MEGASTRUCTURES
![Page 2: Bandra - Worli sea link](https://reader033.vdocuments.site/reader033/viewer/2022061520/589d40471a28abd17d8b71e1/html5/thumbnails/2.jpg)
BANDRA WORLI SEA-LINKBANDRA WORLI SEA LINK
Presented By
TE ( CIVIL)Ankita Pal
SSJCET
![Page 3: Bandra - Worli sea link](https://reader033.vdocuments.site/reader033/viewer/2022061520/589d40471a28abd17d8b71e1/html5/thumbnails/3.jpg)
INTRODUCTION
Officially known as Rajiv Gandhi Sea Link.
Cable-stayed bridge with pre-stressed concrete-steel viaducts.
Links the Bandra (Western suburb) and Worli ( South Mumbai).
Inaugurated on June 30 , 2009.
Among the most complex & advanced construction projects ever in India.
![Page 4: Bandra - Worli sea link](https://reader033.vdocuments.site/reader033/viewer/2022061520/589d40471a28abd17d8b71e1/html5/thumbnails/4.jpg)
Designed By : Sheshadri Srinivasan (Structural engineer , Working in Lebanese Engineering Firm Dar-Al-Handshah )
Commissioned By : Maharashtra State Road Development Corporation
Constructed By : Hindustan Construction company , India ( HCC)
![Page 5: Bandra - Worli sea link](https://reader033.vdocuments.site/reader033/viewer/2022061520/589d40471a28abd17d8b71e1/html5/thumbnails/5.jpg)
HISTORY Mahim Causeway was the only link connecting westernsuburbs to island
city of Mumbai, making it highlycongested during the peak hours .
Vehicular traffic admeasuring about 120,000 PCUtravels on the Mahim causeway everyday and during peak hours and it takes about forty minutes to travelfrom Mahim causeway to Worli, a distance of about 8km.
![Page 6: Bandra - Worli sea link](https://reader033.vdocuments.site/reader033/viewer/2022061520/589d40471a28abd17d8b71e1/html5/thumbnails/6.jpg)
LOCATION
![Page 7: Bandra - Worli sea link](https://reader033.vdocuments.site/reader033/viewer/2022061520/589d40471a28abd17d8b71e1/html5/thumbnails/7.jpg)
BASIC INFO Official Name “ Rajiv Gandhi Setu ”
Carries 8 Lanes of Traffic
Owner MSRDC
Design Cable-stayed, Concrete-Steel precast viaducts
Total length 5.6 Km ( 3.5 miles )
Width 2 20 m ( 66 ft ) Highest Point 126 m ( 413 ft ) Longest Span 2 250 m ( 820 ft ) Vertical Clearance 20 m ( below bridge for transportation )
Foundation Type Pile Foundation Toll System Automated 16-Lane Toll Plaza
![Page 8: Bandra - Worli sea link](https://reader033.vdocuments.site/reader033/viewer/2022061520/589d40471a28abd17d8b71e1/html5/thumbnails/8.jpg)
Time Frame
Estimated Time Frame : 5 years Construction begin : June 1995 Construction end : March 2003
Actual Time Frame : 11 years Construction begin : October 2000 Construction End : 24 March 2010 Opened : 30 June 2009
![Page 9: Bandra - Worli sea link](https://reader033.vdocuments.site/reader033/viewer/2022061520/589d40471a28abd17d8b71e1/html5/thumbnails/9.jpg)
BUDGET
Estimated Cost : ₹ 665.81 Cr Actual Cost : ₹ 1653.25 Cr
The Increament in project cost was due to payments of escalation 213 ₹Cr on account of inordinate delay in completion (61 months ) .
New technical changes in the bridge at the behest of new consultant 70 Cr ₹.
Contractor for delay in award of work 125 Cr .₹
Interest liability due to delayed completion 230 Cr .₹
![Page 10: Bandra - Worli sea link](https://reader033.vdocuments.site/reader033/viewer/2022061520/589d40471a28abd17d8b71e1/html5/thumbnails/10.jpg)
PIERS : The span between the piers is 50 maters .
This distance arrived by considering optimization between foundation cost Vs. superstructure cost .
If the piers are wide apart then foundation cost comes down , but the superstructure becomes heavier and its cost goes up .
Moreover, more number of piers provide better wind resistance .
![Page 11: Bandra - Worli sea link](https://reader033.vdocuments.site/reader033/viewer/2022061520/589d40471a28abd17d8b71e1/html5/thumbnails/11.jpg)
![Page 12: Bandra - Worli sea link](https://reader033.vdocuments.site/reader033/viewer/2022061520/589d40471a28abd17d8b71e1/html5/thumbnails/12.jpg)
CABLE WIRE Are also known as ‘ Parallel Wire Stay Cables ’.
Manufactured by “Shanghai Pujiang Cable Co. Ltd” China .
Each cable consists a group of steel wires ( 6 wires ) .
Each steel wire has a diameter 7mm with a breaking limit of 6.28 Tones.
Group of these wires was packed in two layers of HDPE (High Density Poly Ethylene) material .
![Page 13: Bandra - Worli sea link](https://reader033.vdocuments.site/reader033/viewer/2022061520/589d40471a28abd17d8b71e1/html5/thumbnails/13.jpg)
![Page 14: Bandra - Worli sea link](https://reader033.vdocuments.site/reader033/viewer/2022061520/589d40471a28abd17d8b71e1/html5/thumbnails/14.jpg)
Highly uneven and variable foundation bed even for plane area of one pile .
The maritime Board does not allow marine traffic in monsoon season . Thus work was halted Mid-May only to re-commence in October . Effectively reducing the work schedule to only seven month in a year .
Needed for extra steel trusses , further experts .
Delay due to change in design of stray Cable .
![Page 15: Bandra - Worli sea link](https://reader033.vdocuments.site/reader033/viewer/2022061520/589d40471a28abd17d8b71e1/html5/thumbnails/15.jpg)
BENEFITS
Considerable savings in travel time from 40 min to 8 min
Estimated savings in fuel and vehicle operating cost is around $ 16.2 million .
Stress free driving . Reduced accidents and noise pollution . Reduction in air pollution .