
C10/E8/3
CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS) 12-Nov-15
Lintol
A
M 14 30.00 420.00
Supply and fix the following timber door complete
with metal frames, painting, ironmongery and other
accessories for the proper installation of the works
all as per architect's drawings and the
manufacturer's detail :-
B Single leaves timber flush door overall size 900 mm x
2400 mm high as per architect's drawing No 4 345.00 1,380.00
C Single leaves waterproofed timber flush door overall
size 750 mm x 2400 mm high as per architect's drawing
No 2 315.00 630.00
Supply and fix the following powder coated
aluminium folded door complete with aluminium
frames, painting, ironmongery and other
accessories for the proper installation of the works
all as per architect's drawings and the
manufacturer's detail :-
D A set of aluminium folded door overall size 750mm x
2100mm high with 6mm thick clear glass panel (FD1)
No 0 1,500.00 0.00
2,430.00
Amount (RM)Rate (RM)
ELEMENT NO.9 : INTERNAL DOORS
To Summary
Description UnitItem
125mm wide x 200mm high cast in-situ concrete or
precast, grade 25 as described lintol including
reinforcement and formwork setting in position, jointed
and pointed in cement mortar (1:3) all as per detail
drawing.
Quantity
= RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00
C10/E9/1
CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS) 12-Nov-15
Cement and sand (1:6) with and approved
plasticiser as described
A 19mm thick Plainface to walls, column and the like. M2 80 23.00 1,840.00
Cement and sand (1:3) as described screed to
receive tiles
B 19mm Thick to receive ceramic wall tiles M2 49 19.00 931.00
Prepare and apply one coat alkali resisting primer
sealer and two coats of approved emulsion paint
C Plastered walls, column and the like M2 80 7.00 560.00
D To wall and column M2 49 70.00 3,430.00
6,761.00
ELEMENT NO.10 : INTERNAL WALL FINISHES
Rate (RM) Amount (RM)
To Summary
200mm x 200mm glazed ceramic wall tiles or
approved equivalent ; bedded in cement and sand
(1: 3) screed (measured separately) ; jointing in neat
matching coloured cement ; in approved colour,
thickness and pattern
Item Description Unit Quantity
= RM16.00
= RM16.00
C10/E10/1
CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS) 12-Nov-15
Cement and sand (1:3) backing screed as
specified:
A To received tiles M2 86 19.00 1,634.00
200mm x 200mm non-slip ceramic tiles or
approved equivalent as described bedded and
jointed in cement and sand (1:3) mortar as
described and pointed in matching coloured
cement and laid on screeded bed (measured
separately) to required pattern
B To floor M2 86 60.00 5,160.00
-------------------------------
Timber strip floor finish or approved equivalent as
described lay and jointed with approved material
all as per architect's drawings and the
manufacturer's detail :-
C To Floor M2 0 75.00 -
6,794.00
ELEMENT NO.11 : INTERNAL FLOOR FINISHES
Quantity
To Summary
Amount (RM)Rate (RM)DescriptionItem Unit
= RM16.00
= RM16.00
= RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00
C10/E11/1
CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS) 12-Nov-15
CEILING FINISHES
Cement and sand (1:6) with and approved
plasticiser as specified :
A 19mm thick to plainface soffit of concrete slab and
beam.
M2 0 28.00 0.00
Suspended Gypsum Board
B M2 110 45.00 4,950.00
C To soffit of plastered concrete slab and beam. M2 0 7.00 0.00
D To soffit of gypsum board ceiling. M2 110 7.00 770.00
5,720.00
ELEMENT NO.12 INTERNAL CEILING FINISHES
To Summary
Quantity
Prepare and apply one coat approved alkali
resisting primer sealer and two coats emulsion paint
as specified.
Item
1200mm x 600mm Suspended gypsum board with
cornice or approved equivalent and fixed to ceiling joist
and spacer including all accessories as per Architect's
Drawing and manufacturer's detail.
