1.1 General
Theprovisionsof thispartare intended tomaintainor increase thecurrentdegreeofpublicsafetyaswellas
healthandgeneralwelfareinexistingbuildingswhilepermittingalteration,additiontoorchangeofuse.
Inaddition,certainenvironmentalmeasurestomaketheexistingbuildingstocksustainable, isalsoarequirement
thatneedstobeaddressedtomakebuildingsmoreenergyefficientandenvironmentallyresponsive.Thisconcept
isintroducedinChapter2ofthisPart.
1.2 Applicability
1.2.1
General
The provision of this part shall apply to existing buildings that will continue to be or are proposed to be in
occupancy groups A, B, E, F, H, I, M, R and S. The provisions shall not apply to buildings of historical or
architecturalvalue identifiedandclassifiedbydesignatedauthorities.Forbuildingsofhistoricalorarchitectural
value buildings, the provisions of Sec 1.5: Historic or Architecturally Valuable Buildings, of Part 1, Sec 1.16:
BuildingsandPlacesofHistoricalorArchitectural Value,ofPart3andchapter3:Conservation andrehabilitation
ofhistoricalandculturalheritage,ofPart9,shallbeapplicable.
Certainprovisions toexistingbuildingsand landuseevenwhenadditions,alterationsoramendmentsarenot
proposedareincludedinSection2.3:SustainabilitymeasuresforexistingbuildingsChapter2ofthisPart.
1.2.2 Changeinuse
1.2.2.1
Nochange
in
use
of
any
existing
building
shall
be
made
without
permission
from
the
permitting
authority.
1.2.2.2 Nochangeinuseofanexistingbuildingshallbeallowed iftheproposeduseisnotinconformitywithland
usepatternasreferredinPart3,Sec1.3,andwithinthepermittedoccupancyclassesofPart3,Sec1.4,as
maybedeterminedbythecityorareadevelopmentauthoritieshavingjurisdictions.
1.2.2.3 Whereanexistingbuildingischangedtoanewusegroupclassification,theprovisionsforthenewusegroup
inthisCodeshallbeusedtodeterminecompliance.
1.2.3 PartChangeinuse
1.2.3.1 Nochangeinuseofanypartofanexistingbuildingshallbemadewithoutpermissionfromthepermitting
authority.
1.2.3.2 Whereaportionofthebuildingischangedtoanewusegroupclassification,andthatportionisseparated
fromtheremainderofthebuildingwithfireseparationassemblieshavingafireresistanceratingasrequired
by Part 4, Fire Protection, for the separate uses, the portion changed shall bemade to conform to the
provisionsofthisCode.
PERSONAL COLLECTION OF
ENGR. PRANOY BARUA
BANGLADESH STEEL RE-ROLLING MILLS LTD
-
8/11/2019 Bangladesh National Building Code 2012 Part 09 Alteration, Addition to and Change of Use of Existing Buildings
2/15
Part9
Alteration,AdditiontoandChangeofUseofExistingBuildings
92
Vol.3
1.2.3.3 Where a portion of the building is changed to a new use group classification, and that portion is not
separatedfromtheremainderofthebuildingwithfireseparationassemblieshavingafireresistancerating
asrequiredbyPart4,Fire,fortheseparateuses,theprovisionsofthisCodewhichapplytoeachuseshall
apply to theentirebuilding.Where thereareconflictingprovisions, thoserequirementswhichsecure the
greaterpublicsafetyshallapplytotheentirebuildingorstructure.
1.2.4 Additions
1.2.4.1
Noaddition
to
any
existing
buildings
shall
be
made
without
permission
from
the
permitting
authority.
1.2.4.2 AdditionstoexistingbuildingsshallcomplywithalltherequirementsofthisCodefornewconstructionsas
setforthinPart3ofthisCodeandshallcomplywithfirerequirementssetforthinPart4ofthisCode.
1.2.4.3 Thecombinedheightandareaoftheexistingbuildingsandnewadditionsshallnotexceedtheheightand
openspacerequirementsfornewbuildingsspecifiedinPart3ofthisCode.
1.2.4.4 WhereaseparatingwallthatcomplieswithPart4,FireProtection,isprovidedbetweentheadditionandthe
existingbuilding,theadditionshallbeconsideredasaseparatebuilding.
1.2.5
Alterations
1.2.5.1
AnexistingbuildingorportionthereofwhichdoesnotcomplywiththerequirementsofthisCodefornew
construction (Part3) shallnotbe altered in suchamanner that results in thebuildingbeing less safeor
sanitarythansuchbuildingisatpresent.
1.2.5.2 If, in the alteration the present level of safety or sanitation is to be reduced, the portion altered shall
conformtotherequirementsofthisCode.
1.2.6 Removal
1.2.6.1 Any construction within the site which does not have approval of the appropriate authority must be
removedbefore any new addition, alterationor changeof use is carried out.All other types of existing
constructionandtheirchangesshallcomplywithsubclauses1.2.4and1.2.5ofthisPart.
1.2.6.2 Before demolishing a building of construction type 1 (Part 4: Fire Protection) the owner shall notify all
utilities having service connectionswithin thebuilding or plot, such aswater, gas, electricity, sewer and
otherconnections.
1.2.6.3 Apermit todemolishabuildingshallnotbe issueduntilaclearance isobtained fromutilitiesstating that
theirrespectiveserviceconnectionsandappurtenantequipments,suchas,metersandregulatorshavebeen
removedorsealedandpluggedinasafemanner.
