Earned Value for Gauchito Rocket Project

TRANSCRIPT

Page 1: Bailey Gauchito Project Unit5 Presentation

Ansari X Prize Gauchito Rocket Project

Thomas N. Bailey

GM593-01N

August 28, 2012

Page 2: Bailey Gauchito Project Unit5 Presentation

Overview

• Project Background• Situation at Four Weeks

– EVM Metrics– S-Curve

• Situation at Eight Weeks– Rebaseline Gannt Chart– EVM Metrics– S-Curve

• Conclusion

2

Page 3: Bailey Gauchito Project Unit5 Presentation

Project Background

• Space Systems Technologies Corporation (SSTC) is subcontracted by Scaled Composites to build a 7/8 scale model of Gauchito rocket

– Earned Value Management (EVM) will be used for project management

– Project duration is 11 weeks

– Work Breakdown Structure (WBS) consists of 15 tasks

3

Page 4: Bailey Gauchito Project Unit5 Presentation

Situation At First Project Review

• Project baselined with 11 weeks duration and 18 weeks of level of effort

• Budget at Completion (BAC) equals $143,530

4

ID BCWP (PV) TASK Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 BAC TotalsA 1.0 ASSEMBLE ENGINE MOUNT $5,760 $5,760 $11,520B 2.0 FIN PREPARATION $4,320 $4,320C 3.0 MARK FIN AND LAUNCH LUG LINES $4,320 $4,320D 4.0 INSERTING ENGINE MOUNT $4,320 $4,320 $8,640E 5.0 ATTACH FINS $4,320 $4,320F 6.0 ATTACH SHOCK CORD $4,320 $4,320 $8,640G 7.0 ASSEMBLE NOSE CONE $2,880 $2,880H 8.0 ATTACH PARACHUTE/SHOCK CORD $1,440 $1,440I 9.0 ATTACH LAUNCH LUG $1,440 $1,440J 10.0 PAINTING THE ROCKET $5,760 $5,760K 11.0 APPLICATION OF DECALS $1,440 $1,440L 12.0 APPLYING CLEAR COAT $1,440 $1,440M 13.0 DISPLAY NOZZLE ASSEMBLY $4,320 $4,320N 14.0 ROCKET PREFLIGHT $2,880 $2,880O 15.0 PREPARE FOR TEST LAUNCH $1,440 $1,440

EQUIPMENT $1,025 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,025MATERIAL $15,685 $2,500 $5,800 $0 $0 $375 $270 $650 $2,125 $300 $50,000 $77,705

$143,530Weekly Total $38,310 $14,020 $10,120 $4,320 $4,320 $1,815 $6,030 $2,090 $7,885 $3,180 $51,440

Cumulative Cost (PV) $38,310 $52,330 $62,450 $66,770 $71,090 $72,905 $78,935 $81,025 $88,910 $92,090 $143,530

Page 5: Bailey Gauchito Project Unit5 Presentation

EVM Metrics After 4 Weeks

• Earned Value analysis after 4 weeks reported the following:– BCWS = $66,770– ACWP = $68,210– BCWP = $62,450– SV = -$4,320 (project is $4,320 behind schedule)– CV = -$5,760 (project is $5,760 over budget)– SPI = 0.94– CPI = 0.92– EAC = $156,768 (EAC is 9% over BAC)– VAC = -$13,238– ETC = $88,558 (expected cost needed to complete all

remaining work)

• Project is one week behind schedule and over budget– Project EAC is still within acceptable range and not in trouble

5

Page 6: Bailey Gauchito Project Unit5 Presentation

S-Curve After 4 Weeks

6

Page 7: Bailey Gauchito Project Unit5 Presentation

Situation At Week Eight

• Scaled Composites decided to modify the project’s scope

– Drop the Test Launch Preparation deliverable (task #15)

– Request SSTC to replan the project

– SSTC to present new revamp edbaseline for approval

– SSTC to present EVM metrics of rebaseline project to present time

7

Page 8: Bailey Gauchito Project Unit5 Presentation

Rebaseline Gannt Chart

8

ID TASKS Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11A 1.0 ASSEMBLE ENGINE MOUNTB 2.0 FIN PREPARATIONC 3.0 MARK FIN AND LAUNCH LUG LINESD 4.0 INSERTING ENGINE MOUNTE 5.0 ATTACH FINSF 6.0 ATTACH SHOCK CORDG 7.0 ASSEMBLE NOSE CONEH 8.0 ATTACH PARACHUTE/SHOCK CORDI 9.0 ATTACH LAUNCH LUGJ 10.0 PAINTING THE ROCKETK 11.0 APPLICATION OF DECALSL 12.0 APPLYING CLEAR COATM 13.0 DISPLAY NOZZLE ASSEMBLYN 14.0 ROCKET PREFLIGHT

Page 9: Bailey Gauchito Project Unit5 Presentation

9

Rebaseline Gannt Chart with Resources

• BACRebaseline = $97,850

ID BCWP (PV) TASK Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 BAC TotalsA 1.0 ASSEMBLE ENGINE MOUNT $5,760 $5,760 $5,760 $17,280B 2.0 FIN PREPARATION $4,320 $4,320C 3.0 MARK FIN AND LAUNCH LUG LINES $4,320 $4,320D 4.0 INSERTING ENGINE MOUNT $4,320 $4,320 $8,640E 5.0 ATTACH FINS $4,320 $4,320F 6.0 ATTACH SHOCK CORD $4,320 $4,320 $8,640G 7.0 ASSEMBLE NOSE CONE $2,880 $2,880H 8.0 ATTACH PARACHUTE/SHOCK CORD $1,440 $1,440I 9.0 ATTACH LAUNCH LUG $1,440 $1,440J 10.0 PAINTING THE ROCKET $5,760 $5,760K 11.0 APPLICATION OF DECALS $1,440 $1,440L 12.0 APPLYING CLEAR COAT $1,440 $1,440M 13.0 DISPLAY NOZZLE ASSEMBLY $4,320 $4,320N 14.0 ROCKET PREFLIGHT $2,880 $2,880

EQUIPMENT $1,025 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,025MATERIAL $15,685 $2,500 $0 $5,800 $0 $0 $375 $270 $650 $2,125 $300 $27,705

$97,850Weekly Total $38,310 $14,020 $5,760 $10,120 $4,320 $4,320 $1,815 $6,030 $2,090 $7,885 $3,180

Cumulative Cost (PV) $38,310 $52,330 $58,090 $68,210 $72,530 $76,850 $78,665 $84,695 $86,785 $94,670 $97,850

Page 10: Bailey Gauchito Project Unit5 Presentation

Rebaseline EVM Metrics After 8 Weeks

• Earned Value analysis after rebaseline and after 8 weeks reported the following:– BCWS = $84,695– ACWP = $84,695– BCWP = $84,695– SV = $0 (project on schedule)– CV = $0 (project is on budget)– SPI = 1.0– CPI = 1.0– EAC = $97,850 (EAC equals to BAC)– VAC = $0– ETC = $13,155 (expected cost needed to complete all

remaining work)

• Project is on schedule and on cost (doing very well)10

Page 11: Bailey Gauchito Project Unit5 Presentation

Rebaseline S-Curve

11

Page 12: Bailey Gauchito Project Unit5 Presentation

Conclusion

• At direction from Scaled Composites, project duration remains at 11 weeks– Last deliverable was removed– Project was rebaselined

• EVM after 8 weeks reports project is on schedule and on cost and is doing very well