UnitDescription Amount (RM)Rate (RM)
= RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00
= RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00
= RM16.00 = RM16.00 = RM16.00 = RM16.00
C10/E12/1
CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS) 12-Nov-15
WALL FINISHES
Prepare and apply one coat alkali resisting primer
sealer and two coats of approved weathersheild
paint
A Plastered walls, column and the like. M2 80 8.00 640.00
B Ditto, to copings and the like. M 53 3.00 159.00
FLOOR FINISHES
Cement and sand (1:3) finished with steel trowel as
described :-
C To received tiles M2 24 19.00 456.00
300mm x 300mm homogeneous tiles or approved
equivalent as described bedded and jointed in
cement and sand (1:3) mortar as described and
pointed in matching coloured cement and laid on
screeded bed (measured separately) to required
pattern
D To floor M2 18 80.00 1,440.00
200mm x 200mm non-slip ceramic tiles or approved
equivalent as described bedded and jointed in
cement and sand (1:3) mortar as described and
pointed in matching coloured cement and laid on
screeded bed (measured separately) to required
pattern
E To floor M2 6 60.00 360.00
Cement and sand (1:3) as described paving
trowelled hard and smooth to
F 25mm thick cement render to apron and floor M2 50 20.00 1,000.00
G 50mm thick concrete in print texture M2 0 30.00 -
H 50mm thick grove line for ramp texture M2 0 30.00 -
CEILING FINISHES
Cement and sand (1:6) with and approved
plasticiser as specified :
J 19mm thick to plainface soffit of concrete slab M2 6 15.00 90.00
Asbestos Free Ceiling
K 1200mm x 600mm asbestos free ceiling sheets or
approved equivalent and fixed to ceiling joist and
spacer including all accessories as per Architect's
Drawing and manufacturer's detail.
M2 108 40.00 4,320.00
L To soffit of concrete slab M2 6 8.00 48.00
M To soffit of asbestos ceiling. M2 108 8.00 864.00
N To concrete in print texture M2 0 12.00 -
9,377.00
ELEMENT NO. 13 : EXTERNAL FINISHES
To Summary
Rate (RM)Item Amount (RM)Description Unit Quantity
Prepare and apply one coat approved alkali
resisting primer sealer and two coats weathershield
paint as specified.
= RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00
= RM16.00
= RM16.00 = RM16.00 = RM16.00 = RM16.00
= RM16.00 = RM16.00 = RM16.00 = RM16.00
C10/E13/1
CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS) 12-Nov-15
Concrete Top
A
No 0 650.00 0.00
B
No 1 3,000.00 3,000.00
C Construct concrete top overall size 850mm x 350mm
wide x 250mm high concrete (1:2:4-20mm Aggregate)
ditto, casting 1 no wash hand basin (measured
separately) ditto No 2 650.00 1,300.00
Mild Steel Plinth
D Mild steel plinth for water tank (measured separately)
including waterproofed plywood and anti corrosion
painting and all related works as per Engineer's
drawing
Item 1,200.00 1,200.00
5,500.00
Rate (RM) Amount (RM)
ELEMENT NO. 14 : BUILDER'S WORK IN CONNECTION
To Summary
Item Description Unit Quantity
Construct L-shape concrete top, overall size 900mm x
600mm wide x 800mm high concrete (1:2:4-20mm
Aggregate) including formwork, layer of mesh fabric
reinforcement well lapped at joint including support
beam and casting 1 no. sink (measured separately) and
finish with 200mm x 200mm ceramic tiles, 10mm PVC
tile trim edging strip, corner edging piece all as per
detail drawing
Construct L-shape concrete top, overall size 4200mm x
600mm wide x 800mm high concrete (1:2:4-20mm
Aggregate) including formwork, layer of mesh fabric
reinforcement well lapped at joint including support
beam and finish with 200mm x 200mm ceramic tiles,
10mm PVC tile trim edging strip, corner edging piece
all as per detail drawing
= RM16.00
C10/E14/2
CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS) 12-Nov-15
Pedestal water closet
A
No. 2 600.00 1,200.00
Wash hand basin
B
No. 2 420.00 840.00
Toilet Roll
C
No. 2 50.00 100.00
Soap Holder
D
No. 2 35.00 70.00
Hand Spray Bidet
E
No. 2 25.00 50.00
Water Tab
F No. 10 15.00 150.00
Floor Trap
G
No. 4 30.00 120.00
2,530.00
ELEMENT NO.15 : SANITARY FITTING
Description Unit Quantity
Approved equivalent Low level Pedestal water closet
comprising of water closet tank and water cisten 'P' or
'S' trap and white plastic hinged seat cover and jointed
up and plugging and screwing water closet tank to tile
concrete floor including working or making good floor
and wall tiling around.