1.3 Implementation
1.3.1
Investigation
and
Evaluation
Fortheproposedworksrelatingtoalteration,additiontoandchangeofuse,theownerofthebuildingshallcause
the existing buildings to be investigated and evaluated by competent professionals in accordance with the
provisionsofthisCode.
1.3.2 StructuralAnalysis
1.3.2.1 Theowner shall have a structural analysis of theexistingbuilding carriedout byprofessional experts to
determinetheadequacyofallstructuralsystemsfortheproposedalteration,additionorchangeofuse.
-
8/11/2019 Bangladesh National Building Code 2012 Part 09 Alteration, Addition to and Change of Use of Existing Buildings
3/15
ApplicabilityandImplementation Chapter1
Bangladesh
National
Building
Code
2012
93
1.3.2.2 Theexistingbuilding togetherwith theadditionoralterationshallbecapableofsupporting theminimum
loadrequirementsspecifiedinPart6:StructuralDesign,ofthisCode.
1.3.3 Submittal
TheresultsoftheinvestigationandevaluationasrequiredinSec.1.3.1abovealongwithallproposedcompliance
alternativesshallbesubmittedtotheBuildingOfficialforpermissiontoimplementaddition,alterationorchange
ofuse.
1.3.4 DeterminationofCompliance
TheBuildingOfficialshallexamineallrelevantdocuments,asspecifiedbytheauthorities,anddeterminewhether
the existingbuilding,with theproposed additions, alterationsor changeofuse, complieswith theprovisions
specifiedinthisCodefortheoccupancyclassificationandtypeofconstruction.
-
8/11/2019 Bangladesh National Building Code 2012 Part 09 Alteration, Addition to and Change of Use of Existing Buildings
4/15
Part9
Alteration,AdditiontoandChangeofUseofExistingBuildings 95
Chapter 2
Evaluation and Compliance
2.1 Evaluation
Theevaluationoftheexistingbuildingwiththeproposedadditions,alterationsorchangeofuse,shalltake into
consideration the planning requirements as well as those relating to public safety and environmental
sustainability.
2.1.1 PlanningRequirements
2.1.1.1 ThepermittingauthoritythroughbuildingofficialsshalldetermineifanyprovisionsofthisCodeareviolated
bytheproposedchangeofuse,additionoralterationworks.
2.1.1.2 Thegeneralrequirementsforbuildingsinvariousoccupancyclassesandtypesofconstructionarespecified
inPart3:GeneralBuildingRequirementsandPart8:BuildingServices,ofthisCode.Theseinclude:
a) Landuseclassificationandpermitteduse(Sec.1.3Part3)
b) Requirementofplots(Sec.1.5,Part3)
c) Meansofaccess(Sec.1.6,Part3);andstaircase(Sec.1.12.5,Part3)
d) Universal accessibility requirementsof various Sectionsof Chapter 3 andAppendixD: universal
accessibility
e) Openspaceswithinaplot;minimumseparationofbuildingsinthesameplot;roadfront,sideand
rearopenspaces,PermittedConstruction intheMandatoryOpenSpace(Sec.1.7Part3)
f) GeneralheightandarealimitationsbasedonFAR(Sec.1.8.2,Part3)orbasedonRoadWidth(Sec.
1.8.3,Part3)
g)
Off
street
(on
site)
parking
spaces
(Sec.
1.9,
Part
3
and
Appendix
F:
Road
Hierarchy,
On
street
and
OnsiteParking)
h) Streetencroachment(Sec.1.10,Part3)
i) Communityopenspaceandamenitiesforvarioustypesofbuildings (Sec.1.11,Part3)
j) Ventilation requirements (natural:Sec.1.17,Part3;artificial:Chapter3,Part8:AirConditioning,
HeatingandVentilation)
k) Lighting and illumination requirements (Sec 1.17, Sec 4.4.1: Electric lighting, 4.6.1: Daylighting,
4.6.2:Supplementary lightingsystem, Part3andChapter1:ElectricalandElectronicEngineering
ServicesforBuildings,Part8)
l) Sanitationanddrainagerequirements(Sec1.18,Sec4.2.5:Sitedrainageandrunoffcoefficient,4.3:
WaterEfficiencyandmanagementofPart3andChapters5:WaterSupplyandChapter6:Sanitary
Drainage,Part8)
m)
Minimumdimension
of
habitable
and
non
habitable
parts
of
the
buildings
(Sec.
1.12,
Part
3).
2.1.1.3 The existing building with proposed alteration or addition shall conform to the requirements of new
buildings intheproposedoccupancyclassification.Theproposedalterationoradditionshallnotmakethe
buildinglesssanitarythanpresent.
2.1.1.4 Topromote thepreservationofhistoricbuildings,openspaceoruniquearchitectural/ culturalresources,
the local permitting authority shall transfer development rights (TDR), as decided by the authority, to
ownersascompensation,inaccordancewithAppendixE,Part3ofthisCode.
-
8/11/2019 Bangladesh National Building Code 2012 Part 09 Alteration, Addition to and Change of Use of Existing Buildings
5/15
Part9
Alteration,AdditiontoandChangeofUseofExistingBuildings
96
Vol.3
2.1.2
Safety
Requirements
2.1.2.1 Additions or alterations to an existing building or structure are not to be made if such additions or
alterations cause thebuildingor structure tobeunsafeormorehazardousbasedon fire safety, lifeand
structuralsafetyorenvironmental degradation.
2.1.2.2 The fire safety requirement shall take into consideration the structural fire resistance, smoke and fire
detection, fire protective signaling and fire suppression system feature of the facility and satisfy the
requirementsofvariouselementsforTypes1,2and3fireresistivebuildingsshallbesatisfied.
2.1.2.3 The fire resistance of the wall used for compartmentalization of a building shall not be less than that
specifiedinsubsectionsofSec2.4,Part3ofthisCode.
2.1.2.4 Ductpenetrationsofthiswallshallnotbepermitted.Ferrousorcopperpipingandconduitshallbeallowed
to penetrate or pass through the wall if the openings around such piping and conduit are sealed with
impervious noncombustible materials sufficiently tight to prevent fire transfer of smoke or combustible
gasesfromonesideofthewalltotheothersideandaresomaintained.
2.1.2.5 Thefiredoorbetweencompartmentsservingashorizontalexitshallbesoinstalled,fittedandprovidedwith
gasketsthatsuchfiredoorwillprovideasubstantialbarriertothepassageofsmoke.
2.1.2.6 Thefloor/ceilingshallbeofsuchconstructionthatthefireresistiveintegritybetweenstoriesismaintained.
2.1.2.7 The smokedetection capabilitywithin the facilitybasedon the location andoperationof automatic fire
detectors shall be evaluated with respect to the requirements of Chapter 3: Means of Escape and 4:
EquipmentandInbuiltFacilitiesofPart4forthevariousoccupanciesinthisCode.
2.1.2.8 Wherea fireprotecting alarmandsignalingsystem isprovided, thecapabilityof thesystemshallalsobe
evaluated(Part4).
2.1.2.9 Theabilityofthenaturalormechanicalventing,exhaustorpressurizationsystemtocontrolthemovement
ofsmokefromafireshallbeevaluated.
2.1.2.10
TheshaftandexitenclosuresshallsatisfytherequirementsspecifiedinPart4:FireProtection,ofthisCode.
2.1.2.11 The configuration, characteristics and support features for means of egress in the facility including the
capacityofand thenumberofexit routesavailable to thebuildingoccupants shallbeevaluatedand the
adequacyof themeansofegress routes leading toasafearea shallbeexamined.The lengthof theexit
access travelpath inwhichbuildingoccupants areconfined toa singlepathof travel shallbeevaluated.
Similarly the length ofexit access travel to an approved exit shall beevaluatedwith respect to theexit
requirementsforvariousoccupanciesasdetailedinPart4:FireProtectionofthisCode.
2.1.2.12 The efficiency and effectiveness of the elevator equipments and controls that are available to the fire
department to rescue building occupants from upper floors during a fire when such an equipment is
installed,shallbeevaluated.
2.1.2.13 Thepresenceofandreliabilityofmeansofegressemergencylightingsystemshallbeevaluated.
2.1.2.14 Theabilitytosuppressfirebasedontheinstallationofautomaticsprinklerandstandpipesystemsshallbe
evaluated (chapter 4: Equipment and Inbuilt Facilities Standards and 5: Specific Requirements for Fire
DetectionandExtinguishingSystem,Part4:FireProtection).
2.1.2.15 The lightningprotectionofthebuildingshallsatisfytherequirementsspecified inchapter1:Electricaland
ElectronicEngineeringServicesforBuildingsofPart8.
-
8/11/2019 Bangladesh National Building Code 2012 Part 09 Alteration, Addition to and Change of Use of Existing Buildings
6/15
EvaluationandCompliance Chapter1
Bangladesh
National
Building
Code
2012
97
2.1.3 EgressRequirements
2.1.3.1 Additiontooralterationorchangesofuseofabuildingshallnotbepermittedifsuchadditionoralteration
orchangeofusecausesviolationoftheegressrequirementsspecifiedinChapter3,MeansofEscape,Part4:
FireProtection.
2.1.3.2
Permissionsshall
not
be
granted
for
any
such
work
that
will
obstruct
or
block
or
hamper
the
existing
means
of egress of the building or any other building unless an equivalent and adequate means of egress is
provided.
2.1.4 StructuralRequirements
2.1.4.1 Additionsto,alterationsorchangeofuseofanexistingbuildingorstructureshallnotbepermittedifthey
causeanoverloadingorinstabilityofthestructuralelementsincludingthefoundation.
2.1.4.2 Onevaluation,ifthestructureoftheexistingbuildingisfoundinnonconformitywiththesafetyprovisions
ofthiscode,thebuildingwillbedeclaredasunsafebuildingbytheauthority.
2.1.4.3
Forall
buildings
identified
as
an
unsafe
building
the
authorities
shall
identify
measures
that
remove
danger
tothestructure,lifeorpropertysothatthebuildingcanbemadesafeforoccupation.
2.1.4.4 Buildingsthatcannotbemadestructurallysafewillbedeclaredunfitforoccupationanddemolishedbythe
authorities.
2.1.5 EnvironmentalRequirements
Additionsto,alterationsorchangeofuseofanexistingbuildingorstructureshallnotbepermitted if
theycauseenvironmental degradationandunsustainabledevelopmentinthelocality.