Item
150mm x 150mm stainless steel cover to floor trap
with 100mm diameter openable stainless steel grating
including connecting to pipes and setting in concrete
floor and making good tiling works.
Rate (RM) Amount (RM)
Supply and fix the following sanitary fittings and
accessories, including jointing and connecting to
services and soil and waste pipes and making good
all work disturbed
Approved equivalent jointless cultured marble
countertop wash hand basin bowl complete with
bright chrome plated pillar tap, 32mm dia. Plastic
bottle trap and fixed counter with an approved bracket
to all around.
Approved equivalent vitreous china semi recessed
toilet roll holder, plugged and screwed to tiled
brickwall including working or making good wall
tiling around.
Approved equivalent vitreous china soap holder.
Approved equivalent hand spray controlled complete
with 1200mm flexible hose with hook handle
including jointing to galvanised mild steel tubing
Approved equivalent water tab complete with all
jointing
To Collection
= RM16.00 = RM16.00 = RM16.00 = RM16.00
= RM16.00 = RM16.00 = RM16.00 = RM16.00
= RM16.00 = RM16.00 = RM16.00 = RM16.00
= RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00
C10/E15/3
CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS) 12-Nov-15
ELEMENT NO.15 : SANITARY FITTING
Description Unit QuantityItem Rate (RM) Amount (RM)
Mirror
A
No. 2 70.00 140.00
Shower
B
No. 2 35.00 70.00
Sink
C
No. 1 450.00 450.00
Testing
D On completion of the Sanitary Installation, test and
commision all fittings for water tightness and make
good all defects, re-test and leave whole in perfect
working order to the satisfaction of the S.O. and
Authorities Item 500.00
1,160.00To Collection
Supply and fix the following sanitary fittings and
accessories, including jointing and connecting to
services and soil and waste pipes and making good
all work disturbed (Cont'd)
An approved equivalent jointless aluminium sink
double bowl double drainer complete with bright
chrome plated pillar tap, 32mm diameter plastic bottle
trap and fixed counter with an approved bracket to all
around.
600mm x 450mm x 6mm Thick mirror with and
including 6mm Thick water proofed plywood backing
fix to 37.70 mm x 19mm aluminium frame edging all
around and plugged and screwed mirror with
chromium plated dome headed screws to tile wall.
Approved equivalent shower rose with arm and wall
flange and fixing to wall and making good all
connection.
= RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00
= RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00 = RM16.00
C10/E15/4
CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS) 12-Nov-15
ELEMENT NO.15 : SANITARY FITTING
Description Unit QuantityItem Rate (RM) Amount (RM)
ELEMENT NO.16 : SANITARY FITTINGS
Collection
Page C10/E16/1 2,530.00
Page C10/E16/2 1,160.00
3,690.00 To Summary
C10/E15/5
CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS) 12-Nov-15
Low Cabinet
A To supply and install low cabinet overall size 4500mm
x 600mm x 780mm high, all as per Architectural's
drawing.
No 0 1,200.00 0.00
B Ditto, overall size 7850mm x 600mm x 780mm high,
all as per Architectural's drawing.