2.2 Compliance
2.2.1.1 Whenanevaluationiscarriedoutasdescribedaboveandtheexistingbuildingwiththeproposedalteration,
additionand/orchangeofusesatisfytherequirementspecifiedfortherelevantoccupancyclassification,the
resultsoftheevaluationshallbeacceptedbytheBuildingOfficial.
2.2.1.2 Theownershallfullycomplywiththeresultsofsuchevaluationfortheexistingbuildingwiththeproposed
alteration, addition and/or changeofuse for the relevantoccupancy classification and its recommended
remediesifrelevantassetforthinSec2.1.4above.
2.3 Sustainabilitymeasuresforexistingbuildings
2.3.1 Evenwhen there are no proposals for additions, alterations or change of use,measures tomake Existing
Building stock sustainable and environmentally responsive and energy efficient shall be proposed by the
authority after evaluating the condition of the existing buildings, when it is found that environmental
degradationistakingplaceorsuchisfearedbyexperts.Thesemeasuresmayinclude,butwillnotberestricted
to:
a) introductionofrenewableenergy
b) installationofrainwaterharvesting
c) installationofgroundwaterrechargesystems
d) introductionoflowenergysources
-
8/11/2019 Bangladesh National Building Code 2012 Part 09 Alteration, Addition to and Change of Use of Existing Buildings
7/15
Part9
Alteration,AdditiontoandChangeofUseofExistingBuildings
98
Vol.3
2.3.2
Any sustainabilityand /orenergyefficiencymeasure suggested shall complywith relevant requirements in
Chapter4:EnergyEfficiencyandSustainability,Part3ofthisCode.
-
8/11/2019 Bangladesh National Building Code 2012 Part 09 Alteration, Addition to and Change of Use of Existing Buildings
8/15
Part9
Alteration,AdditiontoandChangeofUseofExistingBuildings 99
Chapter 3
Conservation and rehabilitation of historical
and cultural heritage
3.1 Scope
Historical places, buildings, objects and manifestation of cultural, scientific, symbolic, spiritual and
religious value are important expressions of the culture and heritage, identity and religious beliefs of
societies. Their role and importance, particularly in the light of the need for cultural identity and
continuityinarapidlychangingworld,needtobepromoted.
Buildings, spaces, places and landscapes charged with historical, cultural, spiritual and religious value
represent an important element of stable and humane social life and community pride. Without
appropriaterestoration/conservation, thearchitecturalevolutioninrelationtosocioculturalconceptof
acountrys
heritage
remains
misinterpreted,
and
can
lead
to
virtual
disappearance.
3.2 TerminologyandConceptualDefinitions
3.2.1 Conservation
National legislationand international treatiesandregulationsaimtostrikeabalancebetweentheneed
fordevelopmentandtheneedtoconservetheenvironmentforthefuture.Conservationcanbedefined
bythefollowingconcepts:
a) Plannedmanagementofanaturalresource/ecosystemorparticularbuiltformorenvironment
to prevent exploitation, pollution, destruction or neglect to ensure the future usabilityof the
resource.
b)
Retentionof
existing
buildings
or
groups
of
buildings,
landscapes
etc.
taking
care
not
to
alter
or
destroycharacterordetail,eventhoughrepairsorchangesmaybenecessary.
Conservationconventionallyisconcernedtopreserveasmuchoriginalfabricaspossible.
3.2.2 Restoration
Thisistheprocessofcarryingonalterationsandrepairstoabuildingwiththeintentionofrestoringitto
itsoriginalform,often involvingreinstatementofmissingorbadlydamagedparts,so itusually includes
replication. Asfaraspossible,effortsaremadetoreplicatethematerialsandconstructiontechniquesof
theoriginalinthisendeavor.
Whileoftennecessaryafteradisaster, it isgenerallyregardedasmoredrasticthanconservation, which
suggestsretention,repairandmaintenance.
3.3 GeneralGuidelinesforHeritageBuildingsandSites
3.3.1 Conservation, rehabilitationandculturally sensitiveadaptive reuseofurban, ruralandarchitectural
heritageshallbeinaccordancewiththesustainableuseofnaturalandhumanmaderesources.Access
to culture and the cultural dimension of development is of utmost importance, benefiting all the
peoplewhohavesuchaccess.
-
8/11/2019 Bangladesh National Building Code 2012 Part 09 Alteration, Addition to and Change of Use of Existing Buildings
9/15
Part9
Alteration,AdditiontoandChangeofUseofExistingBuildings
910
Vol.
3
3.3.2 Inordertopromotehistoricalandculturalcontinuityandtoencouragebroadcivicparticipationinall
kindsofculturalactivities, theGovernmentattheappropriate levels, includingthe localauthorities,
shouldundertakethefollowing:
a) Identifyanddocument,wheneverpossible,thehistoricalandculturalsignificanceofareas,
sites,landscapes,ecosystems,buildingsandotherobjectsandmanifestations
b) Establish conservation goals relevant to the cultural and spiritual development of the
society;
c)
Promote
awareness
of
heritage
in
order
to
highlight
its
value
and
the
need
for
its
conservation andthefinancialviabilityofrehabilitation;
d) Encourage and support the local heritage and cultural institutions, association and
communities in theirconservationandrehabilitationeffortsand inculcate inchildrenand
youthanadequatesenseoftheirheritage;
e) Promote adequate financial and legal support for the effective protection of cultural
heritage;
f) Promote education and training in traditional skills in all disciplines appropriate to the
conservation andpromotionofheritage.