No 0 2,500.00 0.00
Wardrobe
C To supply and install wardrobe overall size 1800mm x
600mm x 2100mm high, all as per Architectural's
drawing.
No 0 900.00 0.00
D Ditto, overall size 2400mm x 600mm x 2100mm high,
all as per Architectural's drawing.
No 0 1,200.00 0.00
E Ditto, overall size 2700mm x 600mm x 2100mm high,
all as per Architectural's drawing.
No 0 1,400.00 0.00
SHOE'S RACK
F To supply and install shoe's rack overall size 2200mm x
450mm x 2100mm high, all as per Architectural's
drawing.
No 0 600.00 0.00
0.00
ELEMENT NO. 16 : BUILT-IN FURNITURE
To Summary
Item Description Unit Quantity Rate (RM) Amount (RM)
= RM16.00
C10/E16/6
CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS) 12-Nov-15
Item Description Unit Qty. Rate (RM) Amount (RM)
All Provisional Quantites
A UPVC Waste, Soil and Vent Pipe to BS4515, BS5255
& BS4660 including all joints, bends, tees, branches,
expansion joints, fittings, approved type bats holders,
etc as shown in the drawings:-
a) 150mm dia. UPVC soil underground sewer line M 22 25.00 550.00
a) 100mm dia. UPVC soil underground and stack M 34 20.00 680.00
b) 75mm dia. UPVC waste underground and vent M 15 18.00 270.00
c) 50mm dia. UPVC Pipe M 10 15.00 150.00
B UPVC floor gully trap, 110 x 20 extension grating
collar, 82 x 50 concentric reducer to be connected to
50mm dia. UPVC 'P' trap, 100mm square frame
including setting on and surrounding with concrete
(Grade 30) as described.
Nos. 4 150.00 600.00
C Gully Trap at Ground Floor of deep sealed coated cast
iron type with outlet dimeter to suit c/w all necessary
extension piece and cast iron hinged grating gully to be
bendded and surrounded with plain concrete (Grade
30), 100mm dia. waste pipe with gasket of tar.
Nos. 1 200.00 200.00
D No 6 500.00 3,000.00
5,450.00To Summary
600mm x 600mm x 900mm (average) deep house
manhole constructed of 115mm thick clay bricks
jointed and pointed in cement and sand (1:3) mortar as
described with and including excavations, formworks,
grade 25 concrete bedding, layer of BRC A8, 50mm
grade 15 concrete blinding and all necessary
rendering, plastering etc. all as per details.
ELEMENT NO.17 : INTERNAL SANITARY SERVICES
C10/E17/7
CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS) 12-Nov-15
Item Description Unit Qty. Rate (RM) Amount (RM)
All Provisional Quantites
A SIRIM approved type (MS 1225:1991) HDPE Water
Storage tank c/w inlet/outlet opening, level indicator,
float valve, manhole, air vent, drain/overflow piping c/w
elevated structure support and all necessary accessories:
i) 900 Litres (200 gals) Nos. 2 400.00 800.00
B ABS (Acrylonitrile Butadiene Styrene) PN15 to MS 1419:
Part 1: 1997, MS 1058: Part 2: 2002, AS3518: Part 1:
1988 c/w fittings, bends, supports, brackets, tees, valves
and all necessary accessories from water tank distribute
to toilet:
i) 15mm dia. ABS PN15 Pipe (internal distribution) Meter 13 35.00 455.00
ii) 20mm dia. ABS PN15 Pipe (internal distribution) Meter 22 40.00 880.00
iii) 25mm dia. ABS PN15 Pipe (internal distribution) Meter 18 55.00 990.00
iv) 25mm dia. Gate Valve Nos. 5 45.00 225.00
C 20mm dia. water meter for Banglo unit. Lot 1 50.00 50.00
D 20mm dia. lockable valve for water meter. No. 1 50.00 50.00
E 20mm dia. Gate Valve for water meter No. 1 50.00 50.00
F 25mm dia. Stainless Steel 304 (Sch 40) stand pipe for
water meter c/w all necessary fittings.