3.3.3 Tointegratedevelopmentwithconservationandrehabilitationgoals,theGovernmentatappropriate
levels,includingMinistries,localauthoritiesandmunicipalities,shallundertakethefollowing:
a) Recognizingthathistoricalandculturalheritageisanimportantasset,strivetomaintainthe
social,cultural
and
economic
viability
of
historically
and
culturally
important
sites
and
communities;
b) Preserve the inherited historical settlement and landscape forms, while protecting the
integrityof thehistoricalurban fabricand therebyguidingnew construction inhistorical
areas;
c) Provideadequate legaland financial support for the implementationofconservation and
rehabilitation activities, in particular through adequate training of specialized human
resources;
d) Promote incentives for such conservation and rehabilitation to public, private and non
profitdevelopers;
e) Promote community based action for the conservation, rehabilitation, regeneration and
maintenanceofneighborhoods;
f)
Support
public
and
private
sector
and
community
partnership
for
the
rehabilitation
of
inner
citiesandneighborhoods;
g) Ensure the incorporation of environmental concerns in conservation and rehabilitation
projects;
h) Takemeasurestoreduceacidrainandothertypesofenvironmentalpollutionthatdamage
tobuildingsandotheritemsofculturalandhistoricalvalue;
i) Adopt human settlement planning policies, including transport and other infrastructure
policies,thatavoidenvironmentaldegradationofhistoricalandculturalareas;
j) Ensure that the accessibility concerns of people with disabilities are incorporated in
conservation andrehabilitation projects.
3.3.4 Intheeventthattheownerofasite/buildingneedstobecompensatedforcurtailingdevelopment,
thetransferofunuseddevelopmentrightsshallbemadeasstipulatedinAppendixE,Part3.
3.4 CriteriaforprotectionofaHeritageBuilding/monument
3.4.1 Identification
Heritagebuildingsaretobeenlisted/identifiedbyaresponsiblecommitteetobeformedbytherelevant
departmentsof theGovernment,consistingofexperts inhistory,culture,architecture,engineeringand
other relevant fields, in consultation with theAdvisoryCommittee to theDepartmentofArchaeology,
Government of Bangladesh, as constituted under the Antiquities Act of 1968. Once identified, the
Government may, by notification in the official Gazette, declare any heritage building to be a protected antiquity
under this same Act.
-
8/11/2019 Bangladesh National Building Code 2012 Part 09 Alteration, Addition to and Change of Use of Existing Buildings
10/15
Conservationandrehabilitationofhistoricalandculturalheritage Chapter3
Bangladesh
National
Building
Code
2012
911
3.4.2
Categorization
Heritage buildings are to be categorized in accordance with its degree of dilapidation / dilapidated
conditions
3.4.3 Chronology
Heritagebuildingsunderconsiderationwillalsobecategorizedchronologicallyinanattempttodetermine
theirancientcharacterandage
3.4.4
Documentation
Beforeanyconservationworkisinitiated,athoroughresearchanddocumentationistobecarriedouton
theheritagebuildingsunderconsiderationbyrelevanttechnicalexpertsonhistory,culture,architecture,
engineeringandmaterialsciences,toensurethattherestorationworkisfaithfullycarriedout.
Asitesurvey (preferablywithdigitalequipments)shallbeconductedbefore initiating theworkofeach
andindividualbuilding/structure.
Inorder tounderstand the location,dimension anddepthof foundationof columns /piersor similar
structuralcomponents,partofthefootingcanbeexposedbyexcavatingtheearthworkwiththeguidance
ofexperiencedtechnicalpersonsexecutedbyexperiencedworkers.
Subsequently at every stage of the conservation work the technical aspects and process of various
activitiesaretobedocumented
3.4.5 CommunityParticipation
Inordertoensurecommunityparticipationintheconservationprocess,scaleddrawingsoftheproposed
conservation shall be appended to the site during construction so that the public may become
accustomedtotheproposalandhavetheoptionofregisteringtheiropinionregardingthesame.
Ifnecessary theproposals shallbeamended if strongpublicopinion is found against theproposal for
conservation/restoration.
Wherepossible,localyouthgroupsshallbeusedforfacilitatingtheconservation process.
3.4.6 Protectionofthebuilding/site
3.4.6.1 Aclearspacearoundeachmonumentshallbeformedasanimmediateenvironmentalprotectionto
themonument.
This
area
should
follow,
as
the
case
may
be,
the
original
line
of
the
enclosure
wall.
3.4.6.2 In ruralor suburban settingnonew structures /built formsof any size, shape shallbeallowed to
developwithin theUNESCO /UNDPsuggestedareaofhalfamile radius from theepicenterof the
monumentunderconsideration.
3.4.6.3 Inruralor suburbansettings,aparceloflandrepresentingapproximatelyacircularareaofahalfmile
radiusofthefarmland immediatelysurroundingtheheritagebuilding/monumentshallbeacquired
toprotectitfromencroachment
3.4.6.4
Inurbanareasormetropolitancitiesan immediatebufferzoneassetbythepermittingauthorities,
butnotlessthan3metersinwidth,adjacenttotheheritagebuilding,mustbekeptabsolutelyfreeof
any
structure
or
establishment
of
similar
nature
surrounding
the
heritage
building
or
its
part
thereof.