Meter 3 150.00 450.00
G 25mm dia. ABS PN15 Underground Pipe tapping from
external recticulation mains water meter and from water
meter to water tank at celing roof c/w all necessary
fittings.
Meter 20 45.00 900.00
H 25mm dia. 90 deg. Elbow Nos. 12 50.00 600.00
J 25mm dia. Tee Nos. 3 80.00 240.00
5,690.00To Summary
ELEMENT NO.18 : INTERNAL COLD WATER SERVICES
C10/E18/8
CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS) 12-Nov-15
Item Description Unit Qty. Rate (RM) Amount (RM)
All Provisional Quantities
Turfing
A Trim, level and grade horizontal or sloping surface of
ground to receive turfing (measured separately) and
remove all surplus excavated materials off site to
Contractor's own dumping area M2 0 4.00 0.00
B Spot turfing including 50mm Thick bed of black earth as
specified, on flat ground. M2 0 5.00 0.00
Fencing and Gates
C 1500mm High overall fencing including all necessary
column, excavation, formwork and disposal of surplus
excavated material complete. M 0 380.00 0.00
Mild Steel Gates
D Decorative fencing to main entrance as specified in
Architect Drawings. Item 0.00 0.00
0.00To Summary
Special Interlocking Clay Brick all as per architect's
drawings and the manufacturer's detail
ELEMENT NO.19 : EXTERNAL WORKS
C10/E19/9
CADANGAN MEMBINA 1 UNIT RUMAH BANGLO SATU (1) TINGKAT (IBS) 12-Nov-15
SUMMARY
ELEMENT NO. 1 - WORK BELOW LOWEST FLOOR FINISH Page C10/E1/3 14,415.50
ELEMENT NO. 2 - APRON AND PERIMETER DRAIN Page C10/E2/3 8,197.50
ELEMENT NO. 3 - FRAME Page C10/E3/1 7,399.60
ELEMENT NO. 4 - UPPER FLOOR Page C10/E4/1 1,913.40
ELEMENT NO. 5 - ROOF Page C10/E5/3 23,994.00
ELEMENT NO. 6 - STAIRCASE Page C10/E6/4 5,735.20
ELEMENT NO. 7 - EXTERNAL WALL & INTERNAL WALL Page C10/E7/1 22,439.00
ELEMENT NO. 8 - WINDOW AND EXTERNAL DOOR Page C10/E8/3 11,490.00
ELEMENT NO. 9 - INTERNAL DOOR Page C10/E9/1 2,430.00
ELEMENT NO. 10 - INTERNAL WALL FINISHES Page C10/E10/1 6,761.00
ELEMENT NO. 11 - INTERNAL FLOOR FINISHES Page C10/E11/1 6,794.00
ELEMENT NO. 12 - INTERNAL CEILING FINISHES Page C10/E12/1 5,720.00
ELEMENT NO. 13 - EXTERNAL FINISHES Page C10/E13/3 9,377.00
ELEMENT NO. 14 - BUILDER'S WORK IN CONNECTION Page C10/E14/1 5,500.00
ELEMENT NO. 15 - SANITARY FITTINGS Page C10/E15/3 3,690.00
ELEMENT NO. 16 - BUILT-IN FURNITURE Page C10/E16/1 -
ELEMENT NO. 17 - INTERNAL SANITARY SERVICES Page C10/E17/1 5,450.00
ELEMENT NO. 18 - INTERNAL COLD WATER SERVICES Page C10/E18/1 5,690.00
ELEMENT NO. 19 - EXTERNAL WORKS Page C10/E19/1 -
ELEMENT NO. 20 - ELECTRICAL WORKS (ALLOWANCE) - 8,500.00
155,496.20
SUMMARY
Total to Summary Of Building Works
Amount (RM)Item Description
= RM16.00 = RM16.00 = RM16.00 = RM16.00
C10/Summ