The adjacent buildings (proposed) should follow certain height restrictions to be imposed by the
permittingauthorityassetforthinSec3.4.5.5below.
3.4.6.5 Ingeneral,theheightofanyproposedbuildingsadjacenttoheritagebuildingsshallbekeptlimitedto
withintwotimestheheightoftheheritagebuildingunderconsideration.
3.4.6.6 Toprotectthemonumentagainsthuman impact,movementofvisitorswithinthestructureandsite
shallbecontrolled.Climbingoverthefabricofthemonumentshallbeillegalandbepreventedatall
times.
-
8/11/2019 Bangladesh National Building Code 2012 Part 09 Alteration, Addition to and Change of Use of Existing Buildings
11/15
Part9
Alteration,AdditiontoandChangeofUseofExistingBuildings
912
Vol.
3
3.4.6.7
Signages shall be installed within the site and building premises to guide visitors by creating
circumambulatorypathorcirculationareaaroundeachoftheheritagebuildings/monuments.
3.4.7 OriginalElements
3.4.7.1 Structures that impinge directly on the monument/s, identified to be additions, alterations or
extensions of any form or kind on to the original monument/s, shall be removed/ relocated
elsewhere,inanattempttorecognizetheoriginalform/featureofthemonument.
3.4.7.2 Alloriginalstructuresandarchitecturalelementsaretoberetainedandrestored.
3.4.7.3 Intheeventthatsuchelementshavetoberepaired,theirfeaturesaretoberetainedintact.
3.4.8 Useofbuildingmaterials
3.4.8.1 Allrepairing,restorationandrenovationworkshallbedonefollowingtheoriginaldesignanddetails
ineverystepwiththesame/similarbuildingmaterialsused
3.4.8.2 Selectionand applicationofmaterialsare tobemade inharmonywith thematerialsused in the
past/duringtheperiodoforiginalconstructionofthemonument/building underconsideration
3.4.8.3 Sand
3.4.8.3.1 Sandused inthemakingofmortar,shallbecoarsegrained,perfectlyclean,sharpandyellowish
color,inorderthatasuccessfulresultmaybeobtainedforcementandlimemortar.Finegrained,
dustyanddirtysandshallnotbeusedandeachfreshconsignmentshallbecarefully inspectedin
ordertoseethatitcorrespondswiththesampleapprovedinthefirstcase.
3.4.8.3.2 Sands,whichwouldotherwisebeofgoodquality,but containing lumpsof foreignmatter,ora
qualityofdustyparticlesmaybeused,onlyafterithasbeenthoroughlywashedandexamined.
3.4.8.3.3 Seasandcontainsaquantityofsaltwhichwillcauseefflorescencewhenthemortarisset.Ifused
forthe
mortar,
the
salt
from
this
sand
shall
be
eliminated
by
very
thorough
washing
in
clean
water,
thewaterbeingrenewedateachwashing.
3.4.8.4 Brick
3.4.8.4.1 Nomodern bricks are to be used on any old buildingswithout the approvalof an appropriate
technicalperson/expertofConservation.
3.4.8.4.2 Inrepairingbrickwork,bricksofthesamesizeandfabricastheoriginalshallbeused.Inabsenceof
instructions,thebricksshallbe laid inthesamebond,andthemortarjointsshallbeofthesame
thicknessandtonedtothesamecoloras intheoriginalwork.Whendesirable,themortarjoints
mayberecessedabout6.5mm 12.5mmbackfromtheface.
3.4.8.5
Cement
3.4.8.5.1 Cementshallbeslowsetting,complyingwiththestandardspecificationofPortlandcement.Inthe
absence of specific instruction/s, the use of cement on any conspicuous part of a building for
pointing,plasteringorotherpurposes shallbe avoided, as ifvisible, itwillexpressanoticeably
modernnotetothestructure.
3.4.8.6 Cementconcretemix
3.4.8.6.1 TheCementconcreteshallbevariedinaccordancewithlocalnecessities.
-
8/11/2019 Bangladesh National Building Code 2012 Part 09 Alteration, Addition to and Change of Use of Existing Buildings
12/15
Conservationandrehabilitationofhistoricalandculturalheritage Chapter3
Bangladesh
National
Building
Code
2012
913
3.4.8.6.2
Themixforfoundationsshallbe1partofPortlandcement,3partsofsandand8partsofclean
stone,brickorgravelbrokentoapproximatelyoneandhalfinch,mixedthoroughly.
3.4.8.6.3 Themixforflooringandterracingshallbe,1partofPortlandcement,2partsofsandand5partsof
stone,brickorgraveletc.brokenapproximatelyto1inchring.
3.4.8.7 Limemortar
Limemortarofwhichthetensilestrengthislessthan100lbs.persq.inchisnottobeusedinconservation
works.A
practical
and
quick
way
of
testing
lime
mortar
on
the
work
itself
is
to
take
ahandful
of
mortar
fromthetroughandafteraminuteortwo,towashitoffthehand.Iftheskinisleftroughafterwashing,
themortarmaybeconsideredfitforuse.
3.4.8.8 Limewash
3.4.8.8.1
Theuseof limewashorpaint isstrictly forbiddenexceptunderspecialcircumstanceswhen the
permissionshallbetakenfromanappropriateauthority/expertonconservation.
3.4.8.8.2 If it is important toremove limewash fromanoldsurfaceofaheritageestablishment,extreme
precautionshallbetakentopreventinjurytoanyinscriptions,relieforpaintingunderneath.Lime
washmayoftenberemovedbybrushingwithsoapandwater,butacidmustnotbeusedforthe
removal
of
lime
wash
from
marble
or
limestone,
the
surface
of
which
is
liable
to
damage
by
the
acidwork.
3.4.9 Upgradingandadaptivereuse
3.4.9.1
Adaptive reuse shall follow logical consequence considering public requirements of the region,
touristinfluxandsocioculturalcontextoftheregionunderinfluence.
3.4.9.2 Thedecisionof includingdifferent functions shallbemadeonlyafter thorough investigationbya
committeeworkingundertheguidelineofexpertsinarchaeologyandarchitecture oftheregion.
3.4.10Repairing,consolidationandrestoration
3.4.10.1
Inorder
to
prevent
salt
action
on
the
buildings,
all
materials
used
in
the
mortar
mixes
shall
be
free
of
anyimpurities.Thebricksshallbeacquiredonlyfromthebestbrickkilnsandtestedtoensurethey
arealsofreefromimpurities.Anylimeshallbepureslakedlimemadefromreallimestoneandnota
substitute.
3.4.10.2 Toprotectthestructuresfrompenetrationbyrainwater,awaterproofmembrane,suchasthinlayer
ofconcrete,shallbeplacedbetweenthearchaeologicalstructureandanygrasscoverings.
3.4.10.3 Major building features such as cornices, string courses, kiosks and/or cupolas etc. shall be
reconstructed, sothatthewaterrunningoffthemainbuiltformofthestructureisthrownclearof
thebrickwallorassociatedfaade.
3.4.10.4 Allreplacementofexternalbrickfacadesshallhaveaheavylayerofpolythenesheetbarrierplaced
between the old and the new brickwork in order to prevent the transfer of salts from the old
brickworktothenew.
3.4.10.5
Toprotectandtreatthebricksofvariousshapesandformsusedinwalls,columns,projectedeves/
corniceusedonexternalfaade,thoseshallfirstlyberecordedchronologically,andthenbecleaned
ofvegetation, particularlyalgae/weedsetc.,priortosoakingthemseveraltimesincleanwaterto
removeanysalttherein.
-
8/11/2019 Bangladesh National Building Code 2012 Part 09 Alteration, Addition to and Change of Use of Existing Buildings
13/15
Part9
Alteration,AdditiontoandChangeofUseofExistingBuildings
914
Vol.
3
3.4.10.6
Treatment of decorative brickwork and terra cotta shall be carried out step by step; firstly by
thoroughlywashinginfreshwater.Secondly,afterallthesaltshavebeenleechedout,thebrickwork
or the terra cotta shall be treated with a consolidant chemical recommended by conservation
experts.
3.4.10.7 Inordertosecuretheplaques,insitu,thoseshallbeanchoredtothemainfabricwithstainlesssteel
clamps.
3.4.10.8
Surfacedrains
shall
be
installed
in
order
to
discharge
surface
water
from
the
large
courts
and
also
from the nooks and corners of the building premises and monument under consideration. Any
repairing, restoration and renovation work that this entails shall be done following the original
designanddetailsineverystepusingthesamebuildingmaterialsandtechniques.
3.4.11Grouting
Grouting is to put a thin layer ofmortar, following the required technical specification, in the spaces
betweentiles,bricksorsimilarothermaterialsusedinconservationwork.
3.4.11.1 A void which can not be thoroughly cleaned out with water can be satisfactorily filled under
pressure,sincethereareboundtobedustysurfaceswithwhichthegroutwillnotmakeasolidjoint.
3.4.11.2
Numerousholes
must
be
left
in
the
pointing
for
the
escape
of
air
and
for
the
liquid
grout.
3.4.11.3 Thepointingmustbe fairly hard and seton the outer surfacebefore grouting is commenced.A
periodofthreetofourweekisusuallynecessaryforthistotakeplace.
3.4.11.4 Wherecementhasbeenused for filling thejointsat thebackof the limepointing, thengrouting
maybestartedtendaysafterwards.
3.4.11.5 Thewholebodyofthewalltobetreated(wheregroutingistobeperformed)shouldbethoroughly
washedoutwithwater(forcedunderapressureofabout15lbs.to20lbs.persquareinch)starting
fromthetopofthewallandworkingdownwards.Thewallsmust,however,bethoroughlysaturated
beforegroutingiscommenced.
3.4.11.6
Themixture
in
the
machine
is
to
consist
of
not
more
than
three
parts
of
sand
to
one
of
cement,
or
asnearthisratio(inordertoresistthenatureofsandtoflowinthemachine)
3.4.11.7 Thegroutingofcavitiesshouldbestartedatthebaseofthewall.Eachgroutingpointshouldbefed
twicefromthemachine.
3.4.11.8
Thepressuretobeobtainedinthemachineshould,asarule,benotlessthan25lbs.normorethan
35 lbs. per square inch; air should be pumped into to compressor until 35 lbs. per sq. inch is
attained,andthepressureshouldnotbeallowedtoreducebelow25lbs.persq.inchforordinary
cases. However,wherethewallisthinorweakthepressuremaybereducedto12lbs.or15lbsper
sq.inch.Iftheaboveprecautionsaretaken,thisshouldhavenobadeffectuponthelimepointing.
3.4.12
Hand
Grouting
3.4.12.1 Inhandgrouting,theproportionsofcementtosandwilldependbothuponthecharacter
of thevoids tobe filledandupon thedegreesof finenessof the sand. If thevoidsare
large, one part of cement to two parts of sand may be used, but if small, then the
proportionofsandshouldnotexceedonepart.
3.4.12.2 It is importanttokeepthecementandsandthoroughlymixedbycontinuallyshakingthe
caninwhichthegroutisheld.
-
8/11/2019 Bangladesh National Building Code 2012 Part 09 Alteration, Addition to and Change of Use of Existing Buildings
14/15
Conservationandrehabilitationofhistoricalandculturalheritage Chapter3
Bangladesh
National
Building
Code
2012
915
3.4.12.3
It isnecessary to leave,above thegroutinghole,another smallhole for theescapeofair
whilegroutisbeingpouredin.
3.4.12.4 Incaseswhereawallisweak,orathinskinoffacingmaterialisbondedtomainwall,itmust
beefficientlyboardedandstruttedintopositionbeforethegroutingworkisstarted.
3.4.13Underpinning
3.4.13.1
Underpinning is applied to the building of new work underneath an existing structure
withoutdisturbing its stability.Underpinningmaybenecessarywhen the foundationofa
wallofanancient /heritagebuilding is tobe replacedwithnew foundationorwhen the
existingfoundationofawallisrequiredtobestrengthenedforsustainability.
3.4.13.2 All excavations for underpinning must be carefully and adequately planked and properly
strutted(topreventtiltingandbuckling;inordertopreventthis,thejoistsarestruttedapart
in themidspan all along the length); All themasonrywork etc., immediately above the
proposed stretchofunderpinning,mustbeadequatelyheldbyrakingshoresonagoodsolid
foundation.
3.4.13.3
Wherealong
length
of
wall
has
to
be
underpinned,
the
work
must
be
carried
out
in
sections
about1minwidthandtothedepthindicatedintheestimate;themasonryoverheadandthe
earthatthesidesmustbethoroughlyshoredupandstrutted.
3.4.13.4 Ifunderpinningexceeds1m inheight, themasonry istobebuiltup in layersnotexceeding
0.60m.Eachlayeristobeallowedtosetbeforethelayeraboveisadded.
3.4.13.5 When two sections are to be carried out together, they must not adjoin. Generally, a
minimumdistanceof3.5m is tobemaintainedbetween two sections.Theholesmustbe
keptquitefreefromwaterbypumping.
3.4.13.6 Allconcretemustbewell rammed intoadense solidmasswhenpossible,andwhere the
heightofthehole issufficienttoramvertically,theconcretemustbewellpumped infrom
thefrontface.
3.4.13.7 When the footingsof thewall are very looseanddisintegrated, thejoints shouldbewell
washedoutandfilledwithcementgrout,ifpossible,beforetheunderpinningisstarted.
3.4.14Decoration andDetails
3.4.14.1 Inlaywork(Pietradura)
In therepairof inlaywork (pietradura),thegreatestcare isnecessary inorder toensure that thenew
stonesarefixedexactly,andthattheedgesoftheexistinggroundworkarenotscrapped.Thisshouldbe
donestep
by
step
following
aconservation
manual.
3.4.14.2 The fret cutting should be done by means of a plain soft iron wire mounted on a split
bamboobow.Solidpatternsarecutbyworkingthebowlikeafretsaw.
3.4.14.3 Theinlayblocksarecutontheslantwithaninwardslopeofabout15degreesontheedges
tofacilitatethefitting.
-
8/11/2019 Bangladesh National Building Code 2012 Part 09 Alteration, Addition to and Change of Use of Existing Buildings
15/15
Part9
Alteration,AdditiontoandChangeofUseofExistingBuildings
3.5 AreaConservationforHistoricDistricts
3.5.1 IndentifyingHistoricDistricts:
Whenneighborhoods/regionsofancientheritagebuiltformsarepresentinanyurban/semiurban/rural
setting, these shallbe identified asHistoricdistrictsby theAdvisoryCommittee to theDepartmentof
Archaeology,GovernmentofBangladesh,asconstitutedundertheAntiquitiesActof1968.Suchdistricts
willbeconsideredasrepresentingahistoricperiodoftheregion.Principlesofareaconservationshallbe
applied
for
the
protection
and
preservation
of
these
historic
districts.
3.5.2 PlanningParametersandConservationGuidelines
3.5.2.1
Anappropriateplanshallbedrawn inordertoshowtheboundaryofconservationareas,thecore
areas, the buildings to be conserved, the residential and other functional areas to be retained /
restoredandtheenvelopecontrolsites.
3.5.2.2 Theschemeshallincludearehabilitationplanforperson/sdisplacedintheConservationprocess.
3.5.2.3 Forbuildingstobeconserved,eachandeverybuildingofhistoricalimportanceistobeconserved/
restoredinaccordancewiththeconservationguidelinessetforthinSections3.3and3.4above.
3.5.2.4
Taking
into
consideration
community
needs,
the
area
shall
be
assigned
functions
that
can
sustain
its
existenceandcontributetotheeconomicfunctioningofthearea.
3.5.2.5 The plan and detailing of the entire area shall comply with energy efficient and sustainability
guidelinessetforthinChapter4:EnergyEfficiencyandSustainability,Part3ofthisCode.